A BIM-based digital typesetting system and method for non-standard equipment
Through the digital layout system of non-standard equipment based on BIM, combined with the use and maintenance data and environmental monitoring data, the equipment layout and environmental matching are optimized, and the problems of low design efficiency and insufficient environmental adaptability of traditional non-standard equipment are solved, and the equipment operation efficiency is improved and lifespan ensures reasonable use of space and safety of equipment.
Patent Information
- Application Number
- CN202411106233.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-13
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2044-08-13
AI Technical Summary
Traditional non-standard equipment design and production methods have problems such as long design cycle, low production efficiency and low material utilization. The existing technology ignores the matching degree of equipment with the actual operating environment and overall spatial planning, resulting in degradation or conflict in equipment performance. Inefficient.
Using BIM-based digital layout system and methods for non-standard equipment, the equipment priority sorting, floor determination and location matching are used to ensure that the equipment operates in a suitable environment and improve production efficiency .
It realizes that the equipment operates under more suitable environmental conditions, extends the equipment life, reduces maintenance costs, improves the consistency and efficiency of the production process, ensures the safe placement of equipment and the rational use of space, and enhances the rationality of the overall layout. and accessibility.
Smart Images

Figure CN118627467B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of digital typesetting, and in particular to a BIM-based non-standard equipment digital typesetting system and method. Background Art
[0002] Non-standard equipment refers to equipment that is not manufactured in accordance with the unified industry standards and specifications promulgated by the state, but is designed by itself according to its own use and needs. BIM technology is a digital tool used in engineering design, construction, and management. By integrating the digital and informationized models of buildings, it is shared and transmitted throughout the life cycle of project planning, operation, and maintenance, enabling engineering and technical personnel to correctly understand and efficiently respond to various building information, providing a basis for collaborative work for the design team and all parties involved in the construction, including construction and operation units, and playing an important role in improving production efficiency, saving costs, and shortening construction periods.
[0003] However, there are many problems with the traditional design and production of non-standard equipment, such as long design cycle, low production efficiency, low material utilization, etc. In order to solve these problems, people propose to combine BIM technology with the layout of non-standard equipment. However, the existing technical solutions often ignore the matching degree between the equipment and the actual operating environment; different equipment has different requirements for environmental conditions such as temperature, humidity and light, and the lack of consideration of environmental adaptability may cause equipment performance degradation or damage; in addition, the existing technical solutions do not give a clear layout order, and often only focus on the local equipment layout, while ignoring the overall space planning and the relationship between equipment, which may lead to conflicts between equipment and inefficiency. Summary of the invention
[0004] Technical issues solved
[0005] In response to the technical problems in the background technology, the present invention proposes a BIM-based digital layout system and method for non-standard equipment. By integrating usage, maintenance data and environmental monitoring data, and using the BIM model to perform equipment priority sorting, floor determination and position matching, the equipment can be optimized and layout can be achieved, ensuring that the equipment operating environment is suitable and easy to maintain, thereby improving production efficiency; thereby solving the technical problems recorded in the background technology.
[0006] Technical Solution
[0007] To achieve the above objectives, the present invention is implemented through the following technical solutions:
[0008] A BIM-based non-standard equipment digital typesetting method, comprising:
[0009] Obtain the usage and maintenance data of each non-standard equipment from historical data; set up several environmental monitoring points in the actual site, place an environmental sensor group at each environmental monitoring point and periodically collect environmental data around its location; perform pre-processing operations on the acquired and collected data; establish several associated sets, and put the non-standard equipment required in the same production line into the same associated set;
[0010] According to the historical usage and maintenance data of each non-standard equipment, the operation times of each non-standard equipment are obtained. , the duration of each run and the number of repairs or maintenance required ; Calculate the weights of the total operating time and the number of repairs or maintenance times according to the maximum and minimum values of the total operating time and the number of repairs or maintenance times of all non-standard equipment and ; Combine the total operation time and repair or maintenance times of each non-standard equipment with the corresponding weight to obtain the priority index of each non-standard equipment , all non-standard equipment according to the priority index The sizes are placed in the typesetting queue in order;
[0011] Non-standard devices are sequentially taken out from the layout queue to determine the layout floor. Whenever a non-standard device in the layout queue determines the layout floor, several associated sets to which the non-standard device belongs are taken out, and the average priority index of the remaining non-standard devices in each associated set is calculated; the layout floor is determined sequentially in the order of the average priority index;
[0012] Whenever a non-standard device confirms the layout floor, it will be matched with each environmental monitoring point on the corresponding floor for environmental adaptability, and the environmental difference value of the device at each environmental monitoring point will be generated. , according to the environmental difference Select the most suitable layout position based on the size.
[0013] Specifically, the corresponding usage data and maintenance data are obtained from the historical database of each non-standard equipment, and the data are integrated into a unified data platform; pre-processing operations are performed on the obtained data, including the processing of missing values and outliers; the data import function of the BIM software is used to correspond the integrated usage data and maintenance data with the non-standard equipment in the BIM model; the processing flow of each production line is obtained, and the non-standard equipment required for each production line is recorded, and the non-standard equipment required for the same production line is placed in the associated set of the production line.
[0014] Specifically, the actual site of each layer is divided into several sub-areas using a grid, several intersections in the grid are used as environmental monitoring points, and an environmental sensor group is placed at each environmental monitoring point to collect the temperature, humidity and light intensity of each location;
[0015] During the specified equipment operation time, the temperature, humidity and light intensity at each environmental monitoring point are collected in real time and transmitted to the BIM system; for each location, the BIM system calculates the average, maximum and minimum values of the three environmental data during the equipment operation time based on the environmental data collected within one month.
[0016] Furthermore, the usage and maintenance data of each non-standard equipment in a certain month is randomly taken out from the data platform, including the number of times each non-standard equipment has been run in the past month. , the duration of each run and the number of repairs or maintenance required ;
[0017] Calculate the weights of total operating hours and repair or maintenance times according to the maximum and minimum total operating hours and repair or maintenance times of all non-standard equipment. and , the expression is: ;in Indicates Non-standard equipment, Indicates Non-standard equipment Run again.
[0018] Furthermore, the total operation time and the number of repairs or maintenance of each non-standard equipment are combined with the corresponding weight to obtain the priority index of each non-standard equipment. , the expression is: ; When the priority index of a non-standard device The larger the value, the higher the layout priority of the device. All non-standard devices are placed in the layout queue in order of size.
[0019] Specifically, take the non-standard equipment ranked first from the layout queue to determine the layout floor; determine the floor according to the priority index. The larger the priority index, the lower the floor it is placed on. Before preliminarily determining the floor where each non-standard equipment is located, it is necessary to determine whether the remaining load-bearing capacity and area of the floor are sufficient to place the equipment. If they are not sufficient to support the storage of a non-standard equipment, further floor selection is required, specifically:
[0020] Take out the non-standard equipment ranked first from the layout queue, and preliminarily layout it on the first layer of the BIM system to determine whether the remaining load-bearing capacity and area of the first layer are sufficient to place the equipment. When determining the remaining load-bearing capacity, compare the weight of the equipment with the remaining load-bearing capacity of the current floor. When determining the remaining area, it is necessary to combine the length, width and safety interval of the bottom of the equipment, specifically the length plus the safety interval multiplied by the width plus the safety interval, and compare the result with the remaining area of the floor. If it is determined that the floor is sufficient to place the equipment, place the equipment on the corresponding floor. If it is determined that the floor is not sufficient to place the equipment, place the equipment on the next floor, that is, the floor with the number of floors plus one.
[0021] Furthermore, after the non-standard device A in the layout queue determines the layout floor, several association sets to which the device belongs are screened out, and a group of association sets with the highest comprehensive priority index is selected by calculation, and the next non-standard device to be determined for the layout floor is selected from this group of association sets; specifically, the priority indexes of all non-standard devices in each layout set are averaged, and the result is used as the comprehensive priority index of each layout set; a group of association sets with the highest comprehensive priority index is screened out, and the layout floors of each non-standard device in the association set are selected in descending order of priority index; if it is determined that the current floor is not large enough to place the non-standard device B in the association set, the non-standard device with a priority index lower than that of the device in the same association set is given priority, and the non-standard device B is placed on the next floor of the floor; when all devices in an association set have selected the layout floor, this association set is removed from the association set of the non-standard device A, and the next group of association sets is selected;
[0022] When all non-standard devices in all associated sets of non-standard device A have selected the layout floor, these non-standard devices are deleted from the layout queue, and the layout floor of the next non-standard device in the layout queue is selected.
[0023] Specifically, every time a non-standard device confirms the layout floor, it is necessary to determine the specific location of the device on the corresponding floor, and use all environmental monitoring points on the floor as candidate layout locations for the device; obtain the most suitable operating environment data and the maximum tolerance environment data of the non-standard device, including the optimal temperature, humidity or light intensity when the device is operating, and the maximum and minimum tolerance temperature, humidity or light intensity when the device is operating;
[0024] Compare the maximum and minimum values of the three environmental data monitored at each environmental monitoring point, and compare them with the maximum and minimum environmental data of the current equipment to be typeset in turn. When the maximum value of the environmental data monitored at a certain environmental monitoring point is greater than the maximum environmental value of the equipment, or the minimum value of the environmental data monitored at a certain environmental monitoring point is less than the maximum environmental value of the equipment, the environmental monitoring point will be deleted from the equipment's candidate layout position; if all environmental monitoring points have been deleted, the equipment needs to be placed on the next floor and the layout position must be re-determined.
[0025] Furthermore, the average temperature collected by the remaining environmental monitoring points is obtained. , average humidity and the average light intensity , and combine it with the optimal environmental data of the equipment during operation to generate the environmental difference of the equipment at each environmental monitoring point , the expression is: ;
[0026] in, , , Represents the weight coefficients of temperature difference, humidity difference and light intensity difference respectively. The specific values are set by the administrator. ; , , are respectively the optimum temperature, humidity and light intensity for the operation of the device; Indicates Environmental monitoring points;
[0027] Select the environmental difference between the equipment and the remaining environmental monitoring points The minimum environmental monitoring point is used as the layout position of the equipment;
[0028] After all non-standard equipment on a floor has been selected for layout, all equipment is fine-tuned using the relevant tools in the BIM system so that there is at least a safe distance between each device and a main road can be generated to reach all non-standard equipment.
[0029] A BIM-based non-standard equipment digital typesetting system, including:
[0030] Data acquisition and preprocessing module, which obtains the usage and maintenance data of each non-standard equipment from historical data, including the number of times each non-standard equipment has been run , the duration of each run and the number of repairs or maintenance required ; Set up several environmental monitoring points in the actual site, place an environmental sensor group at each environmental monitoring point and periodically collect environmental data around its location, including temperature, humidity and light intensity; obtain processing flow data of each production line;
[0031] The data analysis module calculates the average, maximum and minimum values of the three environmental data during the equipment operation time based on the environmental data collected within a month; and calculates the weights of the total operation time and the number of repairs or maintenance times based on the maximum and minimum values of the total operation time and the number of repairs or maintenance times of all non-standard equipment. and ; Combine the total operation time and repair or maintenance times of each non-standard equipment with the corresponding weight to obtain the priority index of each non-standard equipment ; Match the environmental adaptability of each non-standard device with each environmental monitoring point on the corresponding floor, and generate the environmental difference value of the device at each environmental monitoring point ;
[0032] The digital typesetting module includes a floor determination unit and a typesetting position determination unit; the floor determination unit selects non-standard equipment floors from low floors to high floors in turn, and determines whether the remaining load-bearing capacity and area of the floor are sufficient to place the equipment; whenever a non-standard equipment in the typesetting queue determines the typesetting floor, several associated sets to which the non-standard equipment belongs are taken out, and the average priority index of the remaining non-standard equipment in each associated set is calculated; the typesetting floors are determined in order of the average priority index; the typesetting position determination unit determines the typesetting floor according to the environmental difference. Select the most suitable layout position based on the size.
[0033] Beneficial Effects
[0034] The present invention provides a BIM-based non-standard equipment digital typesetting system and method, which has the following beneficial effects:
[0035] 1. Provide more accurate layout solutions for non-standard equipment by integrating historical usage and maintenance data with real-time environmental data; this method not only optimizes equipment layout and improves production efficiency, but also lays the foundation for layout of equipment running under more suitable environmental conditions, thereby extending the service life of equipment and reducing maintenance costs; at the same time, by grouping equipment on the same production line into related sets, the consistency and efficiency of the production process are further improved;
[0036] 2. Calculate the priority index of each non-standard equipment based on its total operating time and the number of repairs or maintenance. Determine the layout order based on the priority index. The longer the total operating time of the equipment, the more critical the role it plays in the production process. Therefore, giving these equipment priority layout can ensure that they are optimized in spatial layout, easy to operate and maintain, thereby minimizing downtime. For equipment with a high number of repairs or maintenance, it means that these equipment may have a higher failure rate or require more frequent maintenance to maintain their performance. Prioritizing such equipment can make it easier to access and perform regular maintenance, which helps reduce unexpected downtime, improve equipment utilization, and reduce the cost and impact of emergency repairs.
[0037] 3. Intelligent equipment layout is achieved by comprehensively considering factors such as equipment priority, size, weight, floor load-bearing capacity and area. This method not only improves layout efficiency and accuracy, but also ensures the rational use of floor space and safe placement of equipment. By processing the associated set, the layout relationship between equipment is optimized so that the associated equipment can be as close as possible, which is convenient for subsequent operation and maintenance management.
[0038] 4. By comprehensively considering environmental data and the environmental adaptability of equipment, accurate selection of layout positions for non-standard equipment is achieved; this method not only ensures that the equipment can operate in the most suitable environment and extend the service life of the equipment, but also optimizes the equipment layout and improves space utilization efficiency through intelligent environmental difference calculation; in addition, by using the fine-tuning tools of the BIM system, the main roads leading to all equipment can be planned while ensuring safe intervals between equipment, thereby enhancing the rationality and accessibility of the overall layout and providing great convenience for subsequent equipment maintenance and management; this digital layout method not only improves layout efficiency and accuracy, but also provides a solid guarantee for the overall operational efficiency and safety of the building. BRIEF DESCRIPTION OF THE DRAWINGS
[0039] Figure 1 A flowchart of the steps of the BIM-based non-standard equipment digital typesetting method provided by the present invention;
[0040] Figure 2 A structural schematic diagram of the BIM-based non-standard equipment digital typesetting system provided by the present invention. DETAILED DESCRIPTION
[0041] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0042] refer to Figure 1 The present invention provides a BIM-based non-standard equipment digital typesetting method, comprising:
[0043] Step 1: Obtain the usage and maintenance data of each non-standard equipment from historical data; set up several environmental monitoring points in the actual site, place an environmental sensor group at each environmental monitoring point and periodically collect environmental data around its location; perform preprocessing operations on the acquired and collected data; establish several associated sets, and put the non-standard equipment required in the same production line into the same associated set;
[0044] The step one includes the following steps:
[0045] Step 101: Obtain corresponding usage data and maintenance data from the historical database of each non-standard device, and integrate the data into a unified data platform to ensure the accuracy and consistency of the data; perform preprocessing operations on the acquired data, specifically including processing of missing values and outliers, to facilitate subsequent analysis;
[0046] Step 102: Use the data import function of the BIM software to match the integrated usage data and maintenance data with the non-standard equipment in the BIM model to ensure that each equipment has corresponding data attributes in the BIM model;
[0047] Step 103: Use a grid to divide the actual site of each layer into several sub-areas, use several intersections in the grid as environmental detection points, and place an environmental sensor group at each environmental monitoring point to collect the temperature, humidity and light intensity of each location; different equipment has different working environments and different requirements for temperature, humidity and light intensity; in addition, too high or too low temperature, humidity and light intensity will also have a corresponding impact on non-standard equipment;
[0048] During the specified equipment operation time, the temperature, humidity and light intensity at each environmental monitoring point are collected in real time and transmitted to the BIM system. After pre-processing, BIM can accurately know the environmental data at each environmental monitoring point; for each location, the BIM system calculates the average, maximum and minimum values of the three environmental data during the equipment operation time based on the environmental data collected within one month;
[0049] Step 104: Obtain the processing flow of each production line, record the non-standard equipment required for each production line, and put the non-standard equipment required for the same production line into the associated set of the production line; in subsequent typesetting, the equipment on the same production line needs to be placed at a close distance;
[0050] When using, combine the contents in steps 101 to 104:
[0051] By integrating historical usage and maintenance data with real-time environmental data, a more accurate layout plan is provided for non-standard equipment. This method not only optimizes the equipment layout and improves production efficiency, but also lays the foundation for the layout of equipment running under more suitable environmental conditions, thereby extending the service life of the equipment and reducing maintenance costs. At the same time, by grouping equipment on the same production line into related sets, the consistency and efficiency of the production process are further improved.
[0052] Step 2: Based on the historical usage and maintenance data of each non-standard equipment, obtain the number of operations of each non-standard equipment , the duration of each run and the number of repairs or maintenance required ; Calculate the weights of the total operating time and the number of repairs or maintenance times according to the maximum and minimum values of the total operating time and the number of repairs or maintenance times of all non-standard equipment and ; Combine the total operation time and repair or maintenance times of each non-standard equipment with the corresponding weight to obtain the priority index of each non-standard equipment , all non-standard equipment according to the priority index The sizes are placed in the typesetting queue in order;
[0053] The step 2 includes the following steps:
[0054] Step 201: retrieve the usage and maintenance data of each non-standard device in a certain month from the data platform, including the number of times each non-standard device has been run in the past month. , the duration of each run and the number of repairs or maintenance required in Indicates Non-standard equipment, Indicates Non-standard equipment Run again.
[0055] Step 202: Calculate the weights of the total operation time and the number of repairs or maintenance times according to the maximum and minimum values of the total operation time and the number of repairs or maintenance times of all non-standard equipment. and , the expression is:
[0056] ;
[0057] Step 203: Combine the total operation time and the number of repairs or maintenance of each non-standard device with the corresponding weight to obtain the priority index of each non-standard device. , the expression is: ; The equipment with longer total operation time and the equipment with more repair or maintenance needs more priority in typesetting; therefore, when the priority index of a non-standard equipment The larger the value, the higher the layout priority of the device. All non-standard devices are placed in the layout queue in order of size.
[0058] When using, combine the contents in steps 201 to 203:
[0059] The priority index of each non-standard equipment is calculated based on its total operating time and the number of repairs or maintenance. The layout order is determined based on the priority index. The longer the total operating time of the equipment, the more critical the role it plays in the production process. Therefore, giving these equipment priority layout can ensure that they are optimized in spatial layout, easy to operate and maintain, thereby minimizing downtime. For equipment with a high number of repairs or maintenance, it means that these equipment may have a higher failure rate or require more frequent maintenance to maintain their performance. Prioritizing such equipment can make it easier to access and perform regular maintenance, which helps reduce unexpected downtime, improve equipment utilization, and reduce the cost and impact of emergency repairs.
[0060] Step 3: Take out non-standard devices from the layout queue in turn to determine the layout floor. Whenever a non-standard device in the layout queue determines the layout floor, take out several associated sets to which the non-standard device belongs, and calculate the average priority index of the remaining non-standard devices in each associated set; determine the layout floor in order of the average priority index;
[0061] The step three includes the following steps:
[0062] Step 301: Take the non-standard equipment ranked first from the layout queue to determine the layout floor; determine the floor according to the priority index. The larger the priority index, the lower the floor it needs to be placed on, so that workers can operate or repair the equipment more conveniently. Before preliminarily determining the floor where each non-standard equipment is located, it is necessary to determine whether the remaining load-bearing capacity and area of the floor are sufficient to place the equipment. If it is not sufficient to support the storage of a non-standard equipment, further floor selection is required, specifically:
[0063] Take out the non-standard equipment ranked first from the layout queue, and preliminarily layout it on the first layer of the BIM system to determine whether the remaining load-bearing capacity and area of the first layer are sufficient to place the equipment. When determining the remaining load-bearing capacity, compare the weight of the equipment with the remaining load-bearing capacity of the current floor; when determining the remaining area, it is necessary to combine the length, width and safety interval of the bottom of the equipment, specifically, the length plus the safety interval multiplied by the width plus the safety interval, and compare the result with the remaining area of the floor; if it is determined that the floor is sufficient to place the equipment, place the equipment on the corresponding floor; if it is determined that the floor is insufficient to place the equipment, place the equipment on the next floor, that is, the floor with the number of the floor plus one;
[0064] Step 302, when the non-standard device A in the layout queue determines the layout floor, several association sets to which the device belongs are screened out, and a group of association sets with the highest comprehensive priority index is selected by calculation, and the next non-standard device to be determined for the layout floor is selected from this group of association sets; specifically, the priority indexes of all non-standard devices in each layout set are averaged, and the result is used as the comprehensive priority index of each layout set; a group of association sets with the highest comprehensive priority index is screened out, and the layout floors of each non-standard device in the association set are selected in order from large to small according to the priority index; if it is determined that the current floor is not large enough to place the non-standard device B in the association set, the non-standard device with a priority index lower than that of the device in the same association set is given priority, and the non-standard device B is placed on the next floor of the floor; when all devices in an association set have selected the layout floor, this association set is removed from the association set of the non-standard device A (it is only removed when the floor is selected, and does not affect the storage of the association set), and step 302 is repeated;
[0065] Step 303: When all non-standard devices in all associated sets of non-standard device A have been selected for layout floors, these non-standard devices are deleted from the layout queue, and step 301 is repeated;
[0066] When using, combine the contents in steps 301 to 303:
[0067] Intelligent equipment layout is achieved by comprehensively considering factors such as equipment priority, size, weight, floor load-bearing capacity and area. This method not only improves layout efficiency and accuracy, but also ensures rational use of floor space and safe placement of equipment. By processing associated sets, the layout relationship between devices is optimized so that associated devices can be as close as possible to facilitate subsequent operation and maintenance management.
[0068] Step 4: Whenever a non-standard device confirms the layout floor, it will be matched with each environmental monitoring point on the corresponding floor for environmental adaptability, and the environmental difference value of the device at each environmental monitoring point will be generated. , according to the environmental difference Choose the most suitable layout position according to the size;
[0069] The step 4 includes the following steps:
[0070] Step 401: Whenever a non-standard device confirms a layout floor, its specific location on the floor needs to be determined, and all environmental monitoring points on the floor are used as candidate layout locations for the device; the most suitable operating environment data and the maximum tolerance environment data of the non-standard device are obtained, including the optimal temperature, humidity or light intensity when the device is operating, and the maximum and minimum tolerance temperature, humidity or light intensity when the device is operating;
[0071] Step 402: compare the maximum and minimum values of the three environmental data monitored at each environmental monitoring point, and compare them with the maximum and minimum environmental data of the current equipment to be typeset in turn. When the maximum value of the environmental data monitored at a certain environmental monitoring point is greater than the maximum environmental value of the equipment, or the minimum value of the environmental data monitored at a certain environmental monitoring point is less than the maximum environmental value of the equipment, then delete the environmental monitoring point from the equipment's to-be-selected typesetting position; if all environmental monitoring points have been deleted, then place the equipment on the next floor and repeat step 402; otherwise, proceed to step 403;
[0072] Step 403: Obtain the average temperature collected by the remaining environmental monitoring points , average humidity and the average light intensity , and combine it with the optimal environmental data of the equipment during operation to generate the environmental difference of the equipment at each environmental monitoring point , the expression is:
[0073] ;in, , , Represents the weight coefficients of temperature difference, humidity difference and light intensity difference respectively. The specific values are set by the administrator. ; , , are respectively the optimum temperature, humidity and light intensity for the operation of the device; Indicates Environmental monitoring points;
[0074] Select the environmental difference between the equipment and the remaining environmental monitoring points The minimum environmental monitoring point is used as the layout position of the equipment;
[0075] Step 404: After all non-standard equipment on a floor has been selected for layout positions, all equipment are fine-tuned using relevant tools in the BIM system so that there is at least one safe interval between each device and a main road can be generated to reach all non-standard equipment;
[0076] When used, combine the contents in steps 401 to 404:
[0077] By comprehensively considering environmental data and the environmental adaptability of equipment, accurate selection of layout positions for non-standard equipment is achieved; this method not only ensures that the equipment can operate in the most suitable environment and extend the service life of the equipment, but also optimizes the equipment layout and improves space utilization efficiency through intelligent environmental difference calculation; in addition, by using the fine-tuning tools of the BIM system, the main roads leading to all equipment can be planned while ensuring safe intervals between equipment, thereby enhancing the rationality and accessibility of the overall layout and providing great convenience for subsequent equipment maintenance and management; this digital layout method not only improves layout efficiency and accuracy, but also provides a solid guarantee for the overall operational efficiency and safety of the building.
[0078] refer to Figure 2 The present invention also provides a BIM-based non-standard equipment digital typesetting system, comprising:
[0079] Data acquisition and preprocessing module, which obtains the usage and maintenance data of each non-standard equipment from historical data, including the number of times each non-standard equipment has been run , the duration of each run and the number of repairs or maintenance required ; Set up several environmental monitoring points in the actual site, place an environmental sensor group at each environmental monitoring point and periodically collect environmental data around its location, including temperature, humidity and light intensity; obtain processing flow data of each production line;
[0080] The data analysis module calculates the average, maximum and minimum values of the three environmental data during the equipment operation time based on the environmental data collected within a month; and calculates the weights of the total operation time and the number of repairs or maintenance times based on the maximum and minimum values of the total operation time and the number of repairs or maintenance times of all non-standard equipment. and ; Combine the total operation time and repair or maintenance times of each non-standard equipment with the corresponding weight to obtain the priority index of each non-standard equipment ; Match the environmental adaptability of each non-standard device with each environmental monitoring point on the corresponding floor, and generate the environmental difference value of the device at each environmental monitoring point ;
[0081] The digital typesetting module includes a floor determination unit and a typesetting position determination unit; the floor determination unit selects non-standard equipment floors from low floors to high floors in turn, and determines whether the remaining load-bearing capacity and area of the floor are sufficient to place the equipment; whenever a non-standard equipment in the typesetting queue determines the typesetting floor, several associated sets to which the non-standard equipment belongs are taken out, and the average priority index of the remaining non-standard equipment in each associated set is calculated; the typesetting floors are determined in order of the average priority index; the typesetting position determination unit determines the typesetting floor according to the environmental difference. Select the most suitable layout position according to the size and fine-tune the layout position through the BIM system.
[0082] In the above embodiments, all or part of the embodiments may be implemented by software, hardware, firmware or any combination thereof. When implemented by software, all or part of the embodiments may be implemented in the form of a computer program product. The computer program product includes one or more computer instructions. When the computer program instructions are loaded and executed on a computer, all or part of the processes or functions described in the embodiments of the present invention are generated. The computer may be a general-purpose computer, a special-purpose computer, a computer network, or other programmable device. The computer instructions may be stored in a computer storage medium or transmitted via a computer storage medium.
[0083] Computer instructions can be transmitted from one website, computer, server or data center to another website, computer, server or data center by wired (e.g., coaxial cable, optical fiber, digital subscriber line (DSL)) or wireless (e.g., infrared, wireless, microwave, etc.) means. Computer storage media can be any available media that can be accessed by a computer or a data storage device such as a server or data center that includes one or more available media. Available media can be magnetic media (e.g., floppy disks, hard disks, tapes), optical media (e.g., DVDs), or semiconductor media (e.g., solid state drives (SSDs)).
[0084] The above is only a specific implementation of the present application, but the protection scope of the present application is not limited thereto. Any person skilled in the art who is familiar with the present technical field can easily think of changes or substitutions within the technical scope disclosed by the present invention, which should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.
Claims
1. A BIM-based digital typesetting method for non-standard equipment, characterized by: include: Obtain the usage and maintenance data of each non-standard equipment from historical data; set up several environmental monitoring points in the actual site, place an environmental sensor group at each environmental monitoring point and periodically collect environmental data around its location; perform pre-processing operations on the acquired and collected data; establish several associated sets, and put the non-standard equipment required in the same production line into the same associated set; According to the historical usage and maintenance data of each non-standard equipment, the operation times C of each non-standard equipment is obtained. 1i , the duration of each run T ij and the number of repairs or maintenance requiredC 2i ; Calculate the weights μ1 and μ2 of the total operation time and the number of repairs or maintenance times according to the maximum and minimum values of the total operation time and the number of repairs or maintenance times of all non-standard equipment; Combine the total operation time and the number of repairs or maintenance times of each non-standard equipment with the corresponding weight to obtain the priority index Yxj of each non-standard equipment i , all non-standard equipment according to the priority index Yxj i The sizes are placed in the typesetting queue in order; Non-standard devices are sequentially taken out from the layout queue to determine the layout floor. Whenever a non-standard device in the layout queue determines the layout floor, several associated sets to which the non-standard device belongs are taken out, and the average priority index of the remaining non-standard devices in each associated set is calculated; the layout floor is determined sequentially in the order of the average priority index; Whenever a non-standard device confirms the layout floor, it will be matched with each environmental monitoring point on the corresponding floor for environmental adaptability, and the environmental difference value De of the device at each environmental monitoring point will be generated. iz , according to the environmental difference De iz The size of the CSS file is used to select the most suitable layout position for placement, specifically: Whenever a non-standard device confirms the layout floor, it is necessary to determine the specific location of the device on the corresponding floor, and use all environmental monitoring points on the floor as candidate layout locations for the device; obtain the most suitable operating environment data and the maximum tolerance environment data of the non-standard device, including the optimal temperature, humidity or light intensity when the device is operating, and the maximum and minimum tolerance temperature, humidity or light intensity when the device is operating; Compare the maximum and minimum values of the three environmental data monitored at each environmental monitoring point, and compare them with the maximum and minimum environmental data of the current equipment to be typeset in turn. When the maximum value of the environmental data monitored at a certain environmental monitoring point is greater than the maximum environmental value of the equipment, or the minimum value of the environmental data monitored at a certain environmental monitoring point is less than the maximum environmental value of the equipment, then delete the environmental monitoring point from the equipment's candidate typesetting position; if all environmental monitoring points have been deleted, then the equipment needs to be placed on the next floor and the typesetting position needs to be re-determined; Get the average temperature collected by the remaining environmental monitoring points Average humidity and the average light intensity Combine it with the optimal environmental data of the equipment during operation to generate the environmental difference value De of the equipment at each environmental monitoring point iz , the expression is: Among them, α, β, and γ represent the weight coefficients of temperature difference, humidity difference, and light intensity difference, respectively. The specific values are set by the administrator, and α+β+γ=1; BTe i , BHu i BL i are respectively the optimal temperature, humidity and light intensity when the equipment is in operation; z represents the zth environmental monitoring point; Select the environmental difference De from the remaining environmental monitoring points with the equipment iz The minimum environmental monitoring point is used as the layout position of the equipment.
2. A BIM-based non-standard equipment digital typesetting method as claimed in claim 1, characterized in that: Obtain the corresponding usage data and maintenance data from the historical database of each non-standard equipment, and integrate the data into a unified data platform; Perform preprocessing operations on the acquired data, including the processing of missing values and outliers; use the data import function of the BIM software to match the integrated usage data and maintenance data with the non-standard equipment in the BIM model; obtain the processing flow of each production line, and record the non-standard equipment required for each production line, and put the non-standard equipment required in the same production line into the associated set of the production line.
3. A BIM-based non-standard equipment digital typesetting method as claimed in claim 2, characterized in that: The actual site of each layer is divided into several sub-areas using a grid, and several intersections in the grid are used as environmental monitoring points. An environmental sensor group is placed at each environmental monitoring point to collect the temperature, humidity and light intensity of each location; During the specified equipment operation time, the temperature, humidity and light intensity at each environmental monitoring point are collected in real time and transmitted to the BIM system; for each location, the BIM system calculates the average, maximum and minimum values of the three environmental data during the equipment operation time based on the environmental data collected within one month.
4. A BIM-based non-standard equipment digital typesetting method as claimed in claim 3, characterized in that: Extract the usage and maintenance data of each non-standard equipment in a certain month from the data platform, including the number of times each non-standard equipment has been run in the past month. 1i , the duration of each run T ij and the number of repairs or maintenance requiredC 2i ; The weights μ1 and μ2 of the total operating time and the number of repairs or maintenance are calculated based on the maximum and minimum values of the total operating time and the number of repairs or maintenance in all non-standard equipment. The expression is: Where i represents the i-th non-standard device, and ij represents the j-th operation of the i-th non-standard device.
5. A BIM-based non-standard equipment digital typesetting method as claimed in claim 4, characterized in that: The total operation time and the number of repairs or maintenance of each non-standard equipment are combined with the corresponding weight to obtain the priority index Yxj of each non-standard equipment. i , the expression is: When the priority index Yxj of a non-standard device i The larger the value, the higher the layout priority of the device. All non-standard devices are placed in the layout queue in order of size.
6. A BIM-based non-standard equipment digital typesetting method as claimed in claim 5, characterized in that: Take the non-standard equipment ranked first from the layout queue to determine the layout floor; determine the floor according to the priority index. The larger the priority index, the lower the floor it will be placed on. Before preliminarily determining the floor where each non-standard equipment is located, it is necessary to determine whether the remaining load-bearing capacity and area of the floor are sufficient to place the equipment. If it is not sufficient to support the storage of a non-standard equipment, further floor selection is required, specifically: Take out the non-standard equipment ranked first from the layout queue, and layout it preliminarily on the first layer of the BIM system. Determine whether the remaining load-bearing capacity and area of the first layer are sufficient to place the equipment. When determining the remaining load-bearing capacity, compare the weight of the equipment with the remaining load-bearing capacity of the current floor. When determining the remaining area, combine the length, width and safety interval of the bottom of the equipment, specifically, the length plus the safety interval multiplied by the width plus the safety interval, and compare the result with the remaining area of the floor. If it is determined that the floor is sufficient to place the equipment, place the equipment on the corresponding floor. If it is determined that the floor is not large enough to place the device, the device is placed on the next floor, that is, the floor with the floor number plus one.
7. A BIM-based non-standard equipment digital typesetting method as claimed in claim 6, characterized in that: When the non-standard device A in the layout queue determines the layout floor, several association sets to which the device belongs are screened out, and a group of association sets with the highest comprehensive priority index is selected by calculation. The next non-standard device to be determined for the layout floor is selected from this group of association sets; specifically, the priority indexes of all non-standard devices in each layout set are averaged, and the result is used as the comprehensive priority index of each layout set; a group of association sets with the highest comprehensive priority index is screened out, and the layout floors of each non-standard device in the association set are selected in order of priority index from large to small; If it is determined that the current floor is not large enough to place the non-standard device B in the associated set, the non-standard device with a lower priority index than the device in the same associated set is given priority, and the non-standard device B is placed on the next floor of the floor; when all devices in an associated set have been selected for layout floors, this associated set is removed from the associated set of non-standard device A, and the next group of associated sets is selected; When all non-standard devices in all associated sets of non-standard device A have selected the layout floor, these non-standard devices are deleted from the layout queue, and the layout floor of the next non-standard device in the layout queue is selected.
8. A BIM-based non-standard equipment digital typesetting method as claimed in claim 7, characterized in that: After all non-standard equipment on a floor has been selected for layout, all equipment is fine-tuned using the relevant tools in the BIM system so that there is at least a safe distance between each device and a main road can be generated to reach all non-standard equipment.
9. A BIM-based non-standard equipment digital typesetting system, characterized in that: include: The data acquisition and preprocessing module obtains the usage and maintenance data of each non-standard equipment from the historical data, including the number of operations of each non-standard equipment C 1i , the duration of each run T ij and the number of repairs or maintenance requiredC 2i ; Set up several environmental monitoring points in the actual site, place an environmental sensor group at each environmental monitoring point and periodically collect environmental data around its location, including temperature, humidity and light intensity; obtain processing flow data of each production line; The data analysis module calculates the average, maximum and minimum values of the three environmental data during the operation time of the equipment based on the environmental data collected within one month; calculates the weights μ1 and μ2 of the total operation time and the number of repairs or maintenance times of all non-standard equipment based on the maximum and minimum values of the total operation time and the number of repairs or maintenance times; combines the total operation time and the number of repairs or maintenance times of each non-standard equipment with the corresponding weight to obtain the priority index Yxj of each non-standard equipment i ; Match the environmental adaptability of each non-standard device with each environmental monitoring point on the corresponding floor, and generate the environmental difference value De of the device at each environmental monitoring point iz ; The digital typesetting module includes a floor determination unit and a typesetting position determination unit; the floor determination unit selects non-standard equipment floors from low floors to high floors in turn, and determines whether the remaining load-bearing capacity and area of the floor are sufficient for the placement of the equipment; whenever a non-standard equipment in the typesetting queue determines the typesetting floor, several associated sets to which the non-standard equipment belongs are taken out, and the average priority index of the remaining non-standard equipment in each associated set is calculated; the typesetting floors are determined in order of the size of the average priority index; the typesetting position determination unit determines the typesetting floor according to the environmental difference De iz Choose the most suitable layout position according to the size; Whenever a non-standard device confirms the layout floor, it is necessary to determine the specific location of the device on the corresponding floor, and use all environmental monitoring points on the floor as candidate layout locations for the device; obtain the most suitable operating environment data and the maximum tolerance environment data of the non-standard device, including the optimal temperature, humidity or light intensity when the device is operating, and the maximum and minimum tolerance temperature, humidity or light intensity when the device is operating; Compare the maximum and minimum values of the three environmental data monitored at each environmental monitoring point, and compare them with the maximum and minimum environmental data of the current equipment to be typeset in turn. When the maximum value of the environmental data monitored at a certain environmental monitoring point is greater than the maximum environmental value of the equipment, or the minimum value of the environmental data monitored at a certain environmental monitoring point is less than the maximum environmental value of the equipment, then delete the environmental monitoring point from the equipment's candidate typesetting position; if all environmental monitoring points have been deleted, then the equipment needs to be placed on the next floor and the typesetting position needs to be re-determined; Get the average temperature collected by the remaining environmental monitoring points Average humidity and the average light intensity Combine it with the optimal environmental data of the equipment during operation to generate the environmental difference value De of the equipment at each environmental monitoring point iz , the expression is: Among them, α, β, and γ represent the weight coefficients of temperature difference, humidity difference, and light intensity difference, respectively. The specific values are set by the administrator, and α+β+γ=1; BTe i , BHu i , BLi i are respectively the optimal temperature, humidity and light intensity when the equipment is in operation; z represents the zth environmental monitoring point; Select the environmental difference De from the remaining environmental monitoring points with the equipment iz The minimum environmental monitoring point is used as the layout position of the equipment.