Construction method suitable for exterior facade concrete line post-pouring

Through technical means such as laser measurement, intelligent batching and high temperature control, the precision, stability and aesthetics problems in the construction of traditional facade concrete lines have been solved, higher quality concrete line construction has been achieved, and the quality of the building has been improved. Cosmetic and structural safety.

CN118728026APending Publication Date: 2024-10-01CHINA CONSTR FOURTH ENG DIV CORP LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410795820.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-19
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

The traditional facade concrete line construction has problems such as inaccurate measurement and positioning, weak formwork installation, weak steel bar binding, uneven concrete pouring and rough surface treatment, which affects the aesthetics of the lines and structural safety.

Method used

Use laser levels and steel tape measures for precise measurement, use multi-layer boards or steel molds to install and reinforce the formwork, fix the formwork with support rods and diagonal braces, use fixed clamps to prevent steel bar displacement, and use intelligent batching systems and AI video monitoring The system ensures uniform distribution of concrete, performs high temperature control and sonic vibration, and uses nanotechnology and thermally sensitive color-changing paint for surface treatment.

Benefits of technology

It improves construction accuracy and structural stability, ensures the flatness and smoothness of lines, enhances waterproofness and aesthetics, extends service life, and improves the appearance and structural safety of the building.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118728026A_ABST
    Figure CN118728026A_ABST
Patent Text Reader

Abstract

The invention discloses a construction method suitable for exterior facade concrete line post-pouring, and relates to the technical field of building construction, and the construction method comprises the steps of S1, construction preparation and measurement positioning; s2, a formwork is installed; s3, reinforcing and supporting the formwork; s4, binding reinforcing steel bars; s5, concrete batching and stirring; s6, concrete pouring; s7, the formwork is removed; s8, maintenance is conducted; s9, quality detection; and S10, surface treatment. According to the construction method suitable for post-pouring of the outer vertical face concrete line, the laser gradienter and the steel tape are combined, and construction errors are reduced; rib plates are additionally arranged inside, and bolts and steel pipes are used for supporting and fixing, so that the strength and rigidity of the formwork are improved, straight lines are ensured, and slurry leakage is prevented; the fixing clamp is adopted to prevent displacement of the reinforcing steel bars, the structural stability and bearing capacity of the lines are guaranteed, and the surface flatness and smoothness are remarkably improved through multi-round grinding, fine repairing and high-quality coating treatment.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a construction method suitable for post-casting of facade concrete lines. Background Art

[0002] As a key element of architectural decoration, facade concrete lines can not only enrich the visual effect of the building, but also effectively enhance the aesthetic and cultural value of the building. The construction quality of facade concrete lines directly affects the overall appearance and structural performance of the building. The production and processing of concrete lines are very critical processes. Traditional concrete line construction methods usually have some technical limitations, such as inaccurate measurement and positioning, unstable formwork installation, uneven concrete pouring, rough surface treatment, etc. These problems may lead to unsightly lines and even affect the safety of the building structure. The shortcomings of the existing technology are:

[0003] The measurement and positioning are not accurate enough: Traditional methods rely on manual measurement and simple tools, which are prone to errors, resulting in line position deviations and affecting the accuracy of subsequent construction.

[0004] The formwork is not installed firmly: Common wooden formwork and simple steel formwork lack strength and rigidity, and are easily deformed during concrete pouring, resulting in uneven lines or leakage.

[0005] The steel bars are not tied firmly: The tying of steel bars often relies on the workers’ experience, and the steel bars may shift, which will affect the bearing capacity and structural stability of the lines.

[0006] Uneven concrete pouring: Traditional pouring technology makes it difficult to ensure uniform distribution of concrete in the formwork, which easily produces gaps and bubbles, affecting the density and strength of the lines.

[0007] Rough surface treatment: Manual smoothing and simple surface treatment methods make it difficult to achieve high standards of flatness and smoothness, affecting the beauty and durability of the lines. Summary of the invention

[0008] In view of the deficiencies in the prior art, the present invention provides a construction method suitable for post-casting of facade concrete lines to solve the problems raised in the above-mentioned background technology.

[0009] To achieve the above object, the present invention provides the following technical solution: a construction method suitable for post-casting of facade concrete lines, comprising the following steps:

[0010] S1. Construction preparation and measurement and positioning

[0011] According to the design drawings, determine the specific size, shape and position of the concrete lines, and use a laser level and steel tape measure to accurately measure the starting and ending points of the marked lines on the facade;

[0012] S2. Template installation

[0013] According to the size and shape of the lines, multi-layer boards or steel molds are used for pre-processing to ensure that the strength and rigidity of the formwork are sufficient to withstand the concrete pressure during pouring;

[0014] S3. Formwork reinforcement and support

[0015] After the formwork is installed, it is fixed with support rods and diagonal braces to ensure that the formwork will not move or deform during concrete pouring. Steel pipe scaffolding or horizontal tie rods are used to reinforce the formwork vertically and horizontally so that it can withstand the lateral pressure during concrete pouring;

[0016] S4. Steel bar binding

[0017] Determine the steel bar configuration within the line according to the design drawings, use φ8-φ12 mm steel bars for binding, and the spacing is determined to be 150-200 mm according to the line size and stress conditions. To prevent the steel bars from shifting, add fixing fixtures between the template and the steel bars;

[0018] S5. Concrete batching and mixing

[0019] The raw materials used for concrete include: cement, sand, gravel and water, and add an appropriate amount of water reducing agent, and mix them thoroughly in a mixer for 3-5 minutes until the concrete is uniform and thick;

[0020] S6. Concrete pouring

[0021] Use a pump truck or bucket to transport concrete to the top of the line template and pour it slowly. During the pouring process, use an inserted vibrator to vibrate to ensure that the concrete fills every corner of the template and expel bubbles. After the vibration is completed, use a trowel to smooth the surface to ensure the flatness and smoothness of the line;

[0022] S7, template removal

[0023] After the concrete reaches the initial hardening strength, that is, 24-48 hours after pouring, remove the formwork, first loosen the support rods and tie rods, and then gradually remove the formwork. When removing, maintain the integrity of the concrete lines and repair any defects on the surface;

[0024] S8. Maintenance

[0025] After the concrete lines are exposed to the air, they should be covered with plastic sheets or sprayed with curing agents in time, and watered at least three times a day for a curing period of 7-14 days to prevent cracks and insufficient strength of the lines;

[0026] S9. Quality Inspection

[0027] Use a tape measure to measure the width, height and thickness of the lines and compare them with the design drawings. Use a laser level to check the straightness and verticality of the lines. Use an ultrasonic detector to test the density and strength of the concrete. If there are deviations or defects, repair them in time.

[0028] S10, Surface treatment

[0029] After the quality inspection is completed and confirmed to be qualified, the concrete lines are surface treated, including grinding, filling and brushing protective coating.

[0030] To further optimize the technical solution, in step S2, the template installation further includes:

[0031] Select and make formwork materials: Use customized high-density polyethylene or fiberglass reinforced plastic formwork;

[0032] Use laser scanning to position the template: Before installation, use a laser scanner to accurately scan the wall to obtain detailed data of the wall, and use the data to fine-tune the template position to ensure that the template fits the wall perfectly;

[0033] Dynamic monitoring and adjustment: Install strain sensors at key positions of the template to monitor the displacement and deformation of the template during concrete pouring in real time, and adjust the template position immediately to ensure the accuracy of the template during the pouring process;

[0034] At the same time, construction workers wear augmented reality glasses, which display the precise location of the template and installation instructions. Through AR technology, construction workers can see the virtual location of the template in the actual site, so as to accurately place the template and reduce errors.

[0035] To further optimize the technical solution, in step S3, the lateral pressure is calculated according to the standard formula:

[0036] [P=0.22\t imes\gamma\t imes t]

[0037] Where P is the lateral pressure (kN / m 2 ), γ is the density of concrete (kN / m 3 ), t is the depth of concrete pouring (m);

[0038] At the same time, the rheometer is used to test the rheological properties of concrete before pouring. The rheological properties determine the fluidity, filling capacity and stability of concrete during pouring.

[0039] The formula model is used to evaluate the rheological properties of concrete, and the formula model is as follows:

[0040] [\tau=\tau_y+k\cdot\dot{\gamma}^n]

[0041] Where (\tau) represents the shear stress, (\tau_y) is the yield stress, (\dot{\gamma}) is the shear rate, and (k) and (n) are material-specific constants used to predict the flow behavior of concrete.

[0042] To further optimize the technical solution, in step S4, the steel bar binding also includes structural reinforcement and post-processing:

[0043] Use carbon fiber materials for reinforcement, apply carbon fiber reinforced polymer tapes or grids to improve the bending and shear resistance of the structure;

[0044] Introducing shape memory alloys as reinforcement materials. Shape memory alloys can restore their original shape under certain temperature or stress after deformation, and are used to improve the seismic resistance of structures.

[0045] Laser scanning and 3D modeling technology are used to accurately measure and analyze the actual state and stress conditions of the structure.

[0046] To further optimize the technical solution, the step S5 further includes:

[0047] Using intelligent batching system, sensors monitor the humidity and temperature of raw materials in real time, automatically adjust the ratio of cement, water and aggregate, and automatically select the best concrete mix according to the preset target performance;

[0048] During the mixing process, the temperature of the concrete is controlled by a cooling or heating system, and sonic vibration technology is applied, using sound waves of a specific frequency to improve the microstructure of the concrete.

[0049] To further optimize the technical solution, in step S6, when pouring concrete, it also includes:

[0050] The AI-based video monitoring system analyzes the pouring quality and uniformity of concrete in real time. Through monitoring data feedback, it automatically adjusts the pouring speed and the working status of the pump truck to ensure uniform distribution of concrete.

[0051] Circulate hot or cold water through pipes to control the temperature of concrete and keep it within a suitable temperature range to avoid affecting the initial and final setting time of concrete due to excessively high or low temperature;

[0052] At the same time, robots or automated equipment are used to replace manual operations to vibrate concrete, automatically adjusting the vibration depth and frequency to ensure that each area can achieve the ideal compaction effect while reducing labor intensity.

[0053] To further optimize the technical solution, in step S7, during the template removal process, the following steps are further included:

[0054] Use RFID tags or QR codes to mark and track templates, and record the usage status and location of each template in real time;

[0055] During the formwork removal process, vibration sensors are used to monitor the response of the concrete structure to ensure that the removal activities do not cause undesirable vibrations that affect the structural integrity of the concrete;

[0056] At the same time, the dismantled formwork and supporting materials are classified and recycled, and all metal parts and waste are reused or reprocessed through professional recycling channels.

[0057] To further optimize the technical solution, the step S8 further includes:

[0058] Based on automatic water spraying equipment and sensor networks, the maintenance environment is monitored and adjusted in real time, and the frequency and amount of water spraying are automatically adjusted according to actual environmental conditions;

[0059] Use self-cleaning photocatalyst plastic sheets to cover the concrete, which decomposes accumulated pollutants under the action of sunlight and reduces maintenance work during curing;

[0060] Use bio-based mulch materials made from biodegradable plant-based fibers that not only provide effective moisture retention properties but also break down naturally after use;

[0061] Implement a remote monitoring system that uses network cameras and sensors to monitor the maintenance site from a central control room. The system provides real-time data and alerts so that maintenance measures can be adjusted in a timely manner.

[0062] To further optimize the technical solution, in step S9, the detection content also includes:

[0063] Use a 3D laser scanner to scan the concrete lines, generate a 3D model, and compare it with the model in the design drawing to detect deviations in shape, size and verticality to ensure that the lines are in line with the design as a whole;

[0064] Use infrared thermal imaging cameras to detect the temperature distribution on the concrete surface, identify potential cracks or voids, and locate internal defects through temperature differences;

[0065] Use non-destructive sound wave reflection technology to detect the density and strength inside the concrete and determine whether there are voids or loose areas in the concrete.

[0066] To further optimize the technical solution, in step S10, the surface treatment further includes:

[0067] Coating materials using nanotechnology provide enhanced water resistance and anti-pollution capabilities;

[0068] Integrate LED light strips or light points during the surface treatment stage to add lighting functions to the concrete lines, which can glow at night and enhance the visual effect of the building;

[0069] Apply thermochromic paint to change color according to temperature changes;

[0070] Use 3D printing technology to create complex formwork for applying special patterns or textures to concrete surfaces.

[0071] Compared with the prior art, the present invention provides a construction method suitable for post-casting of facade concrete lines, which has the following beneficial effects:

[0072] 1. This construction method is suitable for post-casting of exterior concrete lines. It uses a combination of a laser level and a steel tape measure to reduce construction errors. Rigid plates are added inside and fixed with bolts and steel pipes to improve the strength and rigidity of the formwork, ensure that the lines are straight and prevent leakage. Fixed fixtures are used to prevent the displacement of steel bars to ensure the structural stability and bearing capacity of the lines. Through multiple rounds of grinding, fine repairs and high-quality paint treatment, the surface flatness and smoothness are significantly improved. Innovative means such as nanotechnology coatings and thermal induction color-changing paints are used to increase the waterproofness, stain resistance and aesthetics of the lines.

[0073] 2. This construction method, which is suitable for post-casting of facade concrete lines, has significantly improved accuracy, strength, stability and aesthetics, improved construction quality, reduced rework rate, extended the service life of concrete lines, and overall improved the structural safety and appearance of the building. BRIEF DESCRIPTION OF THE DRAWINGS

[0074] Figure 1 The present invention is a schematic flow chart of a construction method suitable for post-casting of facade concrete lines. DETAILED DESCRIPTION

[0075] The following will be combined with the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0076] Example:

[0077] See also Figure 1 , a construction method suitable for post-casting of facade concrete lines, comprising the following specific steps:

[0078] S1. Construction preparation and measurement positioning

[0079] According to the design drawings, determine the specific size, shape and position of the concrete lines. Use a laser level (accuracy: ±0.5 mm / 10 m) and a steel tape measure to accurately measure the starting and ending points of the marked lines on the facade. To ensure that the lines are level during construction, first mark control points every 1 m on the wall and connect these points with ink lines or laser lines as construction reference lines. This ensures that the subsequent template positioning is accurate.

[0080] S2. Template installation

[0081] According to the size and shape of the lines, multi-layer board or steel formwork is used for pre-processing to ensure that the strength and rigidity of the formwork are sufficient to withstand the concrete pressure during pouring. The multi-layer board formwork needs to be made of 15 mm thick plywood, while the steel formwork is welded with 4 mm thick steel plates and reinforced plates are added inside. When installing the formwork, bolts and connectors are used to fix it, and steel pipe supports are set on the outside to maintain the straightness of the formwork. It is necessary to ensure that the joints between the formworks are tight to prevent concrete leakage.

[0082] The template installation also includes:

[0083] Select and make formwork materials: Use customized high-density polyethylene or fiberglass reinforced plastic formwork;

[0084] Use laser scanning to position the template: Before installation, use a laser scanner to accurately scan the wall to obtain detailed data of the wall, and use the data to fine-tune the template position to ensure that the template fits the wall perfectly;

[0085] Dynamic monitoring and adjustment: Install strain sensors at key positions of the template to monitor the displacement and deformation of the template during concrete pouring in real time, and adjust the template position immediately to ensure the accuracy of the template during the pouring process;

[0086] At the same time, construction workers wear augmented reality glasses, which display the precise location of the template and installation instructions. Through AR technology, construction workers can see the virtual location of the template in the actual site, so as to accurately place the template and reduce errors.

[0087] S3. Formwork reinforcement and support

[0088] After the formwork is installed, it is fixed with support rods (diameter: 48 mm, wall thickness: 3 mm) and diagonal braces to ensure that the formwork will not move or deform during concrete pouring. Use steel pipe scaffolding or horizontal tie rods to reinforce the formwork vertically and horizontally so that it can withstand the lateral pressure during concrete pouring. Calculate the lateral pressure according to the standard formula:

[0089] [P=0.22\t imes\gamma\t imes t]

[0090] Where P is the lateral pressure (kN / m2 ), γ is the density of concrete (kN / m 3 ), t is the depth of pouring concrete (m).

[0091] At the same time, the rheometer is used to test the rheological properties of concrete before pouring. The rheological properties determine the fluidity, filling capacity and stability of concrete during pouring.

[0092] The formula model is used to evaluate the rheological properties of concrete, and the formula model is as follows:

[0093] [\tau=\tau_y+k\cdot\dot{\gamma}^n]

[0094] Where (\tau) represents the shear stress, (\tau_y) is the yield stress, (\dot{\gamma}) is the shear rate, and (k) and (n) are material-specific constants used to predict the flow behavior of concrete.

[0095] S4.Rebar Binding

[0096] According to the design drawings, the steel bar configuration within the line is determined. Usually, φ8-φ12 mm steel bars are used for binding. The spacing is determined according to the line size and stress conditions, generally 150-200 mm. To prevent the steel bar from shifting, a fixing fixture can be added between the template and the steel bar.

[0097] Among them, steel bar binding also includes structural reinforcement and post-processing:

[0098] Use carbon fiber materials for reinforcement, apply carbon fiber reinforced polymer tapes or grids to improve the bending and shear resistance of the structure;

[0099] Introducing shape memory alloys as reinforcement materials. Shape memory alloys can restore their original shape under certain temperature or stress after deformation, and are used to improve the seismic resistance of structures.

[0100] Laser scanning and 3D modeling technology are used to accurately measure and analyze the actual state and stress conditions of the structure.

[0101] S5. Concrete batching and mixing

[0102] The raw materials used in concrete include: cement, sand, gravel and water. Mix the ingredients according to the mix ratio, for example, use a ratio of 1:2:4 (i.e. 1 part cement, 2 parts sand and 4 parts gravel). Add an appropriate amount of water reducing agent to improve the fluidity of the concrete. Mix thoroughly in a mixer for 3-5 minutes until the concrete is uniform and thick.

[0103] Also includes:

[0104] Using intelligent batching system, sensors monitor the humidity and temperature of raw materials in real time, automatically adjust the ratio of cement, water and aggregate, and automatically select the best concrete mix according to the preset target performance;

[0105] During the mixing process, the temperature of the concrete is controlled by a cooling or heating system, and sonic vibration technology is applied, using sound waves of a specific frequency to improve the microstructure of the concrete.

[0106] S6. Concrete pouring

[0107] Use a pump truck or bucket to deliver concrete to the top of the line formwork and pour slowly. During the pouring process, use an inserted vibrator (frequency: 4000 times / minute) to vibrate to ensure that the concrete fills every corner of the formwork and removes bubbles. After the vibration is completed, use a trowel to smooth the surface to ensure the flatness and smoothness of the line.

[0108] Among them, when pouring concrete, it also includes:

[0109] The AI-based video monitoring system analyzes the pouring quality and uniformity of concrete in real time. Through monitoring data feedback, it automatically adjusts the pouring speed and the working status of the pump truck to ensure uniform distribution of concrete.

[0110] Circulate hot or cold water through pipes to control the temperature of concrete and keep it within a suitable temperature range to avoid affecting the initial and final setting time of concrete due to excessively high or low temperature;

[0111] At the same time, robots or automated equipment are used to replace manual operations to vibrate concrete, automatically adjusting the vibration depth and frequency to ensure that each area can achieve the ideal compaction effect while reducing labor intensity.

[0112] S7. Formwork removal

[0113] The formwork can be removed only after the concrete reaches the initial hardening strength (usually 24-48 hours after pouring). When removing, first loosen the support rods and tie rods, and then gradually remove the formwork. When removing, pay attention to maintaining the integrity of the concrete lines and repair any defects that may appear on the surface.

[0114] Among them, the process of template removal also includes:

[0115] Use RFID tags or QR codes to mark and track templates, and record the usage status and location of each template in real time;

[0116] During the formwork removal process, vibration sensors are used to monitor the response of the concrete structure to ensure that the removal activities do not cause undesirable vibrations that affect the structural integrity of the concrete;

[0117] At the same time, the dismantled formwork and supporting materials are classified and recycled, and all metal parts and waste are reused or reprocessed through professional recycling channels.

[0118] S8. Maintenance

[0119] After the concrete lines are exposed to the air, they need to be covered with plastic sheets or sprayed with curing agents in time to keep them moist. Water them at least three times a day, and the curing period is generally 7-14 days to prevent cracks and insufficient strength in the lines.

[0120] Among them, it also includes:

[0121] Based on automatic water spraying equipment and sensor networks, the maintenance environment is monitored and adjusted in real time, and the frequency and amount of water spraying are automatically adjusted according to actual environmental conditions;

[0122] Use self-cleaning photocatalyst plastic sheets to cover the concrete, which decomposes accumulated pollutants under the action of sunlight and reduces maintenance work during curing;

[0123] Use bio-based mulch materials made from biodegradable plant-based fibers that not only provide effective moisture retention properties but also break down naturally after use;

[0124] Implement a remote monitoring system that uses network cameras and sensors to monitor the maintenance site from a central control room. The system provides real-time data and alerts so that maintenance measures can be adjusted in a timely manner.

[0125] S9. Quality Inspection

[0126] Use a tape measure to measure the width, height and thickness of the lines and compare them with the design drawings. Use a laser level to check the straightness and verticality of the lines, and use an ultrasonic detector to test the density and strength of the concrete. If there are deviations or defects, they need to be repaired in time.

[0127] The testing contents also include:

[0128] Use a 3D laser scanner to scan the concrete lines, generate a 3D model, and compare it with the model in the design drawing to detect deviations in shape, size and verticality to ensure that the lines are in line with the design as a whole;

[0129] Use infrared thermal imaging cameras to detect the temperature distribution on the concrete surface, identify potential cracks or voids, and locate internal defects through temperature differences;

[0130] Use non-destructive sound wave reflection technology to detect the density and strength inside the concrete and determine whether there are voids or loose areas in the concrete.

[0131] S10. Surface treatment

[0132] After the quality inspection is completed and confirmed to be qualified, the concrete lines are surface treated, including grinding, filling and brushing protective coatings, etc. According to the design requirements, waterproofing agents can be applied or secondary decoration can be performed to improve the beauty and durability of the lines.

[0133] Among them, surface treatment also includes:

[0134] Coating materials using nanotechnology provide enhanced water resistance and anti-pollution capabilities;

[0135] Integrate LED light strips or light points during the surface treatment stage to add lighting functions to the concrete lines, which can glow at night and enhance the visual effect of the building;

[0136] Apply thermochromic paint to change color according to temperature changes;

[0137] Use 3D printing technology to create complex formwork for applying special patterns or textures to concrete surfaces.

[0138] The beneficial effects of the present invention are:

[0139] 1. This construction method is suitable for post-casting of exterior concrete lines. It uses a combination of a laser level and a steel tape measure to reduce construction errors. Rigid plates are added inside and fixed with bolts and steel pipes to improve the strength and rigidity of the formwork, ensure that the lines are straight and prevent leakage. Fixed fixtures are used to prevent the displacement of steel bars to ensure the structural stability and bearing capacity of the lines. Through multiple rounds of grinding, fine repairs and high-quality paint treatment, the surface flatness and smoothness are significantly improved. Innovative means such as nanotechnology coatings and thermal induction color-changing paints are used to increase the waterproofness, stain resistance and aesthetics of the lines.

[0140] 2. This construction method, which is suitable for post-casting of facade concrete lines, has significantly improved accuracy, strength, stability and aesthetics, improved construction quality, reduced rework rate, extended the service life of concrete lines, and overall improved the structural safety and appearance of the building.

[0141] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

[0142] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A construction method suitable for post-casting of facade concrete lines, characterized in that: The following steps are involved: S1. Construction preparation and measurement and positioning According to the design drawings, determine the specific size, shape and position of the concrete lines, and use a laser level and steel tape measure to accurately measure the starting and ending points of the marked lines on the facade; S2. Template installation According to the size and shape of the lines, multi-layer boards or steel molds are used for pre-processing to ensure that the strength and rigidity of the formwork are sufficient to withstand the concrete pressure during pouring; S3. Formwork reinforcement and support After the formwork is installed, it is fixed with support rods and diagonal braces to ensure that the formwork will not move or deform during concrete pouring. Steel pipe scaffolding or horizontal tie rods are used to reinforce the formwork vertically and horizontally so that it can withstand the lateral pressure during concrete pouring; S4. Steel bar binding Determine the steel bar configuration within the line according to the design drawings, use φ8-φ12 mm steel bars for binding, and the spacing is determined to be 150-200 mm according to the line size and stress conditions. To prevent the steel bars from shifting, add fixing fixtures between the template and the steel bars; S5. Concrete batching and mixing The raw materials used for concrete include: cement, sand, gravel and water, and add an appropriate amount of water reducing agent, and mix them thoroughly in a mixer for 3-5 minutes until the concrete is uniform and thick; S6. Concrete pouring Use a pump truck or bucket to transport concrete to the top of the line template and pour it slowly. During the pouring process, use an inserted vibrator to vibrate to ensure that the concrete fills every corner of the template and expel bubbles. After the vibration is completed, use a trowel to smooth the surface to ensure the flatness and smoothness of the line; S7, template removal After the concrete reaches the initial hardening strength, that is, 24-48 hours after pouring, remove the formwork, first loosen the support rods and tie rods, and then gradually remove the formwork. When removing, maintain the integrity of the concrete lines and repair any defects on the surface; S8. Maintenance After the concrete lines are exposed to the air, they should be covered with plastic sheets or sprayed with curing agents in time, and watered at least three times a day for a curing period of 7-14 days to prevent cracks and insufficient strength of the lines; S9. Quality Inspection Use a tape measure to measure the width, height and thickness of the lines and compare them with the design drawings. Use a laser level to check the straightness and verticality of the lines. Use an ultrasonic detector to test the density and strength of the concrete. If there are deviations or defects, repair them in time. S10, Surface treatment After the quality inspection is completed and confirmed to be qualified, the concrete lines are surface treated, including grinding, filling and brushing protective coating.

2. A construction method suitable for post-casting of facade concrete lines according to claim 1, characterized in that: In step S2, the template installation further includes: Select and make formwork materials: Use customized high-density polyethylene or fiberglass reinforced plastic formwork; Use laser scanning to position the template: Before installation, use a laser scanner to accurately scan the wall to obtain detailed data of the wall, and use the data to fine-tune the template position to ensure that the template fits the wall perfectly; Dynamic monitoring and adjustment: Install strain sensors at key positions of the template to monitor the displacement and deformation of the template during concrete pouring in real time, and adjust the template position immediately to ensure the accuracy of the template during the pouring process; At the same time, construction workers wear augmented reality glasses, which display the precise location of the template and installation instructions. Through AR technology, construction workers can see the virtual location of the template in the actual site, so as to accurately place the template and reduce errors.

3. A construction method suitable for post-casting of facade concrete lines according to claim 1, characterized in that: In step S3, the lateral pressure is calculated according to the standard formula: [P=0.22\times\gamma\times t] Where P is the lateral pressure (kN / m 2 ), γ is the density of concrete (kN / m 3 ), t is the depth of concrete pouring (m); At the same time, the rheometer is used to test the rheological properties of concrete before pouring. The rheological properties determine the fluidity, filling capacity and stability of concrete during pouring. The formula model is used to evaluate the rheological properties of concrete, and the formula model is as follows: [\tau=\tau_y+k\cdot\dot{\gamma}^n] Where (\tau) represents the shear stress, (\tau_y) is the yield stress, (\dot{\gamma}) is the shear rate, and (k) and (n) are material-specific constants used to predict the flow behavior of concrete.

4. A construction method suitable for post-casting of facade concrete lines according to claim 1, characterized in that: In step S4, the steel bar binding also includes structural reinforcement and post-processing: Use carbon fiber materials for reinforcement, apply carbon fiber reinforced polymer tapes or grids to improve the bending and shear resistance of the structure; Introducing shape memory alloys as reinforcement materials. Shape memory alloys can restore their original shape under certain temperature or stress after deformation, and are used to improve the seismic resistance of structures. Laser scanning and 3D modeling technology are used to accurately measure and analyze the actual state and stress conditions of the structure.

5. A construction method suitable for post-casting of facade concrete lines according to claim 1, characterized in that: The step S5 further includes: Using intelligent batching system, sensors monitor the humidity and temperature of raw materials in real time, automatically adjust the ratio of cement, water and aggregate, and automatically select the best concrete mix according to the preset target performance; During the mixing process, the temperature of the concrete is controlled by a cooling or heating system, and sonic vibration technology is applied, using sound waves of a specific frequency to improve the microstructure of the concrete.

6. A construction method suitable for post-casting of facade concrete lines according to claim 1, characterized in that: In the step S6, when pouring concrete, it also includes: The AI-based video monitoring system analyzes the pouring quality and uniformity of concrete in real time, and automatically adjusts the pouring speed and the working status of the pump truck through monitoring data feedback to ensure uniform distribution of concrete; Circulate hot or cold water through pipes to control the temperature of concrete and keep it within a suitable temperature range to avoid affecting the initial and final setting time of concrete due to excessively high or low temperature; At the same time, robots or automated equipment are used to replace manual operations to vibrate concrete, automatically adjusting the vibration depth and frequency to ensure that each area can achieve the ideal compaction effect while reducing labor intensity.

7. A construction method suitable for post-casting of facade concrete lines according to claim 1, characterized in that: In the step S7, during the template removal process, the following steps are also included: Use RFID tags or QR codes to mark and track templates, and record the usage status and location of each template in real time; During the formwork removal process, vibration sensors are used to monitor the response of the concrete structure to ensure that the removal activities do not cause undesirable vibrations that affect the structural integrity of the concrete; At the same time, the dismantled formwork and supporting materials are classified and recycled, and all metal parts and waste are reused or reprocessed through professional recycling channels.

8. A construction method suitable for post-casting of facade concrete lines according to claim 1, characterized in that: The step S8 further includes: Based on automatic water spraying equipment and sensor networks, the maintenance environment is monitored and adjusted in real time, and the frequency and amount of water spraying are automatically adjusted according to actual environmental conditions; Use self-cleaning photocatalyst plastic sheets to cover the concrete, which decomposes accumulated pollutants under the action of sunlight and reduces maintenance work during curing; Use bio-based mulch materials made from biodegradable plant-based fibers that not only provide effective moisture retention properties but also break down naturally after use; Implement a remote monitoring system that uses network cameras and sensors to monitor the maintenance site from a central control room. The system provides real-time data and alerts so that maintenance measures can be adjusted in a timely manner.

9. A construction method suitable for post-casting of facade concrete lines according to claim 1, characterized in that: In step S9, the detection content also includes: Use a 3D laser scanner to scan the concrete lines, generate a 3D model, and compare it with the model in the design drawing to detect deviations in shape, size and verticality to ensure that the lines are in line with the design as a whole; Use infrared thermal imaging cameras to detect the temperature distribution on the concrete surface, identify potential cracks or voids, and locate internal defects through temperature differences; Use non-destructive sound wave reflection technology to detect the density and strength inside the concrete and determine whether there are voids or loose areas in the concrete.

10. A construction method suitable for post-casting of facade concrete lines according to claim 1, characterized in that: In the step S10, the surface treatment further comprises: Coating materials using nanotechnology provide enhanced water resistance and anti-pollution capabilities; Integrate LED light strips or light points during the surface treatment stage to add lighting functions to the concrete lines, which can glow at night and enhance the visual effect of the building; Apply thermochromic paint to change color according to temperature changes; Use 3D printing technology to create complex formwork for applying special patterns or textures to concrete surfaces.