Cold storage polyurethane spraying thermal insulation construction method

Through scientific and reasonable construction process adjustment and step-by-step construction, the problems of complex, long-time and high-cost construction process of cold storage polyurethane spray insulation are solved, the construction efficiency and quality are improved, and the strong bonding and construction of polyurethane and the base layer are ensured. Security.

CN118728080APending Publication Date: 2024-10-01SHANDONG LUQIAO CONSTR
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410887224.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-03
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

The existing cold storage polyurethane spray insulation construction process is complex, time-consuming, high-cost and low-standardized, and lacks efficient and low-cost construction methods.

Method used

Adopt scientific and reasonable construction process adjustments, including pre-construction preparation, step-by-step construction of walls, ceilings, warehouse boards, buffer rooms and columns, etc., by spraying cyanide moisture-proof and vapor barrier layers, installing wooden keels, polyurethane spray insulation layers, Anti-crack mortar protective layer, inner color steel plate outer protection and other steps ensure the precise control and insertion of each process, improving construction efficiency and quality.

Benefits of technology

It has shortened construction time, reduced costs, improved project quality, reduced construction waste and repair costs, ensured strong bonding between polyurethane and the base layer, avoided foam shedding, and improved the uniformity and flatness of the sprayed surface. , enhancing the safety of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118728080A_ABST
    Figure CN118728080A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of polyurethane spraying, and particularly relates to a cold storage polyurethane spraying heat preservation construction method which comprises the steps of preparation before construction, wall surface construction, spraying of a cyanogen setting damp-proof vapor-proof layer, wood keel installation construction, polyurethane spraying heat preservation construction, anti-crack mortar protection layer construction and inner side color steel plate outer protection construction. Checking and accepting a wall surface base layer; checking the base surface of the ceiling; mounting a warehouse plate and a top plate; installing and constructing a buffer room; mounting and fixing the polyurethane sandwich panel positioning grooves; mounting and fixing the polyurethane sandwich panel; wall surface heat preservation construction; constructing a column insulating layer; compared with the prior art, the method has the advantages and positive effects that the conventional construction process flow is broken, the construction process is perfected on the basis of the existing operation through adjustment and interpenetration of working procedures, a relatively efficient and simple working mode is provided for the polyurethane spraying process, the construction cost is reduced, the engineering quality and the engineering progress are effectively controlled, and the construction efficiency is improved. The construction waste and repair cost is greatly reduced, and the effect is remarkable.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of polyurethane spraying, and in particular relates to a cold storage polyurethane spraying insulation construction method. Background Art

[0002] In recent years, with the continuous development of the construction industry, the emergence of cold storage spray polyurethane insulation technology has once again allowed people to see the advantages of new technology applications. The research and application of cold storage spray polyurethane insulation technology has broken the common problems of traditional building materials with single functions, waterproof but not thermal insulation, thermal insulation but not waterproof, and the insulation layer losing its thermal insulation function once the waterproof layer leaks. The cold storage spray polyurethane process has various functions such as good thermal insulation and waterproofing. The polyurethane rigid foam itself has good thermal insulation, waterproofing, sound insulation and vibration absorption functions.

[0003] Cold storage generally includes walls, ceilings, storage panels, top plates, buffer rooms and columns, and has a relatively complex structure. In addition, since the existing cold storage polyurethane spray insulation construction often has complicated procedures, long construction time, high construction costs and a low degree of construction process standardization, there is an urgent need for a cold storage polyurethane spray insulation construction method with short construction time, low construction cost and a high degree of construction process standardization. Summary of the invention

[0004] In view of the above problems, the present invention provides a cold storage polyurethane spraying insulation construction method.

[0005] In order to achieve the above object, the technical solution adopted by the present invention is: a cold storage polyurethane spray insulation construction method, comprising the following steps: Step 1: Preparation before construction, acceptance of the main project of cold storage; Step 2: Wall construction, spraying cyanocondensate moisture-proof and vapor-proof layer, wooden keel installation and construction, polyurethane spray insulation construction, anti-cracking mortar protective layer construction, inner color steel plate exterior protection construction; Step 3: Acceptance of wall base, inspection of flatness and verticality of construction surface; Step 4: Check the base surface of the ceiling and spray the polyurethane insulation layer in layers; Step 5: Installation of the warehouse and top plates, preparation work, on-site transportation, and injection of sealing paste; Step 6: Installation and construction of the buffer room, acceptance of the buffer room base, installation of galvanized plate positioning grooves at the lower end, installation of polyurethane sandwich panels, and installation of angle iron positioning grooves at the upper end; Step 7: Install and fix the positioning groove of the polyurethane sandwich panel; Step 8: Installation and fixation of polyurethane sandwich panels; Step 9: Wall insulation construction; Step 10: Construction of column insulation layer.

[0006] Preferably, step two includes preparing base materials, installing fire barrier strips, spraying cyanide moisture-proof and vapor barrier layer, installing T-shaped wooden keels with a spacing of 1200mm, spraying the first coat of polyurethane insulation layer, installing transverse wooden keels with a spacing of 1200mm, spraying the second coat of polyurethane insulation layer, spraying anti-cracking mortar to the designed thickness, installing inner color steel plates, and wrapping the corners.

[0007] Preferably, in step 2, before construction, a steel vertical control line is hung on the wall, prefabricated modules are installed, expansion bolts are installed on the top wall and the bottom wall, the expansion bolts are used as hanging points for the side wall hanging wires, and a tensioner is used to tighten the steel plumb lines installed at the inner and outer corners of the wall. The distance between the steel plumb line and the wall is the total thickness of the insulation layer. Before hanging the lines, the flatness of the wall is first checked with a ruler, and the verticality of the wall is checked with a wire support board. The elevation error of each layer is controlled within ±3mm, and the error of the overall vertical projection line is controlled within ±12mm. A fire barrier is installed on the expansion part of the wall, and the finished fire barrier is fixed to the wall with a nail gun. The spacing between the nails is not more than 35 cm, and there are no less than 3 nails on each side.

[0008] Preferably, before spraying the first layer of polyurethane insulation layer, the floating dust on the surface of the base layer of the sprayed polyurethane insulation layer is adsorbed by a vacuum cleaner and the humidity of the air is detected by a hygrometer, and the peak of the polyurethane rigid foam is controlled to be less than 5 mm.

[0009] As a preferred method, the preparation work in step 5 includes checking whether the warehouse board is damaged, removing foreign objects in the board grooves, smoothing the foam of uneven grooves, and removing 10 to 20 cm of plastic film around the edges of the inner and outer panels; The on-site transportation in step 5 includes the use of a crane for transportation. Two ropes should be tied to the two ends of the warehouse board during the transportation. The whole stack of warehouse boards should be moved horizontally during transportation. The polyurethane stacked on site should be padded with flat square wood strips or insulation foam. The polyurethane stacked on site should be kept away from fire sources. In the fifth step, the sealing paste injection includes first placing the warehouse board on its side, cutting the sealing paste tube opening with the convex edge on top, and screwing the injection nozzle on after cutting it into a small 45-degree incision. Then, they are loaded into the sealing paste injection gun together, and a layer of sealing paste is evenly injected into the convex groove of the warehouse board. Before each warehouse board is connected to other warehouse boards, sealing paste should be injected on both sides of the convex groove. During the installation process, it is necessary to ensure that the outer surfaces of each top plate are flush at both ends.

[0010] Preferably, nylon bolts are fixed at equal intervals to ensure that both ends of the outer surfaces of the top plates are flush during installation.

[0011] Preferably, step seven comprises: laying out the positioning grooves of the polyurethane sandwich panels before installation, fixing the positioning grooves of the polyurethane sandwich panels with galvanized expansion bolts, and the positioning grooves of the polyurethane sandwich panels are U-shaped positioning grooves.

[0012] Preferably, step eight comprises: the positioning grooves of the polyurethane sandwich panels at the upper and lower ends of the wall panel are spaced 300 mm apart, the upper opening of the U-shaped positioning groove is sealed with silicone, after being fixed, the protective film of the surface layer of the sandwich panel is torn off, and the tongue and groove are sealed with weather-resistant silicone, when the sandwich panels are butt-jointed, the male and female grooves of the sandwich panels should be applied with a single-component polyurethane caulking agent on both sides of the inner side of the concave and convex grooves in an S-shaped track before the panels are installed, and neutral silicone sealant is applied after the sandwich panels are installed.

[0013] Preferably, step nine includes: installing fire barrier strips, spraying cyanide coagulant, nailing in T-shaped wooden piles, spraying a first coat of polyurethane insulation layer in layers, nailing in transverse wooden keels, spraying a second coat of polyurethane insulation layer to the designed thickness, spraying anti-cracking mortar to the designed thickness, fixing the color steel plate with stainless steel dovetail wire, wrapping the corners, and acceptance.

[0014] Preferably, step ten includes: cleaning the base of the column insulation layer, spraying the cyanocondensation vapor barrier layer, and spraying in layers to achieve the design thickness requirement; The column insulation layer is sprayed with cyanogen condensation moisture-proof layer at the column foot, and then sprayed with polyurethane insulation layer, and multiple steel structure corner guards are set, and the steel structure corner guards are welded and connected to each other; The column insulation layer is sprayed with polyurethane insulation layer on the column head.

[0015] Compared with the prior art, the advantages and positive effects of the present invention are: (1) Break the conventional construction process, scientifically and reasonably arrange the interlaced nodes of each process, and improve the construction process on the basis of existing operations through adjustment and interlacing of the process, so as to provide a relatively efficient and simple working mode for the cold storage polyurethane spraying process, thereby ensuring the construction period, protecting the product, reducing the project cost, and improving the project quality. It provides a scientific construction basis and mature construction process standards for similar projects in the future, saves construction time, reduces construction costs, effectively controls the project quality and progress, and greatly reduces the cost of construction waste and rework, with significant results; (2) Before spraying the first coat of polyurethane insulation layer, the floating dust on the surface of the base layer where the polyurethane insulation layer is sprayed is absorbed by a vacuum cleaner, which can effectively remove the floating dust on the surface of the base layer, ensure the bonding strength of the bonding layer between the polyurethane and the base layer, make the polyurethane and the base layer have a strong bonding force, and improve the actual service life; (3) Before spraying the first coat of polyurethane insulation, the humidity of the air is detected by a hygrometer. By controlling the humidity, the dryness of the construction surface and the humidity of the air are guaranteed to meet the requirements, and the phenomenon of foam shedding is avoided, thereby greatly reducing the possibility of abnormal phenomena in the construction process of polyurethane rigid foam waterproof insulation, thus avoiding quality problems of the finished product; (4) The peak of the polyurethane rigid foam is controlled to be less than 5 mm, which avoids increasing the thickness of the polyurethane surface protective layer and causing increased costs, and improves the uniformity and flatness of the polyurethane spray surface; (5) Spray the first coat of polyurethane insulation layer, install the horizontal wooden keel, and then spray the second coat of polyurethane insulation layer. The thickness of the two coats of polyurethane insulation layer reaches the design requirements. Compared with spraying once to achieve the design requirements, the spraying thickness is more appropriate, avoiding the difficulty in controlling the flatness of the spraying surface due to the spraying thickness being too thick, reducing the difficulty of operation and improving the spraying quality; (6) Install fire barrier strips on the expansion part of the wall and fix the finished fire barrier strips on the wall with a nail gun. The fire barrier strips can play a fire-proof and fire-blocking role, greatly improving safety. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] In order to more clearly illustrate the technical solution of the embodiment of the present invention, the following is a brief introduction to the drawings required for describing the embodiment: Figure 1 This is a flow chart of the construction method of polyurethane spray insulation for cold storage. DETAILED DESCRIPTION

[0017] In order to more clearly understand the above-mentioned objects, features and advantages of the present invention, the present invention is further described below with reference to the accompanying drawings and embodiments.

[0018] In the following description, many specific details are set forth to facilitate a full understanding of the present invention. However, the present invention may also be implemented in other ways than those described herein. Therefore, the present invention is not limited to the specific embodiments of the following disclosure.

[0019] Example 1 Combine the following Figure 1 Specifically explain the cold storage polyurethane spray insulation construction method, such as Figure 1 As shown, a cold storage polyurethane spray insulation construction method comprises the following steps: Step 1: Preparation before construction, acceptance of the main project of cold storage; Step 2: Wall construction, spraying cyanocondensate moisture-proof and vapor-proof layer, wooden keel installation and construction, polyurethane spray insulation construction, anti-cracking mortar protective layer construction, inner color steel plate exterior protection construction; Step 3: Acceptance of wall base, check the flatness and verticality of the construction surface, the maximum deviation of the flatness and verticality of the construction surface is no more than 5mm; Step 4: Check the base surface of the ceiling and spray the polyurethane insulation layer in layers; Step 5: Installation of the warehouse and top plates, preparation work, on-site transportation, and injection of sealing paste; Step 6: Installation and construction of the buffer room, acceptance of the buffer room base, installation of galvanized plate positioning grooves at the lower end, installation of polyurethane sandwich panels, and installation of angle iron positioning grooves at the upper end; Step 7: Install and fix the positioning groove of the polyurethane sandwich panel; Step 8: Installation and fixation of polyurethane sandwich panels; Step 9: Wall insulation construction; Step 10: Construction of column insulation layer.

[0020] Step two includes preparation of base materials, installation of fire barrier strips, spraying of cyanide moisture-proof and vapor barrier layer, installation of T-shaped wooden keels with a spacing of 1200mm, spraying of the first coat of polyurethane insulation layer, installation of transverse wooden keels with a spacing of 1200mm, spraying of the second coat of polyurethane insulation layer, spraying of anti-cracking mortar to the designed thickness, installation of inner color steel plates, and corner wrapping.

[0021] Step 2 Before construction, hang a steel vertical control line on the wall, install prefabricated modules, install expansion bolts on the top and bottom walls, use the expansion bolts as the hanging points for the side wall hanging wires, use a wire tensioner to tighten the steel plumb lines installed at the inner and outer corners of the wall, and the distance between the steel plumb lines and the wall is the total thickness of the insulation layer; before hanging the lines, first use a ruler to check the flatness of the wall, and use a wire support board to check the verticality of the wall. The elevation error of each layer is controlled within ±3mm, and the overall vertical projection line error is controlled within ±12mm. Install a fire barrier strip on the expansion part of the wall, and fix the finished fire barrier strip on the wall with a nail gun. The spacing between the nails is not more than 35 cm, and there are no less than 3 nails on each side.

[0022] In step one, the main wall acceptance meets the requirements of the "Uniform Standard for Inspection of Construction Project Quality", the plastering leveling layer reaches 75% of the strength and is dry; expansion bolts are installed under the top wall and the bottom wall.

[0023] Before spraying the first coat of polyurethane thermal insulation layer, the floating dust on the surface of the base layer of the sprayed polyurethane thermal insulation layer is absorbed by a vacuum cleaner and the humidity of the air is detected by a hygrometer. The peak of the polyurethane rigid foam is controlled to be less than 5 mm.

[0024] When dry and free of floating dust, the bonding layer between the polyurethane and the base layer can exceed the strength of the polyurethane body. However, in the actual construction process, there will be a certain amount of floating dust in the base layer. The polyurethane rigid foam reacts quickly and does not have much time to further penetrate into the base layer. Therefore, the presence of floating dust will affect the bonding strength. Before spraying the first coat of polyurethane insulation layer, the floating dust on the surface of the base layer where the polyurethane insulation layer is sprayed is adsorbed by a vacuum cleaner, which can effectively remove the floating dust on the surface of the base layer, ensure the bonding strength of the bonding layer between the polyurethane and the base layer, make the polyurethane and the base layer have a strong bonding force, and improve the actual service life.

[0025] The phenomenon of foam shedding refers to the phenomenon that after the foam is sprayed, during the curing process, the foam will automatically or with a little external force fall off from the surface of the object being constructed. The bottom layer is crispy and powdery when observed with the naked eye. The following measures are generally taken to overcome and solve the phenomenon of foam shedding: control the humidity of the foaming material and the air; increase the dryness of the construction surface; increase the toughness of the foam; increase the amount of catalyst to promote rapid reaction and strengthen the gelation and aggregation reaction. By using a hygrometer to detect the humidity of the air before spraying the first coat of polyurethane insulation layer, the humidity of the air is guaranteed to meet the regulations by controlling the humidity, avoiding the phenomenon of foam shedding and ultimately avoiding quality problems of the finished product.

[0026] The preparation work in step five includes checking whether the warehouse board is damaged, removing foreign objects in the board groove, smoothing the uneven foam in the concave and convex grooves, and removing 10 to 20 centimeters of plastic film around the edges of the inner and outer panels; the on-site transportation in step five includes using a crane for transportation. When the crane is used for transportation, two ropes should be tied to the two ends of the warehouse board. The whole stack of warehouse boards should be moved horizontally during transportation. The polyurethane stacked on site is padded with flat square wooden strips or insulation foam. The polyurethane stacked on site should be kept away from fire sources; the injection of sealant in step five includes first standing the warehouse board on its side with the convex edge on top, cutting the sealant tube mouth, cutting the injection nozzle into a small 45-degree incision and screwing it on, and then loading them together into the sealant injection gun, and evenly injecting a layer of sealant into the convex groove of the warehouse board. Before each warehouse board is connected to other warehouse boards, the sealant should be injected on both sides of the convex groove. During the installation process, ensure that the outer surfaces of each top plate are flush at both ends.

[0027] Nylon bolts are fixed at equal intervals to ensure that both ends of the outer surface of each top plate are flush during installation.

[0028] Step seven includes: laying out the positioning grooves of the polyurethane sandwich panels before installation, fixing the positioning grooves of the polyurethane sandwich panels with galvanized expansion bolts, and the positioning grooves of the polyurethane sandwich panels are U-shaped positioning grooves.

[0029] Step eight includes: the spacing between the wall panel and the upper and lower polyurethane sandwich panel positioning grooves is 300mm, the upper mouth of the U-shaped positioning groove is sealed with silicone, and after fixing, the protective film of the sandwich panel surface is torn off, and the tongue and groove are sealed with weather-resistant silicone. When the sandwich panels are butt-jointed, the male and female grooves of the sandwich panels must be filled with single-component polyurethane caulking agent on both sides of the inner side of the concave and convex grooves in an S-shaped track before installing the panels. After the sandwich panels are installed, apply neutral silicone sealant.

[0030] Step nine includes: installing fire barrier strips, spraying cyanide, nailing in T-shaped wooden piles, spraying the first coat of polyurethane insulation layer in layers, nailing in transverse wooden keels, spraying the second coat of polyurethane insulation layer to the designed thickness, spraying anti-cracking mortar to the designed thickness, fixing the color steel plate with stainless steel dovetail wire, wrapping the corners, and acceptance.

[0031] Step ten includes: cleaning the base layer of the column insulation layer, spraying the cyanocondensate vapor barrier layer, and spraying in layers to achieve the design thickness requirement; spraying the cyanocondensate moisture-proof layer at the base of the column insulation layer, and then spraying the polyurethane insulation layer, setting up multiple steel structure corner guards, and welding the steel structure corner guards to each other; spraying the polyurethane insulation layer on the top of the column insulation layer.

[0032] The above description is only a preferred embodiment of the present invention and does not limit the present invention in other forms. Any technician familiar with the profession may use the technical content disclosed above to change or modify it into an equivalent embodiment with equivalent changes for application in other fields. However, any simple modification or equivalent change made to the above embodiment based on the technical essence of the present invention without departing from the content of the technical solution of the present invention still falls within the protection scope of the technical solution of the present invention.

Claims

1. A cold storage polyurethane spray insulation construction method, characterized in that: The following steps are involved: Step 1: Preparation before construction, acceptance of the main project of cold storage; Step 2: Wall construction, spraying cyanocondensate moisture-proof and vapor-proof layer, wooden keel installation and construction, polyurethane spray insulation construction, anti-cracking mortar protective layer construction, inner color steel plate exterior protection construction; Step 3: Acceptance of wall base, inspection of flatness and verticality of construction surface; Step 4: Check the base surface of the ceiling and spray the polyurethane insulation layer in layers; Step 5: Installation of the warehouse and top plates, preparation work, on-site transportation, and injection of sealing paste; Step 6: Installation and construction of the buffer room, acceptance of the buffer room base, installation of galvanized plate positioning grooves at the lower end, installation of polyurethane sandwich panels, and installation of angle iron positioning grooves at the upper end; Step 7: Install and fix the positioning groove of the polyurethane sandwich panel; Step 8: Installation and fixation of polyurethane sandwich panels; Step 9: Wall insulation construction; Step 10: Construction of column insulation layer.

2. A cold storage polyurethane spray insulation construction method according to claim 1, characterized in that: Step two includes preparation of base materials, installation of fire barrier strips, spraying of cyanide moisture-proof and vapor barrier layer, installation of T-shaped wooden keels with a spacing of 1200mm, spraying of the first coat of polyurethane insulation layer, installation of transverse wooden keels with a spacing of 1200mm, spraying of the second coat of polyurethane insulation layer, spraying of anti-cracking mortar to the designed thickness, installation of inner color steel plates, and corner wrapping.

3. A cold storage polyurethane spray insulation construction method according to claim 2, characterized in that: Step 2: Before construction, hang a steel vertical control line on the wall, install prefabricated modules, install expansion bolts on the top wall and the bottom wall, use the expansion bolts as the hanging points for the side wall hanging wires, and use a wire tensioner to tighten the steel plumb lines installed at the inner and outer corners of the wall. The distance between the steel plumb line and the wall is the total thickness of the insulation layer. Before hanging the wire, first use a ruler to check the flatness of the wall, and use a wire support board to check the verticality of the wall. The elevation error of each layer is controlled within ±3mm, and the overall vertical projection line error is controlled within ±12mm. Install a fire barrier strip on the expansion part of the wall, and fix the finished fire barrier strip on the wall with a nail gun. The spacing between the nails is not more than 35 cm, and there are no less than 3 nails on each side.

4. A cold storage polyurethane spray insulation construction method according to claim 2, characterized in that: Before spraying the first coat of polyurethane thermal insulation layer, the floating dust on the surface of the base layer of the sprayed polyurethane thermal insulation layer is absorbed by a vacuum cleaner and the humidity of the air is detected by a hygrometer. The peak of the polyurethane rigid foam is controlled to be less than 5 mm.

5. A cold storage polyurethane spray insulation construction method according to claim 1, characterized in that: The preparation work in step 5 includes checking whether the warehouse board is damaged, removing foreign objects in the board grooves, smoothing the foam of uneven grooves, and removing 10 to 20 cm of plastic film around the edges of the inner and outer panels; The on-site transportation in step 5 includes the use of a crane for transportation. Two ropes should be tied to the two ends of the warehouse board during the transportation. The whole stack of warehouse boards should be moved horizontally during transportation. The polyurethane stacked on site should be padded with flat square wood strips or insulation foam. The polyurethane stacked on site should be kept away from fire sources. In the fifth step, the sealing paste injection includes first placing the warehouse board on its side, cutting the sealing paste tube opening with the convex edge on top, and screwing the injection nozzle on after cutting it into a small 45-degree incision. Then, they are loaded into the sealing paste injection gun together, and a layer of sealing paste is evenly injected into the convex groove of the warehouse board. Before each warehouse board is connected to other warehouse boards, sealing paste should be injected on both sides of the convex groove. During the installation process, it is necessary to ensure that the outer surfaces of each top plate are flush at both ends.

6. A cold storage polyurethane spray insulation construction method according to claim 5, characterized in that: Nylon bolts are fixed at equal intervals to ensure that both ends of the outer surface of each top plate are flush during installation.

7. A cold storage polyurethane spray insulation construction method according to claim 1, characterized in that: Step seven includes: laying out the positioning grooves of the polyurethane sandwich panels before installation, fixing the positioning grooves of the polyurethane sandwich panels with galvanized expansion bolts, and the positioning grooves of the polyurethane sandwich panels are U-shaped positioning grooves.

8. A cold storage polyurethane spray insulation construction method according to claim 7, characterized in that: Step eight includes: the spacing between the wall panel and the upper and lower polyurethane sandwich panel positioning grooves is 300mm, the upper mouth of the U-shaped positioning groove is sealed with silicone, and after fixing, the protective film of the sandwich panel surface is torn off, and the tongue and groove are sealed with weather-resistant silicone. When the sandwich panels are butt-jointed, the male and female grooves of the sandwich panels must be filled with single-component polyurethane caulking agent on both sides of the inner side of the concave and convex grooves in an S-shaped track before installing the panels. After the sandwich panels are installed, apply neutral silicone sealant.

9. A cold storage polyurethane spray insulation construction method according to claim 1, characterized in that: Step nine includes: installing fire barrier strips, spraying cyanide, nailing in T-shaped wooden piles, spraying the first coat of polyurethane insulation layer in layers, nailing in transverse wooden keels, spraying the second coat of polyurethane insulation layer to the designed thickness, spraying anti-cracking mortar to the designed thickness, fixing the color steel plate with stainless steel dovetail wire, wrapping the corners, and acceptance.

10. A cold storage polyurethane spray insulation construction method according to claim 1, characterized in that: Step 10 includes: cleaning the base of the column insulation layer, spraying the cyanocondensate vapor barrier layer, and spraying in layers to achieve the design thickness requirements; The column base of the column insulation layer is sprayed with a cyanogen condensation moisture-proof layer, and then a polyurethane insulation layer is sprayed, and multiple steel structure corner guards are set, and the steel structure corner guards are welded to each other; The column insulation layer is sprayed with polyurethane insulation layer on the column head.