Swivel bridge guardrail steel formwork reinforcing and leveling system and construction method
By using the combined design of lower pull bolts, upper pull bolts, leveling rods and tie rod components in the steel formwork of the swivel bridge guardrail, the problem of displacement of the formwork under concrete pressure is solved, and the stable positioning and construction quality of the formwork are achieved. improvement.
Patent Information
- Application Number
- CN202410983687.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-22
- Publication Date
- 2024-10-15
AI Technical Summary
During the construction process of the steel formwork for the guardrail of the swivel bridge, due to the suspended state of the outer formwork, it is easy to cause displacement due to concrete pressure and vibration force, causing the inner and outer formwork to be misformed, affecting the construction quality. The existing diagonal braces are unstable and difficult to effectively adjust.
The lower pull bolts, upper pull bolts, leveling rods, tie rod components and U-shaped gap design between the inner and outer formwork are used to achieve bidirectional positioning and leveling of the formwork through the telescopic rod assembly and tie rod assembly to ensure the stability of the formwork. , and adjust the displacement of the outer formwork through the leveling rod and tie rod assembly.
It improves the installation strength of the inner formwork and the stability of the outer formwork, promptly corrects the displacement and misforming of the outer formwork during the pouring process, improves the construction quality of the guardrail, and avoids rework and re-pouring.
Smart Images

Figure CN118774030A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of rotating bridge construction, and in particular to a rotating bridge guardrail steel formwork reinforcement and leveling system and a construction method. Background Art
[0002] After the pavement structure construction of the rotating bridge is completed, in order to ensure the safety performance of vehicles during passage, guardrail structures will be set up on both sides and in the middle area of the rotating bridge. This type of guardrail structure consists of a concrete base and a metal guardrail on the top. There are two existing construction methods for the concrete base. One is to cast it simultaneously with the pavement structure, and the other is to cast the guardrail on the surface of the pavement after the basic construction of the pavement structure is completed. The former has higher technical difficulty in formwork support and casting, so the latter construction method is usually chosen at present.
[0003] The main body of the rotating bridge is usually large in height, so the strength requirements of the guardrail are relatively high, and there are also quite strict requirements and specifications for the construction process of the concrete guardrail. At present, a steel formwork system is usually used to set up the edge of the bridge body for secondary pouring construction. During the construction process, the inner formwork needs to be vertically fixed on the plane of the bridge body. At present, it is mainly supported by diagonal braces, which are not very stable and have limited strength to support the outer formwork. In addition, during the pouring of concrete into the mold cavity formed between the inner and outer formworks, vibration operations are required. The bottom surface of the outer formwork is suspended. The pressure of the concrete and the vibration force will cause the outer formwork to move downward, resulting in the misalignment of the inner and outer formworks, affecting the quality of the guardrail pouring construction. In serious cases, rework and re-pouring are required. Summary of the invention
[0004] In order to solve the above problems, the present invention proposes a rotating bridge guardrail steel formwork reinforcement and leveling system and a construction method.
[0005] The technical solution of the present invention is: a reinforcement and leveling system for the steel formwork of a rotating bridge guardrail, comprising an inner formwork and an outer formwork arranged vertically on the side edge of the rotating bridge, a plurality of lower tension bolts are arranged at equal intervals between the bottoms of the inner formwork and the outer formwork, a plurality of supports are arranged at equal intervals on the upper end surfaces of the inner formwork and the outer formwork, a U-shaped notch is arranged in the middle of the support, and upper tension bolts are installed between the U-shaped notches of the inner and outer supports; a plurality of telescopic rod assemblies are arranged at equal intervals at the transverse back ribs of the bridge body, and the lower ends of the telescopic rod assemblies are pressed against the U-shaped embedded parts on the bridge body; a leveling rod is arranged between the upper ends of the outer formwork and the inner formwork, the outer end of the leveling rod is inserted into the upper U-shaped buckle arranged on the upper part of the outer formwork, the middle part of the leveling rod is supported on the edge of the inner formwork, and a lower U-shaped buckle is arranged at the bottom of the inner formwork, and a pull rod assembly A is connected between the lower U-shaped buckle and the hook at the outer end of the leveling rod.
[0006] Preferably, channel-shaped vertical back ribs are provided between the transverse back ribs on the outer side surface of the inner formwork, and a pull rod assembly B is connected between the upper end of the vertical back ribs and the U-shaped embedded part on the bridge body.
[0007] Preferably, the end of the lower tension bolt passes through the vertical back rib, and a square gasket is provided between the nut of the lower tension bolt and the vertical back rib, and a square gasket is also provided between the nut at the outer end of the upper tension bolt and the support.
[0008] Preferably, a row of limiting vertical ribs are provided at the edge of the bridge body, and the outer side surface of the bottom of the inner template is supported on the limiting vertical ribs.
[0009] Preferably, a wooden pad is provided between the bottom surface of the inner formwork and the surface of the bridge body.
[0010] Preferably, arc-shaped notches are provided at the end faces of the inner template and the outer template, and the two arc-shaped notches correspond to each other to form an oblong hole.
[0011] Preferably, a pad is provided at the upper end surface of the inner template, and the leveling rod is supported on the pad.
[0012] A construction method for reinforcing and leveling a rotating bridge guardrail steel formwork system comprises the following steps: ⑴ The inner formwork is hoisted and placed on the edge of the bridge body. The outer side of the bottom of the inner formwork is supported on the vertical reinforcement. Then the hook at the lower end of the tie rod assembly B is hooked to the U-shaped embedded part on the bridge body, and the hook at the upper end is hooked into the upper port of the vertical back rib. (2) Place the lower end of the telescopic rod assembly against the U-shaped embedded part on the bridge body, and support the upper end on the bottom surface of the transverse back rib of the inner template. Then alternately adjust the telescopic length of the telescopic rod assembly and the pulling length of the pull rod assembly B to fix the inner template to a vertical state; ⑶ Lift the outer template and place it on the outer side of the inner template. Install the lower tension bolts between the bottoms of the two and tighten them. Then install the upper tension bolts between the supports at the upper ends of the two and tighten them. The inner and outer templates are initially fixed. (4) During the process of pouring concrete into the mold cavity formed between the inner and outer molds and vibrating, the outer mold will move downward due to the pressure of the concrete and the vibration force, resulting in mold misalignment, and the pouring construction will be stopped; (5) Tighten the tie rod assembly A. The upper end of the tie rod assembly A pulls down the inner end of the leveling rod. The outer end of the leveling rod is lifted upward under the action of the lever, and the outer template is lifted upward through the upper U-shaped buckle until the upper end surfaces of the two are in a flush state; ⑹ Tighten the nuts at the ends of the upper tension bolts and the lower tension bolts again to tighten and secure the inner and outer formwork for the second time.
[0013] Preferably, after a section of bridge guardrail is cast, the formwork is removed, and then the construction work of the next section of steel formwork reinforcement and leveling system is carried out according to steps ⑴-⑹.
[0014] The beneficial technical effects of the present invention are: ① The present invention adopts a wooden pad to increase the friction between the inner formwork and the surface of the bridge body, provides lateral limitation for the bottom of the inner formwork by setting vertical ribs, and simultaneously adopts telescopic rods to push and pull the upper part of the inner formwork to perform bidirectional positioning. These combined measures can effectively improve the installation strength of the inner formwork on the bridge body, provide stable and strong support for the outer formwork, and improve the installation quality of the formwork.
[0015] ② The present invention forms a leveling system through the leveling rod, the pull rod assembly and the upper and lower U-shaped buckles on the template, which can timely and effectively adjust and correct the displacement and misalignment of the outer template during the casting construction process, improve the casting construction quality of the guardrail, and avoid rework and re-casting. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is one of the three-dimensional structural schematic diagrams of the present invention; Figure 2 yes Figure 1 A partial enlarged view of Figure 3 The second schematic diagram of the three-dimensional structure of the present invention; Figure 4 yes Figure 3 A partial enlarged view of Figure 5 yes Figure 3 AA section structural diagram; Figure 6 It is a three-dimensional structural schematic diagram of the inner template; Figure 7 It is the on-site construction drawing of the present invention.
[0017] In the figure, 11. inner formwork, 111. lower U-shaped buckle, 12. outer formwork, 121. inner part of upper U-shaped buckle, 13. support, 131. U-shaped notch, 141. upper tension bolt, 142. lower tension bolt, 143. square gasket, 15. bridge body, 151. U-shaped embedded parts, 152. limiting vertical reinforcement, 153. wooden pad, 16. telescopic rod assembly, 17. tie rod assembly B, 181. leveling rod, 182. tie rod assembly A, 183. pad, 191. vertical back rib, 192. horizontal back rib. DETAILED DESCRIPTION
[0018] Example 1, see the attached specification Figure 1-6A steel formwork reinforcement and leveling system for a rotating bridge guardrail includes an inner formwork 11 and an outer formwork 12 vertically arranged on the side of the rotating bridge, a plurality of lower tension bolts 142 are evenly spaced between the bottoms of the inner formwork and the outer formwork, and the lower ends of the two formworks are tightened and fixed by the lower tension bolts, a plurality of supports 13 are evenly spaced on the upper end surfaces of the inner formwork 11 and the outer formwork 12, and a U-shaped notch 131 is provided in the middle of the support, and the U-shaped notch is conducive to the installation or removal of the tension bolts, and the assembly and disassembly operations are more convenient and quick, and an upper tension bolt 141 is installed between the U-shaped notches 131 of the inner and outer supports 13, and the upper tension bolts 141 tighten and fix the upper ends of the two formworks; at the transverse back ribs 192 of the bridge body 15, there are evenly spaced A plurality of telescopic rod assemblies 16, the lower end of the telescopic rod assembly is pressed against the U-shaped embedded part 151 on the bridge body 15, and the telescopic rod assembly 16 adopts the threaded telescopic steel pipe commonly used in current construction; a leveling rod 181 is provided between the upper ends of the outer formwork 12 and the inner formwork 11, and a hook is provided at the outer end of the leveling rod, and the outer end of the leveling rod 181 is inserted into the upper U-shaped buckle 121 provided on the upper part of the outer formwork 12, and the middle part of the leveling rod is supported on the edge of the inner formwork 11, and a lower U-shaped buckle 111 is provided at the bottom of the inner formwork, and a pull rod assembly A 182 is connected between the lower U-shaped buckle 111 and the hook at the outer end of the leveling rod 181. The pull rod assembly is a threaded pull rod commonly used in the market, and the screws at both ends are synchronously retracted and pulled by rotating the middle connecting piece.
[0019] like Figure 3 As shown, a channel-shaped vertical back rib 191 is provided between the transverse back ribs 192 on the outer surface of the inner template 11, and a hook hole is formed at the upper end of the channel-shaped vertical back rib for matching with the hook. A pull rod assembly B 17 is connected between the upper end of the vertical back rib 191 and the U-shaped embedded part 151 on the bridge body 15, and the pull rod assembly B is used to apply a pulling force to the upper end of the inner template 11, and at the same time, a telescopic rod is used to push the upper part of the inner template 11 to achieve push-pull bidirectional positioning. The end of the lower tension bolt 142 passes through the vertical back rib 191, and a square gasket 143 is provided between the nut of the lower tension bolt 142 and the vertical back rib 191, and a square gasket 143 is also provided between the nut at the outer end of the upper tension bolt 141 and the support 13. The vertical back rib 191 and the transverse back rib 192 are used to improve the anti-deformation strength of the template, and the vertical back rib 191 can improve the support strength of the template to the tension bolt.
[0020] like Figure 1 As shown, a row of limiting vertical ribs 152 are provided at the edge of the bridge body 15, and the outer side surface of the bottom of the inner template 11 is supported on the limiting vertical ribs 152, which are used to limit the lower part of the inner template 11 in the lateral direction. A wooden pad 153 is provided between the bottom surface of the inner formwork 11 and the surface of the bridge body 15. The wooden pad 153 is used to increase the friction between the inner formwork 11 and the surface of the bridge body 15, improve its stability, and prevent material leakage during pouring.
[0021] The end faces of the inner template 11 and the outer template 12 are both provided with arc-shaped notches, and the two arc-shaped notches correspond to each other to form an oblong hole, which is used for the steel bar system of the guardrail to pass through, so as to facilitate segmented construction. The round hole can be blocked with a plugging object during the pouring process.
[0022] like Figure 5 and Figure 6 As shown, a pad 183 is provided at the upper end surface of the inner template 11, and the leveling rod 181 is supported on the pad 183. The pad 183 can prevent the pressure of the adjustment rod from damaging the template, and can support the leveling rod 181 to a certain height, making the adjustment process more labor-saving.
[0023] Example 2, see the attached specification Figure 1-6 , a construction method for reinforcing and leveling a rotating bridge guardrail steel formwork system, the steps are as follows: (1) The inner formwork 11 is hoisted and placed on the edge of the bridge body 15, the outer side surface of the bottom of the inner formwork 11 is supported on the vertical reinforcement, and then the hook at the lower end of the tie rod assembly B 17 is hooked to the U-shaped embedded part 151 on the bridge body 15, and the hook at the upper end is hooked into the upper port of the vertical back rib 191; (2) The lower end of the telescopic rod assembly 16 is supported against the U-shaped embedded part 151 on the bridge body 15, and the upper end is supported on the bottom surface of the transverse back rib 192 of the inner template 11, and then the telescopic length of the telescopic rod assembly 16 and the pulling length of the pull rod assembly B 17 are alternately adjusted to fix the inner template 11 to a vertical state. At the same time, the upper part of the inner template 11 is positioned in both directions by pushing with the telescopic rod and pulling with the pull rod. These combined measures can effectively improve the installation strength of the inner template 11 on the bridge body 15; (3) The outer formwork 12 is hoisted and matched to be placed on the outer side of the inner formwork 11, the lower tension bolts 142 are installed between the bottoms of the two and tightened, and then the upper tension bolts 141 are installed between the supports 13 at the upper ends of the two and tightened, and the inner and outer formworks are preliminarily fixed; (4) During the process of pouring concrete into the mold cavity formed between the inner and outer molds and vibrating, the outer mold 12 will move downward due to the pressure of the concrete and the vibration force, resulting in a mold misalignment phenomenon, and the pouring construction will be stopped; (5) Tighten the tie rod assembly A 182, the upper end of the tie rod assembly A 182 pulls the inner end of the leveling rod 181 downward, the outer end of the leveling rod 181 is lifted upward under the action of the lever, and the outer template 12 is lifted upward through the upper U-shaped buckle until the upper end surfaces of the two are in a flush state; (6) Tighten the nuts of the upper tension bolts 141 and the nuts at the ends of the lower tension bolts 142 again, and tighten and fix the inner formwork 11 and the outer formwork 12 for the second time. After a section of bridge guardrail is cast, remove the formwork, and then follow steps (1)-(6) to carry out the construction of the next section of the steel formwork reinforcement and leveling system.
[0024] This embodiment forms a leveling system through the leveling rod 181, the pull rod assembly and the upper and lower U-shaped buckles 111 on the template, which can timely and effectively adjust and correct the displacement and misalignment of the outer template 12 during the casting construction process, thereby improving the casting construction quality of the guardrail.
Claims
1. A steel formwork reinforcement and leveling system for a rotating bridge guardrail, comprising an inner formwork and an outer formwork arranged vertically on the side of the rotating bridge, characterized in that: A number of lower tension bolts are evenly spaced between the bottom of the inner formwork and the outer formwork, a number of supports are evenly spaced on the upper end surfaces of the inner formwork and the outer formwork, a U-shaped notch is provided in the middle of the support, and upper tension bolts are installed between the U-shaped notches of the inner and outer supports; a number of telescopic rod assemblies are evenly spaced at the transverse back ribs of the bridge body, and the lower ends of the telescopic rod assemblies are pressed against the U-shaped embedded parts on the bridge body; a leveling rod is provided between the upper ends of the outer formwork and the inner formwork, and the outer end of the leveling rod is inserted into the upper U-shaped buckle provided on the upper part of the outer formwork, the middle part of the leveling rod is supported on the edge of the inner formwork, and a lower U-shaped buckle is provided at the bottom of the inner formwork, and a pull rod assembly A is connected between the lower U-shaped buckle and the hook at the outer end of the leveling rod.
2. According to claim 1, a rotating bridge guardrail steel formwork reinforcement and leveling system is characterized by: A channel-shaped vertical back rib is provided between the transverse back ribs on the outer side surface of the inner formwork, and a pull rod assembly B is connected between the upper end of the vertical back rib and the U-shaped embedded part on the bridge body.
3. The reinforcing and leveling system for the steel formwork of a rotating bridge guardrail according to claim 2 is characterized by: The end of the lower tension bolt passes through the vertical back rib, and a square gasket is arranged between the nut of the lower tension bolt and the vertical back rib, and a square gasket is also arranged between the nut at the outer end of the upper tension bolt and the support.
4. The reinforcing and leveling system for the rotating bridge guardrail steel formwork according to claim 1 is characterized by: A row of limiting vertical ribs is provided at the edge of the bridge body, and the outer side surface of the bottom of the inner template is supported on the limiting vertical ribs.
5. The reinforcing and leveling system for the rotating bridge guardrail steel formwork according to claim 1 is characterized by: A wooden pad is provided between the bottom surface of the inner template and the surface of the bridge body.
6. The reinforcing and leveling system for the rotating bridge guardrail steel formwork according to claim 1 is characterized by: The end faces of the inner template and the outer template are both provided with arc-shaped notches, and the two arc-shaped notches correspond to each other to form an oblong hole.
7. The reinforcing and leveling system for the rotating bridge guardrail steel formwork according to claim 1 is characterized by: A cushion block is provided at the upper end surface of the inner template, and the leveling rod is supported on the cushion block.
8. A construction method for reinforcing and leveling a rotating bridge guardrail steel formwork according to any one of claims 1 to 7, characterized in that it comprises the following steps: ⑴ The inner formwork is hoisted and placed on the edge of the bridge body. The outer side of the bottom of the inner formwork is supported on the vertical reinforcement. Then the hook at the lower end of the tie rod assembly B is hooked to the U-shaped embedded part on the bridge body, and the hook at the upper end is hooked into the upper port of the vertical back rib. (2) Place the lower end of the telescopic rod assembly against the U-shaped embedded part on the bridge body, and support the upper end on the bottom surface of the transverse back rib of the inner template. Then alternately adjust the telescopic length of the telescopic rod assembly and the pulling length of the pull rod assembly B to fix the inner template to a vertical state; ⑶ Lift the outer template and place it on the outer side of the inner template. Install the lower tension bolts between the bottoms of the two and tighten them. Then install the upper tension bolts between the supports at the upper ends of the two and tighten them. The inner and outer templates are initially fixed. (4) During the process of pouring concrete into the mold cavity formed between the inner and outer molds and vibrating, the outer mold will move downward due to the pressure of the concrete and the vibration force, resulting in mold misalignment, and the pouring construction will be stopped; (5) Tighten the tie rod assembly A. The upper end of the tie rod assembly A pulls down the inner end of the leveling rod. The outer end of the leveling rod is lifted upward under the action of the lever, and the outer template is lifted upward through the upper U-shaped buckle until the upper end surfaces of the two are in a flush state; ⑹ Tighten the nuts at the ends of the upper tension bolts and the lower tension bolts again to tighten and secure the inner and outer formwork for the second time.
9. The reinforcing and leveling system for the rotating bridge guardrail steel formwork according to claim 8 is characterized by: After a section of bridge guardrail is cast, the formwork is removed, and then the construction work of the next section of steel formwork reinforcement and leveling system is carried out according to steps ⑴-⑹.