Construction method for sealing bottom of large-scale set open caisson
By adopting a large-scale caisson bottom seal construction method in deep waters, flat steel wire mesh cavities and gravels are used for layered sealing, combined with automatic monitoring of steel truss cavities and 3D multi-beam depth sounder, deep water sea areas are solved The sealing and quality control problems of mid-caisson bottom seal construction improve construction efficiency and concrete density.
Patent Information
- Application Number
- CN202410991762.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-23
- Publication Date
- 2024-11-08
AI Technical Summary
The existing caisson bottom sealing technology is difficult to ensure effective sealing with uneven seabeds during deep water construction. The implementation of post-grouting technology is complex and the quality control is difficult. The traditional steel structure cabin plate cannot adapt to the internal structure characteristics of the caisson, and the bottom sealing construction The platform is cumbersome and inefficient, and cannot effectively solve the problems of sealing gaps between the caisson outer wall and seabed and treating high mud-containing seawater.
The construction method of large-scale caisson bottom sealing includes underwater blasting and slag cleaning, flat steel wire mesh cavities and multi-layer gravel for layered throwing and filling, steel truss partition plates are installed for partition isolation, and through water pumping equipment The floating platform is equipped with a 3D multi-beam depth sounder for elevation monitoring and automatic pouring of concrete.
Effectively prevent unsolidified concrete from being damaged by moving water, ensure the compactness and stability of the back cover concrete, reduce construction difficulty and cost, improve construction efficiency and quality control, and achieve effective fit and water flow isolation from the seabed.
Smart Images

Figure CN118911182A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of caisson bottom sealing construction, and in particular to a large-scale caisson bottom sealing construction method. Background Art
[0002] With the advancement of science and technology, the world's large-span bridges are developing rapidly, the number is increasing, and the span is constantly breaking through. Caisson foundations have the characteristics of high bearing capacity, high rigidity, good stability, strong earthquake resistance, strong ability to prevent ship collisions and reliable construction. They can sink to a deeper ideal bearing layer or directly sit on the bedrock riverbed (setting the foundation), and reliably transmit the huge load transmitted from the upper part of the bridge. Therefore, they are increasingly used in deep-water foundations of large-span bridges.
[0003] At present, there are three mainstream methods for the partition of large-volume concrete bottom sealing:
[0004] (1) In order to reduce the single bottom sealing area of large-volume cofferdams, many use steel structure bulkheads. The bulkheads are manufactured as a whole and sink to the riverbed synchronously with the cofferdam, or after the cofferdam sinks to the designed elevation of the riverbed, it slides down the riverbed soil layer to a certain depth through a vertical slideway to form multiple bottom sealing partitions and reduce the area of a single bottom sealing partition. This technology is a typical practice in deepwater cofferdam construction, but it cannot be used to seal the gap below the blade foot of the inner partition wall in the caisson, and cannot adapt to the thickening of the blade foot of the inner partition wall in the caisson.
[0005] (2) Backfill the partitions with sand. Utilize the natural height difference of the caisson blade (the blade of the caisson wall is higher than the blade of the partition wall, and the blade of the partition wall is higher than the blade of the ordinary partition wall) to backfill 2 to 3 m of sand at the partition wall to prevent the weak soil layer under the partition wall from causing holes in the bottom concrete. After the partition concrete is poured, the backfill sand will be sucked out.
[0006] (3) The main methods for setting up the bottom seal of the caisson are to use the inner wall of the well to divide and compartmentalize the well for the convenience of construction organization, to set up plug plates to seal the gap between the blade foot and the seabed to prevent the compartments from being crossed, and to use post-grouting to deal with the possible slag inclusions and loose concrete of the bottom seal under the blade foot. For large-scale caissons, the strength, hardness and degree of development of the bedrock of the seabed over a large area are inevitably different. The flatness of the rock surface after the seabed blasting can only be controlled within a certain range, and the height difference is bound to exist. Relying on the plug plates at the bottom of the blade foot to isolate the bottom seal is not only a large project, but also difficult to fully fit the seabed to ensure the isolation effect of compartments. Post-grouting is used to reinforce the bottom of the blade foot. The technical parameters such as the slurry diffusion range, grouting volume, and solidification time need to be tested and verified in advance, which is costly and difficult to implement in actual construction quality control.
[0007] In addition, after the steel caisson sinks to the base and meets the verticality requirements, concrete pouring construction is required. The key to the construction process is that after the steel caisson sinks to the predetermined position, the foundation pit must first be leveled through underwater operations, and crushed stone must be used to level it to ensure that the caisson can be placed stably. The subsequent bottom concrete pouring is extremely critical and needs to be completed quickly to ensure the safety of the caisson.
[0008] However, in actual use, the existing caisson bottom sealing technology still faces problems such as the difficulty and high cost of implementing traditional bottom sealing methods due to complex seabed conditions, as well as insufficient adaptability to construction in special environments such as deepwater areas. Specifically, it is difficult to ensure effective sealing with uneven seabed when sealing the bottom in compartments, and the post-grouting technology is complex to implement and difficult to control quality; the inland river technical solution is not suitable for deepwater environments with blasting rock faces; traditional steel structure bulkheads cannot adapt to the internal structural characteristics of the caisson; the bottom sealing construction platforms are mostly fixed, which are cumbersome to operate and inefficient. Although there are innovations in floating platforms, the equipment as a whole still lacks effective means of elevation monitoring; in addition, the existing technical solutions cannot effectively solve the problem of sealing the gap between the outer wall of the caisson and the seabed and treating high-mud seawater.
[0009] To this end, the present application proposes a large-scale caisson bottom sealing construction method to solve the above-mentioned technical problems. Summary of the invention
[0010] The main purpose of the present invention is to provide a caisson bottom sealing construction method, which solves the problem of water flow isolation in deep-water caisson construction, effectively prevents unsolidified concrete from being damaged by dynamic water, and also adopts improved gravel filling technology and sealing measures to overcome the problems of gravel loss and leakage under the blade foot, thereby ensuring the density and stability of the bottom sealing concrete.
[0011] The present invention adopts the following technical solutions to solve the above technical problems:
[0012] A large-scale caisson bottom sealing construction method comprises the following steps:
[0013] Step 1: Underwater blasting and slag removal are carried out on the seabed bedrock to form an underwater foundation trench. The caisson is floated to the bridge site and then water is added in stages to sink it to the designed elevation. The vertical support is formed by support columns, and the plane position is fixed by an anchor system.
[0014] Step 2: Fill the gap between the outer wall of the caisson and the seabed foundation trench with a flat wire mesh gabion, and then fill multiple gravels of different particle sizes on top of the flat wire mesh gabion in sequence to reduce the porosity of the wire mesh gabion and block the water flow inside and outside the caisson;
[0015] Step 3: During the period of dumping and plugging, the gap between the outer well wall and the seabed foundation trench is cleaned by suction of mud and slag in the first batch of bottom-sealed well holes. After the foundation is cleared to the bedrock, the seabed bedrock elevation at the centerline of the wellbore is scanned, and the corresponding steel truss bulkhead is manufactured for underwater installation;
[0016] Step 4: After the first batch of bulkheads are installed, use pumping equipment to extract the upper layer of clean water in the adjacent wells to replace the water in the first batch of bottom-sealed wells until the specification requirements are met;
[0017] Step 5: Use the construction platform on the top of the caisson to arrange the hopper and lower the guide tube to seal the bottom of the first batch of wells, and pour concrete simultaneously to the designed bottom thickness in one go;
[0018] Step 6: Install the bulkhead plates in the second batch of wells corresponding to the side cable direction to complete the partition isolation. After the bottom sealing of the first batch of wells is completed, transfer the hopper and the guide tube to the second batch of wells to seal the bottom of the second batch of wells, and then pour concrete;
[0019] Step 7: After the first batch of bottom sealing concrete reaches the design strength, all anchor cables are removed. After the second batch of bottom sealing concrete reaches the design strength, the outermost bulkhead is removed and the concrete side is washed underwater. The gap between the inner well wall blade and the seabed bedrock is sealed with bagged cement gravel. The third batch of wellbore bottom sealing is completed, and then concrete pouring is carried out;
[0020] Step 8: Pump out water from the remaining wellbores, remove the bagged cement gravel in the gap between the inner well wall blade and the seabed bedrock, and flush the sealed concrete free surface and the seabed bedrock surface with clean water from the sealed wellbore. Use dry sealing to seal the remaining wellbores, and the bottom sealing construction is completed.
[0021] Preferably, the specific operation steps of dumping multiple gravels of different particle sizes in step 2 include:
[0022] S21. A single or multiple layer of flat wire mesh gabions filled with 15-20 cm stone blocks are dumped close to the outer well wall at the bottom to seal the height gap between the outer well wall blade and the seabed rock surface;
[0023] S22. Add 30 cm thick crushed stones with a coarse particle size of 5 to 10 cm on top of the flat wire mesh gabion to form a suspended skeleton to reduce the porosity of the wire mesh gabion;
[0024] S23. A third layer of 2 to 5 cm thick graded gravel is dumped on top of the 30 cm thick coarse-grained gravel (7) with a diameter of 5 to 10 cm to block the water flow inside and outside the caisson;
[0025] S24. A fourth layer of 30 cm thick gravel with a coarse particle size of 5 to 10 cm is dumped on top of the 2 to 5 cm graded gravel as an anti-scouring cover layer to prevent the third layer of graded gravel from being scoured by water.
[0026] Preferably, the specific operation steps of describing the seabed bedrock elevation at the centerline of the wellbore in step 3 and manufacturing the corresponding steel truss bulkhead for underwater installation include:
[0027] S31. After clearing the foundation to the bedrock, use a multi-beam depth sounder to accurately scan the seabed bedrock elevation at the centerline of the wellbore, and manufacture 8 sets of steel truss bulkheads according to the scanned elevation data at the centerline of the wellbore;
[0028] S32. Use the crane on the top platform of the caisson to vertically lower the bulkhead for underwater installation;
[0029] S33. Divers dive to check the fit between the bulkhead plates and the seabed bedrock, and use bagged cement gravel to seal the local gaps between the roots of the two outermost sets of bulkhead plates and the seabed, and the gaps between the inner well wall blade and the seabed bedrock.
[0030] Preferably, the bulkhead plate is composed of three plates spliced together, the plates are plate one, plate three and plate two, and plate one and plate two are plates located at both ends of plate three.
[0031] Preferably, the specific operation process of underwater installation in step S32 includes:
[0032] S321. First install the parts connected to the shaft wall at both ends, 2.5m away from the inner shaft wall, avoid the raised shear groove at the bottom of the inner wall plate, and lower the first and second plates until they are flush with the height of the corbels, and then move them horizontally, where the corbels are connected to the shaft wall plate;
[0033] S322. Connect the first and second plates to the corbels by bolts, and install horizontal diagonal braces to fix the plane position;
[0034] S323. Then vertically lower the third part of the middle of the bulkhead plate and connect the third part with the first and second parts at both ends through flange bolts.
[0035] Preferably, during the pouring process of step five, during the concrete pouring after the bottom is sealed, a buoy is set in the wellbore, and the buoy is suspended with a 3D multi-beam depth sounder to automatically track and scan the concrete elevation during the bottom sealing period, and the computer automatically records the scanning data and transmits it wirelessly to the management platform.
[0036] Preferably, the installation method of the bulkhead in step six is the same as the installation method of the bulkhead in step three.
[0037] The present invention provides a large-scale caisson bottom sealing construction method. Compared with the prior art, the present invention has the following beneficial effects:
[0038] 1. The present invention implements layered backfilling operations between the outer well wall and the seabed foundation trench, especially uses bottom wire mesh gabions and graded crushed stones, which can not only effectively seal the gap under the outer well wall blade, but also prevent the subsequent graded crushed stones from rolling into the wellbore and interfering with the bottom sealing operation. The top protective layer enhances the anti-scouring ability, and the four-layer backfill structure as a whole forms a complete closed filling structure, constructing a stable water flow isolation barrier, which can block the high-velocity reciprocating tidal flow outside the caisson, create static water working conditions for the inside of the caisson, effectively ensure the quality of the bottom sealing concrete, and greatly improve the casting quality and structural safety of the bottom sealing concrete.
[0039] 2. The present invention arranges a steel truss partitioning bulkhead at the center axis of the wellbore, thereby changing the blocking isolation below the well wall blade foot to isolation in the middle of the wellbore, thereby realizing the transition from independent isolation and bottom sealing of multiple complete wellbores to bottom sealing of adjacent wellbores, greatly reducing the difficulty of deepwater underwater construction of installing plug-ins below the blade foot for bottom sealing and partitioning, and improving construction efficiency.
[0040] 3. The bottom of the steel truss partition bulkhead of the present invention is contoured based on the multi-beam precise scanning data of the bedrock elevation, and combined with the 10 cm non-stiffened flexible skirt at the bottom of the bulkhead, it can effectively fit with the seabed bedrock after being lowered. Therefore, the plane is divided into three sections, and the two end sections are contoured toward the well wall panel, first lowered vertically and then translated horizontally, so that the bulkhead can enter under the blade foot and fit closely with the inner wall panel, which can not only facilitate underwater construction, but also greatly improve the partition isolation effect, effectively prevent leakage through the gap when the bottom sealing concrete is poured, and ensure the bottom sealing quality.
[0041] 4. The present invention solves the problem of incomplete bottom sealing and foundation cleaning of caissons caused by the precipitation of turbid seawater with high mud content by replacing the upper clean water of adjacent wells. It does not need to supply a large amount of clean water separately, thus greatly reducing construction investment.
[0042] 5. The present invention can seal the bottom in batches, so that the anchor system can be untied as early as possible, provide an open water working environment, and eliminate the interference of anchor cables on the construction ships on the sea surface. At the same time, in the process of sealing the bottom, the outer wellbore is sealed first, creating conditions for pumping water from the inner wellbore for dry sealing. This can speed up the construction progress and save construction time.
[0043] 6. The present invention uses a floating platform equipped with a 3D multi-beam depth sounder to automatically monitor the elevation of the bottom seal concrete, thereby greatly improving the elevation measurement accuracy and monitoring efficiency, and can effectively guide the adjustment of the sealing concrete speed and the adjustment of the pouring volume at the distribution point, thereby improving the quality of the bottom seal concrete. BRIEF DESCRIPTION OF THE DRAWINGS
[0044] The drawings constituting a part of the present application are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings:
[0045] Figure 1 It is a schematic diagram of the overall operation steps of the present invention;
[0046] Figure 2 It is a schematic flow chart of the operation steps of the outer foundation trench dumping protection of the well wall of the present invention;
[0047] Figure 3 A schematic flow chart of the steps for manufacturing and installing the first batch of bottom-sealed well bulkhead panels of the present invention;
[0048] Figure 4 It is a schematic flow chart of the operation steps of the bottom sealing process of the wellbore of the present invention;
[0049] Figure 5 A schematic diagram of the three-dimensional structure of the caisson bottom sealing structure of the present invention performing step 1 operation;
[0050] Figure 6 A schematic diagram of the three-dimensional structure of the caisson bottom sealing structure of the present invention performing step 2 operation;
[0051] Figure 7 A schematic diagram of the three-dimensional structure of the caisson bottom sealing structure of the present invention performing step three operation;
[0052] Figure 8 A schematic diagram of the three-dimensional structure of the caisson bottom sealing structure of the present invention performing step 4 operation;
[0053] Fig. 9 A schematic diagram of the three-dimensional structure of the caisson bottom sealing structure of the present invention performing step five operation;
[0054] Fig.10 A schematic diagram of the three-dimensional structure of the caisson bottom sealing structure of the present invention performing step six operation;
[0055] Fig.11 A schematic diagram of the three-dimensional structure of the caisson bottom sealing structure of the present invention performing step seven operation;
[0056] Fig.12 A schematic diagram of the three-dimensional structure of the caisson bottom sealing structure of the present invention performing step eight operation;
[0057] Fig.13 It is a schematic plan view of the riprap protection structure of the present invention;
[0058] Fig.14 It is a schematic plan view of the bulkhead structure of the present invention;
[0059] Fig.15 for Fig.14 A schematic plan view of section 1-1;
[0060] Fig.16 It is a schematic plan view of the buoyancy structure of the present invention;
[0061] Fig.17 for Fig.16 Schematic diagram of the planar cross-section of part 2-2.
[0062] In the figure:
[0063] 1. Underwater foundation trench; 2. Caisson body; 3. Support column; 4. Anchor system; 5. Caisson outer wall; 6. Flat wire mesh gabion; 7. Thick coarse gravel layer; 8. Special gravel layer; 9. Pumping equipment; 10. First batch of wells; 11. Seabed bedrock; 12. Steel truss bulkhead; 13. Corbel; 14. Caisson shear groove; 15. Inner well wall blade; 16. Clear water in the well; 17. Bottom concrete; 18. Floating box; 19. 3D multi-beam echo sounder; 20. Second batch of wells; 21. Third batch of wells; 22. Remaining wells;
[0064] in:
[0065] The steel truss bulkhead plate (12) comprises three plates, namely plate one, plate two and plate three, which are marked as 12-1, 12-2 and 12-3. DETAILED DESCRIPTION
[0066] The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments. In the absence of conflict, the embodiments in this application and the features in the embodiments can be combined with each other. Based on the embodiments in the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.
[0067] In the embodiment, see Figures 1 to 17 .
[0068] like Figure 1 The present invention provides a large-scale caisson bottom sealing construction method, comprising the following steps:
[0069] Step 1: If Figure 5 As shown, the seabed bedrock 11 is blasted underwater and slag is removed to form an underwater foundation trench 1. The caisson body 2 is floated to the bridge site and then water is injected in stages to sink it to the designed elevation. The support columns 3 form a vertical support, and the plane position is fixed by the anchor system 4.
[0070] Step 2: If Figure 2 and Figure 6As shown, the gap between the outer wall 5 of the caisson and the underwater foundation trench 1 of the seabed is filled and blocked for protection, and multiple flat wire mesh gabions 6 are used for filling and blocking, and then multiple gravel layers of different particle sizes are sequentially filled on the multiple flat wire mesh gabions 6, so as to reduce the porosity of the wire mesh gabions and block the water flow inside and outside the caisson;
[0071] The specific operation steps of dump filling and plugging protection are shown in Fig.13 ,include:
[0072] S21. A single or multiple layer of flat wire mesh gabions 6 filled with 15-20 cm stone blocks are thrown against the outer wall 5 of the caisson at the bottom to form a seal for the height gap between the outer wall blade and the seabed rock surface. Multiple flat wire mesh gabions are stacked here, and the gap between them may reach 2m;
[0073] S22. A thick coarse gravel layer 7 is then thrown on top of the flat wire mesh gabion, where the thick coarse gravel layer 7 is a 30 cm thick gravel filling layer with a coarse particle size of 5 to 10 cm, so as to form a suspended skeleton for reducing the porosity of the wire mesh gabion;
[0074] S23. A third layer of specially prepared gravel layer 8 is dumped on top of the thick coarse gravel layer 7. The specially prepared gravel layer 8 is a 2 to 5 cm thick graded gravel filling layer, which is used to block the water flow inside and outside the caisson;
[0075] S24. A fourth thick coarse gravel layer 7 is dumped on top of the 2-5 cm graded gravel, wherein a 30 cm thick coarse gravel with a particle size of 5-10 cm is used as an anti-scouring cover layer to prevent the third graded gravel from being scoured by water;
[0076] In summary, different methods are adopted to fill the gap between the outer well wall and the seabed foundation trench in layers, especially the application of bottom wire mesh gabions and graded crushed stones. The multiple flat wire mesh gabions 6 at the bottom and the coarse-grained crushed stone suspension skeleton can not only effectively seal the gap under the blade foot of the outer well wall, but also prevent the subsequent graded crushed stones from rolling into the wellbore and interfering with the subsequent bottom sealing operation. The surface block stone protective layer can prevent scouring and enhance the anti-scouring ability.
[0077] Therefore, the four-layer structure forms a complete closed filling structure, constructs a stable water flow isolation barrier, blocks the high-speed reciprocating tidal flow outside the caisson, provides a static water working environment for the bottom seal in the well hole, effectively guarantees the quality of the bottom seal concrete 17, and greatly improves the pouring quality and structural safety of the bottom seal concrete 17;
[0078] Step 3: If Figure 3 and Figure 7As shown, during the period of dumping and plugging, the gap between the outer well wall and the seabed foundation trench is simultaneously cleared by suction of mud and slag in the first batch of well holes 10 with the first bottom sealed by using the pumping equipment 9. After clearing the foundation to the bedrock, the elevation of the seabed bedrock 11 at the center line of the first batch of well holes 10 is scanned, and the corresponding 8 groups of steel truss bulkheads 12 are manufactured according to the elevation data at the center axis of the well holes scanned and installed underwater. At this time, the corbels 13 connecting the bulkheads and the well wall plates are welded underwater (it can also be welded in the manufacturing plant before the caisson is floated), and the corbels 13 are used to fix the bulkheads;
[0079] The specific operation steps of using a multi-beam depth sounder to measure the elevation of the seabed bedrock 11 at the centerline of the wellbore and manufacturing the corresponding steel truss bulkhead 12 for underwater installation can be referred to Fig.14 and Fig.15 ,include:
[0080] S31. After clearing the foundation to the bedrock, use a multi-beam depth sounder to accurately scan the elevation of the seabed bedrock 11 at the center line of the first batch of wells 10, and manufacture 8 sets of steel truss bulkheads 12 according to the elevation data at the center axis of the scanned wells;
[0081] S32. Use the crane on the top platform of the caisson to vertically lower the bulkhead plate for underwater installation. The bulkhead plate is composed of three plates, which are plate 1 12-1, plate 2 12-2 and plate 3 12-3. Plate 1 12-1 and plate 2 12-2 are plates located at both ends of plate 3 12-3. Therefore, the specific operation process of underwater installation of the bulkhead plate includes:
[0082] S321. First install the parts connected to the well wall at both ends (plate 1 12-1 and plate 2 12-2), 2.5m away from the inner well wall, avoid the raised caisson shear groove 14 at the bottom of the inner wall plate, and lower the plates 12-1 and 12-2 until they are flush with the height of the bracket 13, and then move them horizontally, wherein the bracket 13 is connected to the well wall plate;
[0083] S322. The plate 12-1, the plate 12-2 and the corbel 13 are connected by bolts, and horizontal diagonal braces are installed to fix the plane position;
[0084] S323. Then vertically lower the installation bulkhead plate in the middle of the three 12-3 parts, and the three plates 12-3 and the two ends of the plate 12-1 and plate 12-2 are connected by flange bolts;
[0085] S33. Divers dive to check the fit between the steel truss bulkheads 12 and the seabed bedrock 11, and seal the local gaps between the roots of the two outermost sets of steel truss bulkheads 12 and the seabed, and the gaps between the inner well wall blade 15 and the seabed bedrock 11 with bagged cement gravel;
[0086] At this time, the bottom of the steel truss partition bulkhead is processed based on the multi-beam precise scanning data of the bedrock elevation, and combined with the 10 cm high thin-walled flexible skirt without stiffening ribs at the bottom of the bulkhead, it can effectively fit with the seabed bedrock 11 after being lowered; the plane is divided into three sections, and the two end sections are manufactured in the direction of the well wall plate, first lowered vertically and then translated horizontally, so that the bulkhead can enter under the blade foot and fit closely with the inner wall plate, which can not only facilitate underwater construction, but also greatly improve the partition isolation effect, effectively prevent leakage through the gap when pouring the bottom seal concrete 17, and ensure the bottom seal quality. The three sections are connected by flanges, which is convenient for underwater construction;
[0087] Here, a multi-beam echo sounder is used for precise measurement, and the flexible skirt and segmented bulkhead are customized based on this data to ensure that the bulkhead fits tightly with the seabed bedrock 11. The innovative segmented lowering and translational installation technology not only simplifies the complex underwater operation process, but also strengthens the sealing effect of the bulkhead, effectively preventing the leakage of the bottom sealing concrete 17;
[0088] The above measures greatly improved the partition isolation effect, effectively prevented leakage through the gap when pouring the bottom seal concrete 17, and ensured the bottom seal quality. In addition, by accurately measuring the seabed elevation of the wellbore centerline, customizing the steel truss partition bulkhead, the innovation from traditional blade foot plugging to multi-wellbore coordinated isolation was realized, which significantly reduced the technical difficulty and operation risk of construction in deepwater environment, improved the construction efficiency, and ensured the independence and integrity of the bottom seal operation of each wellbore, effectively avoiding the phenomenon of concrete cross-compartment.
[0089] It can also be further explained that by setting a steel truss partitioning bulkhead at the center axis of the wellbore, the plugging isolation below the wellbore blade foot is changed to isolation in the middle of the wellbore, realizing the transformation from independent isolation and bottom sealing of multiple complete wellbores to bottom sealing of adjacent (0.5+1+1+0.5) wellbores, which greatly reduces the difficulty of deepwater underwater construction of installing plug-in plates below the blade foot for bottom sealing partition isolation and improves construction efficiency;
[0090] Step 4: If Figure 8 As shown, after the first batch of bulkheads are installed, the upper layer of clean water 16 in the adjacent wells is extracted by an air suction mud machine (pumping equipment 9) to replace the water in the first batch of bottom-sealed wells until the specification requirements are met;
[0091] It should be noted that since turbid seawater will precipitate a lot of mud after being left for a period of time, the bottom sealing hole must be replaced with clean water. Therefore, the bottom wellhead is sealed by replacing the upper clean water of the adjacent wellbore, solving the problem of incomplete bottom sealing and foundation cleaning of the caisson caused by the precipitation of turbid seawater with high mud content. There is no need to supply a large amount of clean water, which greatly reduces the construction investment.
[0092] Step 5: If Fig. 9As shown, the hopper is arranged and the guide tube is lowered using the construction platform on the top of the caisson to seal the bottom of the first batch of wells 10, and the bottom seal concrete 17 is poured simultaneously to the designed bottom seal thickness at one time;
[0093] During the perfusion process, refer to Fig.16 and Fig.17 As shown, during the concrete pouring after the bottom is sealed, a pontoon 18 is arranged in the wellbore, and the pontoon 18 is suspended with a 3D multi-beam depth sounder 19, which automatically tracks and scans the concrete elevation during the bottom sealing period, and the computer automatically records the scanned data and transmits it wirelessly to the management platform;
[0094] Here, a floating platform equipped with a 3D multi-beam echo sounder 19 is used to automatically monitor the elevation of the bottom seal concrete 17. The elevation measurement accuracy and monitoring efficiency are greatly improved, which can effectively guide the adjustment of the plugging concrete speed and the adjustment of the pouring volume at the distribution point, thereby improving the quality of the bottom seal concrete 17;
[0095] Step 6: If Fig.10 As shown, the bulkheads in the second batch of wellbores 20 corresponding to the side cable direction are installed to complete the partition isolation, wherein the 4 groups of bulkheads are removed and used after the first batch of bottom sealing concrete 17 reaches the demoulding strength, and then after the bottom sealing of the first batch of wellbores 10 is completed, the hopper and the conduit are transferred to the second batch of wellbores 20 to seal the bottom of the second batch of wellbores 20, and then the bottom sealing concrete 17 is poured;
[0096] The installation method of the bulkhead here is the same as the installation method of the steel truss bulkhead 12 in step 3;
[0097] Step 7: If Fig.11 As shown, after the first batch of bottom sealing concrete 17 reaches the design strength, all anchor cables are removed. After the second batch of bottom sealing concrete 17 reaches the design strength, the two outermost groups of bulkheads are removed, and the concrete sides are washed underwater. After the gap between the inner well wall blade 15 and the seabed bedrock 11 is sealed with bagged cement gravel, the inner bottom sealing of the third batch of well holes 21 is completed, and then the bottom sealing concrete 17 is poured;
[0098] Step 8: If Fig.12 As shown, water is pumped out of the remaining wellbore 22, the cement rubble bags in the gap between the inner well wall blade 15 and the seabed bedrock 11 are removed, the free surface of the sealed concrete 17 and the rock surface of the seabed bedrock 11 are washed by jetting water 16 in the sealed wellbore, and the remaining wellbore 22 is sealed by dry sealing;
[0099] Finally, the back cover construction is completed. For the back cover construction steps, please refer to Figure 4In the bottom sealing operation, by reasonably arranging the operation sequence and recycling resources (such as the removal and reuse of bulkheads), the construction period is effectively shortened, material consumption is reduced, and the quality control of each batch of bottom sealing operations is guaranteed, which improves the overall economy of the project and the sustainability of construction. At the same time, by sealing the bottom in batches, the anchor system 4 can be untied as early as possible, providing an open water operating environment, and eliminating the interference of anchor cables on construction ships on the sea surface. At the same time, the outer wellbore is sealed first, creating conditions for pumping water from the inner wellbore for dry sealing. Therefore, the above measures can speed up the construction progress and save construction time.
[0100] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
[0101] In addition, it should be noted that if the embodiments of the present invention involve directional indications (such as up, down, left, right, front, back, etc.), the directional indications are only used to explain the relative position relationship, movement status, etc. between the components in a certain specific posture. If the specific posture changes, the directional indication will also change accordingly.
[0102] In addition, if there are descriptions involving "first", "second", etc. in the embodiments of the present invention, the descriptions of "first", "second", etc. are only used for descriptive purposes and cannot be understood as indicating or implying their relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In addition, the meaning of "and / or" appearing in the full text includes three parallel schemes. Taking "A and / or B" as an example, it includes scheme A, or scheme B, or schemes that A and B meet at the same time. In addition, in the embodiments of the present invention, "multiple" refers to more than two. In addition, the technical solutions between the various embodiments can be combined with each other, but it must be based on the ability of ordinary technicians in the field to implement. When the combination of technical solutions is contradictory or cannot be implemented, it should be considered that such a combination of technical solutions does not exist and is not within the scope of protection required by the present invention.
Claims
1. A large-scale caisson bottom sealing construction method, characterized in that: The following steps are involved: Step 1: Underwater blasting and slag removal are carried out on the seabed bedrock to form an underwater foundation trench. The caisson is floated to the bridge site and then water is added in stages to sink it to the designed elevation. The vertical support is formed by support columns, and the plane position is fixed by an anchor system. Step 2: Fill the gap between the outer wall of the caisson and the seabed foundation trench with a flat wire mesh gabion, and then fill multiple gravels of different particle sizes on top of the flat wire mesh gabion in sequence to reduce the porosity of the wire mesh gabion and block the water flow inside and outside the caisson; Step 3: During the period of dumping and plugging, the gap between the outer well wall and the seabed foundation trench is cleaned by suction of mud and slag in the first batch of bottom-sealed well holes. After the foundation is cleared to the bedrock, the seabed bedrock elevation at the centerline of the wellbore is scanned, and the corresponding steel truss bulkhead is manufactured for underwater installation; Step 4: After the first batch of bulkheads are installed, use pumping equipment to extract the upper layer of clean water in the adjacent wells to replace the water in the first batch of bottom-sealed wells until the specification requirements are met; Step 5: Use the construction platform on the top of the caisson to arrange the hopper and lower the guide tube to seal the bottom of the first batch of wells, and pour concrete simultaneously to the designed bottom thickness in one go; Step 6: Install the bulkhead plates in the second batch of wells corresponding to the side cable direction to complete the partition isolation. After the bottom sealing of the first batch of wells is completed, transfer the hopper and the guide tube to the second batch of wells to seal the bottom of the second batch of wells, and then pour concrete; Step 7: After the first batch of bottom sealing concrete reaches the design strength, all anchor cables are removed. After the second batch of bottom sealing concrete reaches the design strength, the outermost bulkhead is removed and the concrete side is washed underwater. The gap between the inner well wall blade and the seabed bedrock is sealed with bagged cement gravel. The third batch of wellbore bottom sealing is completed, and then concrete pouring is carried out; Step 8: Pump out water from the remaining wellbores, remove the bagged cement gravel in the gap between the inner well wall blade and the seabed bedrock, and flush the sealed concrete free surface and the seabed bedrock surface with clean water from the sealed wellbore. Use dry sealing to seal the remaining wellbores, and the bottom sealing construction is completed.
2. The large-scale caisson bottom sealing construction method according to claim 1 is characterized in that: The specific operation steps of dumping multiple gravels with different particle sizes in step 2 include: S21. A single or multiple layer of flat wire mesh gabions filled with 15-20 cm stone blocks are dumped close to the outer well wall at the bottom to seal the height gap between the outer well wall blade and the seabed rock surface; S22. Add 30 cm thick crushed stones with a coarse particle size of 5 to 10 cm on top of the flat wire mesh gabion to form a suspended skeleton to reduce the porosity of the wire mesh gabion; S23. A third layer of 2 to 5 cm thick graded gravel is dumped on top of the 30 cm thick coarse-grained gravel (7) with a diameter of 5 to 10 cm to block the water flow inside and outside the caisson; S24. A fourth layer of 30 cm thick gravel with a coarse particle size of 5 to 10 cm is dumped on top of the 2 to 5 cm graded gravel as an anti-scouring cover layer to prevent the third layer of graded gravel from being scoured by water.
3. The large-scale caisson bottom sealing construction method according to claim 1 is characterized in that: In step 3, the specific operation steps of drawing the seabed bedrock elevation at the centerline of the wellbore and manufacturing the corresponding steel truss bulkhead for underwater installation include: S31. After clearing the foundation to the bedrock, use a multi-beam depth sounder to accurately scan the seabed bedrock elevation at the centerline of the wellbore, and manufacture 8 sets of steel truss bulkheads according to the scanned elevation data at the centerline of the wellbore; S32. Use the crane on the top platform of the caisson to vertically lower the bulkhead for underwater installation; S33. Divers dive to check the fit between the bulkhead plates and the seabed bedrock, and use bagged cement gravel to seal the local gaps between the roots of the two outermost sets of bulkhead plates and the seabed, and the gaps between the inner well wall blade and the seabed bedrock.
4. The large-scale caisson bottom sealing construction method as claimed in claim 3 is characterized in that: The bulkhead plate is composed of three plates spliced together, the plates are plate one, plate three and plate two, and plate one and plate two are plates located at two ends of plate three.
5. The large-scale caisson bottom sealing construction method as claimed in claim 4, characterized in that: The specific operation process of underwater installation in step S32 includes: S321. First install the parts connected to the shaft wall at both ends, 2.5m away from the inner shaft wall, avoid the raised shear groove at the bottom of the inner wall plate, and lower the first and second plates until they are flush with the height of the corbels, and then move them horizontally, where the corbels are connected to the shaft wall plate; S322. Connect the first and second plates to the corbels by bolts, and install horizontal diagonal braces to fix the plane position; S323. Then vertically lower the third part of the middle of the bulkhead plate and connect the third part with the first and second parts at both ends through flange bolts.
6. The large-scale caisson bottom sealing construction method according to claim 1, characterized in that: During the pouring process of step five, during the period of concrete pouring after the bottom is sealed, a buoy is set in the wellbore, and a 3D multi-beam depth sounder is suspended on the buoy to automatically track and scan the concrete elevation during the bottom sealing period. The computer automatically records the scanning data and transmits it wirelessly to the management platform.
7. The large-scale caisson bottom sealing construction method according to claim 1, characterized in that: The installation method of the bulkhead in step six is the same as the installation method of the bulkhead in step three.