Method, device and equipment for optimizing drainage capacity of urban rainwater pipe network and medium

By determining the water level control range of river channels and analyzing the flow rate of drainage pump stations, and adjusting the drainage flow rate of the stormwater pipeline network, the problems of high transformation costs and low applicability in the existing technology are solved, and the efficient drainage capacity optimization of the urban stormwater pipeline network is achieved.

CN118916951APending Publication Date: 2024-11-08SHANGHAI INVESTIGATION DESIGN & RES INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410884141.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-03
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

The existing technology has comprehensively transformed the urban stormwater pipeline network by expanding the pipe diameter and increasing the slope of the pipeline design, which has increased investment costs and time, and has not improved the impact of high water levels on the pipeline drainage of the river, resulting in the transformation of the urban stormwater pipeline network. Low applicability and reduced drainage capacity.

Method used

By obtaining the control range of the river water level in the target study area, determining the target river water level value and the corresponding rainwater pipeline drainage flow, analyzing the project cost reciprocating the flow of the river drainage pump station, and using these data to determine the first and second target curves , select the target river water level control range of the curve intersection area, and adjust the drainage flow of the urban stormwater pipeline network to optimize drainage capacity.

Benefits of technology

It effectively reduces the cost of transformation, improves the drainage capacity of urban stormwater pipelines, avoids the impact of high water levels on the pipeline drainage due to the impact of high river channels, and improves the applicability and efficiency of transformation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118916951A_ABST
    Figure CN118916951A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of waterlogging prevention and control, in particular to an optimization method, device, equipment and medium for the drainage capacity of an urban rainwater pipe network, and the method comprises the steps: determining a target riverway water level quantity value of a riverway water level adjustable range of a target research region, thereby determining the drainage flow of a corresponding target rainwater pipe network; analyzing the project cost corresponding to the watercourse drainage pump station required by the target watercourse water level value; determining a first target curve by using the target river water level value and the drainage flow, determining a second target curve according to the target river water level value and the reciprocal of the construction cost, and adjusting the drainage flow of the urban rainwater pipe network by using a target river water level regulation and control range corresponding to a target intersection area of the first target curve and the second target curve. The drainage capacity of the urban rainwater pipe network is optimized. Therefore, the problems that the investment cost is increased through comprehensive transformation of the pipe network, the applicability of transformation of the rainwater pipe network is low, and the drainage capacity of the urban rainwater pipe network is reduced in the prior art are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of waterlogging prevention and control, and in particular to a method, device, equipment and medium for optimizing the drainage capacity of an urban rainwater pipe network. Background Art

[0002] In recent years, my country's urbanization process has been advancing rapidly, and the impermeable ground has continued to increase, blocking the natural channel for rainwater to infiltrate into the ground. Rainfall has gathered quickly, and heavy rainfall in a short period of time can easily form high-peak and large-volume waterlogging. The water level of the peripheral water network has risen year by year, and the difficulty of external drainage through the pipeline network has increased. The probability of waterlogging in the same scale of rainstorm has increased significantly.

[0003] In the related technology, the rainwater pipe network in the urban area is comprehensively renovated by expanding the pipe diameter or appropriately increasing the pipe design slope, so as to improve the urban waterlogging disaster by improving the drainage capacity of the urban rainwater pipe network. The engineering investment in the renovation process is large and the time is long.

[0004] However, in the related technologies, the overall transformation of the pipeline network by expanding the pipe diameter, increasing the pipeline design slope, etc., increases the investment cost and takes a long time, and cannot improve the supporting effect of high water levels in rivers on pipeline drainage. The applicability of urban rainwater pipeline network transformation is low, and the drainage capacity of urban rainwater pipeline networks is reduced, which needs to be urgently addressed. Summary of the invention

[0005] The present application provides a method, device, equipment and medium for optimizing the drainage capacity of an urban rainwater pipe network, in order to solve the problem in the related art that the comprehensive transformation of the pipe network is carried out by expanding the pipe diameter, increasing the pipe design slope, etc., which increases the investment cost and takes a long time, and cannot improve the supporting effect of the high water level of the river on the drainage of the pipe network. The applicability of the transformation of the urban rainwater pipe network is low, thereby reducing the drainage capacity of the urban rainwater pipe network.

[0006] The first aspect of the present application provides a method for optimizing the drainage capacity of an urban rainwater pipe network, comprising the following steps: obtaining an adjustable range of a river water level in a target study area, and determining a target river water level value within the adjustable range of the river water level; determining the drainage flow of a target rainwater pipe network corresponding to the target river water level value, and analyzing the inverse of a target project cost corresponding to the target river drainage pump station flow required for the target river water level value; determining a first target curve using the target river water level value and the drainage flow of the target rainwater pipe network, and determining a second target curve based on the target river water level value and the inverse of the target project cost, and obtaining a target intersection area based on the first target curve and the second target curve, and determining a target river water level control range corresponding to the target intersection area, and adjusting the drainage flow of the urban rainwater pipe network according to the target river water level control range to optimize the drainage capacity of the urban rainwater pipe network.

[0007] Optionally, in one embodiment of the present application, obtaining the adjustable range of river water level in the target study area includes: selecting the maximum value of river regulation water level using ground elevation data of the target study area, and determining the minimum value of river regulation water level based on the maximum value of river regulation water level; determining the adjustable range of river water level based on the maximum value of river regulation water level and the minimum value of river regulation water level.

[0008] Optionally, in one embodiment of the present application, determining the drainage flow of the target rainwater pipe network corresponding to the target river water level value includes: calculating the drainage flow of the target rainwater pipe network corresponding to the target river water level value based on a first preset simulation method.

[0009] Optionally, in one embodiment of the present application, the analysis of the inverse of the target project cost corresponding to the target river drainage pump station flow required for the target river water level value includes: based on a second preset simulation method, analyzing the target river drainage pump station flow required for the target river water level value; using the target river drainage pump station flow to calculate the project cost of the target river drainage pump station, and determining the inverse of the target project cost.

[0010] Optionally, in one embodiment of the present application, obtaining the target intersection area based on the first target curve and the second target curve includes: determining a target intersection point of the first target curve and the second target curve; and selecting a target intersection area of ​​the first target curve and the second target curve according to preset conditions.

[0011] The second aspect of the present application provides an optimization device for the drainage capacity of an urban rainwater pipe network, including: an acquisition module, used to acquire the adjustable range of the river water level in a target study area, and determine the target river water level value of the adjustable range of the river water level; a determination module, used to determine the drainage flow of the target rainwater pipe network corresponding to the target river water level value, and analyze the inverse of the target project cost corresponding to the target river drainage pump station flow required by the target river water level value; an adjustment module, used to determine a first target curve using the target river water level value and the drainage flow of the target rainwater pipe network, and determine a second target curve according to the target river water level value and the inverse of the target project cost, and obtain a target intersection area based on the first target curve and the second target curve, and determine the target river water level control range corresponding to the target intersection area, and adjust the drainage flow of the urban rainwater pipe network according to the target river water level control range to optimize the drainage capacity of the urban rainwater pipe network.

[0012] Optionally, in one embodiment of the present application, the acquisition module includes: an acquisition unit, used to select the maximum value of the river channel regulation water level using the ground elevation data of the target study area, and determine the minimum value of the river channel regulation water level based on the maximum value of the river channel regulation water level; a first determination unit, used to determine the controllable range of the river channel water level based on the maximum value of the river channel regulation water level and the minimum value of the river channel regulation water level.

[0013] Optionally, in one embodiment of the present application, the determination module includes: a first calculation unit, configured to calculate the drainage flow of the target rainwater pipe network corresponding to the target river water level value based on a first preset simulation method.

[0014] Optionally, in one embodiment of the present application, the determination module includes: an analysis unit, used to analyze the target river drainage pump station flow required for the target river water level value based on a second preset simulation method; a second calculation unit, used to calculate the project cost of the target river drainage pump station using the target river drainage pump station flow, and determine the inverse of the target project cost.

[0015] Optionally, in one embodiment of the present application, the adjustment module includes: a second determination unit, used to determine a target intersection point of the first target curve and the second target curve; and a selection unit, used to select a target intersection area of ​​the first target curve and the second target curve according to preset conditions.

[0016] The third aspect of the present application provides an electronic device, comprising: a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor executes the program to implement the method for optimizing the drainage capacity of an urban rainwater pipe network as described in the above embodiment.

[0017] The fourth aspect of the present application provides a computer-readable storage medium, which stores a computer program. When the program is executed by a processor, it implements the above method for optimizing the drainage capacity of an urban rainwater pipe network.

[0018] The fifth aspect of the present application provides a computer program product, including a computer program, which is executed by a processor to implement the above method for optimizing the drainage capacity of an urban rainwater pipe network.

[0019] The embodiment of the present application can determine the target river water level value of the adjustable range of the river water level in the target research area, and determine the drainage flow of the target rainwater pipe network corresponding to the target river water level value, analyze the inverse of the target engineering cost corresponding to the target river drainage pump station flow required by the target river water level value, determine the first curve using the target river water level value and the drainage flow, and determine the second curve according to the target river water level value and the inverse of the target engineering cost, and select the intersection area of ​​the first curve and the second curve to adjust the drainage flow of the urban rainwater pipe network using the target river water level control range corresponding to the intersection area, effectively reduce the transformation cost, and improve the drainage capacity of the urban rainwater pipe network. Thus, the problem that the comprehensive transformation of the pipe network by expanding the pipe diameter, increasing the pipeline design slope, etc. in the related art is solved, which increases the investment cost and takes a long time, and cannot improve the supporting effect of the high water level of the river on the pipe network drainage, the applicability of the urban rainwater pipe network transformation is low, and the drainage capacity of the urban rainwater pipe network is reduced.

[0020] Additional aspects and advantages of the present application will be given in part in the description below, and in part will become apparent from the description below, or will be learned through the practice of the present application. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] The above and / or additional aspects and advantages of the present application will become apparent and easily understood from the following description of the embodiments in conjunction with the accompanying drawings, in which:

[0022] Figure 1 A flow chart of a method for optimizing the drainage capacity of an urban rainwater pipe network provided according to an embodiment of the present application;

[0023] Figure 2 This is a schematic diagram of determining the adjustable range of river water level in a specific embodiment of the present application;

[0024] Figure 3 A schematic diagram of determining the drainage flow of a rainwater pipe network according to a specific embodiment of the present application;

[0025] Figure 4 A schematic diagram of determining the inverse of the construction cost according to a specific embodiment of the present application;

[0026] Figure 5 A schematic diagram of a first target curve and a second target curve in a drawing coordinate system according to a specific embodiment of the present application;

[0027] Figure 6 A schematic diagram of a coordinate system established for a specific embodiment of the present application;

[0028] Figure 7 A schematic diagram of selecting an intersection area for a specific embodiment of the present application;

[0029] Figure 8A schematic diagram of the structure of a device for optimizing the drainage capacity of an urban rainwater pipe network provided according to an embodiment of the present application;

[0030] Fig. 9 It is a schematic diagram of the structure of an electronic device provided according to an embodiment of the present application. DETAILED DESCRIPTION

[0031] The embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present application, and should not be construed as limiting the present application.

[0032] The following describes the method, device, equipment and medium for optimizing the drainage capacity of the urban rainwater pipe network in the embodiments of the present application with reference to the accompanying drawings. In view of the related technologies mentioned in the above background technology, the comprehensive transformation of the pipeline network by expanding the pipe diameter, increasing the pipeline design slope, etc., increases the investment cost and takes a long time, and cannot improve the supporting effect of the high water level of the river on the drainage of the pipeline network. The applicability of the transformation of the urban rainwater pipeline network is low, and the drainage capacity of the urban rainwater pipeline network is reduced. The present application provides a method for optimizing the drainage capacity of the urban rainwater pipeline network. In this method, the target river water level value of the river water level controllable range in the target study area can be determined, and the drainage flow of the target rainwater pipeline network corresponding to the target river water level value can be determined. The inverse of the target project cost corresponding to the target river drainage pump station flow required by the target river water level value is analyzed, and the first curve is determined using the target river water level value and the drainage flow, and the second curve is determined according to the target river water level value and the inverse of the target project cost, and the intersection area of ​​the first curve and the second curve is selected to use the target river water level control range corresponding to the intersection area to adjust the drainage flow of the urban rainwater pipeline network, effectively reducing the transformation cost and improving the drainage capacity of the urban rainwater pipeline network. This solves the problem in related technologies that the overall renovation of the pipeline network by expanding the pipe diameter, increasing the pipeline design slope, etc., increases the investment cost and takes a long time, and cannot improve the supporting effect of the high water level of the river on the pipeline drainage, the applicability of the urban rainwater pipeline network renovation is low, and the drainage capacity of the urban rainwater pipeline network is reduced.

[0033] Specifically, Figure 1 A flow chart of a method for optimizing the drainage capacity of an urban rainwater pipe network provided in an embodiment of the present application.

[0034] like Figure 1 As shown, the method for optimizing the drainage capacity of the urban rainwater pipe network includes the following steps:

[0035] In step S101, the adjustable range of the river water level in the target study area is obtained, and the target river water level value of the adjustable range of the river water level is determined.

[0036] In the embodiment of the present application, the target study area is an area within a city where the drainage capacity of the rainwater pipe network needs to be improved; the target river water level value is the river water level value used for analysis in this application.

[0037] It can be understood that the embodiment of the present application can obtain the adjustable range of the river water level in the target study area in the following steps, that is, the highest value and the lowest value of the river water level, and determine the target river water level value of the adjustable range of the river water level. For example, the embodiment of the present application can select the river water level value for analysis in the adjustable range of the river water level, which can be recorded as H1, H2, ..., H n , effectively improving the feasibility of optimizing the drainage capacity of urban rainwater pipe networks.

[0038] Optionally, in one embodiment of the present application, the adjustable range of river water level in the target study area is obtained, including: selecting the maximum value of the river control water level using the ground elevation data of the target study area, and determining the minimum value of the river control water level based on the maximum value of the river control water level; determining the adjustable range of the river water level based on the maximum value of the river control water level and the minimum value of the river control water level.

[0039] In the actual implementation process, Figure 2 As shown, the embodiment of the present application can determine the maximum value H of the river channel regulation water level according to the ground elevation of the study area. H , the highest value H H Generally, it is 0.3 to 0.5 m below the ground elevation. Then, the lowest value of the river channel water level H is determined according to the highest value of the river channel water level. L , the minimum value H L Generally, it is 0.5 to 1.0 m below the highest value. Therefore, the adjustable range of the river water level is determined according to the highest and lowest values ​​of the river water level, i.e. H H ~H L , and thus the river water level can be analyzed more accurately.

[0040] In step S102, the drainage flow of the target rainwater pipe network corresponding to the target river water level value is determined, and the inverse of the target engineering cost corresponding to the target river drainage pump station flow required by the target river water level value is analyzed.

[0041] It can be understood that the embodiments of the present application can simulate and calculate the drainage flow of the rainwater pipe network corresponding to different river water level values, wherein the drainage flow of the rainwater pipe network can be recorded as Q, and analyze the river drainage pump station flow required for different river water level control values, and then determine the inverse of the required project cost based on the river drainage pump station flow, wherein the inverse of the project cost can be recorded as 1 / M, thereby effectively controlling the optimization cost of the urban rainwater pipe network.

[0042] Optionally, in one embodiment of the present application, determining the drainage flow of the target rainwater pipe network corresponding to the target river water level value includes: calculating the drainage flow of the target rainwater pipe network corresponding to the target river water level value based on a first preset simulation method.

[0043] In the embodiment of the present application, the first preset simulation method can be various mathematical model calculations, etc., which can predict the quantitative value of the drainage flow of the rainwater pipe network under certain given conditions. The specific calculation method is not specifically limited here.

[0044] As a possible way to achieve this, Figure 3 As shown, the embodiment of the present application can simulate and calculate the drainage flow Q of the rainwater pipe network corresponding to the water level value of each river channel, that is, H1, H2, ... H n The corresponding drainage flow of the rainwater pipe network is Q1, Q2, ... Q n , effectively improving the convenience of optimizing the drainage capacity of urban rainwater pipe networks.

[0045] Optionally, in one embodiment of the present application, the inverse of the target project cost corresponding to the target river drainage pump station flow required for the target river water level value is analyzed, including: based on a second preset simulation method, analyzing the target river drainage pump station flow required for the target river water level value; using the target river drainage pump station flow to calculate the project cost of the target river drainage pump station, and determining the inverse of the target project cost.

[0046] In the embodiment of the present application, the second preset simulation method can be various mathematical formulas, various mathematical model calculations, etc., which can predict the quantitative value of the flow of a river drainage pump station under certain given conditions. The specific calculation method is not specifically limited here.

[0047] In some embodiments, Figure 4 As shown, the embodiment of the present application can simulate and calculate the flow rate N of the river drainage pump station required for each river water level value, and calculate the engineering cost M required to build the flow rate N of the river drainage pump station, and obtain the inverse of the engineering cost 1 / M, so as to obtain H1, H2, ... H n The corresponding inverse of the project cost is 1 / M1, 1 / M2, ... 1 / M n , effectively reducing the cost of optimizing the drainage capacity of the urban rainwater pipe network.

[0048] In step S103, a first target curve is determined using the target river water level value and the drainage flow of the target rainwater pipe network, and a second target curve is determined based on the target river water level value and the inverse of the target project cost, and a target intersection area is obtained based on the first target curve and the second target curve, and a target river water level control range corresponding to the target intersection area is determined, and the drainage flow of the urban rainwater pipe network is adjusted according to the target river water level control range to optimize the drainage capacity of the urban rainwater pipe network.

[0049] It is understandable that the embodiment of the present application can use the target river water level value and the drainage flow of the target rainwater pipe network to determine the first target curve, for example, in combination with Figure 5 and Figure 6 As shown, the embodiment of the present application can establish a coordinate system, where the X-axis is the river water level value, the Y-axis is the drainage flow of the rainwater pipe network, and the Y-axis is the inverse of the project cost. In this coordinate system, a first target curve of the river water level value and the drainage flow of the rainwater pipe network is drawn, that is, Figure 6 The realization curve in the first target curve and the second target curve of the inverse of the project cost, that is, Figure 6 The dotted curve in the figure can then be selected as the target intersection area of ​​the first target curve and the second target curve in the following steps, so as to use the target river water level control range corresponding to the intersection area to adjust the drainage flow of the urban rainwater pipe network. This can effectively avoid excessive investment due to excessive project scale and reduce the cost of transformation. It can also effectively alleviate the supporting effect of high water level in the river on the drainage of the rainwater pipe network and improve the drainage capacity of the pipe network.

[0050] Among them, in establishing Figure 6 After the coordinate system in the first simulation calculation, the embodiment of the present application calculates the n regulated river water level values ​​H1, H2, ... H n and the drainage flow of the rainwater pipe network Q1, Q2, ... Q n , respectively, are drawn in the established coordinate system, and each point is connected with a smooth curve or with a broken line when the points are dense, to obtain a first target curve; then, the embodiment of the present application can be based on the n regulated river water level values ​​H1, H2, ... H determined in the second simulation calculation n And the reciprocal of the project cost 1 / M1, 1 / M2, ... 1 / M n , respectively draw them in the established coordinate system, connect the points with smooth curves or connect the points with broken lines when the points are dense, and get the second target curve.

[0051] Among them, n regulated river water level values ​​H1, H2, ... H n and the drainage flow of the rainwater pipe network Q1, Q2, ... Q n There is a one-to-one correspondence between n regulated river water level values ​​H1, H2, ...H nAnd the reciprocal of the project cost 1 / M1, 1 / M2, ... 1 / M n It also corresponds one to one.

[0052] In one embodiment of the present application, obtaining a target intersection area based on the first target curve and the second target curve includes: determining a target intersection point of the first target curve and the second target curve; and selecting a target intersection area of ​​the first target curve and the second target curve under preset conditions.

[0053] In the present application example, the preset conditions are conditions for maximizing the project benefits.

[0054] In some instances, such as Figure 7 As shown, the embodiment of the present application can determine the intersection of the first target curve and the second target curve, determine the data within the range near the intersection, and analyze the actual rationality of the data, so as to determine the range of the intersection area. That is to say, the intersection area is determined within a certain range near the intersection, which can effectively exert the benefits of the project and avoid the waste of investment caused by the excessive scale of the water conservancy project due to the low water level control, as well as the problems of poor effect and failure to give full play to the benefits of the project due to the high water level control.

[0055] According to the optimization method of the drainage capacity of the urban rainwater pipe network proposed in the embodiment of the present application, the target river water level value of the river water level controllable range of the target study area can be determined, and the drainage flow of the target rainwater pipe network corresponding to the target river water level value can be determined, and the inverse of the target engineering cost corresponding to the target river drainage pump station flow required by the target river water level value can be analyzed, and the first curve can be determined by using the target river water level value and the drainage flow, and the second curve can be determined according to the target river water level value and the inverse of the target engineering cost, and the intersection area of ​​the first curve and the second curve can be selected to adjust the drainage flow of the urban rainwater pipe network by using the target river water level control range corresponding to the intersection area, effectively reducing the transformation cost and improving the drainage capacity of the urban rainwater pipe network. Thus, the problem that the comprehensive transformation of the pipe network by expanding the pipe diameter, increasing the pipeline design slope, etc. in the related art is solved, which increases the investment cost and takes a long time, and cannot improve the supporting effect of the high water level of the river on the pipe network drainage, the applicability of the urban rainwater pipe network transformation is low, and the drainage capacity of the urban rainwater pipe network is reduced.

[0056] Next, a device for optimizing the drainage capacity of an urban rainwater pipe network proposed in accordance with an embodiment of the present application will be described with reference to the accompanying drawings.

[0057] Figure 8 It is a block diagram of a device for optimizing the drainage capacity of an urban rainwater pipe network according to an embodiment of the present application.

[0058] like Figure 8As shown, the device 10 for optimizing the drainage capacity of the urban rainwater pipe network includes: an acquisition module 100 , a determination module 200 and an adjustment module 300 .

[0059] Specifically, the acquisition module 100 is used to obtain the adjustable range of the river water level in the target research area, and determine the target river water level value in the adjustable range of the river water level.

[0060] The determination module 200 is used to determine the drainage flow of the target rainwater pipe network corresponding to the target river water level value, and analyze the inverse of the target engineering cost corresponding to the target river drainage pump station flow required by the target river water level value.

[0061] The adjustment module 300 is used to determine a first target curve using the target river water level value and the drainage flow of the target rainwater pipe network, and to determine a second target curve based on the target river water level value and the inverse of the target project cost, and to obtain a target intersection area based on the first target curve and the second target curve, and to determine a target river water level control range corresponding to the target intersection area, and to adjust the drainage flow of the urban rainwater pipe network according to the target river water level control range to optimize the drainage capacity of the urban rainwater pipe network.

[0062] Optionally, in one embodiment of the present application, the acquisition module 100 includes: an acquisition unit and a first determination unit.

[0063] Among them, the acquisition unit is used to select the maximum value of the river channel regulation water level using the ground elevation data of the target study area, and determine the minimum value of the river channel regulation water level based on the maximum value of the river channel regulation water level.

[0064] The first determining unit is used to determine the adjustable range of the river channel water level according to the maximum value of the river channel regulation water level and the minimum value of the river channel regulation water level.

[0065] Optionally, in one embodiment of the present application, the determination module 200 includes: a first calculation unit.

[0066] Among them, the first calculation unit is used to calculate the drainage flow of the target rainwater pipe network corresponding to the target river water level value based on the first preset simulation method.

[0067] Optionally, in one embodiment of the present application, the determination module 200 includes: an analysis unit and a second calculation unit.

[0068] Among them, the analysis unit is used to analyze the target river drainage pump station flow required for the target river water level value based on the second preset simulation method.

[0069] The second calculation unit is used to calculate the engineering cost of the target river drainage pump station by using the flow of the target river drainage pump station, and determine the inverse of the target engineering cost.

[0070] Optionally, in one embodiment of the present application, the adjustment module 300 includes: a second determination unit and a selection unit.

[0071] The second determining unit is used to determine a target intersection point between the first target curve and the second target curve.

[0072] The selection unit is used to select a target intersection area of ​​the first target curve and the second target curve according to a preset condition.

[0073] It should be noted that the aforementioned explanation of the embodiment of the method for optimizing the drainage capacity of an urban rainwater pipe network is also applicable to the device for optimizing the drainage capacity of an urban rainwater pipe network of this embodiment, and will not be repeated here.

[0074] According to the optimization device for the drainage capacity of the urban rainwater pipe network proposed in the embodiment of the present application, the target river water level value of the adjustable range of the river water level in the target research area can be determined, and the drainage flow of the target rainwater pipe network corresponding to the target river water level value can be determined, and the inverse of the target engineering cost corresponding to the target river drainage pump station flow required by the target river water level value can be analyzed, and the first curve can be determined by using the target river water level value and the drainage flow, and the second curve can be determined according to the target river water level value and the inverse of the target engineering cost, and the intersection area of ​​the first curve and the second curve can be selected to adjust the drainage flow of the urban rainwater pipe network by using the target river water level control range corresponding to the intersection area, effectively reducing the transformation cost and improving the drainage capacity of the urban rainwater pipe network. Thus, the problem that the comprehensive transformation of the pipe network by expanding the pipe diameter, increasing the pipeline design slope, etc. in the related art is solved, which increases the investment cost and takes a long time, and cannot improve the supporting effect of the high water level of the river on the pipe network drainage, the applicability of the urban rainwater pipe network transformation is low, and the drainage capacity of the urban rainwater pipe network is reduced.

[0075] Fig. 9 A schematic diagram of the structure of an electronic device provided in an embodiment of the present application. The electronic device may include:

[0076] A memory 901 , a processor 902 , and a computer program stored in the memory 901 and executable on the processor 902 .

[0077] When the processor 902 executes the program, the method for optimizing the drainage capacity of the urban rainwater pipe network provided in the above embodiment is implemented.

[0078] Furthermore, the electronic device further comprises:

[0079] The communication interface 903 is used for communication between the memory 901 and the processor 902 .

[0080] The memory 901 is used to store computer programs that can be executed on the processor 902 .

[0081] The memory 901 may include a high-speed RAM memory, and may also include a non-volatile memory (non-volatile memory), such as at least one disk memory.

[0082] If the memory 901, the processor 902 and the communication interface 903 are implemented independently, the communication interface 903, the memory 901 and the processor 902 can be connected to each other through a bus and communicate with each other. The bus can be an Industry Standard Architecture (ISA) bus, a Peripheral Component Interconnect (PCI) bus or an Extended Industry Standard Architecture (EISA) bus. The bus can be divided into an address bus, a data bus, a control bus, etc. For ease of representation, Fig. 9 Only one thick line is used in the diagram, but this does not mean that there is only one bus or only one type of bus.

[0083] Optionally, in a specific implementation, if the memory 901, the processor 902 and the communication interface 903 are integrated on a chip, the memory 901, the processor 902 and the communication interface 903 can communicate with each other through an internal interface.

[0084] The processor 902 may be a central processing unit (CPU), or an application specific integrated circuit (ASIC), or one or more integrated circuits configured to implement the embodiments of the present application.

[0085] This embodiment also provides a computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the above-mentioned method for optimizing the drainage capacity of an urban rainwater pipe network.

[0086] This embodiment also provides a computer program product, including a computer program, which is executed by a processor to implement the above method for optimizing the drainage capacity of an urban rainwater pipe network.

[0087] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or N embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

[0088] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include at least one of the features. In the description of this application, "N" means at least two, such as two, three, etc., unless otherwise clearly and specifically defined.

[0089] Any process or method description in a flowchart or otherwise described herein may be understood to represent a module, fragment or portion of code comprising one or N executable instructions for implementing the steps of a custom logical function or process, and the scope of the preferred embodiments of the present application includes alternative implementations in which functions may not be performed in the order shown or discussed, including performing functions in a substantially simultaneous manner or in reverse order depending on the functions involved, which should be understood by technicians in the technical field to which the embodiments of the present application belong.

[0090] The logic and / or steps represented in the flowchart or otherwise described herein, for example, can be considered as an ordered list of executable instructions for implementing logical functions, and can be embodied in any computer-readable medium for use by an instruction execution system, device or apparatus (such as a computer-based system, a system including a processor, or other system that can fetch instructions from an instruction execution system, device or apparatus and execute instructions), or in combination with these instruction execution systems, devices or apparatuses. For the purpose of this specification, "computer-readable medium" can be any device that can contain, store, communicate, propagate or transmit a program for use by an instruction execution system, device or apparatus, or in combination with these instruction execution systems, devices or apparatuses. More specific examples of computer-readable media (a non-exhaustive list) include the following: an electrical connection with one or N wirings (electronic devices), a portable computer disk box (magnetic device), a random access memory (RAM), a read-only memory (ROM), an erasable and programmable read-only memory (EPROM or flash memory), a fiber optic device, and a portable compact disk read-only memory (CDROM). In addition, the computer-readable medium may even be paper or other suitable medium on which the program is printed, since the program may be obtained electronically by optically scanning the paper or other medium and then editing, interpreting or processing in other suitable ways as necessary and then storing it in a computer memory.

[0091] It should be understood that the various parts of the present application can be implemented by hardware, software, firmware or a combination thereof. In the above embodiment, the N steps or methods can be implemented by software or firmware stored in a memory and executed by a suitable instruction execution system. For example, if implemented by hardware, as in another embodiment, it can be implemented by any one or a combination of the following technologies known in the art: a discrete logic circuit having a logic gate circuit for implementing a logic function for a data signal, a dedicated integrated circuit having a suitable combination of logic gate circuits, a programmable gate array (PGA), a field programmable gate array (FPGA), etc.

[0092] A person skilled in the art may understand that all or part of the steps in the method for implementing the above-mentioned embodiment may be completed by instructing related hardware through a program, and the program may be stored in a computer-readable storage medium, which, when executed, includes one or a combination of the steps of the method embodiment.

[0093] In addition, each functional unit in each embodiment of the present application may be integrated into a processing module, or each unit may exist physically separately, or two or more units may be integrated into one module. The above-mentioned integrated module may be implemented in the form of hardware or in the form of a software functional module. If the integrated module is implemented in the form of a software functional module and sold or used as an independent product, it may also be stored in a computer-readable storage medium.

[0094] The storage medium mentioned above may be a read-only memory, a magnetic disk or an optical disk, etc. Although the embodiments of the present application have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limiting the present application. A person of ordinary skill in the art may change, modify, replace and modify the above embodiments within the scope of the present application.

Claims

1. A method for optimizing the drainage capacity of an urban rainwater pipe network, characterized in that: The following steps are involved: Obtaining a controllable range of river water level in a target study area, and determining a target river water level value within the controllable range of river water level; Determine the drainage flow of the target rainwater pipe network corresponding to the target river water level value, and analyze the inverse of the target engineering cost corresponding to the target river drainage pump station flow required by the target river water level value; A first target curve is determined using the target river water level value and the target stormwater pipe network drainage flow, and a second target curve is determined based on the target river water level value and the inverse of the target project cost, and a target intersection area is obtained based on the first target curve and the second target curve, and a target river water level control range corresponding to the target intersection area is determined, and the drainage flow of the urban stormwater pipe network is adjusted according to the target river water level control range to optimize the drainage capacity of the urban stormwater pipe network.

2. The method according to claim 1, characterized in that The adjustable range of the river water level in the target study area includes: Selecting the maximum value of the river channel regulation water level by using the ground elevation data of the target study area, and determining the minimum value of the river channel regulation water level according to the maximum value of the river channel regulation water level; The adjustable range of the river channel water level is determined according to the maximum value of the river channel regulated water level and the minimum value of the river channel regulated water level.

3. The method according to claim 1, characterized in that: The determining of the target drainage flow of the rainwater pipe network corresponding to the target river water level value includes: Based on a first preset simulation method, the drainage flow of the target rainwater pipe network corresponding to the target river water level value is calculated.

4. The method according to claim 1, characterized in that: The inverse of the target engineering cost corresponding to the target river drainage pump station flow required for analyzing the target river water level value includes: Based on the second preset simulation method, analyzing the target river drainage pump station flow required for the target river water level value; The target river drainage pump station flow rate is used to calculate the project cost of the target river drainage pump station, and the inverse of the target project cost is determined.

5. The method according to claim 1, characterized in that The obtaining a target intersection area based on the first target curve and the second target curve includes: determining a target intersection point of the first target curve and the second target curve; A target intersection area between the first target curve and the second target curve is selected according to a preset condition.

6. A device for optimizing the drainage capacity of an urban rainwater pipe network, characterized in that: include: An acquisition module is used to acquire the adjustable range of the river water level in the target study area and determine the target river water level value in the adjustable range of the river water level; A determination module, used to determine the drainage flow of the target rainwater pipe network corresponding to the target river water level value, and analyze the inverse of the target engineering cost corresponding to the flow of the target river drainage pump station required by the target river water level value; An adjustment module is used to determine a first target curve using the target river water level value and the drainage flow of the target rainwater pipe network, and to determine a second target curve according to the target river water level value and the inverse of the target project cost, and to obtain a target intersection area based on the first target curve and the second target curve, and to determine a target river water level control range corresponding to the target intersection area, and to adjust the drainage flow of the urban rainwater pipe network according to the target river water level control range to optimize the drainage capacity of the urban rainwater pipe network.

7. The device according to claim 6, characterized in that The acquisition module comprises: An acquisition unit, used for selecting a maximum value of a river channel regulation water level by using the ground elevation data of the target study area, and determining a minimum value of a river channel regulation water level according to the maximum value of the river channel regulation water level; The first determining unit is used to determine the adjustable range of the river channel water level according to the maximum value of the river channel regulated water level and the minimum value of the river channel regulated water level.

8. The device according to claim 6, characterized in that The determination module comprises: The first calculation unit is used to calculate the drainage flow of the target rainwater pipe network corresponding to the target river water level value based on a first preset simulation method.

9. The device according to claim 6, characterized in that The determination module comprises: An analysis unit, configured to analyze the target river drainage pump station flow required for the target river water level value based on a second preset simulation method; The second calculation unit is used to calculate the engineering cost of the target river drainage pump station using the flow of the target river drainage pump station, and determine the inverse of the target engineering cost.

10. The device according to claim 6, characterized in that The adjustment module comprises: a second determining unit, configured to determine a target intersection point of the first target curve and the second target curve; A selection unit is used to select a target intersection area of ​​the first target curve and the second target curve according to a preset condition.

11. An electronic device, characterized in that: include: A memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor executes the program to implement the method for optimizing the drainage capacity of an urban rainwater pipe network as described in any one of claims 1 to 5.

12. A computer-readable storage medium having a computer program stored thereon, characterized in that: The program is executed by a processor to implement a method for optimizing the drainage capacity of an urban rainwater pipe network as described in any one of claims 1 to 5.

13. A computer program product, comprising a computer program, characterized in that The computer program is executed by a processor to implement the method for optimizing the drainage capacity of an urban rainwater pipe network as described in any one of claims 1 to 5.