Constant-speed gas lift flowing device and equipment thereof

By setting up an inclined gas lifting and injection channel in the gas lifting device and using Rafael nozzle technology, the high-pressure gas and the well fluid flow direction are consistent, and the efficient stability and corrosion resistance of the gas lifting device are achieved, which solves the problem of The problem of low gas lifting efficiency and stability in the prior art.

CN118933679APending Publication Date: 2024-11-12SICHUAN HAOYUN TONGXING OIL & GAS ENGINEERING TECHNOLOGY SERVICES CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411084462.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-08
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

In the existing gas lifting device, the high-pressure gas injection direction is inconsistent with the fluid direction in the wellbore, resulting in energy loss, gas lifting efficiency and stability reduction, and a "short circuit" is easily formed at low-level pressure, resulting in ineffective gas lifting.

Method used

Design a constant-speed gas lifting flow device. By setting a cylinder in the middle of the oil pipe and opening an inclined gas lifting and injection channel on the side wall of the cylinder, the high-pressure gas flow direction is almost the same as the well fluid flow direction, using Rafael The nozzle technology enables the gas to reach a critical flow state, reduces liquid slippage, and reduces erosion through dislocation spiral deployment.

Benefits of technology

It improves the gas lifting efficiency and stability, reduces liquid slippage, enhances liquid discharge efficiency, and reduces scale deposition, improving gas-liquid mixing and drainage efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933679A_ABST
    Figure CN118933679A_ABST
Patent Text Reader

Abstract

The invention discloses a constant-speed gas lift flowing device and equipment thereof, and relates to the technical field of gas production processes, the constant-speed gas lift flowing device comprises a barrel connected in series in the middle of an oil pipe, and the two ends of the barrel are open and both communicated with the oil pipe; a plurality of gas lift gas injection channels are formed in the annular side wall of the cylinder body, and the two ends of each gas lift gas injection channel penetrate through the inner wall and the outer wall of the cylinder body respectively; in the direction from the outer end to the inner end of the gas lift gas injection channel, the gas lift gas injection channel inclines towards the flowing direction of well fluid; the gas lift gas injection channel comprises a Laval pipe section in the length direction of the gas lift gas injection channel. By the adoption of the scheme, the flowing direction of high-pressure gas is almost consistent with the flowing direction of fluid in a shaft, the high-pressure gas transmits kinetic energy to liquid flowing along the pipe wall at a low speed, and therefore liquid slippage is reduced, the gas lifting efficiency is improved, injected gas can reach critical flowing, flowing is in a constant-speed state, liquid drainage is uniform, and the liquid drainage efficiency is better improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of gas production technology, and in particular to a constant speed gas lift flow device and equipment thereof. Background Art

[0002] The gas lift process is an artificial lifting process that injects high-pressure gas into the oil pipe through a high-pressure gas source to reduce the flow pressure gradient above the gas injection point, reduce the slip loss during the lifting process, discharge the bottom hole liquid, increase the production pressure difference, and restore or improve the production capacity of the gas well. Compared with other processes, the gas lift process has great advantages. It has a wide range of applications, a low failure rate, and a long maintenance-free period.

[0003] There are dozens of gas lift valves of various types currently used abroad. The commonly used unbalanced bellows casing pressure-operated valve in China. The main gas lift valve currently used is the gas injection pressure-operated valve. The gas lift valve mandrel is the carrier of the valve. At present, it is suitable for various situations (conventional gas lift, high-pressure gas lift, acidification and drainage process, suitable for high-sulfur gas wells), suitable for various tubing sizes (1.5in, 2in, 2.5in, 3.0in), various buckle types, and different types of gas lift valve mandrels suitable for different corrosive media (ordinary materials, stainless steel, 35CrMo, 718). The integral gas lift valve mandrel can be made stronger than the connected tubing of the same type, and has a service life longer than the tubing to ensure that the process will not fail due to the mandrel. At present, the integral mandrel completely replaces the welded mandrel.

[0004] The use of gas lift valves is currently the main process for water drainage and gas production in gas lift, but the current process has the following problems:

[0005] 1) Natural gas and water flow upward from the bottom of the well to the wellhead, while when the conventional gas lift injection gas enters the working cylinder from the annulus through the gas lift valve, the injection direction of the injection gas is downward, see Figure 3 The gas lift ejection direction of the middle working cylinder. The downward-flowing injected gas will cause a large amount of energy loss, and the gas lift efficiency and gas lift stability will be greatly reduced.

[0006] 2) The working tube of the gas lift valve is a mixing channel for high-pressure gas and well fluid. When gas lift is not implemented, the flow velocity in the center of the working tube is the fastest, and the flow velocity along the pipe wall is the lowest. Since the outlet of the gas lift valve working tube is at a 90-degree angle to the flow direction of the fluid in the oil pipe, when the gas lift gas enters the working tube from the annulus through the working tube, it will pass through the low-speed area, the central high-speed area, and then to the low-speed area on the opposite pipe wall. The high-pressure gas forms turbulence locally, and the gas lift efficiency is low.

[0007] 3) In the design of process parameters for conventional gas lift devices, multi-point gas injection should be avoided as much as possible, because this will reduce the gas lift efficiency. At the same time, the injection pressure, injection volume and drainage volume will fluctuate violently. Even when the formation pressure drops to a certain level, a "short circuit" will be formed, causing the injected gas to circulate in the wellbore, resulting in ineffective gas lift.

[0008] In summary, there is an urgent need for a gas lift flow device that can improve gas lift efficiency and gas lift stability. Summary of the invention

[0009] The present invention aims to solve the deficiencies of the prior art and to provide a constant speed gas lift flow device and equipment thereof. By adopting this solution, the flow direction of the high pressure gas is almost consistent with the flow direction of the fluid in the wellbore. The high pressure gas transfers kinetic energy to the liquid flowing at a low speed along the pipe wall, thereby reducing liquid slippage and improving the gas lift efficiency. The injected gas can reach the critical flow and the flow is in a constant speed state, which is convenient for uniform liquid discharge and more conducive to improving the liquid discharge efficiency.

[0010] The present invention is achieved through the following technical solutions:

[0011] A constant velocity gas lift flow device, comprising:

[0012] A cylinder connected in series in the middle of the oil pipe, with both ends of the cylinder open and connected to the oil pipe;

[0013] A plurality of gas lift and gas injection channels are provided on the circumferential side wall of the cylinder, and two ends of the gas lift and gas injection channels respectively penetrate the inner wall and the outer wall of the cylinder;

[0014] From the outer end to the inner end of the gas lift gas injection channel, the gas lift gas injection channel is inclined toward the direction of well fluid flow;

[0015] Along its length direction, the gas lift and gas injection channel includes a Rafale pipe section.

[0016] In the prior art, the gas lift process is an artificial lift process that uses a high-pressure gas source to inject high-pressure gas into the oil pipe to reduce the flow pressure gradient above the gas injection point, reduce slippage losses during the lifting process, discharge the bottom hole liquid, increase the production pressure difference, and restore or improve the production capacity of the gas well. Compared with other processes, the gas lift process has great advantages, it has a wide range of applications, low failure rate, and a long maintenance-free period. Figure 1 and Figure 2As shown, let AA be the static liquid level position after the gas well is flooded. When high-pressure gas is injected from the casing, the high-pressure gas causes the casing liquid level to drop and the tubing liquid level to rise. When the casing liquid level drops to the inlet BB of the first gas lift valve, the gas lift valve is opened by the pressure of the high-pressure gas, and the high-pressure gas enters the tubing through the gas lift valve. Under the action of the gas expansion force, the liquid above the BB interface is lifted to the ground. At the same time, due to the large amount of high-pressure gas entering the tubing, the casing pressure is reduced. When the casing pressure drops to the closing pressure of the gas lift valve, the first gas lift valve is closed. Then, the high-pressure gas forces the casing liquid level to drop and the tubing liquid level to rise. When the casing liquid level drops to the inlet CC of the second gas lift valve, the second gas lift valve is opened by the high-pressure gas, and the liquid above the CC-BB interface is lifted to the ground. In this way, the liquid level in the tubing is continuously lowered until the gas well resumes production. In the process of process parameter design, the depth, opening pressure and other parameters are designed starting from the first gas lift valve above, and then the second gas lift valve, and then proceed downwards. Therefore, through the above-mentioned gas lift valve gas production principle, the following will occur: 1) the injected gas flowing downward will cause a large amount of energy loss, and the gas lift efficiency and gas lift stability will be greatly reduced; 2) when the gas lift injected gas passes through the annulus into the interior of the working barrel, it will pass through the low-speed area, the central high-speed area, and then to the low-speed area of ​​the opposite pipe wall in sequence. The high-pressure gas will form turbulence locally, and the gas lift efficiency is low; 3) when the formation pressure drops to a certain level, a "short circuit" is formed, causing the injected gas to circulate in the wellbore, resulting in the ineffectiveness of gas lift and other problems. Therefore, the present invention provides a constant-speed gas lift flow device and equipment thereof. By adopting this scheme, the flow direction of the high-pressure gas is almost consistent with the flow direction of the fluid in the wellbore. The high-pressure gas transfers kinetic energy to the liquid flowing at a low speed along the pipe wall, thereby reducing liquid slippage and improving gas lift efficiency. The injected gas can reach critical flow, and the flow is in a constant speed state, which is convenient for uniform liquid discharge and more conducive to improving liquid discharge efficiency. In addition, the present invention has also made improvements in anti-erosion. Usually, the flow center speed is fast and the flow velocity along the pipe wall is low. The present invention makes the flow velocity of the pipe wall high, which can significantly reduce the deposition of scale for high-temperature wells prone to scaling. At the same time, the fast flow rate can also make some scale detach from the pipe wall. The Rafale nozzle design can significantly improve the flow state, make the gas-liquid mixing more uniform, and improve the drainage efficiency.

[0017] In the specific scheme, it includes a cylinder connected in series in the middle of the oil pipe, the cylinder and the oil pipe are coaxially arranged, and both ends are connected to the oil pipe; an inclined gas lift injection channel is arranged on the side wall of the cylinder, and the gas lift injection channel is inclined in the direction of the well fluid flow, so that the external high-pressure gas source can inject high-pressure gas into the interior through the gas lift injection channel, and the injection direction of the high-pressure gas is the same as the basic direction of the well fluid flow, so that the high-pressure gas can transfer kinetic energy to the liquid flowing along the pipe wall at a low speed, thereby reducing liquid slippage and improving gas lift efficiency. Secondly, since the gas lift injection channel includes a Rafael pipe section, using the Rafael nozzle principle, its outlet pressure is only related to the external transmission pressure; by controlling the external transmission pressure, the injected gas reaches the critical flow rate. Since the maximum speed in the constant speed gas lift flow device reaches the critical flow rate, its flow rate is the critical flow rate and it is impossible to continue to increase. Therefore, other natural gas (total gas injection volume minus total critical flow rate) naturally enters the next level flow device, thereby continuing to increase the gas lift depth, forming a relay lift, and improving the gas lift efficiency. In a word: the diameter of the valve hole of the gas lift valve on the conventional gas lift string is much larger than the nozzle size of the constant speed gas lift device. Its flow is not critical flow rate. The pressure at the valve is affected by the wellhead back pressure and fluctuates with the wellhead pressure fluctuation. The gas volume passing through the first gas lift valve also changes. However, the high-pressure gas flow in the nozzle of the designed constant speed gas lift device is critical flow, which does not change with the change of wellhead pressure and its flow rate is constant. Therefore, it flows through the critical constant speed and the speed does not change with the wellhead pressure, which further improves the gas lift efficiency. Figure 7 As shown in the figure, a schematic diagram of a high-pressure gas injection flow channel of a constant-speed gas lift flow device is shown. The principle is that after the high-pressure gas passes through the large bypass channel ① and then enters the extremely narrow channel ②, part of its potential energy is converted into kinetic energy, so that the speed of the high-pressure gas reaches or approaches the speed of sound. Its speed is constant and does not change with the change of downstream pressure. After flowing out from ③, it mixes with the well fluid. Generally, for natural gas with a relative density of 0.6, when P③ / P①<0.546, that is, when the ratio of downstream pressure to upstream pressure is less than 0.546, the gas reaches the critical flow rate. The shape of the flow channel is obtained through the critical flow rate and Lafarge nozzle theory combined with the experimental device.

[0018] In addition, the present invention has also made improvements in anti-erosion. In conventional gas lift processes, the flow center speed is usually fast and the flow velocity along the pipe wall is low. In the present invention, the high-pressure gas can transfer kinetic energy to the liquid flowing at a low speed along the pipe wall, so that the flow velocity of the pipe wall is high. For high-temperature wells that are prone to scaling, the scale deposition can be significantly reduced. At the same time, the fast flow rate can also make some scale detach from the pipe wall. The Rafale nozzle design can significantly improve the flow state, make the gas-liquid mixing more uniform, and improve the drainage efficiency.

[0019] In order to reduce turbulence and erosion, several of the gas lift injection channels are spirally distributed in the axial direction of the cylinder. In this solution, several gas lift injection channels are spirally distributed as a whole to form a complete spiral hole arrangement. The advantage is that it prevents the erosion of the inner wall of the flow device by high-pressure gas when the holes are evenly arranged in the radial direction, and the formed annular erosion zone will reduce the tensile strength of the tool. Even under the same material and process conditions, such staggered spiral deployment can significantly reduce erosion; in addition, the deployment of high-pressure gas injection holes by staggered spirals is also beneficial to reduce the impact of turbulence in the gas-liquid mixing zone, thereby improving the water-carrying efficiency of gas lift.

[0020] In order to realize the selection of the length of the cylinder and the rapid splicing, the cylinder includes a plurality of collars, which are coaxially spliced ​​in sequence. The present invention can design the specific number of holes and the aperture according to the gas injection amount and the gas injection pressure, so that the gas injection in each hole can reach the critical flow. At this time, the change of the input pressure will not cause the change of the discharge amount, and the flow is in a constant speed state; wherein, as shown in the figure, there are 6 collars, and 4 to 6 gas lift gas injection channels are arranged in each collar, preferably 4 gas lift gas injection channels, and the 4 gas lift gas injection channels are gradually increased in a spiral of 90 degrees in sequence. Between adjacent collars, each collar and the previous collar are spirally rotated 15 to 30 degrees, preferably 15 degrees, so as to form a complete spiral hole arrangement.

[0021] In order to provide an outlet end face for the injected high-pressure gas and allow the high-pressure gas to enter along the flow direction of the well fluid, the inner side of the collar includes a large-diameter section and a small-diameter section connected to each other, and the end face between the large-diameter section and the small-diameter section is a spiral end face arranged along the axial direction of the collar, and the inner end of each of the gas lift injection channels on the collar passes through the spiral end face.

[0022] In order not to affect the flow rate of the high-pressure gas and allow the high-pressure gas to smoothly enter the internal flow channel along its axial direction, the spiral end surface is inclined from the large diameter section side to the small diameter section side and is perpendicular to the axis of the gas lift injection channel.

[0023] As a redundancy solution, adjacent rings are detachably connected.

[0024] As a splicing method between several sleeves, the large diameter section and the small diameter section are respectively located at the outlet end and the inlet end of the sleeve, and the outer side of the inlet end of the sleeve is provided with a reduced diameter section, and the outer diameter of the reduced diameter section is adapted to the inner diameter of the outlet end. Adjacent sleeves and sleeves and oil pipes are connected with the outlet end through the reduced diameter section for socket connection or threaded connection. Of course, in order to make the connection node more stable, other fixed connection methods such as welding can also be used.

[0025] Further solutions:

[0026] The present invention also provides a constant speed gas lift equipment, including an oil pipe deep into the well, along the length direction of the oil pipe, a plurality of constant speed gas lift flow devices are sequentially connected in series at intervals on the oil pipe; and also includes a gas injection device, which is used to provide high-pressure gas to each of the gas lift injection channels.

[0027] In this scheme, a constant-speed gas lift flow device is used in the first upper stage. The flow mode of the injected gas in the flow channel of the gas lift device is critical flow, and its outlet pressure is only related to the external transmission pressure. Since the maximum speed in the upper constant-speed gas lift flow device reaches the critical flow rate, its flow rate is the critical flow rate and it is impossible to continue to increase. Therefore, other natural gas (total gas injection volume minus total critical flow rate) naturally enters the next-level flow device, thereby continuing to increase the gas lift depth, forming a relay lift, and improving the gas lift efficiency. In a word: the valve hole diameter of the gas lift valve on the conventional gas lift string is much larger than the nozzle size of the constant-speed gas lift device. Its flow is non-critical flow rate. The pressure at the valve is affected by the wellhead back pressure and fluctuates with the wellhead pressure fluctuation. The gas volume passing through the first gas lift valve also changes. However, in the designed constant-speed gas lift device, the high-pressure gas flow in its nozzle is critical flow, which does not change with the change of wellhead pressure, and its flow rate is constant. When the high-pressure gas source is sufficient, that is, the injection pressure and injection volume are relatively high, the first-stage constant-speed gas lift flow device can be further divided into two groups during gas lift design; usually, the first-stage constant-speed gas lift flow device has no more than 9 flow channels. If the constant-speed gas lift flow device is in two groups, it is advisable that the flow channels in each group do not exceed 4. The number design and depth position must ensure that they are in a critical flow state under the designed gas injection pressure.

[0028] Compared with the prior art, the present invention has the following advantages and beneficial effects:

[0029] 1. The present invention provides a constant speed gas lift flow device and equipment thereof, wherein the flow direction of high pressure gas is almost consistent with the flow direction of fluid in the wellbore, and the high pressure gas transfers kinetic energy to the liquid flowing at a low speed along the pipe wall, thereby reducing liquid slippage and improving gas lift efficiency.

[0030] 2. The present invention provides a constant-speed gas lift flow device and equipment thereof, and also makes improvements in anti-erosion. Usually, the flow center speed is fast and the flow speed along the pipe wall is low, while the present invention makes the flow speed of the pipe wall high, which can significantly reduce the deposition of scale for high-temperature wells prone to scaling. At the same time, the fast flow rate can also make some scale detach from the pipe wall.

[0031] 3. The present invention provides a constant-speed gas lift flow device and equipment thereof. The Lafayette nozzle design can significantly improve the flow state. The high-pressure gas flow in the nozzle is a critical flow and does not change with the change of the wellhead pressure. The flow rate is constant, which further improves the gas lift efficiency. The gas-liquid mixing is more uniform and the drainage efficiency is higher.

[0032] 4. The present invention provides a constant-speed gas lift flow device and equipment thereof, which deploys high-pressure gas injection holes by staggered spirals to prevent erosion of the inner wall of the flow device by high-pressure gas when the holes are evenly distributed in the radial direction. The formed annular erosion zone will reduce the tensile strength of the tool. Even under the same material and process conditions, such staggered spiral deployment can significantly reduce erosion; in addition, it is also beneficial to reduce the impact of turbulence in the gas-liquid mixing zone, thereby improving the water-carrying efficiency of gas lift. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] In order to more clearly illustrate the technical solutions of the exemplary embodiments of the present invention, the following briefly introduces the drawings required for use in the embodiments. It should be understood that the following drawings only illustrate certain embodiments of the present invention and should not be regarded as limiting the scope. For those of ordinary skill in the art, other relevant drawings can be obtained based on these drawings without creative work. In the drawings:

[0034] Figure 1 This is a principle diagram of the gas lift drainage gas production process in the prior art;

[0035] Figure 2 It is a schematic diagram of a downhole pipe string for a gas lift drainage and gas production process in the prior art;

[0036] Figure 3 It is a cross-sectional view of a gas lift valve working cylinder in the prior art;

[0037] Figure 4 A schematic diagram of the structure of a constant speed gas lift flow device provided by the present invention;

[0038] Figure 5 A cross-sectional view of a single collar provided for the present invention;

[0039] Figure 6 A side view of a single collar provided for the present invention;

[0040] Figure 7 This is a schematic structural diagram of the gas lift and gas injection channel provided by the present invention.

[0041] Marks and corresponding parts names in the attached drawings:

[0042] 1-cylinder, 101-throwing ring, 2-gas lift injection channel, 201-Rafale pipe section. DETAILED DESCRIPTION

[0043] In order to make the objectives, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with embodiments and drawings. The exemplary embodiments of the present invention and their description are only used to explain the present invention and are not intended to limit the present invention.

[0044] Embodiment 1:

[0045] This embodiment 1 provides a constant speed gas lift flow device, such as Figure 1-Figure 7 As shown, including:

[0046] A cylinder 1 connected in series in the middle of the oil pipe, with both ends of the cylinder 1 open and connected to the oil pipe;

[0047] A plurality of gas lift and gas injection channels 2 are provided on the circumferential side wall of the cylinder 1, and two ends of the gas lift and gas injection channels 2 respectively penetrate the inner wall and the outer wall of the cylinder 1;

[0048] From the outer end to the inner end of the gas lift gas injection channel 2, the gas lift gas injection channel 2 is inclined toward the direction of well fluid flow;

[0049] Along its length direction, the gas lift and gas injection channel 2 includes a Rafale pipe section 201 .

[0050] In the prior art, the gas lift process is an artificial lift process that uses a high-pressure gas source to inject high-pressure gas into the oil pipe to reduce the flow pressure gradient above the gas injection point, reduce slippage losses during the lifting process, discharge the bottom hole liquid, increase the production pressure difference, and restore or improve the production capacity of the gas well. Compared with other processes, the gas lift process has great advantages, it has a wide range of applications, low failure rate, and a long maintenance-free period. Figure 1 and Figure 2As shown, let AA be the static liquid level position after the gas well is flooded. When high-pressure gas is injected from the casing, the high-pressure gas causes the casing liquid level to drop and the tubing liquid level to rise. When the casing liquid level drops to the inlet BB of the first gas lift valve, the gas lift valve is opened by the pressure of the high-pressure gas, and the high-pressure gas enters the tubing through the gas lift valve. Under the action of the gas expansion force, the liquid above the BB interface is lifted to the ground. At the same time, due to the large amount of high-pressure gas entering the tubing, the casing pressure is reduced. When the casing pressure drops to the closing pressure of the gas lift valve, the first gas lift valve is closed. Then, the high-pressure gas forces the casing liquid level to drop and the tubing liquid level to rise. When the casing liquid level drops to the inlet CC of the second gas lift valve, the second gas lift valve is opened by the high-pressure gas, and the liquid above the CC-BB interface is lifted to the ground. In this way, the liquid level in the tubing is continuously lowered until the gas well resumes production. In the process of process parameter design, the depth, opening pressure and other parameters are designed starting from the first gas lift valve above, and then the second gas lift valve, and then proceed downwards. Therefore, through the above-mentioned gas lift valve gas production principle, the following will occur: 1) the injected gas flowing downward will cause a large amount of energy loss, and the gas lift efficiency and gas lift stability will be greatly reduced; 2) when the gas lift injected gas passes through the annulus into the interior of the working barrel, it will pass through the low-speed area, the central high-speed area, and then to the low-speed area of ​​the opposite pipe wall in sequence. The high-pressure gas will form turbulence locally, and the gas lift efficiency is low; 3) when the formation pressure drops to a certain level, a "short circuit" is formed, causing the injected gas to circulate in the wellbore, resulting in the ineffectiveness of gas lift and other problems. Therefore, the present invention provides a constant-speed gas lift flow device and equipment thereof. By adopting this scheme, the flow direction of the high-pressure gas is almost consistent with the flow direction of the fluid in the wellbore. The high-pressure gas transfers kinetic energy to the liquid flowing at a low speed along the pipe wall, thereby reducing liquid slippage and improving gas lift efficiency. The injected gas can reach critical flow, and the flow is in a constant speed state, which is convenient for uniform liquid discharge and more conducive to improving liquid discharge efficiency. In addition, the present invention has also made improvements in anti-erosion. Usually, the flow center speed is fast and the flow velocity along the pipe wall is low. The present invention makes the flow velocity of the pipe wall high, which can significantly reduce the deposition of scale for high-temperature wells prone to scaling. At the same time, the fast flow rate can also make some scale detach from the pipe wall. The Rafale nozzle design can significantly improve the flow state, make the gas-liquid mixing more uniform, and improve the drainage efficiency.

[0051] The specific scheme includes a cylinder 1 connected in series in the middle of the oil pipe, the cylinder 1 and the oil pipe are coaxially arranged, and both ends are connected to the oil pipe; an inclined gas lift injection channel 2 is arranged on the side wall of the cylinder 1, and the gas lift injection channel 2 is inclined in the direction of well fluid flow, so that an external high-pressure gas source can inject high-pressure gas into the interior through the gas lift injection channel 2, and the injection direction of the high-pressure gas is basically the same as the flow direction of the well fluid, so that the high-pressure gas can transfer kinetic energy to the liquid flowing at a low speed along the pipe wall, thereby reducing liquid slippage and improving gas lift efficiency. Secondly, since the gas lift injection channel 2 includes the Rafale pipe section 201, using the Rafale nozzle principle, its outlet pressure is only related to the external transmission pressure; by controlling the external transmission pressure, the injected gas reaches the critical flow rate. Since the maximum speed in the constant speed gas lift flow device reaches the critical flow rate, its flow rate is the critical flow rate and it is impossible to continue to increase. Therefore, other natural gas (total gas injection volume minus total critical flow rate) naturally enters the next level flow device, thereby continuing to increase the gas lift depth, forming a relay lift, and improving the gas lift efficiency. In a word: the valve hole diameter of the gas lift valve on the conventional gas lift string is much larger than the nozzle size of the constant speed gas lift device. Its flow is not a critical flow rate. The pressure at the valve is affected by the wellhead back pressure and fluctuates with the wellhead pressure fluctuation. The gas volume passing through the first gas lift valve also changes; and the designed constant speed gas lift device, the high-pressure gas flow in its nozzle is a critical flow, which does not change with the change of the wellhead pressure, and its flow rate is constant. Therefore, through the critical constant flow, and the speed does not change with the wellhead pressure, the gas lift efficiency is further improved. Figure 7 As shown in the figure, a schematic diagram of a high-pressure gas injection flow channel of a constant-speed gas lift flow device is shown. The principle is that after the high-pressure gas passes through the large bypass channel ① and then enters the extremely narrow channel ②, part of its potential energy is converted into kinetic energy, so that the speed of the high-pressure gas reaches or approaches the speed of sound. Its speed is constant and does not change with the change of downstream pressure. After flowing out from ③, it mixes with the well fluid. Generally, for natural gas with a relative density of 0.6, when P③ / P①<0.546, that is, when the ratio of downstream pressure to upstream pressure is less than 0.546, the gas reaches the critical flow rate. The shape of the flow channel is obtained through the critical flow rate and Lafarge nozzle theory combined with the experimental device.

[0052] In addition, the present invention has also made improvements in anti-erosion. In conventional gas lift processes, the flow center speed is usually fast and the flow velocity along the pipe wall is low. In the present invention, the high-pressure gas can transfer kinetic energy to the liquid flowing at a low speed along the pipe wall, so that the flow velocity of the pipe wall is high. For high-temperature wells that are prone to scaling, the scale deposition can be significantly reduced. At the same time, the fast flow rate can also make some scale detach from the pipe wall. The Rafale nozzle design can significantly improve the flow state, make the gas-liquid mixing more uniform, and improve the drainage efficiency.

[0053] In order to reduce turbulence and erosion, several of the gas lift injection channels 2 are distributed in a spiral in the axial direction of the cylinder 1. In this solution, several gas lift injection channels 2 are distributed in a spiral as a whole to form a complete spiral hole arrangement. The advantage is that it prevents the erosion of the inner wall of the flow device by high-pressure gas when the holes are evenly arranged in the radial direction, and the formed annular erosion zone will reduce the tensile strength of the tool. Even under the same material and process conditions, such staggered spiral deployment can significantly reduce erosion; in addition, the deployment of high-pressure gas injection holes by staggered spirals is also beneficial to reduce the impact of turbulence in the gas-liquid mixing zone, thereby improving the water-carrying efficiency of gas lift.

[0054] In order to select the length of the cylinder 1 and quickly splice it, the cylinder 1 includes a plurality of collars 101, and the collars 101 are coaxially spliced ​​in sequence. The present invention can design the specific number of holes and the aperture according to the gas injection amount and the gas injection pressure, so that the gas injection in each hole can reach the critical flow. At this time, the change of the input pressure will not cause the change of the discharge amount, and the flow is in a constant speed state; wherein, as shown in the figure, there are 6 collars 101, and 4 to 6 gas lift gas injection channels 2 are arranged in each collar 101, preferably 4 gas lift gas injection channels 2, and the 4 gas lift gas injection channels 2 are gradually increased in a spiral of 90 degrees in sequence. Between adjacent collars 101, each collar 101 and the previous collar 101 are spirally rotated 15 to 30 degrees, preferably 15 degrees, so as to form a complete spiral hole arrangement.

[0055] In order to provide an outlet end face for the injected high-pressure gas and allow the high-pressure gas to enter along the flow direction of the well fluid, the inner side of the collar 101 includes a large-diameter section and a small-diameter section connected to each other, and the end face between the large-diameter section and the small-diameter section is a spiral end face arranged along the axial direction of the collar 101, and the inner end of each of the gas lift injection channels 2 on the collar 101 passes through the spiral end face.

[0056] In order not to affect the flow rate of the high-pressure gas and allow the high-pressure gas to smoothly enter the internal flow channel along its axial direction, the spiral end surface is inclined from the large diameter section side to the small diameter section side and is perpendicular to the axis of the gas lift injection channel 2.

[0057] As a redundancy solution, adjacent rings 101 are detachably connected.

[0058] As a splicing method between several sleeves 101, the large diameter section and the small diameter section are respectively located at the outlet end and the inlet end of the sleeve 101, and the outer side of the inlet end of the sleeve 101 is provided with a reduced diameter section, and the outer diameter of the reduced diameter section is adapted to the inner diameter of the outlet end. The adjacent sleeves 101 and the sleeve 101 and the oil pipe are connected with the outlet end through the reduced diameter section for socket connection or thread connection. Of course, in order to make the connection node more stable, other fixed connection methods such as welding can also be used.

[0059] Embodiment 2:

[0060] This embodiment 2 is further limited on the basis of embodiment 1, and also provides a constant speed gas lift equipment, including an oil pipe deep into the well, along the length direction of the oil pipe, a plurality of constant speed gas lift flow devices are connected in series on the oil pipe at intervals; it also includes a gas injection device, and the gas injection device is used to provide high-pressure gas to each of the gas lift injection channels 2.

[0061] In this scheme, a constant-speed gas lift flow device is used in the first upper stage. The flow mode of the injected gas in the flow channel of the gas lift device is critical flow, and its outlet pressure is only related to the external transmission pressure. Since the maximum speed in the upper constant-speed gas lift flow device reaches the critical flow rate, its flow rate is the critical flow rate and it is impossible to continue to increase. Therefore, other natural gas (total gas injection volume minus total critical flow rate) naturally enters the next-level flow device, thereby continuing to increase the gas lift depth, forming a relay lift, and improving the gas lift efficiency. In a word: the valve hole diameter of the gas lift valve on the conventional gas lift string is much larger than the nozzle size of the constant-speed gas lift device. Its flow is non-critical flow rate. The pressure at the valve is affected by the wellhead back pressure and fluctuates with the wellhead pressure fluctuation. The gas volume passing through the first gas lift valve also changes. However, in the designed constant-speed gas lift device, the high-pressure gas flow in its nozzle is critical flow, which does not change with the change of wellhead pressure, and its flow rate is constant. When the high-pressure gas source is sufficient, that is, the injection pressure and injection volume are relatively high, the first-stage constant-speed gas lift flow device can be further divided into two groups during gas lift design; usually, the first-stage constant-speed gas lift flow device has no more than 9 flow channels. If the constant-speed gas lift flow device is in two groups, it is advisable that the flow channels in each group do not exceed 4. The number design and depth position must ensure that they are in a critical flow state under the designed gas injection pressure.

[0062] The specific implementation methods described above further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above description is only a specific implementation method of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.

Claims

1. A constant velocity gas lift flow device, characterized in that: include: A cylinder (1) connected in series in the middle of the oil pipe, wherein both ends of the cylinder (1) are open and both are connected to the oil pipe; A plurality of gas lift and gas injection channels (2) are provided on the circumferential side wall of the cylinder (1), and two ends of the gas lift and gas injection channels (2) respectively penetrate the inner wall and the outer wall of the cylinder (1); From the outer end to the inner end of the gas lift gas injection channel (2), the gas lift gas injection channel (2) is inclined toward the direction of well fluid flow; Along its length direction, the gas lift and gas injection channel (2) comprises a Rafale pipe section (201).

2. A constant velocity gas lift flow device according to claim 1, characterized in that: The plurality of gas lift and gas injection channels (2) are distributed in a spiral manner in the axial direction of the cylinder (1).

3. A constant velocity gas lift flow device according to claim 1, characterized in that: The cylinder (1) comprises a plurality of collars (101), and the plurality of collars (101) are coaxially spliced ​​in sequence.

4. A constant velocity gas lift flow device according to claim 3, characterized in that: The inner side of the collar (101) comprises a large diameter section and a small diameter section connected to each other, the end face between the large diameter section and the small diameter section is a spiral end face arranged along the axial direction of the collar (101), and the inner end of each of the gas lift and gas injection channels (2) on the collar (101) passes through the spiral end face.

5. A constant velocity gas lift flow device according to claim 4, characterized in that: The spiral end surface is inclined from the large diameter section side to the small diameter section side, and is perpendicular to the axis of the gas lift and gas injection channel (2).

6. A constant velocity gas lift flow device according to claim 4, characterized in that: Adjacent collars (101) are detachably connected.

7. A constant velocity gas lift flow device according to claim 6, characterized in that: The large diameter section and the small diameter section are respectively located at the outlet end and the inlet end of the collar (101); the outer side of the inlet end of the collar (101) is provided with a reduced diameter section, and the outer diameter of the reduced diameter section is matched with the inner diameter of the outlet end.

8. A constant velocity gas lift flow device according to claim 7, characterized in that: Adjacent collars (101) and collars and the oil pipe are connected with the outlet end by socket or thread connection via the reduced diameter section.

9. A constant speed gas lift device, characterized in that: It comprises an oil pipe deep downhole, along the length direction of the oil pipe, a plurality of constant speed gas lift flow devices are sequentially connected in series at intervals on the oil pipe, and the constant speed gas lift flow device is the constant speed gas lift flow device according to any one of claims 1 to 8.

10. A constant speed gas lift device according to claim 9, characterized in that: It also comprises a gas injection device, which is used to provide high-pressure gas to each of the gas lift gas injection channels (2).