Method for reinforcing tunnel by adopting patch type inserted and connected prefabricated composite plates

By using a prefabricated composite panel reinforcement method with patch plug connection at the waist of the tunnel, combining ultra-high performance concrete and FRP grid, using a mortise and tenon structure-patch plug connection interface, the FRP material in negative bend in the prior art is solved. The insufficient moment zone reinforcement achieves efficient reinforcement and overall enhancement of the tunnel waist.

CN118933857APending Publication Date: 2024-11-12BEIJING UNIV OF TECH
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411346432.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-25
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

In the existing tunnel reinforcement technology, FRP materials can only be used for reinforcement of positive bending moment zones and cannot be used for negative bending moment zones. The reinforcement integrity is poor and the construction is difficult to control, and the economy is poor. It is urgently needed to be suitable for the waist of the tunnel. Reinforcement method.

Method used

The prefabricated composite plate reinforcement method is adopted for patch plug-in connection. Arc molds are manufactured through measurement design and design, and the ultra-high performance concrete is poured and combined with FRP grids are formed to form prefabricated composite plates, and the mortise and tenon structure-patch plug-in connection interface is used for Installation on site, combined with chemical anchor bolts and connecting bolts for fixing.

Benefits of technology

It realizes effective reinforcement of the negative bending moment zone of the tunnel waist, improves the bearing capacity and stiffness, simplifies the installation process, reduces water leakage, and enhances the reinforcement effect.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933857A_ABST
    Figure CN118933857A_ABST
Patent Text Reader

Abstract

The invention discloses a method for reinforcing a tunnel by using patch-type inserted and connected prefabricated composite boards, which relates to the technical field of tunnel reinforcement and comprises the following steps: S1, manufacturing an arc-shaped plate-shaped mold and an FRP (Fiber Reinforce Plastic) grid according to a measurement result and a reinforcement requirement; s2, the FRP-UHPC composite board is prefabricated and maintained; s3, the tunnel lining structure to be reinforced is treated; s4, the first prefabricated composite board is tightly attached to the surface of the tunnel and fixed through chemical anchor bolts, the second prefabricated composite board is installed along the connecting port of the first prefabricated composite board, and the connecting port is fixed through connecting bolts; and S5, the step S4 is repeated, and the tunnel is completely reinforced. Through field measurement, the quality of the prefabricated slab can be better controlled, and the reinforcement quality is ensured; reinforcing parts can be better connected through the mortise and tenon joint structure-patch type inserting connection interface, and the overall rigidity of the reinforcing layer can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of tunnel reinforcement, in particular to a method for reinforcing a tunnel by using prefabricated composite plates connected by patch-type plug-in connections. Background Art

[0002] With the accelerating pace of urbanization and the continuous development and utilization of urban underground space, tunnels, as a primary structural form of urban rail transit, are experiencing a continuous increase in depth, length, and cross-sectional area. Over the course of years of operation, some tunnel structures are gradually experiencing structural defects such as water leakage, cracks, missing corners, gapping joints, tunnel segment shifting, and deformation. Some of these defects have already impacted normal tunnel operations and, if further developed, could threaten normal traffic safety.

[0003] FRP (fiber reinforced plastic) and steel plates are two common reinforcement components used in shield tunnels. However, FRP can only withstand tension and is therefore typically used only for the positive bending moment zone near the tunnel vault, not the negative bending moment zone near the tunnel waist. While steel plates are suitable for reinforcing both positive and negative bending moment zones, providing superior integrity and high rigidity, they require numerous welds, making construction quality difficult to control, and they consume a large amount of steel, making economical efficiency difficult to guarantee.

[0004] Therefore, there is an urgent need for a method for reinforcing tunnels using prefabricated composite panels with patch-type plug-in connections to solve the above problems. Summary of the Invention

[0005] The purpose of the embodiments of the present invention is to provide a method for reinforcing a tunnel using prefabricated composite panels connected by patch-type plug-in connections, so as to solve the problems raised in the above-mentioned background technology.

[0006] To achieve the above object, the present invention provides the following technical solutions:

[0007] A method for reinforcing a tunnel using prefabricated composite panels connected by patch-type plug-in connections comprises the following steps:

[0008] S1: Measure the geometric dimensions of the tunnel body and the reinforcement parts according to the design requirements, ensure the accuracy of the dimensions of the composite plate connection interface, and manufacture the curved plate mold and FRP grid;

[0009] S2: Mix ultra-high performance concrete and pour it into a curved plate mold. Prefabricate the FRP-UHPC composite panel and place the FRP grid in the mold during the pouring process. After the pouring is completed, the FRP-UHPC composite panel is maintained at room temperature for moisture retention.

[0010] S3: Clean and roughen the surface of the tunnel lining structure to be reinforced to expose the aggregate, and drill holes at the designated locations;

[0011] S4: Mix the epoxy resin and hardener in the prescribed proportions and apply the mixed epoxy resin evenly on the concrete surface, ensuring that the epoxy resin covers the entire reinforced area and forms a uniform film;

[0012] S5: Place the first FRP-UHPC prefabricated composite panel on the tunnel surface and fix it with chemical anchor bolts;

[0013] S6: Install the second FRP-UHPC prefabricated composite panel along the connection interface of the first FRP-UHPC prefabricated composite panel to ensure fit. The connection interfaces of two adjacent prefabricated composite panels in the transverse direction are fixed with inter-ring plate edge connection bolts, and the connection interfaces of two adjacent prefabricated composite panels in the longitudinal direction are fixed with circumferential plate edge connection bolts.

[0014] S7: Repeat steps S5-S6 to completely reinforce the tunnel.

[0015] As a further solution of the present invention: the connection interface of the prefabricated composite panel adopts a mortise and tenon structure-patch type plug-in connection interface.

[0016] Compared with the prior art, the present invention has the following beneficial effects:

[0017] According to the measurement of geometric parameters of the on-site reinforcement position, a mold with a mortise and tenon structure-patch-type plug-in connection interface is made. After pouring high-performance concrete, the FRP grid is placed in the mold in the middle of pouring so that it is located in the center of the precast panel to form a precast composite panel. According to different reinforcement requirements, the size of the mold can be adjusted to adapt to on-site conditions; and according to different reinforcement requirements, different FRP grid thicknesses and layers can be used to parametrically control the reinforcement bearing capacity and stiffness; the combination of high-performance concrete and FRP grid has higher bearing capacity and stiffness; precast panels are used for on-site installation, and the mortise and tenon structure-patch-type plug-in connection interface makes installation more convenient; the mortise and tenon structure-patch-type plug-in connection interface can provide a certain amount of circumferential stiffness, and the interface is further reinforced with connecting bolts, which has a stronger reinforcement effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 Schematic diagram of the three-dimensional structure of a method for reinforcing a tunnel using prefabricated composite panels connected by patch-type plug-in connection according to an embodiment of the present invention.

[0019] Figure 2 It is a front view of a method for reinforcing a tunnel using prefabricated composite panels connected by patch-type plug-in connection according to an embodiment of the present invention.

[0020] Figure 3 Schematic diagram of the three-dimensional structure of the prefabricated composite panel in an embodiment of the present invention.

[0021] Figure 4 The figure is a flow chart of a method for reinforcing a tunnel using prefabricated composite panels connected by patch-type plug-in connection according to an embodiment of the present invention.

[0022] In the figure: 1. Tunnel body; 2. Prefabricated composite panel; 3. Chemical anchor bolt; 4. Inter-ring panel edge connection bolt; 5. Circumferential panel edge connection bolt; 6. Lane. DETAILED DESCRIPTION

[0023] The following will clearly and completely describe the technical solutions in the embodiments of the present invention in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. All other embodiments obtained by ordinary technicians in this field based on the embodiments of the present invention without making any creative efforts shall fall within the scope of protection of the present invention.

[0024] In an embodiment of the present invention, a method for reinforcing a tunnel using prefabricated composite panels connected by patch-type plug-in connection includes the following steps:

[0025] S1: Measure the geometric dimensions of the tunnel body 1 and the reinforcement parts according to the design requirements, ensure the accurate dimensions of the composite plate connection interface, and manufacture the curved plate mold and FRP grid;

[0026] S2: Mix ultra-high performance concrete (UHPC) and pour it into a curved plate-shaped mold. Prefabricate the FRP-UHPC composite panel 2 and place the FRP grid in the mold during the pouring process. After the pouring is completed, the FRP-UHPC composite panel 2 is subjected to room temperature moisture maintenance.

[0027] S3: Clean and roughen the surface of the tunnel lining structure to be reinforced to expose the aggregate, and drill holes at the designated locations;

[0028] S4: Mix the epoxy resin and hardener in the prescribed proportions and apply the mixed epoxy resin evenly on the concrete surface, ensuring that the epoxy resin covers the entire reinforced area and forms a uniform film;

[0029] S5: placing the first FRP-UHPC prefabricated composite panel 2 close to the tunnel surface and fixing it with chemical anchor bolts 3;

[0030] S6: Install the second FRP-UHPC prefabricated composite panel 2 along the connection interface of the first FRP-UHPC prefabricated composite panel 2 to ensure fit. The connection interfaces of two adjacent prefabricated composite panels 2 in the transverse direction are fixed with inter-annular plate edge connection bolts 4, and the connection interfaces of two adjacent prefabricated composite panels 2 in the longitudinal direction are fixed with circumferential plate edge connection bolts 5.

[0031] S7: Repeat steps S5-S6 to completely reinforce the tunnel.

[0032] The connection interface of the prefabricated composite panel adopts a mortise and tenon structure-patch type plug-in connection interface.

[0033] The present invention combines ultra-high performance concrete (UHPC) and FRP grid, making full use of the characteristics of FRP grid, such as light weight, high strength, corrosion resistance, and good fatigue resistance, and ultra-high performance concrete, such as high strength, high rigidity, good durability, strong interface adhesion, low permeability, and good fire resistance, so that the prepared composite board has stronger bearing capacity and rigidity; the present invention uses prefabricated panels for on-site installation, and can perform parameterized control of various properties of the prefabricated panels according to reinforcement requirements, and the connection interface adopts the form of mortise and tenon structure-patch-type plug-in connection interface, which makes installation more convenient; secondly, the mortise and tenon structure-patch-type plug-in connection interface can provide a certain circumferential rigidity, and the interface is further reinforced by connecting bolts, which has a stronger reinforcement effect and can also reduce the dripping of leaking water after reinforcement.

[0034] In this embodiment, a protruding block is provided on one side of the prefabricated composite panel 2, and a recessed interface is provided on the other side corresponding thereto. The protruding block on one prefabricated composite panel 2 matches the recessed interface on the adjacent prefabricated composite panel 2, and the two prefabricated composite panels 2 can be connected together in an insertable manner.

[0035] In this embodiment, the thickness of the FRP mesh is 1 to 5 mm, and the grid spacing of the FRP mesh is 50 to 100 mm. Spacers are used to control the minimum spacing between the FRP mesh and the inner surface of the tunnel lining structure to 2 to 3 mm. The coating thickness of the epoxy resin glue is 0.1 to 0.5 mm, and the thickness of the ultra-high performance concrete protective layer of the FRP mesh is 12 to 20 mm.

[0036] As an embodiment of the present invention, the material of the FRP mesh in step S1 is aramid fiber, carbon fiber, glass fiber or basalt fiber.

[0037] As an embodiment of the present invention, in step S2, the number of FRP mesh layers can be adjusted according to the reinforcement requirements and mechanical performance requirements.

[0038] As an embodiment of the present invention, in step S4, a brush or a roller brush may be used to apply the epoxy resin.

[0039] As an embodiment of the present invention, step S4 can be omitted according to the tunnel reinforcement requirements.

[0040] As an embodiment of the present invention, in step S6, according to the tunnel reinforcement requirements, a layer of epoxy resin may be evenly applied to the connection interfaces of the prefabricated composite panels.

[0041] The epoxy resin can improve the bonding strength between the prefabricated composite panel 2 and another prefabricated composite panel 2 and between the prefabricated composite panel 2 and the tunnel body 1, thereby improving the durability thereof.

[0042] The working principle of the present invention is as follows: the present invention uses polymers such as carbon fiber (CFRP), glass fiber (GFRP), and basalt fiber (BFRP) to reinforce ultra-high performance concrete (UHPC). The two are combined to form a high-performance composite material to reinforce the tunnel structure; geometric parameters are measured according to the on-site reinforcement position to produce prefabricated composite panels with mortise and tenon structure-patch-type plug-in connection interfaces, and the ratio of the number of fiber layers to the cement base can be flexibly adjusted to form reinforcement materials with different mechanical properties. During on-site construction, the prefabricated composite panels are spliced ​​along the panel edge interfaces and fixed with chemical anchors, connecting bolts, etc. to reinforce the tunnel structure.

[0043] It will be apparent to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above and that the invention can be embodied in other specific forms without departing from the spirit or essential characteristics of the invention. Therefore, the embodiments should be considered in all respects as illustrative and non-restrictive, and the scope of the invention is defined by the appended claims, not the foregoing description, and all variations within the meaning and range of equivalents of the claims are intended to be included therein. Any reference sign in a claim should not be construed as limiting the claim to which it relates.

[0044] In addition, it should be understood that although this specification is described in terms of implementation methods, not every implementation method contains only one independent technical solution. This narrative method of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment can also be appropriately combined to form other implementation methods that can be understood by those skilled in the art.

Claims

1. A method for reinforcing a tunnel using prefabricated composite panels connected by patch-type plug-in connections, It is characterized in that The following steps are involved: S1: Measure the geometric dimensions of the tunnel body and the reinforcement parts according to the design requirements, ensure the accuracy of the dimensions of the composite plate connection interface, and manufacture the arc plate mold and FRP grid; S2: Mix ultra-high performance concrete, pour it into a curved plate-shaped mold, prefabricate the FRP-UHPC composite board, place the FRP grid in the mold during the pouring process, and after the pouring is completed, perform room temperature moisture maintenance on the FRP-UHPC composite board; S3: Clean and roughen the surface of the tunnel lining structure to be reinforced to expose the aggregate, and drill holes at the marked positions; S4: Mix and stir the epoxy resin and hardener in the prescribed proportion, and evenly apply the mixed epoxy resin on the concrete surface to ensure that the epoxy resin covers the entire reinforcement area and forms a uniform film; S5: The first FRP-UHPC prefabricated composite panel is placed close to the tunnel surface and fixed with chemical anchor bolts; S6: Install the second FRP-UHPC prefabricated composite panel along the connection interface of the first FRP-UHPC prefabricated composite panel to ensure the fit. The connection interfaces of two adjacent prefabricated composite panels in the transverse direction are fixed with annular plate edge connection bolts, and the connection interfaces of two adjacent prefabricated composite panels in the longitudinal direction are fixed with annular plate edge connection bolts; S7: Repeat steps S5-S6 to completely reinforce the tunnel.

2. A method for reinforcing a tunnel using prefabricated composite panels with patch-type plug-in connections according to claim 1, It is characterized in that The connection interface of the prefabricated composite panel adopts a mortise and tenon structure-patch type plug-in connection interface.

3. A method for reinforcing a tunnel using prefabricated composite panels with patch-type plug-in connections according to claim 1, It is characterized in that The material of the FRP mesh in step S1 is aramid fiber, carbon fiber, glass fiber or basalt fiber.

4. A method for reinforcing a tunnel using prefabricated composite panels with patch-type plug-in connections according to claim 1, It is characterized in that In step S2, the number of FRP mesh layers can be adjusted according to the reinforcement requirements and mechanical performance requirements.

5. A method for reinforcing a tunnel using prefabricated composite panels with patch-type plug-in connections according to claim 1, It is characterized in that In step S4, the epoxy resin may be applied using a brush or a roller brush.

6. A method for reinforcing a tunnel using prefabricated composite panels with patch-type plug-in connections according to claim 1, It is characterized in that Step S4 can be omitted according to the tunnel reinforcement requirements.

7. A method for reinforcing a tunnel using prefabricated composite panels with patch-type plug-in connections according to claim 1, It is characterized in that In step S6, according to the tunnel reinforcement requirements, a layer of epoxy resin can be evenly applied to the connection interface of the prefabricated composite panel.