Single-track tunnel secondary lining trolley framework auxiliary assembly suspension device and assembly method thereof
By using door frame suspension wire rope, upper longitudinal beam suspension wire rope and sliding longitudinal beam suspension wire rope in a single-line tunnel, combined with electric hoist and auxiliary fixed connection, the problem of difficulty in assembly of the second lining trolley is solved, and the problem of assembly of the second lining trolley is realized Quick installation and efficient assembly.
Patent Information
- Application Number
- CN202411190436.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-28
- Publication Date
- 2024-11-12
AI Technical Summary
In a single-line tunnel, the narrow structure of the second-lined trolley makes it difficult to assemble conventional small cranes and operate them.
The door frame suspended wire rope, upper longitudinal beam suspended wire rope, sliding longitudinal beam suspended wire rope and multiple electric hoists are used, and the auxiliary fixed connection and walking mechanism is combined to form a quick installation assembly method.
The rapid installation of door framing, upper longitudinal beam and top sliding longitudinal beam is achieved, which reduces installation difficulty and improves installation efficiency. The auxiliary beam and walking mechanism form a stable frame structure, further improving installation efficiency.
Smart Images

Figure CN118933883A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of tunnel construction, and relates to a single-line tunnel secondary lining trolley skeleton auxiliary assembly suspension device and an assembly method thereof. Background Art
[0002] Due to the small clearance size of the single-track railway tunnel, during the pouring of the secondary lining concrete, the height and width of the secondary lining trolley of the single tunnel present a flat cross-section. The secondary lining trolley is installed in the narrow structure tunnel. It is difficult to assemble it using a conventional small crane, and the operation is difficult. Summary of the invention
[0003] The technical problem to be solved by the present invention is to provide a single-track tunnel secondary lining trolley frame auxiliary assembly suspension device and an assembly method thereof, which can solve the problem that conventional small cranes are difficult to assemble and operate.
[0004] The technical solution adopted by the present invention is: a single-track tunnel secondary lining trolley skeleton auxiliary assembly suspension device, including a portal frame suspension wire rope, an upper longitudinal beam suspension wire rope, a sliding longitudinal beam suspension wire rope and a plurality of electric winches, the portal frame suspension wire rope is tied at one end to the middle of the top side of the portal frame, and the other end is connected to the first electric winch after passing through a first fixed pulley, the first fixed pulley is connected to the middle of the top side of the tunnel, the first electric winch is installed on the ground, four upper longitudinal beam suspension wire ropes are symmetrically arranged in the tunnel, one end of the two upper longitudinal beam suspension wire ropes on one side is tied to the two upper longitudinal beams, and the other end is respectively passed through the second fixed pulley. The second fixed pulley and the third fixed pulley are respectively connected to the tunnel wall above the inner upper longitudinal beam and the outer upper longitudinal beam, the fourth fixed pulley is connected to the tunnel wall above the outer side of the trolley (the left or right side outside), the second electric winch is installed on the tunnel floor and is located outside the bottom longitudinal beam, two steel wire ropes are used on one side of the sliding longitudinal beam suspension, the two ends are longitudinally tied at both ends of the sliding longitudinal beam, and the other end is connected to the third electric winch after passing the fifth fixed pulley and the sixth fixed pulley, and the fifth fixed pulley and the sixth fixed pulley are longitudinally fixedly connected to the top of the tunnel side.
[0005] Furthermore, the auxiliary assembly suspension device of the second lining trolley frame of the single-track tunnel also includes two auxiliary cross beams and a seventh fixed pulley for auxiliary fixing and connecting the front and rear ends of the two bottom longitudinal beams. The seventh fixed pulley is installed in the middle of the top side of the tunnel front and back with the first fixed pulley. The portal frame suspension wire rope is connected to the first electric winding machine after passing through the seventh fixed pulley. The two auxiliary cross beams can connect the screw jack mounting holes at the bottom of the two ends of the bottom longitudinal beam connected to the four walking mechanisms to form the entire bottom walking mechanism assembly.
[0006] Furthermore, iron shoes are used on the track to lock the walking mechanism components.
[0007] Furthermore, the above-mentioned single-track tunnel secondary lining trolley frame auxiliary assembly suspension device also includes auxiliary walking wheels that are detachably fixedly connected to the bottom of the two columns of the portal frame.
[0008] Furthermore, the above-mentioned single-track tunnel second lining trolley skeleton auxiliary assembly suspension device also includes an eighth fixed pulley, which is installed on the top of the tunnel in a longitudinally consistent manner with the fifth fixed pulley and the sixth fixed pulley, and is located in front of the walking mechanism assembly. The sliding longitudinal beam suspension wire rope bypasses the eighth fixed pulley and is connected to the third electric winch.
[0009] Furthermore, the auxiliary assembly suspension device of the second lining trolley skeleton of the single-track tunnel also includes an auxiliary support block, which is located behind the walking mechanism assembly and has a sloped surface on the upper side. It uses two to support the two columns of the inclined portal frame.
[0010] An assembly method for an auxiliary assembly suspension device for a secondary lining trolley frame of a single-track tunnel, the method comprising: connecting two auxiliary cross beams to the bottom of two bottom longitudinal beams to form a walking mechanism assembly, the walking mechanism assembly being located on a track, the first fixed pulley being located at the front top of the walking mechanism assembly, the seventh fixed pulley being located at the rear top of the walking mechanism assembly, the eighth fixed pulley being located at the front of the walking mechanism assembly, the fifth fixed pulley and the sixth fixed pulley being arranged in two rows, respectively located at the upper outer sides of the left and right sides of the walking mechanism assembly, the second fixed pulley and the third fixed pulley being arranged in two groups, respectively located at the upper left and right sides of the walking mechanism assembly, and the two upright posts of the first door frame being installed with auxiliary walking After the wheel is raised, the top of the gate frame is tied with a gate frame suspension wire rope, the first electric winch is controlled to lift it to a suspended position, the auxiliary walking wheel is removed, the walking mechanism assembly is controlled to move toward one side of the suspended gate frame, and when it moves to the first gate frame installation position on the front side, it is stopped and locked, the winch and the two columns of the gate frame are controlled to be lowered, the two locating pins set at the bottom of the two columns are inserted into the bottom longitudinal beam to achieve positioning, and the columns and the bottom longitudinal beam are locked with bolts, the tied gate frame suspension wire rope is removed, the locking state of the walking mechanism assembly is released, the walking mechanism assembly is controlled to return to the initial position, and the first Two door frames, the second door frame installation process adopts the installation process of the first door frame, completes the installation of the second door frame, moves to the upper longitudinal beam installation position between the first door frame and the second door frame, and suspends the corresponding upper longitudinal beam with the upper longitudinal beam suspension wire rope. After suspending it on the top crossbeam of the door frame, manually control the rotation direction, lower it to the installation position, and use bolts to lock it with the two door frames. After completing the installation of the upper longitudinal beam between the first door frame and the second door frame, install the third door frame and the upper longitudinal beam between the third door frame and the second door frame, in sequence. Repeat, after completing the installation of the last gantry and upper longitudinal beam, and after completing the installation of the two adjacent gantry frames, fix the fork-type scissors support between the two adjacent gantry frames, return the walking mechanism assembly to the starting position, tie the sliding longitudinal beam at both ends of the sliding longitudinal beam suspension wire rope, control the third electric winch to suspend it above the top beam, manually move it to the top beam, repeat the lifting of the sliding beam, complete the installation of all sliding longitudinal beams, complete the assembly of the main frame structure of the walking gantry, and build an operating platform on the top beam to assemble the parts of the arch structure. The parts of the arch structure can be suspended by the upper longitudinal beam suspension wire rope.
[0011] Beneficial effects of the present invention: Compared with the prior art, the present invention is aimed at assembling the secondary lining trolley of a single-track tunnel in a narrow space. By adopting the assembly structure of the present invention, the rapid installation of the portal frame, the upper longitudinal beam and the top sliding longitudinal beam can be realized. After installation, it is also convenient to install the small components of the arch part using the ready-made lifting equipment, which greatly improves the installation efficiency and reduces the installation difficulty. The auxiliary crossbeam is used to connect the two bottom longitudinal beams and then form a walking mechanism component with the walking power mechanism to form a frame structure. The assembly is coordinated during the walking process, which has better stability and can further improve the installation efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 This is a three-dimensional schematic diagram of the secondary lining construction trolley for a single-track railway tunnel; Figure 2 It is a schematic diagram of the three-dimensional structure of the traveling platform of the secondary lining construction trolley of a single-track railway tunnel; Figure 3 This is a front view structural diagram of the auxiliary assembly suspension device for the secondary lining trolley frame of a single-track tunnel; Figure 4 This is a front view structural diagram of the auxiliary assembly suspension device for the secondary lining trolley frame of a single-track tunnel (after the installation of the traveling trolley); Figure 5 This is a schematic diagram of the right side installation structure of the auxiliary assembly suspension device for the secondary lining trolley frame of a single-track tunnel; Figure 6 This is a schematic diagram of the pull rod installation structure; Figure 7 It is a schematic diagram of the side view of the pull rod structure. DETAILED DESCRIPTION
[0013] The invention will be further described below in conjunction with the accompanying drawings and specific embodiments.
[0014] like Figure 1-2As shown, the structure of the secondary lining construction trolley for a single-track railway tunnel includes a gate frame 1 and a power travel mechanism 2. Four power travel mechanisms 2 are installed at the four corners of the gate frame 1. The four power travel mechanisms 2 are placed on two rails 5 in pairs. The gate frame 1 includes multiple gate frames 101 and bottom longitudinal beams 102. When the bottom longitudinal beams 102 are in use, multiple screw jacks 16 need to be arranged at the bottom and the screw jacks 16 are connected to the ground through a gate support frame 17. The two free ends at the bottom of the multiple gate frames 101 are fixedly connected to the two bottom longitudinal beams 102 and along the bottom longitudinal beams 102. Evenly arranged in the length direction, multiple upper longitudinal beams 103 are fixedly connected between two adjacent door frames 101. Each door frame 101 includes a top crossbeam 104 and a column 105. Two columns 105 are fixedly connected at the bottom of both ends of the top crossbeam 104. The power walking mechanism 2 is connected to the lifting hydraulic cylinder 20 through the supporting column 18. The supporting column 18 passes through the connecting sleeve 19 set at the end of the bottom longitudinal beam 102. The upper end of the lifting hydraulic cylinder 20 is fixedly connected to the vertical support pier 21, and the vertical support pier 21 is fixedly connected to the column 105, which can realize the lifting of the entire door frame.
[0015] An arch structure is installed above the top crossbeam 104. The arch structure is a structure with variable transverse length, including a left-section top arch and a right-section top arch. The bottoms of the left-section top arch and the right-section top arch are both provided with a lower sliding longitudinal beam 111 and an upper sliding longitudinal beam 116. The lower sliding longitudinal beam 111 and the upper sliding longitudinal beam 116 are used to support and slide the arch structure.
[0016] Embodiment 1: For the installation of the above-mentioned trolley structure, as shown in FIG. Figure 3-7The specific structure of the suspension device using the skeleton of the secondary lining trolley for auxiliary assembly in a single-track tunnel includes a portal frame suspension wire rope 2301, an upper longitudinal beam suspension wire rope 2302, a sliding longitudinal beam suspension wire rope 2303 and multiple electric winches 2304. The portal frame suspension wire rope 2301 is tied at one end to the middle of the top side of the portal frame, and the other end is connected to the first electric winch 2304 after passing through the first fixed pulley 2305. The first fixed pulley 2305 is connected to the middle of the top side of the tunnel. The first electric winch 2304 is installed on the ground. Four upper longitudinal beam suspension wire ropes 2302 are symmetrically arranged on the left and right of the tunnel. One end of the two upper longitudinal beam suspension wire ropes 2302 on one side is tied to the two upper longitudinal beams, and the other end is passed through the second fixed pulleys respectively. 2306, the third fixed pulley 2307 and the fourth fixed pulley 2308 are connected to the second electric winch 2304, the second fixed pulley 2306 and the third fixed pulley 2307 are respectively connected to the tunnel wall above the inner upper longitudinal beam and the outer upper longitudinal beam, the fourth fixed pulley 2308 is connected to the tunnel wall above the outer side of the trolley (the left side or the right side), the second electric winch 2304 is installed on the tunnel floor and is located outside the bottom longitudinal beam, the sliding longitudinal beam suspension steel wire rope 2303 uses two wires on one side, the two ends are longitudinally tied to the two ends of the sliding longitudinal beam, and the other end is connected to the third electric winch 2304 after passing through the fifth fixed pulley 2309 and the sixth fixed pulley 2310, the fifth fixed pulley 2309 and the sixth fixed pulley 2310 are connected to the third electric winch 2304, and the fifth fixed pulley 2309 and the sixth fixed pulley 2310 are connected to the tunnel wall above the outer side of the trolley (the left side or the right side). 10 is longitudinally fixedly connected to the top of the tunnel side, and can hoist the sliding longitudinal beam to the top of the portal frame for installation. It also includes two auxiliary crossbeams 2311 and the seventh fixed pulley 2312 that are auxiliary and fixedly connected to the front and rear ends of the two bottom longitudinal beams. The seventh fixed pulley 2312 and the first fixed pulley 2305 are installed in the middle of the top side of the tunnel in front and back. The portal frame suspension wire rope 2301 passes around the seventh fixed pulley 2312 and is connected to the first electric winding machine. The two auxiliary crossbeams can connect the screw jack installation holes at the bottom of the two ends of the bottom longitudinal beams connected to the four walking mechanisms to form the entire bottom walking mechanism assembly, which can stably walk on the track or be locked with iron shoes 2315, so as to facilitate the installation of the portal frame and the arch structure. The seventh fixed pulley 2312 It is possible to remotely suspend and lift the door frame into the air, then move the walking mechanism assembly to the corresponding position, remove the auxiliary walking wheels, lower the door frame and install it to the corresponding position, and also include auxiliary walking wheels 2313 that are detachably fixed to the bottom of the two columns of the door frame. The auxiliary walking wheels are added to facilitate suspension and dragging, and also include an eighth fixed pulley 2314. The eighth fixed pulley 2314 is installed on the top of the tunnel in a longitudinally consistent manner with the fifth fixed pulley 2309 and the sixth fixed pulley 2310, and is located in front of the walking mechanism assembly. The sliding longitudinal beam suspension wire rope 2303 bypasses the eighth fixed pulley 2314 and is connected to the third electric winch 2304, and then the sliding longitudinal beam suspension wire rope 2303 bypasses a section of the fixed pulley away from the sliding longitudinal beam.It can avoid interference between the sliding longitudinal beam suspension wire rope 2303 and the suspended sliding longitudinal beam, which affects the suspension of the sliding longitudinal beam. It also includes an auxiliary support block 2316. The auxiliary support block 2316 is located behind the walking mechanism assembly. A slope surface is arranged on the upper side. Two of them are used to support the two upright posts of the inclined door frame, which is convenient for the initial suspension of the door frame; it also includes two pull rods 2317. The two pull rods 2317 are arranged along the length direction of the second lining trolley. The outer end of the pull rod 2317 is provided with a groove 2318 for clamping the sliding longitudinal beam downward. The inner end of the pull rod 2317 is movably inserted into the pitch block 2319. The pitch block 2319 is rotatably connected to the double-ear hinge seat 2320. The double-ear hinge seat 2320 is connected to the bolt mounting hole of the top cross beam 104 of the door frame 101 of the second lining trolley. The inner end of 317 is spirally connected with a nut 2321, and the nut 2321 rests on the inner side of the pitch block 2319. When in use, the double-ear hinge seat 2320 is connected to the bolt mounting hole with a bolt and fixed, the operating slot is inserted into the suspended sliding longitudinal beam, the operating nut is rotated, and the sliding longitudinal beam is pulled above the horizontal section on one side of the top crossbeam 104, and the suspension rope is controlled to lower the sliding longitudinal beam to a suitable position. The pitch block 2319 rotates accordingly, so that the pull rod always adapts to the lowering of the pitch sliding longitudinal beam. The pull rod can effectively pull the suspended sliding longitudinal beam to a suitable position and lower it, avoiding poor safety caused by manual operation, and saving time and effort, easy to operate, and easy to disassemble after use. The loading and unloading are convenient and quick; the two inner side surfaces of the slot 2318 are arc-shaped and provided with a rubber layer, which can play a good protective role when the sliding longitudinal beam is clamped.
[0017] When in use, two auxiliary cross beams 2311 are connected to the bottom of two bottom longitudinal beams 102 to form a walking mechanism assembly (including a power walking mechanism 2). The walking mechanism assembly is located on the track 5, the first fixed pulley 2305 is located at the front top of the walking mechanism assembly, the seventh fixed pulley 2312 is located at the rear top of the walking mechanism assembly, the eighth fixed pulley 2314 is located in front of the walking mechanism assembly, the fifth fixed pulley 2309 and the sixth fixed pulley 2310 are arranged in two rows, respectively located on the upper left and right sides of the walking mechanism assembly, the second fixed pulley 2306 and the third fixed pulley 2307 are arranged in two groups, respectively located on the upper left and right sides of the walking mechanism assembly, and symmetrically arranged. After the auxiliary walking wheels 2313 are installed on the two uprights 105 of the first door frame 101, the door frame is used. The suspension wire rope is tied to the top of the door frame 101, and the first electric winch 2304 is controlled to lift it to a suspended position, and the auxiliary walking wheel 2313 is removed. The walking mechanism assembly is controlled to move toward one side of the suspended door frame 101. When it moves to the first door frame 101 installation position on the front side, it stops and is locked (the auxiliary iron shoe 2315 is locked). The winch 2304 and the two columns 105 of the door frame 101 are controlled to be lowered (the column position is manually controlled). The two positioning pins set at the bottom of the two columns 105 are inserted into the bottom longitudinal beam 101 to achieve positioning, and the columns 105 and the bottom longitudinal beam 102 are locked with bolts. The tied door frame suspension wire rope 2301 is removed, and the locking state of the walking mechanism assembly is released. The walking mechanism assembly is controlled to move to the side of the suspended door frame 101. The walking mechanism assembly returns to the initial position, and the second door frame 101 continues to be suspended. The installation process of the second door frame 101 adopts the installation process of the first door frame 101. After the installation of the second door frame 101 is completed, it is moved to the installation position of the upper longitudinal beam 103 between the first door frame 101 and the second door frame 101. The upper longitudinal beam suspension wire rope 2302 is tied to the corresponding upper longitudinal beam 103 for suspension. After being suspended on the top crossbeam 104 of the door frame 101, the rotation direction is manually controlled to lower it to the installation position, and it is locked with the two door frames 101 with bolts. After the installation of the upper longitudinal beam 103 between the first door frame 101 and the second door frame 101 is completed, the third door frame 101 is installed, and The upper longitudinal beam 103 between the third gantry frame 101 and the second gantry frame 101 is installed, and the process is repeated in sequence. After the installation of the last gantry frame 101 and the upper longitudinal beam 103 is completed, and after the installation of the two adjacent gantry frames 101 is completed, the fork-type scissors support 122 is fixedly connected between the two adjacent gantry frames 101, and the walking mechanism assembly returns to the starting position, and the sliding longitudinal beam (upper sliding beam or lower sliding beam) is tied to the sliding longitudinal beam suspension wire rope 2303 at both ends, and the third electric winch 2304 is controlled to suspend it above the top crossbeam 104, and it is manually moved to the top crossbeam 104, and the lifting of the sliding beam is repeated to complete the installation of all sliding longitudinal beams (installation of the lower sliding longitudinal beam and the upper sliding longitudinal beam), and the main frame structure assembly of the walking gantry is completed.An operating platform is built on the top crossbeam 104 to assemble the parts of the vault structure, and the parts of the vault structure can be suspended by the upper longitudinal beam suspension wire rope 2302.
[0018] The above description is only a specific implementation mode of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can easily think of changes or substitutions within the technical scope disclosed by the present invention, which should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.
Claims
1. Auxiliary assembly suspension device for the secondary lining trolley frame of a single-track tunnel, characterized by: The invention comprises a gantry frame suspension steel wire rope (2301), an upper longitudinal beam suspension steel wire rope (2302), a sliding longitudinal beam suspension steel wire rope (2303) and a plurality of electric winches (2304). The gantry frame suspension steel wire rope (2301) is used to have one end tied to the middle of the top side of the gantry frame, and the other end is connected to the first electric winch (2304) after passing through a first fixed pulley (2305). The first fixed pulley (2305) is connected to the middle of the top side of the tunnel. The first electric winch (2304) is installed on the ground. Four upper longitudinal beam suspension steel wire ropes (2302) are arranged symmetrically on the left and right sides of the tunnel. One end of the two upper longitudinal beam suspension steel wire ropes (2302) on one side is tied to the two upper longitudinal beams, and the other end is passed through a second fixed pulley (2306), a third fixed pulley (2307) and a third fixed pulley (2308). The fourth fixed pulley (2308) is connected to the second electric winch (2304), the second fixed pulley (2306) and the third fixed pulley (2307) are respectively connected to the tunnel wall above the inner upper longitudinal beam and the outer upper longitudinal beam, the fourth fixed pulley (2308) is connected to the tunnel wall above the outer side of the trolley, the second electric winch (2304) is installed on the tunnel floor and is located outside the bottom longitudinal beam, the sliding longitudinal beam suspension steel wire rope (2303) uses two wires on one side, the two ends are longitudinally tied to the two ends of the sliding longitudinal beam, and the other end is connected to the third electric winch (2304) after passing through the fifth fixed pulley (2309) and the sixth fixed pulley (2310), and the fifth fixed pulley (2309) and the sixth fixed pulley (2310) are longitudinally fixedly connected to the top of the tunnel side.
2. The auxiliary assembly suspension device for the secondary lining trolley frame of a single-track tunnel according to claim 1 is characterized in that: It also includes two auxiliary cross beams (2311) and a seventh fixed pulley (2312) for auxiliary fixing and connecting the front and rear ends of the two bottom longitudinal beams. The seventh fixed pulley (2312) is installed in the middle of the top side of the tunnel in front and back with the first fixed pulley (2305). The portal frame suspension wire rope (2301) is connected to the first electric winding machine after passing through the seventh fixed pulley (2312). The two auxiliary cross beams can be connected to the screw jack installation holes at the bottom of the two ends of the bottom longitudinal beam with four walking mechanisms to form the entire bottom walking mechanism assembly.
3. The auxiliary assembly suspension device for the secondary lining trolley frame of a single-track tunnel according to claim 2 is characterized in that: Iron shoes (2315) are used on the track to lock the walking mechanism components.
4. The auxiliary assembly suspension device for the secondary lining trolley frame of a single-track tunnel according to claim 1 is characterized in that: It also includes auxiliary walking wheels (2313) which are detachably fixed to the bottoms of the two upright posts of the door frame.
5. The auxiliary assembly suspension device for the secondary lining trolley frame of a single-track tunnel according to claim 1 is characterized in that: It also includes an eighth fixed pulley (2314), which is installed on the top of the tunnel in a longitudinally consistent manner with the fifth fixed pulley (2309) and the sixth fixed pulley (2310) and is located in front of the walking mechanism assembly. The sliding longitudinal beam suspension wire rope (2303) bypasses the eighth fixed pulley (2314) and is connected to the third electric winch (2304).
6. The auxiliary assembly suspension device for the secondary lining trolley frame of a single-track tunnel according to claim 3 is characterized by: It also includes an auxiliary support block (2316), which is located behind the walking mechanism assembly and has a sloped surface on its upper side. The auxiliary support block (2316) is supported on two upright posts of the inclined door frame.
7. The method for assembling the auxiliary assembly suspension device of the secondary lining trolley frame of a single-track tunnel according to claim 2, characterized in that: The method is as follows: two auxiliary cross beams are connected to the bottom of two bottom longitudinal beams to form a walking mechanism assembly, the walking mechanism assembly is located on the track, the first fixed pulley is located at the front top of the walking mechanism assembly, the seventh fixed pulley is located at the rear top of the walking mechanism assembly, the eighth fixed pulley is located in front of the walking mechanism assembly, the fifth fixed pulley and the sixth fixed pulley are arranged in two rows, which are respectively located on the upper left and right sides of the walking mechanism assembly, the second fixed pulley and the third fixed pulley are arranged in two groups, which are respectively located on the upper left and right sides of the walking mechanism assembly and are symmetrically arranged, after the auxiliary walking wheels are installed on the two columns of the first door frame, the door frame is suspended by steel wire ropes to bind the door frame. At the top, control the first electric winch to lift it to the suspended position, remove the auxiliary walking wheel, control the walking mechanism assembly to move toward the side of the suspended door frame, and when it moves to the first door frame installation position on the front side, stop and lock it, control the winch and the two columns of the door frame to be lowered, insert the two positioning pins set at the bottom of the two columns into the bottom longitudinal beam to achieve positioning, and use bolts to lock the columns and the bottom longitudinal beam, remove the bundled door frame suspension wire rope, release the locking state of the walking mechanism assembly, control the walking mechanism assembly to retract to the initial position, and continue to suspend the second door frame. The installation process uses the installation process of the first door frame, completes the installation of the second door frame, moves to the upper longitudinal beam installation position between the first door frame and the second door frame, and suspends the upper longitudinal beam with the corresponding upper longitudinal beam by tying the upper longitudinal beam with the upper longitudinal beam suspension wire rope. After suspending it on the top crossbeam of the door frame, manually control the rotation direction, lower it to the installation position, and use bolts to lock it with the two door frames. After completing the installation of the upper longitudinal beam between the first door frame and the second door frame, install the third door frame, and the upper longitudinal beam between the third door frame and the second door frame. Repeat in sequence to complete the final After the rear gantry and upper longitudinal beam are installed, and after the installation of the two adjacent gantry frames is completed, the fork-type scissors support is fixedly connected between the two adjacent gantry frames, the walking mechanism assembly returns to the starting position, and the sliding longitudinal beam is tied to the sliding longitudinal beam at both ends of the sliding longitudinal beam suspension wire rope, and the third electric winch is controlled to suspend it above the top cross beam, and it is manually moved to the top cross beam, and the lifting of the sliding beam is repeated to complete the installation of all sliding longitudinal beams, complete the assembly of the main frame structure of the walking gantry, and build an operating platform on the top cross beam to assemble the parts of the vault structure. The parts of the vault structure can be suspended by the upper longitudinal beam suspension wire rope.