Section steel combined bridge and construction method thereof
Through the combination of embedded bolts and precast concrete cross-dividing plates, the problems of long construction cycles and difficult to guarantee quality in the traditional steel composite bridge welding process are solved, and efficient and low-cost construction methods are realized, which improves the integrity of the bridge and Durability.
Patent Information
- Application Number
- CN202411296438.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-18
- Publication Date
- 2024-11-15
AI Technical Summary
The welding process of traditional steel composite bridges has problems such as long construction cycle, difficulty in ensuring welding quality, and a lot of labor and cost, which limits the development of steel composite bridges.
Prefabricated bolts are used to combine prefabricated bridge deck panels with steel main beams, and prefabricated concrete cross-dividing plates are connected to the steel main beams. Pouring is done through reserved grooves and embedded steel bars to avoid a large amount of welding work and improve structural integrity and safety.
It reduces construction costs, improves construction efficiency and integrity, enhances the connectivity and durability of the structure, avoids the shortcomings of weld connections, and significantly improves engineering efficiency.
Smart Images

Figure CN118958121A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of bridges, and in particular to a steel composite bridge and a construction method thereof. Background Art
[0002] Steel structure bridges have comprehensive advantages such as light weight, high strength, short construction period, good durability, good earthquake resistance, recyclability, and environmental protection. With the improvement of national steel production capacity, the advancement of steel structure bridge construction technology and the introduction of relevant national policies, domestic steel structure bridges have continued to develop rapidly in recent years. Steel-concrete composite beams can give full play to the tensile strength of steel and the compressive strength of concrete, while reducing the cost of the project. They have the advantages of high material utilization, small scale of pier foundation, fast construction, small impact on traffic, and recyclability, and have broad development prospects. Steel composite beams are easy to construct because the main beam is easy to construct. In some cases, standard hot-rolled steel can be used, which has natural advantages of high efficiency, fast speed, and low cost.
[0003] Traditional steel main beams and cross beams are both made of steel structure, and are usually connected to each other by welding; between the steel main beam and the bridge deck, shear nails are usually used to connect them so that the two can work together as a whole. However, the large number of welded seams connecting the cross beams and longitudinal beams of conventional steel-concrete composite beams have problems such as long construction period, poor welding quality, large manpower consumption, and high cost; the existing welded composite beam bridge deck and main beam are connected by shear nails, which requires on-site welding and also has the same problem. The traditional welding process cannot give full play to the characteristics of high precision and fast construction of steel, which limits the development of steel composite bridges.
[0004] Therefore, it is necessary to invent a steel composite bridge which is convenient to construct, has good integrity, can effectively improve the construction efficiency of the composite bridge, and avoids the many shortcomings of the welding process. Summary of the invention
[0005] One of the purposes of the present application is to provide a steel composite bridge and a construction method thereof, in which the prefabricated bridge deck and the steel main beam are effectively combined into a whole by pre-embedded bolts, and the prefabricated concrete diaphragm is connected to the steel main beam by pre-embedded bolts, so as to further improve the lateral integrity and safety of the structure, so that the construction of the bridge structure is convenient, efficient, integrated, and has excellent fatigue resistance.
[0006] The technical solution of this application is:
[0007] A steel composite bridge comprises a plurality of steel main beams, a plurality of precast bridge decks and a plurality of precast concrete diaphragms; the plurality of steel main beams are arranged in parallel and spaced apart along the length direction of the bridge; the plurality of precast concrete diaphragms are respectively connected between the webs of two adjacent steel main beams and extend along the width direction of the bridge; the plurality of precast bridge decks are laid on the top plates of the steel main beams and the tops of the precast concrete diaphragms and extend along the width direction of the bridge.
[0008] As a technical solution of the present application, a plurality of first embedded bolts are arranged on the prefabricated bridge deck, and the first embedded bolts are far away from the area where the cross-partition is located; first reserved bolt holes corresponding to the first embedded bolts are arranged on the top plate of the steel main beam, and the first embedded bolts are connected to the first reserved bolt holes through first nuts.
[0009] As a technical solution of the present application, the precast bridge deck is provided with a reserved groove running through the top and bottom, the reserved groove is located directly above the precast concrete diaphragm and extends along the width direction of the bridge; a plurality of shear nails are provided on the top plate of the steel main beam, the shear nails are located in the area where the reserved groove is located; the precast bridge deck is provided with a first embedded steel bar extending along the length direction of the bridge, the reserved groove is provided with a second embedded steel bar extending along the width direction of the bridge, and the precast concrete diaphragm is provided with a third embedded steel bar extending along the height direction; the reserved groove is used to cast the first embedded steel bar, the second embedded steel bar, the third embedded steel bar and the shear nails into a whole by post-pouring concrete.
[0010] As a technical solution of the present application, the exposed ends of the first embedded steel bar and the third embedded steel bar are both closed arc structures, and the second embedded steel bar passes through the exposed ends of the first embedded steel bar and the third embedded steel bar in sequence and is connected to the first embedded steel bar.
[0011] As a technical solution of the present application, the width of the reserved groove is smaller than the width of the precast concrete diaphragm.
[0012] As a technical solution of the present application, the web of the steel main beam is provided with a plurality of second embedded bolt holes at intervals along the height direction; one side of the precast concrete cross partition at the middle position is provided with second embedded bolts at intervals along the height direction, and the other side is provided with third reserved bolt holes at intervals along the height direction, and the second embedded bolts connect adjacent second embedded bolt holes and adjacent third reserved bolt holes through second nuts.
[0013] As a technical solution of the present application, a plurality of grouting holes are opened on the precast concrete diaphragm, and the grouting holes are adjacent to the second embedded bolts, and are connected to the second embedded bolts by sequentially injecting high-strength grouting material and concrete into the grouting holes.
[0014] As a technical solution of the present application, the web of the steel main beam is provided with a plurality of second embedded bolt holes at intervals along the height direction; one side of the precast concrete cross partition at the outermost edge is provided with second embedded bolts at intervals along the height direction, and the other side is provided with third reserved bolts at intervals along the height direction, and the third reserved bolts are connected to the adjacent second embedded bolt holes through a third nut.
[0015] As a technical solution of the present application, a plurality of grouting holes are opened on the precast concrete diaphragm, and the grouting holes are adjacent to the third reserved bolts, and are connected to the third reserved bolts by sequentially injecting high-strength grouting material and concrete into the grouting holes.
[0016] A construction method for a steel composite bridge comprises the following steps:
[0017] The first reserved bolt holes and the shear nails are respectively constructed on the top plate of the steel main beam, and the second embedded bolt holes are constructed on the web plate of the steel main beam to complete the erection of the steel main beam;
[0018] The second embedded bolts, the third reserved bolts, the third reserved bolt holes and the grouting holes, which are all facing the web of the steel main beam, are respectively constructed on the precast concrete diaphragm, and the third embedded steel bars facing the reserved grooves on the precast bridge deck are constructed on the precast concrete diaphragm; the precast concrete diaphragm is erected; for the precast concrete diaphragm in the middle position, the adjacent second embedded bolt holes and the adjacent third reserved bolt holes are connected by the second embedded bolts and the second nuts, and the grouting holes are connected with the second embedded bolts by sequentially injecting high-strength grouting material and concrete into the grouting holes; for the precast concrete diaphragm at the outermost edge, the adjacent second embedded bolt holes are connected by the third reserved bolts and the third nuts, and the grouting holes are connected with the third reserved bolts by sequentially injecting high-strength grouting material and concrete into the grouting holes;
[0019] On the prefabricated bridge deck, first embedded bolts facing the steel main beam, the reserved grooves, first embedded steel bars facing the reserved grooves are respectively constructed, and second embedded steel bars are constructed in the reserved grooves; the prefabricated bridge deck is erected, and connected to the first reserved bolt holes through the first embedded bolts and first nuts;
[0020] The first pre-embedded steel bar, the second pre-embedded steel bar, the third pre-embedded steel bar and the shear nail are cast into a whole by pouring concrete in the reserved groove;
[0021] After the post-cast concrete on the prefabricated bridge deck is cured, the auxiliary structure construction is carried out.
[0022] Beneficial effects of this application:
[0023] In the steel composite bridge and its construction method of the present application, the present application avoids a large amount of welding work by bolting, thereby ensuring the construction quality, reducing the cost, and enhancing the safety and durability of the structure. At the same time, compared with the conventional steel composite bridge, the prefabricated bridge deck in the present application avoids the processes of cast-in-place formwork, bracket, steel bar binding, etc. The first embedded bolt reduces the design of the post-casting section of the prefabricated bridge deck, improves the prefabrication rate of the structure, greatly improves the work efficiency, and reduces the construction difficulty; and, through the first embedded bolt, the prefabricated bridge deck and the steel main beam are effectively combined into a whole, and they are jointly stressed, thereby further improving the overall connectivity and firmness of the steel composite bridge. The use of prefabricated concrete diaphragms avoids a large number of connection structures between steel diaphragms and main beams, which is convenient for construction and reduces costs; at the same time, the bolting of the prefabricated concrete diaphragms and the steel main beams also avoids the shortcomings of weld connection and reduces the construction workload. In addition, the prefabricated concrete diaphragms have high rigidity and improve the lateral integrity of the structure. Furthermore, in order to ensure the quality of the transverse connection, the grouting holes reserved on the precast concrete diaphragm are supplemented with grouting later, which can further enhance the connection performance of the overall structure. The first embedded steel bars and the second embedded steel bars in the precast bridge deck, the third embedded steel bars in the precast concrete diaphragm, and the shear nails arranged in the local area of the steel beam are cast together through the post-cast concrete of the cast-in-place section of the precast bridge deck and are jointly stressed, ensuring the integrity of the structure. In addition, the reserved groove reduces the size of the precast bridge deck, which is conducive to the hoisting of precast assembled components, improves construction efficiency, and reduces construction difficulty. It can be seen that the present application is convenient to construct, efficient, and low-cost, and can effectively improve the integrity and durability of the steel composite bridge, with significant engineering benefits. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] In order to more clearly illustrate the technical solutions of the implementation methods of the present application, the drawings required for use in the implementation methods will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.
[0025] Figure 1 A schematic diagram of a steel composite bridge provided in an embodiment of the present application;
[0026] Figure 2 A schematic diagram of a steel composite bridge from a first angle provided in an embodiment of the present application;
[0027] Figure 3 for Figure 2 Section Ⅰ-Ⅰ in the figure;
[0028] Figure 4 for Figure 2 Section II-II in the figure;
[0029] Figure 5 for Figure 2 Section III-III in the figure;
[0030] Figure 6 for Figure 2 Section IV-IV in the figure;
[0031] Figure 7 for Figure 2 Section V-V in the figure.
[0032] Icons: 1-steel main beam; 2-precast bridge deck; 3-precast concrete diaphragm; 4-first embedded bolt; 5-first reserved bolt hole; 6-first nut; 7-reserved groove; 8-shear nail; 9-first embedded steel bar; 10-second embedded steel bar; 11-third embedded steel bar; 12-second embedded bolt hole; 13-second embedded bolt; 14-grouting hole. DETAILED DESCRIPTION
[0033] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. The components of the embodiments of the present application described and shown in the drawings here can be arranged and designed in various different configurations.
[0034] Therefore, the following detailed description of the embodiments of the present application provided in the accompanying drawings is not intended to limit the scope of the present application for which protection is sought, but merely represents selected embodiments of the present application. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in the field without creative work are within the scope of protection of the present application.
[0035] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.
[0036] In the description of the present application, it should be noted that the terms "upper", "lower", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, or the orientations or positional relationships in which the inventive product is usually placed when in use. These are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.
[0037] In addition, in the present application, unless otherwise clearly specified and limited, the first feature being above or below the second feature may include the first and second features being in direct contact, or may include the first and second features not being in direct contact but being in contact through another feature between them. Moreover, the first feature being above, above, and above the second feature includes the first feature being directly above and obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. The first feature being below, below, and below the second feature includes the first feature being directly below and obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.
[0038] In addition, the terms "horizontal", "vertical" and the like do not mean that the components are required to be absolutely horizontal or suspended, but can be slightly tilted. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but can be slightly tilted.
[0039] In the description of this application, it should also be noted that, unless otherwise clearly specified and limited, the terms "disposed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0040] Example:
[0041] Please refer to Figure 1 , with reference Figures 2 to 7 The present application provides a steel composite bridge, comprising a plurality of steel main beams 1, a plurality of precast bridge decks 2 and a plurality of precast concrete diaphragms 3; wherein the plurality of steel main beams 1 are arranged in parallel and at intervals along the length direction of the bridge; at the same time, the plurality of precast concrete diaphragms 3 are respectively connected between the webs of two adjacent steel main beams 1 and extend along the width direction of the bridge; and the plurality of precast bridge decks 2 are laid on the top plates of the steel main beams 1 and the tops of the precast concrete diaphragms 3 and extend along the width direction of the bridge.
[0042] The use of precast concrete diaphragms 3 avoids a large number of connection structures between steel diaphragms and main beams, which is convenient for construction and reduces costs; at the same time, the bolting of precast concrete diaphragms 3 and steel main beams 1 also avoids the shortcomings of welded connections and reduces construction workload. In addition, the precast concrete diaphragms 3 have high rigidity and improve the lateral integrity of the structure.
[0043] It should be noted that for the steel main beam 1, a suitable spacing is selected according to the bridge lane layout and structural calculations, on the one hand to ensure that the force on the steel main beam 1 is reasonable, and on the other hand to ensure the force characteristics and lifting weight of the precast bridge deck 2 and the precast concrete diaphragm 3; then, based on the mechanical analysis and lifting weight, the spacing of the precast concrete diaphragms 3 along the length direction of the bridge is determined.
[0044] For the precast bridge deck 2, it is divided into reasonable plane dimensions according to the above structural analysis. The first embedded steel bar 9 and the second embedded steel bar 10 are arranged inside the precast bridge deck 2. The exposed parts of the first embedded steel bar 9 and the second embedded steel bar 10 can be set to a closed arc shape to strengthen the overall connection. The precast bridge deck 2 needs to reserve a reserved groove 7 space along the length direction of the bridge, but on the outside of the steel main beam 1 near the edge, the precast bridge deck 2 does not consider the reserved space. Here, it is mainly connected as a whole through the bolts on the top of the steel main beam 1 at the edge and the anti-collision guardrail to avoid setting up a formwork to cast concrete on the outside of the side beam.
[0045] The precast concrete diaphragm 3 is divided into reasonable plane dimensions according to the above structural analysis. Its width direction needs to fill the net width inside the web of the steel main beam 1, and its height direction can fill the space from the top plate to the top plate of the steel main beam 1. The precast concrete diaphragm 3 is provided with a third embedded steel bar 11, and its exposed part can be set to a closed arc shape to strengthen the overall connection.
[0046] Furthermore, a plurality of first embedded bolts 4 are arranged on the precast bridge deck 2, and the first embedded bolts 4 are far away from the area where the diaphragm is located; at the same time, a first reserved bolt hole 5 corresponding to the first embedded bolt 4 is arranged on the top plate of the steel main beam 1, and the first embedded bolt 4 is connected to the first reserved bolt hole 5 through a first nut 6. In addition, the precast bridge deck 2 is divided into blocks in the area where the precast concrete diaphragm 3 is arranged along the length direction of the bridge according to the bridge needs, and the precast bridge deck 2 is divided into blocks along the width direction of the bridge according to the lifting weight requirements, and the precast bridge deck 2 does not reserve a reserved groove 7 in the outer area adjacent to the steel main beam 1; a reserved groove 7 running through the top and bottom is arranged on the precast bridge deck 2, and the reserved groove 7 is located directly above the precast concrete diaphragm 3 and extends along the width direction of the bridge, and the notch width of the reserved groove 7 is smaller than the width of the precast concrete diaphragm 3; a plurality of shear nails 8 are arranged on the top plate of the steel main beam 1, and the shear nails 8 are arranged on the top plate of the steel main beam 1. The force nail 8 is located in the area where the reserved groove 7 is located. The top plate of the steel main beam 1 is provided with a shear nail 8 at the reserved groove 7, and can be connected with the precast bridge deck 2 as a whole by pouring concrete in the reserved groove 7; the precast bridge deck 2 is provided with a first embedded steel bar 9 extending along the length direction of the bridge, the reserved groove 7 is provided with a second embedded steel bar 10 extending along the width direction of the bridge, and the precast concrete diaphragm 3 is provided with a third embedded steel bar 11 extending along the height direction; the reserved groove 7 is poured with concrete to cast the first embedded steel bar 9, the second embedded steel bar 10, the third embedded steel bar 11 and the shear nail 8 as a whole. The reserved groove 7 reduces the size of the precast bridge deck 2, is conducive to the hoisting of precast assembled components, improves construction efficiency, and reduces construction difficulty.
[0047] Therefore, bolting can avoid a lot of welding work, ensure construction quality, reduce costs, and enhance structural safety and durability. At the same time, compared with conventional steel composite bridges, the prefabricated bridge deck 2 in this application avoids the processes of cast-in-place formwork, brackets, and steel bar binding. The first embedded bolts 4 reduce the design of the post-casting section of the prefabricated bridge deck 2, improve the prefabrication rate of the structure, greatly improve work efficiency, and reduce construction difficulty; and, through the first embedded bolts 4, the prefabricated bridge deck 2 and the steel main beam 1 are effectively combined into a whole, and they are jointly stressed, which can further improve the overall connectivity and firmness of the steel composite bridge.
[0048] It should be noted that the exposed ends of the first embedded steel bar 9 and the third embedded steel bar 11 are both in a closed arc structure, and the second embedded steel bar 10 passes through the exposed ends of the first embedded steel bar 9 and the third embedded steel bar 11 in sequence and is connected to the first embedded steel bar 9. The first embedded steel bar 9 and the second embedded steel bar 10 in the precast bridge deck 2, the third embedded steel bar 11 in the precast concrete diaphragm 3, and the shear nails 8 arranged in the local area of the steel main beam 1 are cast into one piece through the post-cast concrete of the cast-in-place section of the precast bridge deck 2 and are jointly subjected to force, ensuring the integrity of the structure.
[0049] Furthermore, the web of the steel main beam 1 is provided with a plurality of second embedded bolt holes 12 at intervals in the height direction. Among them, one side of the precast concrete diaphragm 3 at the middle position is provided with second embedded bolts 13 at intervals in the height direction, and the other side is provided with third reserved bolt holes at intervals in the height direction, and the second embedded bolts 13 connect the adjacent second embedded bolt holes 12 and the adjacent third reserved bolt holes through the second nut. In addition, the precast concrete diaphragm 3 is provided with a plurality of grouting holes 14, which are adjacent to the second embedded bolts 13 and are connected to the second embedded bolts 13 by sequentially injecting high-strength grouting material and concrete into the grouting holes 14. At the same time, one side of the precast concrete diaphragm 3 at the outermost edge is provided with second embedded bolts 13 at intervals in the height direction, and the other side is provided with third reserved bolts at intervals in the height direction, and the third reserved bolts are connected to the adjacent second embedded bolt holes 12 through the third nut. In addition, a plurality of grouting holes 14 are provided on the precast concrete diaphragm 3, and the grouting holes 14 are adjacent to the third reserved bolts, and are connected to the third reserved bolts by sequentially injecting high-strength grouting material and concrete into the grouting holes 14. To ensure the quality of the transverse connection, the grouting holes 14 reserved on the precast concrete diaphragm 3 are supplemented with grouting later, which can further enhance the connection performance of the overall structure.
[0050] In addition, in this embodiment, a construction method of a steel composite bridge is also provided, and the construction method mainly includes the following steps:
[0051] The first reserved bolt holes 5 and the shear nails 8 are respectively constructed on the top plate of the steel main beam 1, and the second embedded bolt holes 12 are constructed on the web of the steel main beam 1, and the erection of the steel main beam 1 is completed;
[0052] The second embedded bolts 10, the third reserved bolts, the third reserved bolt holes and the grouting holes 14, which are all facing the web of the steel main beam 1, are constructed on the precast concrete diaphragm 3, and the third embedded steel bars 11 facing the reserved grooves 7 on the precast bridge deck 2 are constructed on the precast concrete diaphragm 3; the precast concrete diaphragm 3 is erected; for the precast concrete diaphragm 3 at the middle position, the adjacent second embedded bolt holes 12 and the adjacent third reserved bolt holes are connected by the second embedded bolts 13 and the second nuts, and the grouting holes 14 are connected with the second embedded bolts 13 by sequentially injecting high-strength grouting material and concrete into the grouting holes 14; for the precast concrete diaphragm 3 at the outermost edge, the adjacent second embedded bolt holes 12 are connected by the third reserved bolts and the third nuts, and the grouting holes 14 are connected with the third reserved bolts by sequentially injecting high-strength grouting material and concrete into the grouting holes 14;
[0053] On the prefabricated bridge deck 2, first embedded bolts 4, reserved grooves 7, and first embedded steel bars 9 facing the reserved grooves 7 are respectively constructed, and second embedded steel bars 10 are constructed in the reserved grooves 7; the prefabricated bridge deck 2 is erected, and connected with the first reserved bolt holes 5 through the first embedded bolts 4 and the first nuts 6; it is noted that there is no gap between the prefabricated bridge decks 2 at the outer side of the steel main beam 1, so that adjacent prefabricated bridge decks 2 can be smoothly connected;
[0054] The first embedded steel bar 9, the second embedded steel bar 10, the third embedded steel bar 11 and the shear nail 8 are cast into a whole by pouring concrete in the reserved groove 7;
[0055] After the post-cast concrete on the prefabricated bridge deck 2 is cured, the auxiliary structure is constructed, and after the construction is completed, traffic is opened.
[0056] In summary, in the steel composite bridge and its construction method of the present application, the present application avoids a large amount of welding work by bolting, ensures the construction quality, reduces the cost, and enhances the safety and durability of the structure. At the same time, compared with the conventional steel composite bridge, the prefabricated bridge deck 2 in the present application avoids the processes of cast-in-place formwork, bracket, steel bar binding, etc. The first embedded bolt 4 reduces the design of the post-casting section of the prefabricated bridge deck 2, improves the prefabrication rate of the structure, greatly improves the work efficiency, and reduces the construction difficulty; and, through the first embedded bolt 4, the prefabricated bridge deck 2 and the steel main beam 1 are effectively combined into a whole, and they are jointly subjected to force, thereby further improving the overall connectivity and firmness of the steel composite bridge. The use of prefabricated concrete diaphragms 3 avoids a large number of connection structures between steel diaphragms and main beams, facilitates construction, and reduces costs; at the same time, the bolting of the prefabricated concrete diaphragms 3 and the steel main beam 1 also avoids the shortcomings of weld connection and reduces the construction workload. In addition, the prefabricated concrete diaphragms 3 have high rigidity and improve the lateral integrity of the structure. Furthermore, in order to ensure the quality of the transverse connection, the grouting holes 14 reserved on the precast concrete diaphragm 3 are supplemented with grouting later, which can further enhance the connection performance of the overall structure. The first embedded steel bars 9 and the second embedded steel bars 10 in the precast bridge deck 2, the third embedded steel bars 11 in the precast concrete diaphragm 3, and the shear nails 8 arranged in the local area of the steel main beam 1 are cast together through the post-cast concrete of the cast-in-place section of the precast bridge deck 2 and are jointly subjected to force, thereby ensuring the integrity of the structure. In addition, the reserved groove 7 reduces the size of the precast bridge deck 2, is conducive to the hoisting of precast assembled components, improves construction efficiency, and reduces construction difficulty. It can be seen that the present application is convenient to construct, has high efficiency, and low cost, can effectively improve the integrity and durability of the steel composite bridge, and has significant engineering benefits.
[0057] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.
Claims
1. A steel composite bridge, characterized in that: It comprises a plurality of steel main beams, a plurality of precast bridge decks and a plurality of precast concrete diaphragms; the plurality of steel main beams are arranged in parallel and spaced apart along the length direction of the bridge; the plurality of precast concrete diaphragms are respectively connected between the webs of two adjacent steel main beams and extend along the width direction of the bridge; the plurality of precast bridge decks are laid on the top plates of the steel main beams and the tops of the precast concrete diaphragms and extend along the width direction of the bridge.
2. The steel composite bridge according to claim 1, characterized in that: A plurality of first embedded bolts are arranged on the prefabricated bridge deck, and the first embedded bolts are far away from the area where the cross-partition is located; first reserved bolt holes corresponding to the first embedded bolts are arranged on the top plate of the steel main beam, and the first embedded bolts are connected to the first reserved bolt holes through first nuts.
3. The steel composite bridge according to claim 1, characterized in that: The precast bridge deck is provided with a reserved groove running through the top and bottom, the reserved groove is located directly above the precast concrete diaphragm and extends along the width direction of the bridge; a plurality of shear nails are provided on the top plate of the steel main beam, the shear nails are located in the area where the reserved groove is located; the precast bridge deck is provided with a first embedded steel bar extending along the length direction of the bridge, the reserved groove is provided with a second embedded steel bar extending along the width direction of the bridge, and the precast concrete diaphragm is provided with a third embedded steel bar extending along the height direction; the reserved groove is used to cast the first embedded steel bar, the second embedded steel bar, the third embedded steel bar and the shear nails into a whole by post-pouring concrete.
4. The steel composite bridge according to claim 3, characterized in that: The exposed ends of the first embedded steel bar and the third embedded steel bar are both in a closed arc structure, and the second embedded steel bar passes through the exposed ends of the first embedded steel bar and the third embedded steel bar in sequence and is connected to the first embedded steel bar.
5. The steel composite bridge according to claim 3, characterized in that: The width of the reserved groove is smaller than the width of the precast concrete diaphragm.
6. The steel composite bridge according to claim 1, characterized in that: The web of the steel main beam is provided with a plurality of second embedded bolt holes at intervals along the height direction; one side of the precast concrete diaphragm at the middle position is provided with second embedded bolts at intervals along the height direction, and the other side is provided with third reserved bolt holes at intervals along the height direction, and the second embedded bolts connect adjacent second embedded bolt holes and adjacent third reserved bolt holes through second nuts.
7. The steel composite bridge according to claim 6, characterized in that: The precast concrete diaphragm is provided with a plurality of grouting holes, wherein the grouting holes are adjacent to the second embedded bolts and are connected to the second embedded bolts by sequentially injecting high-strength grouting material and concrete into the grouting holes.
8. The steel composite bridge according to claim 1, characterized in that: The web of the steel main beam is provided with a plurality of second embedded bolt holes at intervals along the height direction; the precast concrete cross partition at the outermost side is provided with second embedded bolts at intervals along the height direction, and the other side is provided with third reserved bolts at intervals along the height direction, and the third reserved bolts are connected to the adjacent second embedded bolt holes through third nuts.
9. The steel composite bridge according to claim 8, characterized in that: The precast concrete diaphragm is provided with a plurality of grouting holes, the grouting holes being adjacent to the third reserved bolts, and being connected to the third reserved bolts by sequentially injecting high-strength grouting material and concrete into the grouting holes.
10. A construction method for a steel composite bridge, characterized in that: The following steps are involved: The first reserved bolt holes and the shear nails are respectively constructed on the top plate of the steel main beam, and the second embedded bolt holes are constructed on the web plate of the steel main beam to complete the erection of the steel main beam; The second embedded bolts, the third reserved bolts, the third reserved bolt holes and the grouting holes, which are all facing the web of the steel main beam, are respectively constructed on the precast concrete diaphragm, and the third embedded steel bars facing the reserved grooves on the precast bridge deck are constructed on the precast concrete diaphragm; the precast concrete diaphragm is erected; for the precast concrete diaphragm in the middle position, the adjacent second embedded bolt holes and the adjacent third reserved bolt holes are connected by the second embedded bolts and the second nuts, and the grouting holes are connected with the second embedded bolts by sequentially injecting high-strength grouting material and concrete into the grouting holes; for the precast concrete diaphragm at the outermost edge, the adjacent second embedded bolt holes are connected by the third reserved bolts and the third nuts, and the grouting holes are connected with the third reserved bolts by sequentially injecting high-strength grouting material and concrete into the grouting holes; On the prefabricated bridge deck, first embedded bolts facing the steel main beam, the reserved grooves, first embedded steel bars facing the reserved grooves are respectively constructed, and second embedded steel bars are constructed in the reserved grooves; the prefabricated bridge deck is erected, and connected to the first reserved bolt holes through the first embedded bolts and first nuts; The first pre-embedded steel bar, the second pre-embedded steel bar, the third pre-embedded steel bar and the shear nail are cast into a whole by pouring concrete in the reserved groove; After the post-cast concrete on the prefabricated bridge deck is cured, the auxiliary structure construction is carried out.