Quick plugging device for dredging pressure pipeline and dredging method
By using a rapid sealing device to utilize the pressure inside the pipeline to backflush and quickly seal the blockage, the problem of high cost and poor effectiveness in pressure pipeline dredging is solved, achieving low-cost and high-efficiency dredging results.
Patent Information
- Application Number
- CN202411058055.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-02
- Publication Date
- 2024-11-19
AI Technical Summary
Existing technologies for dredging pressure pipelines are costly and have poor dredging effects, especially in UASB systems where they can easily cause sludge overflow and significant losses.
A rapid sealing device is adopted, including a fixed base, connecting bracket, tightening component and guide rod. It uses the pressure inside the pipeline to backflush out the blockage and quickly seals the pipe opening through the tightening mechanism to prevent sludge from flowing out.
It achieves low-cost and efficient pipe dredging, avoids sludge discharge losses, is simple to operate, and does not affect normal production.
Smart Images

Figure CN118976759A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of pipeline dredging, and in particular relates to a rapid plugging device and a dredging method for pressure pipeline dredging. Background Art
[0002] At present, after a sewage treatment system has been used for a long time, its building structure is prone to corrosion, and some wall and ceiling building materials begin to fall off. The fallen mud, gravel and other impurities are transported by the pump into the inlet of the UASB system distributor, causing pipe blockage and reducing the treatment efficiency of the UASB system.
[0003] Because of the pressure inside the UASB tower, if the blind plate of the pipe is directly removed for dredging, the anaerobic sludge in the UASB tower will easily flow out due to the height difference, making it impossible to seal it, resulting in a large amount of sludge discharge loss. If the sludge (about 200 tons) in the UASB tower tank is transferred or emptied before dredging, it is necessary to customize a sealed tank or a special tank vehicle for temporary storage, which takes a long time and is expensive, and affects the company's normal production. When using the pressure formed by the height difference of the UASB tower to dredge the blockage by backwashing, the UASB tank backwashes the pipeline, which is only effective for slightly blocked pipelines and is easy to cause re-blocking. The dredging effect of severe blockages is poor.
[0004] Therefore, a new technology is needed to solve the problems of high dredging cost and poor dredging effect for pressure pipes in the prior art. Summary of the invention
[0005] In order to solve the above problems in the prior art, the present invention provides a rapid plugging device and a dredging method for dredging a pressure pipeline, the dredging process is simple to operate, the dredging cost of the pressure pipeline can be reduced, and the dredging effect is good.
[0006] The present invention adopts the following technical solutions:
[0007] A rapid plugging device for dredging a pressure pipe comprises a fixing seat, a connecting bracket, a jacking piece and at least two guide rods, wherein the fixing seat is detachably mounted on the pressure pipe to be dredged, an end cap for plugging the pipe mouth of the pressure pipe is mounted at the pipe mouth of the pressure pipe, one end of the connecting bracket is fixedly connected to the fixing seat, and the other end is provided with a connecting plate, the end cap is located between the connecting plate and the fixing seat, one end of the jacking piece passes through the connecting plate and is threadedly connected to the connecting plate, and the other end is abutted and fixed with the end cap of the pressure pipe, and the jacking piece and the fixing seat are respectively located on both sides of the end cap;
[0008] The two guide rods are parallel to each other, and the end cover can move along the two guide rods.
[0009] As a further improvement of the technical solution of the present invention, the guide rod is a long bolt.
[0010] As a further improvement of the technical solution of the present invention, it also includes a handle, which is installed at one end of the tightening member and is located at an end of the connecting plate away from the fixing seat, and there is an angle between the handle and the tightening member.
[0011] As a further improvement of the technical solution of the present invention, the fixing seat includes a fixing sleeve, and the connecting bracket also includes a plurality of connecting columns arranged at intervals. The fixing sleeve is sleeved on the outside of the pressure pipe, and one end of each connecting column is fixedly connected to the fixing sleeve, and the other end is detachably fixedly connected to the connecting plate.
[0012] As a further improvement of the technical solution of the present invention, the fixing sleeve includes two butt-jointed clamps, the ends of the two clamps are sequentially connected end to end to form a cylindrical shape and are sleeved on the outside of the pressure pipe.
[0013] As a further improvement of the technical solution of the present invention, the fixing seat further includes two fixing members, and the two ends of each clamp are respectively provided with a first fixing portion and a second fixing portion, and two adjacent first fixing portions and two adjacent second fixing portions are detachably fixedly connected by the fixing members;
[0014] Each of the clamps further comprises a fixing plate, the first fixing portion, the fixing plate and the second fixing portion are connected in sequence, and the inner surface of the fixing plate is adapted to the outer surface of the pressure pipe.
[0015] As a further improvement of the technical solution of the present invention, the fixing plate is semi-annular.
[0016] A method for dredging a pressure pipeline, using the rapid plugging device for dredging a pressure pipeline as described above, comprises the following steps:
[0017] S1. Stop the work process that requires the use of the pressure pipe to be dredged;
[0018] Stop the anaerobic internal circulation pump and close the water inlet pipe valve, that is, stop adding pressure to the pressure pipe to be dredged;
[0019] S2. Two guide rods are used to replace the two fastening bolts on the end cover of the pressure pipe, wherein a flange for mounting the end cover is provided at the pipe mouth of the pressure pipe, and after removing the two bolts for fixing the end cover and the flange, the two guide rods are respectively installed in the two through holes formed after the bolts are removed;
[0020] S3. The fixing base is installed on the pressure pipe;
[0021] S4. After the installation of the fixing base is completed, the connecting bracket is fixedly connected to the fixing base, and the top member is installed on the connecting plate, and the top member is rotated to tighten the end cover;
[0022] S5. Remove the remaining fixing bolts on the end cover;
[0023] S6. The knob of the tightening member enables the end cover to move along the guide rod in a direction away from the pressure pipe to open the pipe opening of the pressure pipe, and the pressure in the pressure pipe can drive the blockage to be discharged from the pipe opening of the pressure pipe;
[0024] S7. After the blockage is discharged, the knob of the tightening member is turned to enable the end cover to move along the guide rod toward the direction close to the pressure pipe to block the pipe opening of the pressure pipe, and the end cover is fixed to the flange with fixing bolts. After that, the guide rod is removed, and the end cover is fixedly connected to the flange with fixing bolts at the position where the guide rod is installed.
[0025] As a further improvement of the technical solution of the present invention, in step S2, the two guide rods replace the two fastening bolts located at opposite corners on the end cover.
[0026] Compared with the prior art, the present invention has the following beneficial effects:
[0027] The rapid plugging device for dredging pressure pipelines of this scheme is mainly used for blockages at the water inlet end of UASB or other pressure pipeline blind plates or end covers. After opening the pipeline flange blind plate or end cover, the blockage is discharged and dredged by using the pressure recoil in the pipeline. After the dredging is completed, the blockage is sealed to avoid the loss of pipeline contents or the inability to reset the blind plate after removal. It is effective for pipelines with mild to severe blockages. The dredging process is simple to operate, low in cost and does not affect normal production. The fixing seat can fix the tightening mechanism to the pipeline, and tighten the pipeline flange blind plate or end cover through the tightening mechanism, which can limit the movement of the flange blind plate or end cover in the direction along the guide rod, and the guide rod has both a guiding function and can limit the movement of the flange blind plate or end cover in the direction perpendicular to the guide rod. There is no need to remove the pipeline flange blind plate or end cover for dredging, and it only needs to be opened a certain distance to achieve dredging. After dredging is completed, the pipeline flange blind plate or end cover is tightened by the tightening mechanism to seal the pressure pipeline orifice, which can quickly seal the pressure pipeline orifice, and the anaerobic sludge of the UASB tower will not easily flow out through the height difference, resulting in the inability to seal, causing a large amount of sludge discharge loss. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] The technology of the present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments:
[0029] Figure 1 It is a schematic diagram of the overall structure of the rapid plugging device for dredging a pressure pipeline of the present invention;
[0030] Figure 2 is a schematic diagram of the connection structure between the tightening mechanism and the connecting bracket;
[0031] Figure 3 This is an exploded view of the fixed seat structure.
[0032] Reference numerals:
[0033] 1-fixing seat; 11-clamp; 111-first fixing part; 112-fixing plate; 113-second fixing part; 12-fixing piece;
[0034] 2-connecting bracket; 21-connecting plate; 211-threaded hole; 212-through hole; 22-connecting column; 221-threaded section; 222-limiting boss; 23-nut;
[0035] 3-tightening mechanism; 31-handle; 311-crank handle; 312-first connecting rod; 313-second connecting rod; 32-tightening member; 33-tightening seat; 331-convex part; 3311-sunk groove; 332-bottom plate. DETAILED DESCRIPTION
[0036] The following will be combined with the embodiments and drawings to clearly and completely describe the concept, specific structure and technical effects of the present invention, so as to fully understand the purpose, scheme and effect of the present invention. It should be noted that the embodiments in this application and the features in the embodiments can be combined with each other without conflict. The same reference numerals used throughout the drawings indicate the same or similar parts.
[0037] It should be noted that, unless otherwise specified, when a feature is referred to as being "fixed" or "connected" to another feature, it may be directly fixed or connected to the other feature, or it may be indirectly fixed or connected to the other feature. In addition, the descriptions of up, down, left, right, etc. used in the present invention are only relative to the relative positional relationship of the components of the present invention in the drawings.
[0038] Reference Figures 1 to 3A rapid plugging device for dredging a pressure pipe comprises a fixed seat 1, a connecting bracket 2, a tightening mechanism 3 and at least two guide rods, the tightening mechanism 3 comprises a tightening member 32, the fixed seat 1 is detachably mounted on the pressure pipe to be dredged, an end cap for plugging the pipe mouth of the pressure pipe is installed at the pipe mouth of the pressure pipe, one end of the connecting bracket 2 is fixedly connected to the fixed seat 1, and the other end is provided with a connecting plate 21. One end of the tightening member 32 passes through the connecting plate 21 and is threadedly connected to the connecting plate 21, and the other end is abutted and connected to the end cover of the pressure pipe. The end cover is located between the connecting plate 21 and the fixed seat 1, the tightening member 32 and the fixed seat 1 are respectively located on both sides of the end cover, and the tightening member 32 and the connecting plate 21 are located on the same side. The two guide rods are parallel to each other, and the end cover can move along the two guide rods.
[0039] The fixing seat 1 can fix the tightening mechanism 3 to the pressure pipe, and the tightening mechanism 3 tightens the pipe flange blind plate or end cover, which can limit the movement of the flange blind plate or end cover along the guide rod in the direction away from the pressure pipe, and the guide rod has both a guiding function and can limit the movement of the flange blind plate or end cover in the direction perpendicular to the guide rod. There is no need to remove the pipe flange blind plate or end cover for dredging, and it is only necessary to open the end cover so that the end cover and the pressure pipe have a certain distance to achieve dredging. This distance can be selected according to actual conditions. After dredging is completed, the pipe flange blind plate or end cover is tightened by the tightening mechanism 3 to block the pressure pipe orifice, which can quickly block the pressure pipe orifice, and the anaerobic sludge of the UASB tower will not flow out through the height difference, resulting in the inability to block, resulting in a large amount of sludge discharge loss.
[0040] The rapid plugging device for dredging pressure pipelines of this scheme is mainly used for blockages at the water inlet end of UASB or other pressure pipeline blind plates or end covers. A flange for fixing the end cover or blind plate is provided at the pipe mouth of the pressure pipeline. After removing the blind plate or end cover on the pipeline, the blockage is discharged and dredged by using the pressure recoil in the pipeline. After the dredging is completed, the blockage is sealed to avoid the loss of pipeline contents or the inability to reset the blind plate after removal. It is effective for pipelines with mild to severe blockages. The dredging process is simple to operate, low cost and does not affect normal production.
[0041] Specifically, the guide rod is a long bolt, and the screw rod of the long bolt is relatively long, so as to provide guidance for the end cover.
[0042] Specifically, the fixing seat 1 includes a fixing sleeve, and the connecting bracket 2 also includes a plurality of connecting columns 22 arranged at intervals, one end of each connecting column 22 is fixedly connected to the fixing sleeve, and the other end is detachably fixedly connected to the connecting plate 21. The fixing sleeve is sleeved on the outside of the pressure pipe. Since the outer peripheral size of the flange is larger than the cross-sectional size of the pressure pipe and larger than the inner hole size of the fixing sleeve, the flange can limit the fixing sleeve from coming off the pressure pipe. One end of each connecting column 22 can be fixed to the outer surface of the fixing sleeve by welding, and the connecting plate 21 is provided with through holes 212 corresponding to each connecting column 22, and each through hole 212 can allow the corresponding connecting column 22 to pass through.
[0043] Specifically, a threaded section 221 is provided at one end of each connecting column 22 away from the fixed sleeve, and a limiting boss 222 is convexly provided on the outer surface of each connecting column 22. The limiting boss 222 is located at the end of the threaded section 221 close to the fixed sleeve, and a step surface is provided at one end of the limiting boss 222 away from the fixed sleeve, and the movable connecting plate 21 can abut against the step surface. An adapted nut 23 can be installed on the threaded section 221 to fix the connecting plate 21 to each connecting column 22, and at this time, the connecting plate 21 is located between the nut 23 and the limiting boss 222; or two adapted nuts 23 are installed on the threaded section 221, and when the connecting plate 21 is fixed to each connecting column 22, the connecting plate 21 is located between the two nuts 23 on the threaded section 221, and the two nuts 23 on the threaded section 221 are moved to adjust the position of the connecting plate 21 on the connecting column 22.
[0044] Specifically, the tightening mechanism 3 further includes a handle 31, which is mounted at one end of the tightening member 32 and located on a side of the connecting plate 21 away from the fixing seat 1, so as to facilitate the tightening member 32 by turning the knob of the handle 31. The tightening member 32 may preferably be a threaded rod, and a threaded hole 211 adapted to the threaded rod is provided at the center of the connecting plate 21, so that the threaded rod passes through the threaded hole 211 and is threadedly connected to the connecting plate 21.
[0045] Specifically, the handle 31 includes a crank 311, a first connecting rod 312 and a second connecting rod 313. The first connecting rod 312 and the second connecting rod 313 are fixedly connected in an L shape. The first connecting rod 312 and the tightening member 32 are fixedly connected and are perpendicular to each other. The crank 311 is mounted on the second connecting rod 313 and is rotatably connected to the second connecting rod 313. The first connecting rod 312 and the tightening member 32 can be fixedly connected by welding.
[0046] The locking cam 33 is provided on one side of the locking cam 33, and the locking cam 33 is provided on the other side of the locking cam 33. The locking cam 33 is provided on the other side of the locking cam 33, and the locking cam 33 is provided on the other side of the locking cam 33. The locking cam 33 is provided on the other side of the locking cam 33, and the locking cam 33 is provided on the other side of the locking cam 33.
[0047] Specifically, the tightening seat 33 also includes a bottom plate 332, one side of the bottom plate 332 can abut against the end cover, and the other side is provided with a convex portion 331, and a countersunk hole or a countersunk groove 3311 is arranged on the convex portion 331. The arrangement of the bottom plate 332 can increase the contact area between the tightening member 32 and the end cover. When the tightening member 32 tightens the end cover, the pressure on the part of the end cover that contacts the bottom plate 332 is relatively small, which can prevent the end cover from being damaged.
[0048] Specifically, the fixing seat 1 includes two butted clamps 11, the ends of the two butted clamps 11 are butted one by one to form a cylindrical or annular fixing sleeve and is sleeved on the outside of the pressure pipe. The arrangement of the two butt clamps 11 can facilitate installation and disassembly with the pressure pipe.
[0049] Specifically, the fixing seat 1 further includes two fixing members 12, which can be preferably bolts, and the two ends of each clamp 11 are respectively provided with a first fixing portion 111 and a second fixing portion 113. The two butted clamp structures can be symmetrically arranged, in which case the two first fixing portions 111 are adjacent, the two second fixing portions 113 are adjacent, the first fixing portions 111 of the two adjacent clamps 11 are detachably fixedly connected by one fixing member 12, and the second fixing portions 113 of the two adjacent clamps 11 are detachably fixedly connected by the other fixing member 12.
[0050] Specifically, each of the clamps 11 further includes a fixing plate 112, the first fixing portion 111, the fixing plate 112, and the second fixing portion 113 are connected in sequence, and the inner surface of the fixing plate 112 is adapted to the outer surface of the pressure pipe. A plurality of connecting columns 22 are evenly fixed on the outer surfaces of the two fixing plates 112, and the fixing plates 112 may be semi-annular.
[0051] A method for dredging a pressure pipeline, using the rapid plugging device for dredging a pressure pipeline as described above, comprises the following steps:
[0052] S1. Stop the work process that requires the use of the pressure pipe to be dredged. For example, when dredging the pressure pipe of the UASB tower, stop the anaerobic internal circulation pump and close the water inlet pipe valve.
[0053] S2. Use two of the guide rods to replace the two diagonally located fastening bolts on the end cover of the pressure pipe. The guide rods may preferably be long bolts with a longer length. Generally, a flange for mounting the end cover is provided at the pipe mouth of the pressure pipe. The number of bolts for fixing the end cover and the flange is greater than 2. After removing two of the diagonally located bolts for fixing the end cover and the flange, the two guide rods are respectively installed in the two through holes formed after the bolts are removed. Among them, the two coaxially arranged bolt holes on the end cover and the flange form a through hole structure. The guide rod is preferably a long bolt. One end of the screw of the long bolt has a nut. When the screw is inserted into the through hole, the nut is located on the side of the flange away from the end cover.
[0054] S3. Install the fixing base 1 on the pressure pipe.
[0055] S4. After completing the installation of the fixing seat 1, connect the connecting plate 21 with each connecting column 22 to complete the fixed connection between the connecting bracket 2 and the fixing seat 1, and install the tightening member 32 on the connecting plate 21, and rotate the tightening member 32 to tighten the end cover.
[0056] S5. Remove or loosen the remaining fixing bolts on the end cover to separate the end cover from the flange.
[0057] S6. Turn the knob to move the pressing member 32 in a direction away from the pressure pipe orifice by a certain distance. This distance can be set according to actual conditions, so that the end cover can move along the guide rod in a direction away from the pressure pipe orifice to open the pressure pipe orifice by a certain distance, so that the pressure in the pressure pipe can drive the blockage to be discharged from the pressure pipe orifice, and the anaerobic sludge in the UASB tower will not flow out through the height difference, resulting in the inability to seal and causing a large amount of sludge discharge loss.
[0058] S7. After the blockage is discharged, the knob of the tightening member 32 is turned to allow the end cover to move along the guide rod toward the direction close to the pressure pipe to block the pressure pipe orifice, and the end cover is fixed to the flange with fixing bolts to quickly block the pressure pipe orifice. After that, the guide rod is removed, and the end cover is fixedly connected to the flange with fixing bolts at the position where the guide rod is installed. Finally, the connecting bracket 2 and the fixing seat 11 can be removed.
[0059] For other contents of the rapid plugging device and the dredging method for pressure pipe dredging described in the present invention, please refer to the prior art and will not be repeated here.
[0060] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Therefore, any modification, equivalent change and modification made to the above embodiment based on the technical essence of the present invention without departing from the technical solution of the present invention are still within the scope of the technical solution of the present invention.
Claims
1. A rapid plugging device for dredging a pressure pipeline, characterized in that: It comprises a fixing seat, a connecting bracket, a jacking piece and at least two guide rods, wherein the fixing seat is detachably mounted on the pressure pipe to be dredged, an end cap for blocking the pipe mouth of the pressure pipe is mounted at the pipe mouth of the pressure pipe, one end of the connecting bracket is fixedly connected to the fixing seat, and the other end is provided with a connecting plate, the end cap is located between the connecting plate and the fixing seat, one end of the jacking piece passes through the connecting plate and is threadedly connected to the connecting plate, and the other end is abutted and fixed with the end cap of the pressure pipe, and the jacking piece and the fixing seat are respectively located on both sides of the end cap; The two guide rods are parallel to each other, and the end cover can move along the two guide rods.
2. The rapid plugging device for dredging a pressure pipeline according to claim 1, characterized in that: The guide rod is a long bolt.
3. The rapid plugging device for dredging a pressure pipeline according to claim 1 is characterized in that: It also includes a handle, which is installed at one end of the tightening member and is located at an end of the connecting plate away from the fixing seat, and an angle is formed between the handle and the tightening member.
4. The rapid plugging device for dredging a pressure pipeline according to claim 3 is characterized in that: The fixing seat includes a fixing sleeve, and the connecting bracket also includes a plurality of connecting columns arranged at intervals. The fixing sleeve is sleeved on the outside of the pressure pipe, and one end of each connecting column is fixedly connected to the fixing sleeve, and the other end is detachably fixedly connected to the connecting plate.
5. The rapid plugging device for dredging a pressure pipeline according to claim 4 is characterized in that: The fixing sleeve comprises two butt-jointed clamps, the ends of which are connected end to end in sequence to form a cylindrical shape and are sleeved on the outside of the pressure pipe.
6. The rapid plugging device for dredging a pressure pipeline according to claim 5, characterized in that: The fixing seat further comprises two fixing members, and the two ends of each clamp are respectively provided with a first fixing portion and a second fixing portion, and two adjacent first fixing portions and two adjacent second fixing portions are both detachably fixedly connected by the fixing members; Each of the clamps further comprises a fixing plate, the first fixing portion, the fixing plate and the second fixing portion are connected in sequence, and the inner surface of the fixing plate is adapted to the outer surface of the pressure pipe.
7. The rapid plugging device for dredging a pressure pipeline according to claim 4, characterized in that: The fixing plate is semi-annular.
8. A method for unblocking a pressure pipeline, using the rapid plugging device for unblocking a pressure pipeline as claimed in any one of claims 1 to 7, characterized in that: The following steps are involved: S1. Stop the work process that requires the use of the pressure pipe to be dredged; Stop the anaerobic internal circulation pump and close the water inlet pipe valve, that is, stop adding pressure to the pressure pipe to be dredged; S2. Two guide rods are used to replace the two fastening bolts on the end cover of the pressure pipe, wherein a flange for mounting the end cover is provided at the pipe mouth of the pressure pipe, and after removing the two bolts for fixing the end cover and the flange, the two guide rods are respectively installed in the two through holes formed after the bolts are removed; S3. The fixing base is installed on the pressure pipe; S4. After the installation of the fixing base is completed, the connecting bracket is fixedly connected to the fixing base, and the top member is installed on the connecting plate, and the top member is rotated to tighten the end cover; S5. Remove the remaining fixing bolts on the end cover; S6. The knob of the tightening member enables the end cover to move along the guide rod in a direction away from the pressure pipe to open the pipe opening of the pressure pipe, and the pressure in the pressure pipe can drive the blockage to be discharged from the pipe opening of the pressure pipe; S7. After the blockage is discharged, the knob of the tightening member is turned to enable the end cover to move along the guide rod toward the direction close to the pressure pipe to block the pipe opening of the pressure pipe, and the end cover is fixed to the flange with fixing bolts. After that, the guide rod is removed, and the end cover is fixedly connected to the flange with fixing bolts at the position where the guide rod is installed.
9. The method for clearing a pressure pipeline according to claim 8, characterized in that: In step S2, the two guide rods replace the two fastening bolts located at opposite corners on the end cover.
Citation Information
Patent Citations
Construction method for extracting blind plate under coal gas
CN102927363A
Pipeline pressure test and plugging device
CN217559353U
Underwater temporary pipeline plug
CN221075707U
Closure device for connecting a pressure testing device, clamping device for fixing a closure or socket plug, and system and method for leak testing.
DE102020129583A1
A stopple apparatus for gas safety
KR1020160035719A