Overwater high-strength batholith construction method under complex geological environment

By combining backhoe dredgers, underwater picks, and drilling rigs, the problem of delayed construction progress on high-strength rock foundations in complex geological environments was solved, achieving efficient and low-cost construction results.

CN118979466APending Publication Date: 2024-11-19NO 2 ENG CO LTD OF CCCC THIRD HARBOR ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411167282.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-23
Publication Date
2024-11-19

AI Technical Summary

Technical Problem

In complex geological environments, especially in areas of strongly and moderately weathered granite, traditional cutter suction dredgers cannot operate, resulting in delays in the construction of high-strength rock foundations on water and increased costs.

Method used

A combination of backhoe dredgers, underwater jackhammers, dumping and drilling rigs, along with deck barges and dump trucks, is used for precise excavation, crushing and transportation to ensure construction efficiency.

Benefits of technology

It improved construction efficiency, reduced costs, solved the construction difficulties in traditional methods, and ensured the smooth progress of high-strength rock foundation construction on water in complex geological environments.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118979466A_ABST
    Figure CN118979466A_ABST
Patent Text Reader

Abstract

The invention provides an overwater high-strength batholith construction method under a complex geological environment, which comprises the following steps: construction of strong weathering and a covering layer: excavating by using a backhoe dredger and a deck barge, and transporting dredged objects through a mud barge and an earthwork vehicle; the mid-weathered rock is drilled through a drilling machine, the drilled mid-weathered rock is crushed through a gun machine, and then the crushed mid-weathered rock is excavated out through a backhoe dredger; by means of the method, it can be guaranteed that construction of the foundation trench containing the moderately-intense weathered rock is consistent with construction of the harbor basin area, and therefore construction continuity and efficiency are improved. Meanwhile, challenges of different rock characteristics can be coped with by flexibly adjusting equipment and optimizing the construction process, and smooth proceeding of a project is ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of water rock foundation treatment, and in particular to a water high-strength rock foundation construction method under a complex geological environment. Background Art

[0002] In the construction related to the fishing port, except for the foundation trench area, the harbor area south of the north breakwater and west of the dock is generally subject to strong and medium weathered granite, so the suction dredger cannot be used for construction in this area. In addition, the water depth of some projects is relatively shallow, and ships and machinery cannot enter the undredged harbor area for construction, which seriously restricts the construction of breakwaters and docks, resulting in serious delays in the progress of key processes such as harbor dredging, foundation trench excavation, caisson prefabrication, and caisson installation, which increases a lot of costs. Therefore, a treatment construction method for high-strength rock foundation is urgently needed. Summary of the invention

[0003] The technical problem to be solved by the present invention is to provide a method for constructing high-strength rock foundations on water in a complex geological environment, which utilizes a backhoe dredger and a comprehensive method for treating rock foundations on water: construction is carried out using a backhoe dredger, an underwater pickaxe machine, and casting to complete the excavation of the working deck, in conjunction with a drilling blaster, etc., so that the complex rock foundation can be well constructed, thereby improving the foundation for subsequent further construction.

[0004] In order to solve the above technical problems, the technical solutions provided by the present invention are as follows: A method for constructing a high-strength rock foundation on water in a complex geological environment comprises the following steps: Construction of strong weathering and overburden: excavation is carried out using backhoe dredgers and deck barges, and dredged materials are transported by mud barges and earthmoving vehicles; Moderately weathered rock construction: drilling holes in moderately weathered rock with a drilling rig, crushing the drilled moderately weathered rock with a blasting machine, and then removing the crushed moderately weathered rock with a backhoe dredger; Comprehensive treatment method for water rock foundation: use backhoe dredger, underwater pickaxe machine and throwing to complete the excavation operation.

[0005] Furthermore, during the construction of the strong weathering and covering layer in the above steps, a large backhoe dredger is used to assist two deck barges in excavation, and real-time monitoring is performed during the excavation.

[0006] Furthermore, in the construction of the strongly weathered and overburdened layers in the above steps, for the -3.0m area of ​​the harbor, the excavation bottom elevation is controlled below -3.5m, and over-excavation of 50cm is allowed; for the -4.5m area of ​​the harbor and the foundation trench excavation of the wharf and the north breakwater, it is carried out according to the designed bottom elevation, or until the medium-weathered rock layer is reached.

[0007] Furthermore, in the weathered rock construction in the steps, a rock distribution map is first drawn to obtain boreholes, and then the drilling rig drills holes in the rock at intervals of at least 0.5 m.

[0008] Furthermore, it also includes adding blasting and drilling rigs based on the existing drilling rigs and blasting rigs according to the rock distribution map.

[0009] Furthermore, the above-water rock foundation comprehensive treatment method mainly treats the rock foundations at harbors, breakwaters and docks.

[0010] Furthermore, in the above-water rock foundation comprehensive treatment method, the treatment for different rock layers is as follows: For strongly weathered rock formations, an 18m³ grab dredger is used for preliminary excavation; For medium weathered rock formations, a 3500 backhoe dredger with a 7-cubic-meter bucket, an 1800 backhoe dredger with a 5-cubic-meter bucket, and corresponding underwater pickaxe machines are used for crushing and excavation; For particularly hard and medium-weathered rocks, a high-power 870 underwater pickaxe machine is used for crushing.

[0011] Furthermore, for moderately weathered rock formations, a drilling rig can be used for drilling, followed by a blasting machine for crushing.

[0012] Furthermore, it also includes the construction of foundation trenches containing medium to strong weathered rocks. Specifically, the preliminary construction is carried out by using a method of first drilling and then crushing with an underwater pickaxe machine.

[0013] The present invention has the following beneficial effects: The present invention provides a method for constructing high-strength rock foundations on water in a complex geological environment, especially a construction method and system for strongly weathered and moderately weathered rock formations, so as to improve construction efficiency, reduce costs, and solve the problem of difficult rock foundation treatment in the prior art. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 The present invention provides a flow chart of a method for constructing a high-strength rock foundation on water in a complex geological environment. DETAILED DESCRIPTION

[0015] The present invention is described in detail below in conjunction with the various embodiments shown in the accompanying drawings, but it should be noted that these embodiments are not limitations of the present invention, and any equivalent transformations or substitutions in functions, methods, or structures made by ordinary technicians in the field based on these embodiments are all within the scope of protection of the present invention.

[0016] See attached Figure 1As shown, the scheme in the present invention should be used in a local confidential project. This project is specifically introduced as follows: There are strong and medium weathered granites in the foundation trench of the west breakwater pile number XK0+500~XK0+826, the whole section of the north breakwater pile number BK0+000~BK0+380, and the wharf pile number MK0+000~MK0+600 of the Puqian Central Fishing Port Project, of which 33,700 m³ are medium weathered granites. The harbor is filled with silt, sand and residual soil, without strong and medium weathered granites. During the construction process, it was found that in addition to the foundation trench area, the harbor area about 230m south of the north breakwater and about 250m west of the wharf generally had strong and medium weathered granites, and the suction boat could not be constructed in this area. In addition, the water depth of the central fishing port project is relatively shallow, and the ship and machinery in the undredged area of ​​the harbor cannot enter the construction point, which seriously restricts the construction of the breakwater and the wharf. This has resulted in serious delays in the progress of key processes such as harbor dredging, foundation trench excavation, caisson prefabrication, and caisson installation, increasing costs significantly.

[0017] All the gun machines in this embodiment are actually the original water pick-head machines that have been modified into assembled types. At this time, a machine-matched buoyancy box is selected, and the original bucket is replaced with an underwater pick-head machine. First, the harbor dredging construction in this project.

[0018] 1) Early construction methods The harbor dredging of this project uses one 2500m³ / h suction dredger and one 1000m³ / h suction dredger. One 2500m³ / h suction dredger was first put into construction. It was originally planned to complete the harbor dredging in half a year. However, the suction dredger encountered large areas of strong and medium weathered granite in the harbor during construction, and construction was impossible. The position of the ship and the engine could only be changed continuously, and there was no stone area for construction. Due to the large amount of harbor dredging, after evaluation, one 1000m³ / h suction dredger and 2500m³ / h suction dredger were added to dredge the harbor at the same time after 2 months of construction. However, due to the strong and medium weathered granite in the harbor, the construction of the 1000m³ / h suction dredger was also very difficult. After 8 months, 1.2 million m³ of harbor dredging has been completed.

[0019] Heavy grab dredgers and backhoe dredgers are used to excavate the strongly weathered and sand and residual soil covering layers (which cannot be cut by suction vessels) within the scope of the port basin. The medium-weathered rock is drilled by a drill rig and crushed by a blasting machine, and then excavated by a backhoe dredger. Half a year after the construction, an 1800 backhoe dredger (5m³ bucket, 210 underwater blasting machine) and a transport barge were brought in to excavate the rock foundation in the northern part of the port basin; subsequently, an 18m³ grab dredger (equipped with a 90t gravity axe) and two flatbed transport barges were brought in to construct the northern area of ​​the port basin. The 18m³ grab dredger can excavate sand, residual soil and some strongly weathered granite, but it cannot be used for large pieces of medium-weathered granite. Moreover, the 90t gravity axe equipped with the grab dredger is not ideal for crushing medium-weathered granite.

[0020] 2) Main ship machinery and equipment The main marine machinery and equipment invested in the port area are shown in the following table: Table 1 Main marine machinery and equipment invested in the port area

[0021] 3) Situation of strong weathering and covering layer in the harbor The strong weathering and covering layer of 126,900 m³ has been completed in the harbor. According to the earthwork volume, construction conditions and waste soil treatment characteristics of this project, the excavated dredged materials are brought ashore by mud barges and transported to the mud receiving area behind the land by earthmoving vehicles.

[0022] 4) The conditions of the medium-weathered rocks that have been discovered in the harbor For the constructed area of ​​Harbor Basin Zone 1, surveyors counted the amount of medium-weathered rock, with a total of 2502.84 m³, of which about 2047.89 m³ had been processed, leaving 454.95 m³. The volume statistics are shown in Table 2.

[0023] Table 2 Statistics of weathered rock volume in Harbor Area 1

[0024] 5) The remaining unexcavated area of ​​the harbor Combined with the previous construction situation, the original mud surface elevation in the harbor area is -1.5m~-1.7m, and the top elevation of the proven medium-weathered rock layer is -2.0m~-3.0m. For the harbor area, the geological exploration drilling points are arranged at 100m×150m. The geological exploration data cannot fully display the situation of the medium-weathered rock in the harbor, and there are sand and mud covering layers on the rock layer, so the specific amount of medium-weathered rock cannot be found.

[0025] Since the harbor area 1, harbor area 2 and harbor area 3 involve strong and medium weathered granite, the dredger cannot continue construction. The area where the dredger cannot construct is 198,000 square meters, and the remaining area is about 400,000 square meters, as shown in Table 3.

[0026] Table 3 Statistics of areas where cutter suction boats cannot be used for construction

[0027] Secondly, the comprehensive treatment method of the above-water rock foundation - harbor.

[0028] This is the key point in this embodiment, which specifically includes the following aspects: (1) Strong weathering and covering layer construction The construction technology of the strong weathering and covering layer is the same as that of the completed area. Due to the large volume, it is necessary to add a 13m³ heavy-duty backhoe dredger and 2 deck barges for construction. During the dredging construction: the excavation bottom elevation of the -3.0m area of ​​the harbor is in accordance with -3.5m (the specification allows over-excavation of 50cm and meets the water depth required by the harbor when the caisson is installed) or reaches the control of the medium weathering layer; the excavation elevation of the -4.5m area of ​​the harbor and the wharf and the north breakwater foundation trench is in accordance with the design bottom requirements or reaches the control of the medium weathering rock layer. According to the characteristics of the earthwork volume, construction conditions and waste soil treatment of this project, the excavated dredged materials are brought ashore by mud barges and transported to the mud receiving area behind the land by earthmoving vehicles.

[0029] (2) Construction in moderately weathered rock.

[0030] 1) The drilling rig drills holes in weathered rock.

[0031] After the overburden is removed, the medium weathered rock is measured, the rock distribution map is drawn and the excavation volume is counted. The surveying personnel organize the drilling rig to accurately move in and accurately locate the location of the medium weathered rock. The drilling rig drills holes at intervals of 0.5m, and the bottom elevation of the holes is controlled according to the design elevation.

[0032] 2) The 870 blasting machine crushes the medium-weathered rock in the drilled hole.

[0033] After the drilling is completed, the surveying personnel will organize the 870 cannon machine to accurately advance into the drilled area and create cracks in the moderately weathered rock.

[0034] 3) 1800 backhoe dredger removes the broken moderately weathered rock.

[0035] After the drilling rig and 870 blasting machine crushed the medium weathered rock, the backhoe dredger excavated it to the elevation. According to the earthwork volume, construction conditions and waste soil treatment characteristics of this project, the excavated dredged materials were brought ashore by mud barges and transported to the mud receiving area behind the land by earthmoving vehicles.

[0036] 4) According to the evaluation of the previous construction situation, the distribution area of ​​medium-weathered rock is wide and the volume is large. On the basis of the existing drilling and rock drilling equipment, it is planned to add one 870 blasting machine and one drilling rig.

[0037] Again, comprehensive treatment methods for water rock foundations - breakwaters and docks.

[0038] 1) Construction status The total excavation volume of the breakwater and wharf foundation trench of this project is 611,400 m³, including 33,700 m³ of medium-weathered rock. Among them, the section of the west breakwater foundation trench with pile number XK0+000-XK0+500 was constructed by dredgers. Since this project cannot be dumped outside, the mud and sand excavated from the foundation trench were loaded onto ships and dumped into the designated area of ​​the harbor, and then filled into the mud receiving area by suction dredgers.

[0039] During the early stage of construction, for the foundation trench area containing strong and moderately weathered rocks, 3500 backhoe dredgers with 7 cubic buckets, 1800 backhoe dredgers with 5 cubic buckets and 210 underwater pickaxes, mud barges and drilling rigs were used for construction. At the same time, 870 backhoe excavators with 210 underwater pickaxes, 950 backhoe excavators with 185 underwater pickaxes, 460 backhoe excavators with 165 underwater pickaxes and other ship machinery equipment were used to cooperate with the rock foundation removal.

[0040] A 3500 backhoe dredger equipped with a 7-cubic-meter bucket entered the site first to excavate the areas involving strong and moderately weathered granite layers on the west breakwater. During the excavation, due to the excessive strength of the moderately weathered granite, the backhoe bucket and boom were torn, and the boom hydraulic cylinder was damaged.

[0041] The 1800 backhoe dredger entered the site again. The equipment performance is better than that of the 3500 backhoe dredger. It can dredge the medium-weathered granite with cracks after being crushed by the blasting machine.

[0042] So far, the foundation trench excavation of the west breakwater has been basically completed, among which there are still shallow rock foundation points to be cleared in the XK0+700-XK0+826 piles; the excavation of the overburden above the weathered rock layer in the foundation trench of the north breakwater has been completed in a total area of ​​380m; the wharf area has not been excavated due to the limited operating conditions of the port basin water depth. The total amount of foundation trench excavation completed is 525,000 m³.

[0043] 2) Main ship machinery and equipment The main marine equipment put into use in the area of ​​medium-strong weathered rock in the foundation trench is shown in Table 4: Table 4 Main marine equipment invested in the area of ​​foundation pit containing medium to strong weathered rock

[0044] 3) Subsequent construction methods The construction method of the foundation trench containing moderately strong weathered rock is consistent with the construction method of the remaining harbor area Finally, a detailed construction introduction is given.

[0045] Step 1. Strong weathering and covering layer construction: A 13m³ large backhoe dredger and deck barge are used for excavation to ensure that the excavation bottom elevation of the harbor area meets the requirements, and mud barges and earthmoving vehicles are used to transport dredged materials.

[0046] In the construction of the strongly weathered and overburdened layers, a large backhoe dredger with a capacity of 13 cubic meters was used, supplemented by two deck barges to improve the operation efficiency. During the construction process, special emphasis was placed on the different elevation requirements for the port area: for the -3.0m area of ​​the port, the excavation bottom elevation was controlled below -3.5m, and an over-excavation of 50cm was allowed to ensure that the water depth requirements of the port were met during the installation of the caisson; for the -4.5m area of ​​the port and the foundation trench excavation of the wharf and the north breakwater, it was strictly implemented in accordance with the designed bottom elevation, or until the medium-weathered rock layer was reached.

[0047] In order to achieve efficient dredged material treatment, the specific construction method in this embodiment is as follows: 1) Excavation of dredged materials: Backhoe dredgers carry out excavation operations, which are precisely controlled according to the design elevations of different areas.

[0048] The measuring equipment equipped on the dredger monitors the excavation depth in real time to ensure the accuracy of the excavation elevation.

[0049] 2) Transportation and treatment of dredged materials: The dredged material is transported to the shore by mud barges.

[0050] On the shore, earth-moving vehicles are used to transport the dredged materials to the mud receiving area behind the land.

[0051] The construction steps in this embodiment are as follows: for the construction of strongly weathered and overburden layers, first use a 13m³ dredger for excavation, then use a deck barge for assistance, then excavate the dredged material, bring the mud barge ashore, transport it by earthmoving trucks, and process it in the mud receiving area.

[0052] In this embodiment, taking the excavation of the -3.0m area of ​​the harbor as an example, first, the dredger operates according to the bottom elevation of -3.5m required by the design drawings. During the excavation process, the surveyor monitors the excavation depth in real time through the equipment on board to ensure that it does not exceed the over-excavation range allowed by the specification. The dredged materials are collected by the mud barge, transported to the shore, and then distributed to the mud receiving area by the earth moving truck. This process ensures a balance between construction efficiency and environmental protection.

[0053] In this embodiment, not only the construction efficiency is improved, but also the construction quality is ensured, laying a foundation for the smooth progress of subsequent engineering links.

[0054] Step 2. Construction of medium weathered rock: In this embodiment, for medium weathered rock, it includes the following sub-steps: Step 2.1. The drill rig drills holes in the weathered rock, accurately measures and draws a rock distribution map.

[0055] Step 2.2. Use the 870 blasting machine to crush the drilled medium-weathered rock.

[0056] Step 2.3. Use 1800 backhoe dredger to remove the broken medium-weathered rock.

[0057] Step 2.4. Based on the construction situation assessment, add drilling and blasting equipment to improve construction efficiency.

[0058] For the treatment of medium weathered rock, the following detailed construction steps are adopted: 2.1 Drilling rig drilling in weathered rock: After the overburden is removed, high-precision measuring equipment is used to conduct detailed measurements of the moderately weathered rock and create a rock distribution map in order to accurately count the excavation volume.

[0059] The surveyors guided the drilling rig to accurately move forward to ensure that the drilling position of the medium weathered rock layer was accurate. The drilling rig drilled holes in the rock at intervals of 0.5m, and the bottom elevation of the holes was strictly controlled according to the design requirements.

[0060] 2.2 870 blasting machine crushes the drilled medium weathered rock: After the drilling was completed, the surveyors once again organized the 870 blasting machine to accurately locate the drilled area, and then carried out rock crushing operations, using precise blasting technology to create cracks in the moderately weathered rock.

[0061] 2.3 1800 backhoe dredger removes broken medium weathered rock: After the drilling rig and 870 blasting machine completed the crushing of the medium-weathered rock, the 1800 backhoe dredger was responsible for excavating the crushed rock to the designed elevation.

[0062] 2.4 Construction equipment evaluation and addition: According to the evaluation of the previous construction situation and considering the wide distribution range and large volume of medium-weathered rock, it is planned to add one 870 blasting machine and one drilling rig on the basis of the existing drilling rigs and blasting equipment to improve construction efficiency.

[0063] In actual construction, first, the drilling rig is used to accurately drill holes and a rock distribution map is drawn based on the measurement data. Then, the 870 blasting machine accurately crushes the rocks according to the drilling position to ensure the formation of rock cracks. Afterwards, the 1800 backhoe dredger removes the crushed rocks and operates according to the designed elevation. By adding drilling rigs and blasting machine equipment, the construction speed can be significantly increased and the construction period can be shortened.

[0064] For example, in a specific construction area, through the above steps, the drilling work of the 1,000 square meter area was first completed, and a detailed rock distribution map was drawn. Then, under the guidance of the surveyors, the 870 gun machine carried out crushing operations in this area. After the crushing was completed, the 1800 backhoe dredger quickly intervened to dig out the broken rocks. With the support of the new equipment, the efficiency of the entire construction process increased by 30%, effectively shortening the project cycle.

[0065] Step 3. Comprehensive treatment of water rock foundation - breakwaters and docks: In this embodiment, different types of backhoe dredgers, underwater pick dredgers and underwater pick dredgers are used for construction according to different areas and rock types to ensure smooth excavation of the foundation trench.

[0066] This embodiment adopts a comprehensive treatment method for different areas and rock types involved in the excavation of breakwaters and wharf foundation trenches. The core of this method is to accurately select the backhoe dredger, underwater pickaxe machine model and underwater pickaxe machine specifications that match the rock characteristics to ensure the efficiency and safety of the excavation operation.

[0067] 3.1 Equipment selection and configuration: For strongly weathered rock formations, a 3500 backhoe dredger with a 7-cubic-meter bucket is used for initial excavation.

[0068] For medium-weathered rock formations, an 1800 backhoe dredger with a 5-cubic-meter bucket and corresponding underwater pickaxe are used for precise crushing and excavation.

[0069] For particularly hard and moderately weathered rocks, a high-power 870 excavator and a 210 gun head underwater pickaxe are used for crushing.

[0070] 3.2 Construction process: First, the type and distribution of rocks in the foundation pit area are determined through measurement and geological survey.

[0071] According to the rock type and hardness, choose the appropriate dredger and underwater pickaxe equipment for the operation.

[0072] During the excavation process, for moderately weathered rocks that are difficult to excavate directly, a drill is first used to drill holes, and then a blasting machine is used to crush them.

[0073] 3.3 Construction equipment coordination: During construction, different models of underwater pickaxe machines (such as 950 excavator with 185 gun head, 460 excavator with 165 gun head) are used in combination as needed to improve construction flexibility and efficiency.

[0074] Transport barges (such as the Sui Hai Yun 288) are responsible for transporting the dredged material from the construction site to the designated area.

[0075] The construction logic in this embodiment is as follows: A[Rock foundation comprehensive treatment] --> B[Equipment selection] A --> C[Construction process] B --> D[3500 Dredger] B --> E[1800 Dredger] D --> F[Excavation of strongly weathered rock] E --> G[Excavation of medium weathered rock] C --> H[Drilling machine drilling] C --> I[Cannon Machine Destroyed] H --> I G --> J[Underwater pickaxe machine] F --> J J --> K[Dredged material transport] K --> L[Transport Barge] Taking the excavation of a breakwater foundation trench as an example, first, according to the geological survey report, it was determined that there were a large number of medium-weathered rocks in the area. In view of this situation, an 1800 backhoe dredger with a 5-cubic-meter bucket and a corresponding underwater pickaxe was selected for construction. Before excavation, the drilling rig first accurately drilled holes in the medium-weathered rocks, and then an underwater pickaxe consisting of an 870 excavator and a 210 gun head was used to crush the rocks.

[0076] After the crushing was completed, the 1800 backhoe dredger quickly intervened to remove the crushed rocks. During this process, the 950 and 460 underwater pickaxe machines flexibly cooperated according to the on-site conditions to improve the construction efficiency. The dredged materials were transported to the designated area by the "Sui Haiyun 288" transport barge to prepare for the subsequent filling operation.

[0077] Through the above-mentioned comprehensive treatment method, in this embodiment, not only the smooth progress of foundation trench excavation is ensured, but also the construction efficiency is significantly improved and the cost is reduced by optimizing the equipment configuration and construction process.

[0078] Step 4. Main ship and machinery equipment: including backhoe dredgers, underwater pickaxe dredgers, drilling rigs, etc., as well as corresponding transport barges, are used to cooperate in completing the treatment of medium-weathered rock strata.

[0079] In this embodiment, in the construction of treating medium-weathered rock formations, the selection and configuration of key equipment are crucial to improving work efficiency and ensuring construction safety.

[0080] The following is a detailed description of the main ship machinery equipment and its construction methods: 4.1 Backhoe Dredger Model and specification: Choose a large backhoe dredger with strong digging capacity, such as the 3500 backhoe dredger equipped with a 7-cubic-meter bucket, which is suitable for excavation of strongly weathered rock formations.

[0081] Construction application: This equipment is mainly used for preliminary excavation of the -3.0m area of ​​the harbor and removal of the overburden above the medium-weathered rock layer.

[0082] 4.2 Underwater pickaxe machine and underwater pickaxe machine Models and specifications: For medium weathered rock formations, use 1800 backhoe dredgers equipped with 5 cubic buckets and specific models of underwater pick dredgers, such as 210 underwater pick dredgers, for precise crushing.

[0083] Construction application: After the drilling rig completes the drilling operation, the underwater pick and underwater pick are used to crush the medium weathered rock to prepare for the subsequent excavation operation. At this time, the original water pick (i.e., cannon) is changed to a machine equipped with a buoyancy box, and the bucket is replaced with an underwater pick.

[0084] 4.3 Drilling rig Model and Specifications: High-precision drilling rigs are used for accurate positioning and drilling of moderately weathered rock formations.

[0085] Construction application: Before excavation, the drilling rig arranges holes according to the design requirements to provide accurate drilling positions for the blasting machine crushing operation. Similarly, the water pick head machine (blasting machine) at this time is changed to an underwater pick head machine with a buoyancy box, and the bucket is replaced with an underwater pick head machine.

[0086] 4.4 Transport barge Model and specification: Configure transport barges suitable for project requirements, such as "Sui Hai Yun 288" for the transportation of dredged materials.

[0087] Construction application: After the dredger and underwater pickaxe machine complete the excavation of the dredged materials, the transport barge quickly transports the dredged materials from the construction site to the designated area.

[0088] The construction logic in this step is as follows: A[Equipment Configuration and Construction] --> B[Backhoe Dredger] A --> C[Underwater pickaxe machine] A --> D[Drilling rig] A --> E[Transport Barge] B --> F[Excavation of strongly weathered rock] C --> G[Medium weathered rock fragmentation] D --> H[Precision Drilling] E --> I[Dredged Material Transport] F --> J[3500 Backhoe Dredger] G --> K[1800 Backhoe Dredger] H --> L[High precision drilling machine] I --> M["Sui Hai Yun 288"] In actual construction, taking the treatment of medium-weathered rock as an example, first, according to the geological survey results, the specific distribution and hardness of the rock layer are determined. In view of this situation, the 1800 backhoe dredger and 210 underwater pickaxe are selected for crushing operations. After the equipment is in place, the drilling rig will perform precise drilling to ensure the efficiency and safety of the blasting machine crushing operation.

[0089] After the crushing is completed, the 3500 backhoe dredger quickly conducts preliminary excavation to remove the broken rocks. At the same time, the 1800 backhoe dredger performs secondary crushing of rocks that are difficult to directly excavate according to the on-site conditions. The dredged materials are transported out in time by the "Sui Haiyun 288" transport barge to ensure the cleanliness of the construction site and the continuity of operations.

[0090] Through the combination of this equipment configuration and construction method, efficient and safe construction can be carried out according to the characteristics of medium-weathered rock strata. This not only improves construction efficiency, but also reduces equipment loss, providing a strong guarantee for the smooth progress of the project.

[0091] Step 5. Subsequent construction methods: The construction method of the foundation trench containing moderately strong weathered rock should be consistent with the construction method of the harbor area to ensure construction continuity and efficiency.

[0092] When dealing with the foundation trench area containing medium to strong weathered rock, the construction method is consistent with the construction method in the harbor area to ensure the continuity and efficiency of the construction. The specific implementation steps are as follows: Construction preparation: Conduct a detailed geological survey of the foundation pit area to determine the distribution and hardness of medium to strong weathered rocks.

[0093] According to the survey results, select appropriate construction equipment, such as backhoe dredger, underwater pickaxe machine, etc. Rock processing: Use a drilling rig to accurately drill holes in medium to strong weathered rocks in preparation for subsequent crushing operations.

[0094] Use an underwater pickaxe to break the drilled rock to ensure that the rock is fully broken.

[0095] Excavation work: After the rock is crushed, a backhoe dredger is used to excavate the crushed rock until the designed elevation is reached.

[0096] During the excavation process, surveyors monitor the excavation depth in real time to ensure the accuracy of the excavation elevation.

[0097] Dredged material handling: The dredged material is transported to the shore by mud barges.

[0098] On the shore, earth-moving vehicles are used to transport the dredged materials to the mud receiving area behind the land.

[0099] Equipment coordination and optimization: According to the construction progress and rock characteristics, the configuration of underwater pickaxe machines and other equipment can be flexibly adjusted to improve construction efficiency.

[0100] Regularly inspect and maintain the equipment to ensure its normal operation.

[0101] Through the above steps, we can ensure that the construction of the medium-strong weathered rock foundation trench is consistent with the construction of the harbor area, thereby improving the continuity and efficiency of the construction. At the same time, by flexibly adjusting equipment and optimizing construction processes, we can cope with the challenges of different rock characteristics and ensure the smooth progress of the project.

[0102] The following is a construction sequence logic diagram for the above construction steps: A[Subsequent construction method] --> B[Construction preparation] A --> C[Rock Processing] B --> D[Geological Survey] B --> E[Device Selection] C --> F[Drilling machine drilling] C --> G[Underwater pickaxe crusher] D --> H[Distribution of moderately strong weathered rocks] E --> I[Backhoe Dredger] E --> J[Underwater pickaxe machine] F --> K[Precision Drilling] G --> L[Rock Crushing] K --> G L --> M[Excavation work] M --> N[Dredged material disposal] N --> O[Mud barge transport] N --> P[Earthmoving vehicle transport] O --> Q[shore] P --> R[Nani District] The above construction method can ensure that the construction of the medium-strong weathered rock foundation trench is consistent with the construction of the harbor area, thereby improving the continuity and efficiency of the construction. At the same time, by flexibly adjusting equipment and optimizing the construction process, it can cope with the challenges of different rock characteristics and ensure the smooth progress of the project.

[0103] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.

[0104] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A method for constructing high-strength rock foundation on water in a complex geological environment. It is characterized in that The following steps are involved: Construction of strong weathering and overburden: excavation is carried out using backhoe dredgers and deck barges, and dredged materials are transported by mud barges and earthmoving vehicles; Moderately weathered rock construction: drilling holes in moderately weathered rock with a drilling rig, crushing the drilled moderately weathered rock with a blasting machine, and then removing the crushed moderately weathered rock with a backhoe dredger; Comprehensive treatment method for water rock foundation: use backhoe dredger / underwater pickaxe machine and throwing to complete the excavation operation.

2. According to claim 1, a method for constructing a high-strength rock foundation on water in a complex geological environment, It is characterized in that During the construction of the strong weathering and covering layers in the above steps, a large backhoe dredger is used to assist two deck barges in excavation, and real-time monitoring is performed during the excavation.

3. The method for constructing a high-strength rock foundation on water in a complex geological environment according to claim 2, It is characterized in that During the construction of the strongly weathered and overburdened layers in the above steps, for the -3.0m area of ​​the harbor, the excavation bottom elevation is controlled below -3.5m, and over-excavation of 50cm is allowed; for the -4.5m area of ​​the harbor and the foundation trench excavation of the wharf and the north breakwater, it is carried out according to the designed bottom elevation, or until the medium-weathered rock layer is reached.

4. The method for constructing a high-strength rock foundation on water in a complex geological environment according to claim 1, It is characterized in that In the weathered rock construction in the steps, a rock distribution map is first drawn to obtain boreholes, and then a drilling rig drills holes in the rock at intervals of at least 0.5 m.

5. The method for constructing a high-strength rock foundation on water in a complex geological environment according to claim 4, It is characterized in that It also includes adding blasting and drilling rigs to the existing drilling rigs and blasting rigs based on the rock distribution map.

6. The method for constructing a high-strength rock foundation on water in a complex geological environment according to claim 1, It is characterized in that The above-water rock foundation comprehensive treatment method mainly treats the rock foundations at harbors, breakwaters and docks.

7. The method for constructing a high-strength rock foundation on water in a complex geological environment according to claim 1, It is characterized in that In the above-water rock foundation comprehensive treatment method, the treatment for different rock layers is as follows: For strongly weathered rock formations, an 18m³ grab dredger is used for preliminary excavation; For medium weathered rock formations, a 3500 backhoe dredger with a 7-cubic-meter bucket, an 1800 backhoe dredger with a 5-cubic-meter bucket, and corresponding underwater pickaxe machines are used for crushing and excavation; For particularly hard and moderately weathered rocks, high-powered underwater pickaxes are used for crushing.

8. The method for constructing a high-strength rock foundation on water in a complex geological environment according to claim 7, It is characterized in that For moderately weathered rock formations, a drilling rig can be used to drill holes, and then a blasting machine can be used to break them.

9. The method for constructing a high-strength rock foundation on water in a complex geological environment according to claim 1, It is characterized in that It also includes the construction of foundation trenches containing moderately to strongly weathered rock. Specifically, the preliminary construction is carried out by drilling first and then breaking with an underwater pickaxe machine.