Tunnel excavation support construction measure and method for undercrossing river channel
Through the construction method combining two-step mechanical excavation and weak blasting, combined with advance geological forecasting and real-time monitoring, the impact of tunnel excavation on the river is solved, construction efficiency and safety are improved, and tunnel deformation and geological disasters are avoided.
Patent Information
- Application Number
- CN202411250919.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-06
- Publication Date
- 2024-11-22
AI Technical Summary
During the excavation of tunnels under the river, the existing blasting construction methods have an impact on the river, making the construction difficult and lack targeted construction methods.
Two-step mechanical excavation is adopted and supplemented by weak blasting. Through steps such as advance geological forecasting, monitoring and laying out lines, advance support, initial support, bottom plate concrete pouring and side top arch concrete lining, the surrounding rock deformation data is recorded in real time in combination with the monitoring system. , adjust the construction plan to avoid the impact of tunnel excavation on the river.
It effectively avoids the impact of tunnel excavation on the river, improves construction efficiency, and prevents tunnel deformation, landslide and vault collapse and other geological disasters such as construction safety through real-time monitoring and adjustment of support structures, ensuring construction safety.
Smart Images

Figure CN118997773A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of tunnel construction, in particular to a tunnel excavation support construction measure and method for underpass a river channel. Background Art
[0003] When excavating a tunnel that passes under a river, the tunnel excavation project will be affected by geology because the tunnel section passes through the river. The existing blasting construction method will have an impact on the river, and the construction is difficult. There is currently no targeted construction method. Summary of the invention
[0004] The purpose of the present invention is to provide a tunnel excavation support construction measure and method for underpasses, through two-step mechanical excavation, and when necessary, supplemented by weak blasting, to avoid the tunnel excavation project from affecting the river.
[0005] The present invention is implemented by the following technical solution: a tunnel excavation support construction measure and method for underpass river channel, comprising the following steps: Step 1: Advanced geological prediction, through geological methods, geophysical methods, and advanced geological drilling methods, complete the exploration of various lithologies of the tunnel section, and design and change the construction plan according to the exploration results; Step 2: Measure and lay out; according to the on-site conditions, set the vault settlement monitoring point, the first perimeter convergence monitoring line, the first perimeter convergence monitoring point reflector, the second perimeter convergence monitoring line, and the second perimeter convergence detection point reflector; Step 3: Advanced support, using advanced anchor rods, advanced small pipes, advanced large pipe sheds and advanced grouting to provide advanced protection for the soft rock bottom layer; Step 4: Excavation and slag removal on the steps, using a wall drilling machine for drilling and blasting operations, and using an excavator and a loader to remove the slag from the hole excavated by the wall drilling machine; Step 5: For the initial support of the upper steps and the monitoring and measurement of the surrounding rock, a joint support structure of the initial shotcrete layer, steel support and anchor rack is used. The construction is carried out closely following the excavation surface in the order of initial shotcrete, erecting steel frames, driving anchors, hanging meshes and re-shotcrete to the designed thickness. A monitoring system is used to monitor and record the surrounding rock deformation, vault settlement, surface settlement and other data in real time.
[0006] Step 6: Excavation and slag removal of the lower step. After the upper step is supported, a wall drilling machine is used for drilling and blasting operations, and an excavator and loader are used to remove the slag from the hole excavated by the wall drilling machine; Step 7: Initial support of the lower step and monitoring and measurement of surrounding rock. Use a joint support structure of shotcrete layer, steel support, and anchor rack. Follow the excavation surface for construction in the order of shotcrete, anchoring, mesh hanging, and re-shotcrete to the designed thickness. Use a monitoring system to monitor and record data such as surrounding rock surface convergence, vault settlement, and surface settlement in real time. Step 8: pouring concrete on the bottom plate. Use a wet spraying manipulator to spray concrete, seal with quick-setting mortar, and pour concrete on the bottom plate of the hole at the same time; Step 9: Concrete lining of the side and top arches: use a wet spraying robot to spray, seal with quick-setting mortar, and concrete lining the sides and arch tops; Step 10: Secondary lining: Design the secondary lining method in real time based on the data from the monitoring system. Use reinforced concrete lining method for secondary lining. After the secondary lining is completed, carry out cyclic excavation.
[0007] In order to better implement the method of the present invention, further, the advanced support adopts the surface pre-consolidation grouting method to avoid deformation, landslides, roof falls and other problems in the tunnel during construction.
[0008] In order to better implement the method of the present invention, further, the initial support anchor rods of the upper step and the lower step adopt hollow anchor rods, and the steel support spacing is 70 cm. The steel support spacing can be adjusted to 50 cm according to the properties of the surrounding rock. Steel supports are added one by one in the bottom plate as lateral supports.
[0009] In order to better implement the method of the present invention, further, according to the surrounding rock type, the excavation span of the cavern and the buried depth of the cavern, the allowable deformation value of the surrounding rock is estimated as the standard value of the surrounding rock stability state. When the measured total deformation of the surrounding rock is close to the prescribed allowable value or the daily deformation exceeds 1 / 4~1 / 5 of the prescribed allowable value, the support parameters are immediately corrected and secondary support is performed.
[0010] In order to better implement the method of the present invention, further, the bottom plate concrete pouring is performed by pouring a 20 cm thick C20 concrete cushion layer outside the secondary lining structure to avoid deformation and instability of the steel support.
[0011] In order to better implement the method of the present invention, further, in the steps 4 and 6, the monitoring of the surrounding rock surface convergence amount is used to determine the surface deformation after tunnel excavation, and the appropriate time for secondary lining is selected according to the real-time situation.
[0012] In order to better implement the method of the present invention, further, in the steps 4 and 6, the monitoring of the vault settlement is used to determine the stability of the surrounding rock, judge the support effect and avoid the collapse of the vault.
[0013] In order to better implement the method of the present invention, further, in step 4 and step 6, the monitoring of surface settlement is used to avoid landslides of surface buildings.
[0014] Compared with the prior art, the present invention has the following advantages and beneficial effects: 1. The present invention can timely discover abnormal situations through advanced geological forecasting, and predict the location, occurrence, water content and integrity of the surrounding rock structure of the unfavorable geological body in front of the face, so as to provide a basis for optimizing the tunnel construction plan, and timely provide information for preventing possible catastrophic accidents such as water inrush, mud inrush, karst, soft and broken surrounding rock, so as to prepare for the construction in advance and avoid losses.
[0015] 2. The present invention monitors the surface convergence of the surrounding rock to determine the surface deformation after tunnel excavation, selects the appropriate time for secondary lining according to the real-time situation, monitors the settlement of the arch to determine the stability of the surrounding rock, judges the support effect to avoid arch collapse, and monitors the surface settlement to determine whether the project will cause harm to surface buildings.
[0016] 3. The present invention adopts a two-step mechanical tunnel excavation method, which can avoid the impact of tunnel excavation on the river, and provides corresponding construction measures according to the geological changes of the river, which can greatly improve work efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Other features, objects and advantages of the present invention will become more apparent from the detailed description of non-limiting embodiments with reference to the following drawings: Figure 1 This is the process flow chart of tunnel excavation construction for this application; Figure 2 This is a schematic diagram of the longitudinal section of the step method excavation construction for this application; Figure 3 This is a schematic diagram of the measurement point layout for this application.
[0018] Among them: 1-vault settlement monitoring point; 2-first perimeter convergence monitoring line; 3-first perimeter convergence monitoring point reflector; 4-second perimeter convergence monitoring line; 5-second perimeter convergence monitoring point reflector; 6-initial sprayed concrete layer; 7-steel support; 8-anchor rack; 9-upper step; 10-lower step. DETAILED DESCRIPTION
[0019] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0020] Embodiment 1: like Figure 1 , Figure 2 As shown, this embodiment provides a tunnel excavation support construction measure and method for underpass, including the following steps: Step 1: Advanced geological prediction. Through geological methods, geophysical methods, and advanced geological drilling methods, the exploration of various lithologies of the tunnel section is completed, and the construction plan is designed and changed according to the exploration results. The geological sketch prediction method is divided into three types: rock lithology and stratigraphic prediction method, strip-shaped unfavorable geological body impact tunnel length prediction method, and irregular geological body impact tunnel length prediction method. Conduct geological sketches on the rock strata exposed at the face (observe the mineral composition and content of the rock, structural and tectonic characteristics, and special signs), give accurate names, and measure the occurrence and thickness of the rock strata. Measure the distance between the rock strata and the exposed landmark rock strata or interface, and calculate the thickness of its vertical plane. Compare the rock strata with the measured stratigraphic profile and stratigraphic column on the surface to determine its position and stratigraphic position in the surface stratigraphic (rock) sequence. Based on the rock strata sequence of the measured stratigraphic profile and stratigraphic column, combined with the TSP detection results, repeated comparisons and analyses are carried out to finally infer the position and scale of the rock strata that will appear within a certain range in front of the face.
[0021] During the construction process, geological engineers will make geological sketches after each blasting, including the stability of the front and side faces of the tunnel, the occurrence of rock formations, the degree of rock weathering, the development of joints and fissures (occurrence, spacing, length, fillings, quantity), shotcrete cracking, block falling, water gushing, water quality, water impact, concentration of undesirable gases, etc. At the same time, the surface hydrological environment is regularly observed and monitored and recorded to timely understand the impact of tunnel construction on surface water, determine construction control measures, and finally make a geological sketch of the tunnel face and a geological display of the tunnel body. draw a geological sketch and fill in the geological survey record form of the excavation working face: check whether the shotcrete has cracks and development, whether the anchor rods are loose, the status of the steel frame support, etc., and make corresponding records; check whether the side slopes are cracked or peeling, whether there are cracks on the surface; check whether there are abnormal changes in the surface water level.
[0022] The full name of TRT technology is "true reflection tomography" (true reflection body photography), which adopts spatial multi-point reception and excitation; the shot points of the excitation and detectors are spatially distributed to fully obtain spatial wave field information to improve the positioning accuracy of poor geological bodies; this method has high accuracy in determining the position of the reflection interface in the rock mass, the rock mass wave velocity and the classification of engineering categories, etc., which is a great improvement over the TSP method; the detection distance of the TRT method in crystalline rock mass can reach 100~150m, and 60~90m can be predicted in weak soil layers and broken rock mass.
[0023] Tunnel advance geological drilling should use geological drills to determine the geological conditions in front of the heading face and judge whether there are weak fractured zones, water-rich fractured strata, rock strata containing harmful gases, etc.
[0024] Through the results of geological prediction and forecasting, we quantify rock mass parameters, comprehensively determine the surrounding rock types, refine the composition of discontinuous interfaces and layers, and focus on clarifying the geological structure, karst, fault fracture zones; at the same time, we find out the laws of groundwater circulation, water flow characteristics, and groundwater chemical composition; together with relevant experts, we re-analyze the submitted results, and propose necessary safety measures for possible geological problems to guide on-site construction; based on the forecast results, we provide timely feedback to the design unit to adjust the design and change the construction plan.
[0025] Step 2: Measure and lay out; according to the on-site conditions, set up a vault settlement monitoring point 1, a first perimeter convergence monitoring line 2, two first perimeter convergence monitoring point reflectors 3, a second perimeter convergence monitoring line 4, and two second perimeter convergence detection point reflectors 5.
[0026] Step three: Advance support. Because the surrounding rock is broken and cannot stabilize itself after excavation, in order to prevent the top surrounding rock from collapsing, advance anchor rods, advance small guide pipes, advance large pipe racks and advance grouting are mainly used to carry out advance support for the soft rock strata before excavation of the heading face.
[0027] Step 4: Excavate and remove slag on the upper step 9, use a wall drilling machine to perform drilling and blasting operations, and use an excavator and a loader to remove slag from the hole excavated by the wall drilling machine.
[0028] Step 5, initial support of the upper step 9 and monitoring and measurement of the surrounding rock, adopt a joint support structure of the initial sprayed concrete layer 6, steel support 7, and anchor frame 8. The steel support 7 can be connected and lengthened multiple times. The construction is carried out closely following the excavation surface in the order of initial sprayed concrete, erecting steel frame, anchor construction, hanging mesh, and re-sprayed concrete to the designed thickness. The monitoring system is used to monitor and record the surrounding rock deformation, arch settlement, surface settlement and other data in real time.
[0029] Step 6: excavation and slag removal of the lower step 10. After the support of the upper step 9 is completed, a wall drilling machine is used for drilling and blasting operations, and an excavator and a loader are used to remove the slag from the hole excavated by the wall drilling machine.
[0030] Step seven, initial support and surrounding rock monitoring and measurement of the lower step 10, using a joint support structure of shotcrete layer 6, steel support 7, and anchor frame 8, construction is carried out closely following the excavation surface in the order of initial shotcrete, erecting steel frame, anchor construction, hanging mesh, and re-shotcrete to the designed thickness, and a monitoring system is used to monitor and record data such as the surface convergence of the surrounding rock, vault settlement, and surface settlement in real time.
[0031] Step 8: pouring of bottom slab concrete. Use a wet spraying robot to spray concrete, seal with quick-setting mortar, and pour concrete on the bottom slab of the hole at the same time.
[0032] Step 9: Concrete lining of the side and top arches. Use a wet spraying robot to perform spraying operations, seal with quick-setting mortar, and concrete lining the sides and arch tops.
[0033] Step 10: Secondary lining: Design the secondary lining method in real time based on the data from the monitoring system. Use reinforced concrete lining method for secondary lining. After the secondary lining is completed, carry out cyclic excavation.
[0034] Embodiment 2: In view of the possible soft rock deformation in the tunnel, the following measures are taken for the construction of soft rock formation crossing: A. Advance support: Because the surrounding rock is broken and cannot stabilize itself after excavation, in order to prevent the top surrounding rock from collapsing, advance anchor rods, advance small guide pipes, advance large pipe sheds and advance grouting are mainly used to provide advance support for the soft rock formation before excavation of the face.
[0035] B. Initial support: The initial support adopts a combined support structure of anchor, spraying and mesh. The construction is carried out in the order of initial spraying concrete, erecting steel frame and anchor rod, hanging mesh and then spraying concrete to the designed thickness. Double-layer steel frame support is used to strengthen the local large deformation section to control the deformation within the allowable range.
[0036] C. Secondary lining: The secondary lining construction of the soft rock deformation section should be followed up in a timely manner. It is not advisable to lag behind the heading face for too long. The reinforced concrete lining should be constructed in time to allow the lining to jointly bear the deformation pressure of the surrounding rock.
[0037] D. Deformation monitoring: During the safety monitoring during the construction period, the allowable deformation value of the surrounding rock can be estimated as the standard value of the surrounding rock stability state according to the surrounding rock type, cave excavation span and cave body burial depth. When the measured total deformation of the surrounding rock is close to the specified allowable value or the daily deformation exceeds 1 / 4~1 / 5 of the specified allowable value, the support parameters should be corrected immediately, secondary support should be carried out or new reinforcement measures should be taken. E. Hardening treatment of the bottom plate during construction: The bottom plate of the soft rock tunnel section is very easy to soften and deform after being soaked in water and mechanically rolled. After being disturbed, a large amount of mud is generated, which affects the tunnel construction and causes over-excavation of the bottom plate. In severe tunnel sections, the steel support 7 may be deformed and unstable. Therefore, the bottom plate of the extremely soft rock tunnel section is hardened, and a 20cm thick C20 concrete cushion is poured outside the secondary lining structure.
[0038] Embodiment three: The following measures are taken for the construction of the water-gushing mud tunnel section: A. Advance prediction: According to the geological advance prediction and the face revealed by the advance hole, the lithology of the formation, the degree of development of the rock structure surface, the integrity of the rock mass, whether there is seepage water, etc., the leakage volume and pressure are measured, and the water blocking and drainage measures are determined in time to prevent sudden water inrush; the following parts where water inrush may occur shall be monitored and predicted in a strengthened manner, so as to take targeted measures to prevent sudden water inrush as much as possible, ensure construction safety and minimize the losses caused by water inrush. The areas where sudden water inrush may occur are: the intersection of structural surfaces and layers such as faults and crack-dense zones through which the tunnel passes, near the lithological interface, muddy water in the wind drilling hole, lower ground temperature than the previous point, and mud-filled cracks near the face; during construction, combined with engineering geological and hydrogeological conditions, according to the current status of geological prediction research at home and abroad and successful experience, a comprehensive advance prediction method combining multiple prediction methods is proposed to be adopted during the construction process. The principle of "exploration before excavation" should be strictly implemented during the construction process to avoid the occurrence of geological disasters and ensure the safe construction of underground caverns.
[0039] B. Take comprehensive treatment measures such as "interception" (advance pre-grouting to block water) and "crossing" according to the groundwater conditions in each tunnel section.
[0040] C. Tunnel water inrush prevention and control is an important part of tunnel construction. As water inrush has a great impact on construction, it is treated comprehensively through a variety of measures with the help of advanced geological forecasts. Then, comprehensive measures such as advance grouting, timely concrete lining (excavation and lining) and radial consolidation grouting are adopted to intercept water inrush, which can ensure the normal construction and safety of the tunnel and reduce the impact on the surface water environment.
[0041] Embodiment 4: For shallow tunnels, tunnel sections with poor surrounding rock conditions and prominent surrounding rock stability issues, the following treatment measures are taken: A. Use "short steps", "partial excavation", "core soil" and other methods for construction, and follow the principles of "edge first, middle later, soft first, hard later", "short advance, strong support, fast closure", partial excavation and partial support.
[0042] B. Do a good job in advance support; due to the poor self-stabilization ability of the surrounding rock, in order to prevent the collapse of the top surrounding rock, before the excavation of the face, use advance anchors, advance grouting, φ42mm advance small pipes and ф108mm advance large pipe sheds to carry out advance surrounding rock support, improve the conditions for tunnel formation, the stability of the surrounding rock and the safety of excavation operations, and prevent landslides. If necessary, use construction methods such as "surface pre-consolidation grouting" to minimize the deformation, landslides, roof collapse and other engineering geological problems of the tunnel during construction, so that the construction of the project can proceed smoothly.
[0043] C. Tunnel excavation construction adheres to the principle of "mechanical excavation in stages and auxiliary weak blasting when necessary"; the ring excavation method of reserved core soil is adopted, and steel support 7 and anchor spraying support are followed up in time. The initial support adopts a combined support structure of anchor, spraying, steel mesh and steel arch frame. The construction is carried out closely following the excavation surface in the order of erecting steel frame → initial spraying of concrete → driving anchor rods → hanging mesh → re-spraying of concrete to the designed thickness.
[0044] D. Carry out initial support, carry out anchor spraying, mesh hanging and steel support 7 support according to surrounding rock conditions, adjust the spacing of steel support 7 in time, etc.; prevent the left and right arch feet of the same steel support 7 from being suspended in the air at the same time, and take measures to ensure the stability of the bottom of the steel support 7.
[0045] E. Strengthen advanced geological forecasts, use advanced geological drilling, geophysical exploration and other methods to explore the surrounding rock conditions ahead, and make timely adjustments to construction methods and support designs based on the surrounding rock conditions.
[0046] F. In order to prevent landslides and roof collapse after excavation of shallow buried tunnels, the "digging and lining at the same time" method is adopted for construction. Initial support is carried out immediately after excavation, and the distance between the lining working surface and the excavation face is controlled to be no more than 100m, so as to ensure the stability of the tunnel during the construction period and ensure construction safety.
[0047] Embodiment five: Tunnels are subject to construction risks such as large deformation of surrounding rock, water gushing, mud bursting, landslides, and roof collapse. Therefore, temporary safety monitoring during the construction period is a means to ensure the safe construction of the tunnel. The temporary safety monitoring items and contents during the construction period under the Maliao River mainly include: manual inspection, surrounding rock surface convergence monitoring, arch settlement monitoring, surface settlement monitoring, toxic and harmful gas monitoring, and seepage monitoring.
[0048] Manual inspection: Manual inspection during the construction period includes observation of the working face and the support effect of the support structure. The observation of the working face includes the name of the rock, the occurrence of the rock formation, the distribution, direction and occurrence of faults, bedding, joints and other structural surfaces. The observation of the support effect includes the initial support status and the observation of the support effect, such as the cracking location, width, length and depth of the shotcrete. Special forms are used to record the occurrence of the surrounding rock on site, draw a geological plain map, and finally make the tunnel axis and typical cross-sectional geological profile after tunnel excavation construction by collecting data.
[0049] According to the technical requirements for temporary safety monitoring during the construction period, manual inspections should be carried out at least once a day within 50m of the face during the construction period; once every three days if the range exceeds 50m; once a week after lining construction; in case of abnormal conditions such as cracks, falling blocks, water seepage, etc. in the cavern, the inspections should be increased to once a day.
[0050] Each manual inspection report shall be prepared in accordance with the specification requirements, and photos and sketches shall be attached when necessary. For problems found during manual inspections, minor problems shall be dealt with on the spot and detailed records shall be kept. For problems that may have serious consequences, all parties involved in the construction shall be organized to conduct on-site inspections and formulate treatment measures. In case of danger, emergency measures shall be taken in a timely manner.
[0051] Surrounding rock surface convergence monitoring: The purpose of carrying out surrounding rock surface convergence monitoring is to understand the surface deformation after tunnel excavation, so as to ensure the construction safety of personnel and machinery, and facilitate the subsequent selection of the appropriate time for secondary lining.
[0052] According to the technical requirements for temporary safety monitoring during the construction period, the spacing of V-class surrounding rock convergence sections in general tunnels is no more than 30m, and the spacing of fault and broken zone convergence sections is 5~10m. Convergence sections are arranged as much as possible in areas with poor geological conditions, large deformation, and impact on construction safety. Based on the above requirements, the contents of surrounding rock convergence monitoring are initially listed as follows. During actual construction, the convergence monitoring sections can be adjusted or increased according to the actual geological conditions on site and the instructions of the supervisor.
[0053] Measurement point burial and measurement line layout; the measurement point layout is determined according to the construction method, engineering geological conditions, tunnel burial depth and other conditions; when the upper and lower steps are used for excavation, two pairs of measurement points and two measurement lines are arranged. The specific layout positions are as follows: Figure 3 As shown, when burying the measuring point, first use a small impact drill to drill a hole at the location to be measured (the buried depth of the measuring pile is about 200mm, and the diameter of the hole is about 25mm), implant the steel bar and fix it with an anchor, weld a 50mm*50mm thin steel plate to the exposed end of the steel bar, paste a reflective sheet on the steel plate to cooperate with the total station for observation, and set a protective cover at the measuring point.
[0054] like Figure 3 As shown, during the monitoring process, a high-precision total station is used to collect data using an advanced non-contact distance measurement method; considering the special environment in the tunnel, the total station is usually positioned using the free station method. Before each measurement, the reference point group is measured first, and the total station coordinates are calculated by the free station method, and then the observation of this cycle is carried out; the distance of the transverse diameter is calculated based on the three-dimensional coordinate values obtained by the measurement, and the transverse length values obtained twice before and after are subtracted, which is the deformation of the transverse diameter this time; the current length value minus the initial length value is the accumulated transverse deformation; Surrounding rock surface convergence monitoring is one of the main measurement items. Under the premise of avoiding blasting operations to damage the measuring points, each measuring point is buried as close to the excavation face as possible, generally 0.5~2m, and the initial reading is obtained before the next blasting; the initial reading is read within 12h after excavation, no later than 24h, and the initial deformation value reading is completed before the next cycle of excavation; the convergence section is observed twice a day within seven days after excavation or support; once a day within fifteen days, when the face is more than twice the tunnel diameter away from the convergence section, it is observed every two days; after the deformation is stable, it is observed once a week until the observation is stopped after the surrounding rock lining; when excavation is carried out near the convergence section, it is observed once before and after blasting; when reinforcement is carried out near the convergence section or when the measured value is abnormal, the number of observations is increased.
[0055] Establish a management level standard for monitoring deformation, determine the stability and safety of the support structure through comparison and analysis of the monitoring results, and guide the construction. Management level I means the measured deformation value is less than one-third of the allowable deformation value, and the allowable deformation value is determined according to the surrounding rock type. Normal construction can be carried out at this management level. Management level II means one-third of the allowable deformation value ≤ the measured deformation value ≤ two-thirds of the allowable deformation value. This management level requires strengthened support before construction. Management level III means the measured deformation value is greater than two-thirds of the allowable deformation value. Special measures need to be taken at this management level. When the allowable relative displacement value around the tunnel exceeds the deformation level management standard, immediately activate the emergency plan to ensure the safety of personnel in the tunnel, and notify all parties involved in the construction to inspect the site and determine the treatment plan. Measures including but not limited to radial consolidation grouting, increasing cross braces, and increasing steel support density 7 are used for treatment. Experts are invited to make a determination when necessary.
[0056] Vault settlement monitoring; the absolute amount of subsidence of the inner wall of the tunnel vault is called the vault settlement value, and the vault settlement value per unit time is called the vault settlement velocity. Vault settlement measurement also belongs to displacement measurement. The geological conditions of the Kuncheng Tunnel are complex, the burial depth is shallow, and there are many adjacent tunnel sections underpassed. This measurement is more important than convergence measurement. Its measurement data is the most basic information to confirm the stability of the surrounding rock, judge the support effect, guide the construction process, prevent vault collapse, and ensure the quality and safety of construction. The vault settlement value is measured by high-precision levels and total stations. The stability of the surrounding rock is determined, the support effect is judged, the construction process is guided, and the vault collapse is prevented to ensure the quality and safety of construction.
[0057] The measuring point layout method is to be located at the center of the arch, often together with the surrounding convergence measurement points. When burying the measuring points, first use a small impact drill to drill holes at the measuring points (the buried depth of the measuring pile is about 200mm, and the diameter of the drill hole is about 25mm), implant steel bars and fix them with anchors, weld 50mm*50mm thin steel plates on the exposed ends of the steel bars, stick reflective sheets on the steel plates for observation in conjunction with the total station, and set protective covers at the measuring points.
[0058] A high-precision total station is used to measure the sinking of the arch. A reflective film is attached to the measuring point of the arch during measurement. The elevation of the reflector is measured through the rear sight point. The calculation method is to find the change value of the measuring point through the height difference between the two measuring points. The elevation of the reflector for the first time is A1, and the elevation of the reflector for the second time is A2.
[0059] Measuring point sinking value: Δh=A1-A2 Calculation results: If Δh>0, the arch will sink; if Δh<0, the arch will move up; when the arch sinking rate is less than 0.07~0.15mm / d, it is considered that the surrounding rock displacement has reached basic stability; when the arch sinking rate is greater than 1.0mm / d, it indicates that the displacement is unstable and observation should be strengthened; when the arch sinking rate is greater than 5.0mm / d, an alarm should be issued and reinforcement should be carried out.
[0060] During measurement, the observation reference point is set at a stable point three times the tunnel diameter away from the observation point; the spacing of the arch subsidence measurement sections, the measurement frequency, and the measurement of the initial readings are equivalent to convergence measurement; the measurement time should be continued until the arch subsidence is stable. Generally speaking, the temporal change of the arch subsidence increases roughly linearly after excavation, until about 1 to 3 times the tunnel diameter away from the excavation surface, the subsidence development slows down, the slope becomes gentler, and it is asymptotically stable; if there is a bottom drum, it can be measured according to the arch subsidence method.
[0061] When the tunnel settlement value exceeds the deformation management standard, the emergency plan will be immediately activated to ensure the safety of personnel in the tunnel, and all parties involved in the construction will be notified to conduct on-site inspections and determine the treatment plan. Measures including but not limited to radial consolidation grouting, increasing cross braces, and increasing the density of steel supports 7 will be adopted for treatment. Experts will be invited to make a determination when necessary.
[0062] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Any simple modification or equivalent change made to the above embodiment based on the technical essence of the present invention shall fall within the protection scope of the present invention.
Claims
1. A construction measure and method for excavating and supporting a tunnel under a river. It is characterized in that The following steps are involved: Step 1: Advanced geological prediction, through geological methods, geophysical methods, and advanced geological drilling methods, complete the exploration of various lithologies of the tunnel section, and design and change the construction plan according to the exploration results; Step 2: measuring and laying out; according to the on-site conditions, setting the vault settlement monitoring point (1), the first perimeter convergence monitoring line (2), the first perimeter convergence monitoring point reflector (3), the second perimeter convergence monitoring line (4), and the second perimeter convergence detection point reflector (5); Step 3: Advanced support, using advanced anchor rods, advanced small pipes, advanced large pipe sheds and advanced grouting to provide advanced protection for the soft rock bottom layer; Step 4: Go up the steps (9) to excavate and remove the slag. Use a wall drilling machine to perform drilling and blasting operations, and use an excavator and a loader to remove the slag from the hole excavated by the wall drilling machine. Step 5: Initial support and surrounding rock monitoring and measurement for the upper step (9), using a combined support structure of an initial shotcrete layer (6), steel support (7), and anchor rack (8), and following the excavation surface, construction is carried out in the order of initial shotcrete, erecting a steel rack, anchor construction, hanging a mesh, and re-shotcrete to the designed thickness, and using a monitoring system to monitor and record data such as surrounding rock deformation, vault settlement, and surface settlement in real time; Step 6: excavate and remove slag from the lower step (10); after the upper step (9) is supported, a wall drilling machine is used to perform drilling and blasting operations, and an excavator and a loader are used to remove slag from the hole excavated by the wall drilling machine; Step 7: Initial support and surrounding rock monitoring and measurement of the lower step (10), using a combined support structure of an initial shotcrete layer (6), steel support (7), and anchor rack (8), and following the excavation surface, construction is carried out in the order of shotcrete, anchoring, mesh hanging, and re-shotcrete to the designed thickness, and a monitoring system is used to monitor and record data such as the surface convergence of the surrounding rock, the settlement of the vault, and the settlement of the ground in real time; Step 8: pouring concrete on the bottom plate. Use a wet spraying manipulator to spray concrete, seal with quick-setting mortar, and pour concrete on the bottom plate of the hole at the same time; Step 9: Concrete lining of the side and top arches: use a wet spraying robot to spray, seal with quick-setting mortar, and concrete lining the sides and arch tops; Step 10: Secondary lining: Design the secondary lining method in real time based on the data from the monitoring system. Use reinforced concrete lining method for secondary lining. After the secondary lining is completed, carry out cyclic excavation.
2. A tunnel excavation support construction measure and method for underpass river according to claim 1, Features: The advanced support adopts the surface pre-consolidation grouting method to avoid deformation, landslides, roof collapse and other problems in the tunnel during construction.
3. A tunnel excavation support construction measure and method for underpass river according to claim 1, Features: The initial support anchor rods of the upper step (9) and the lower step (10) are hollow anchor rods, and the spacing of the steel supports (7) is 70 cm. The spacing of the steel supports (7) can be adjusted to 50 cm according to the quality of the surrounding rock. Steel supports (7) are added one by one in the bottom plate as lateral supports.
4. The tunnel excavation support construction measure and method for underpass river according to claim 1, Features: According to the surrounding rock type, cave excavation span and cavern burial depth, the allowable deformation value of the surrounding rock is estimated as the standard value of the surrounding rock stability state. When the measured total deformation of the surrounding rock is close to the specified allowable value or the daily deformation exceeds 1 / 4~1 / 5 of the specified allowable value, the support parameters are immediately corrected and secondary support is carried out.
5. The tunnel excavation support construction measure and method for underpass river channel according to claim 1, Features: The bottom slab concrete pouring is performed by pouring a 20 cm thick C20 concrete cushion layer outside the secondary lining structure to prevent the steel support (7) from deforming and becoming unstable.
6. The tunnel excavation support construction measure and method for underpass river channel according to claim 1, Features: The monitoring of the surrounding rock surface convergence amount is used to determine the surface deformation after tunnel excavation and select the appropriate time for secondary lining according to the real-time situation.
7. The tunnel excavation support construction measure and method for underpass river according to claim 1, Features: The monitoring of the vault settlement is used to determine the stability of the surrounding rock, judge the support effect and avoid the collapse of the vault.
8. The tunnel excavation support construction measure and method for underpass river channel according to claim 1, Features: Monitoring of surface subsidence is used to avoid landslides in surface buildings.