Tunnel deformation and fault prevention and control isolation structure and construction method

By arranging parallel isolation tunnels around the tunnel to cut off the stress chain, the deformation problem of the tunnel in high stress and fracture zone areas was solved, reducing the support and repair costs of the tunnel.

CN118997781AActive Publication Date: 2024-11-22INST OF ROCK & SOIL MECHANICS CHINESE ACAD OF SCI +2
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411158998.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-22
Publication Date
2024-11-22
Estimated Expiration
2044-08-22

AI Technical Summary

Technical Problem

In tunnel structures located in high-stress and fracture zone areas, traditional prevention methods have failed to effectively cut off stress chain transmission, leading to large deformations and high repair costs in tunnel structures.

Method used

Isolation tunnels parallel to the tunnel are laid out above, below, to the left and right of the tunnel, including the top isolation tunnel, the bottom isolation tunnel, the left isolation tunnel and the right isolation tunnel, and the stress chain transmission path is cut off by excavating the bare tunnel structure.

Benefits of technology

It effectively reduces tunnel deformation and support costs, lowers long-term repair costs, adapts to stress and fault displacement in different directions, and provides significant prevention and control effects.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118997781A_ABST
    Figure CN118997781A_ABST
Patent Text Reader

Abstract

The invention discloses a tunnel deformation and fault prevention and control isolation structure. The tunnel deformation and fault prevention and control isolation structure comprises a tunnel, a top isolation hole, a bottom isolation hole, a left isolation hole and a right isolation hole, wherein the top isolation hole, the bottom isolation hole, the left isolation hole and the right isolation hole are sequentially formed in the upper side, the lower side, the left side and the right side of the tunnel. Compared with the prior art, the tunnel deformation and fault prevention and control isolation structure has the advantages of being simple in structure, easy to construct, obvious in effect, high in adaptability and the like.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of large deformation prevention and control of tunnels, and in particular to a tunnel deformation and fault prevention and control isolation structure and a construction method. Background Art

[0002] With the development of national engineering construction, tunnels (holes) will inevitably pass through high stress areas of fault structures and fault zone dislocation areas. Both high stress areas and fault zone dislocation areas can cause serious damage to the tunnel (hole) structure and even cause complete destruction of the project.

[0003] At present, the traditional prevention and control method for large deformation of high-stress soft rock tunnels (tunnels) is mostly to strengthen the strength of the primary support, but the hidden danger it brings is the repeated repair of the tunnel (tunnel), resulting in a large waste of costs; similarly, for tunnels (tunnels) passing through active fault zones, their traditional anti-misalignment measures such as articulation, expansion, lining thickening and primary support reinforcement are all shallow field structure and surrounding rock modifications. Since they fail to eliminate stress chain transmission, the risk of damage to the tunnel and lining is still very high, and they still face increased repair costs.

[0004] Therefore, how to provide a tunnel deformation and fault prevention and control isolation structure so that it can achieve the technical effect of cutting off the stress chain transmission path of high stress extrusion tunnels and active fault zone tunnels is a technical problem that technical personnel in this field urgently need to solve. Summary of the invention

[0005] In view of the problems existing in the prior art, the technical problem to be solved by the present invention is to provide a tunnel deformation and fault prevention and control isolation structure, which is used for the deformation prevention and control of high stress extrusion tunnels and the fault prevention and control of tunnels passing through active fault zones, cutting off the stress chain transmission path of high stress extrusion tunnels and active fault zone tunnels from the source, and fundamentally solving the large deformation problem of high stress tunnels and the fault problem of active fault zone tunnels.

[0006] To achieve the above-mentioned purpose, the present invention provides a tunnel deformation and fault prevention and control isolation structure, the tunnel deformation and fault prevention and control isolation structure comprising: a tunnel; a plurality of top isolation holes, a plurality of the top isolation holes are arranged just above the periphery of the tunnel; a plurality of bottom isolation holes, a plurality of the bottom isolation holes are arranged just below the periphery of the tunnel, a plurality of the bottom isolation holes and a plurality of the top isolation holes are symmetrically distributed; a plurality of left isolation holes, a plurality of the left isolation holes are arranged on the left side of the periphery of the tunnel; a plurality of right isolation holes, a plurality of the right isolation holes are arranged On the right side of the outer periphery of the tunnel, several right isolation tunnels and several left isolation tunnels are symmetrically distributed; wherein, each of the top isolation tunnels, each of the bottom isolation tunnels, each of the left isolation tunnels and each of the right isolation tunnels are parallel to the tunnel; the line connecting several of the top isolation tunnels, the tunnel and several of the bottom isolation tunnels in the same plane is a vertical straight line, and the line connecting several of the left isolation tunnels, the tunnel and several of the right isolation tunnels in the same plane is a horizontal straight line, and the vertical straight line and the horizontal straight line are perpendicular to each other.

[0007] In the first aspect, the number of the top isolation holes is greater than or equal to 0; the number of the left isolation holes is greater than or equal to 0, and the number of the top isolation holes and the number of the left isolation holes are not 0 at the same time; when the number of the top isolation holes and the number of the left isolation holes are both not 0, the number of the top isolation holes is the same as the number of the left isolation holes.

[0008] In the first aspect, the diameter of each of the top isolation holes, the diameter of each of the bottom isolation holes, the diameter of each of the left isolation holes, and the diameter of each of the right isolation holes are the same as the diameter of the tunnel.

[0009] In the first aspect, the distances between the tunnel and an adjacent top isolation hole, an adjacent bottom isolation hole, an adjacent left isolation hole and an adjacent right isolation hole are all the same and greater than 3 times the diameter of the tunnel.

[0010] In the first aspect, the distance between any two adjacent top isolation holes, the distance between any two adjacent bottom isolation holes, the distance between any two adjacent left isolation holes, and the distance between any two adjacent right isolation holes are all the same and greater than 3 times the diameter of the tunnel.

[0011] In the first aspect, each of the top isolation holes, each of the bottom isolation holes, each of the left isolation holes, and each of the right isolation holes are in a bare hole state.

[0012] The present invention also provides a deformation prevention and control isolation construction method applicable to a high stress extrusion tunnel, which is used for the construction of the above-mentioned deformation and dislocation prevention and control isolation structure in a high stress area. The deformation prevention and control isolation construction method applicable to a high stress extrusion tunnel includes:

[0013] A tunnel is excavated in the rock mass in the high stress area to obtain a tunnel; an isolation hole is excavated just above the periphery of the tunnel to obtain a top isolation hole; an isolation hole is excavated just below the periphery of the tunnel to obtain a bottom isolation hole; an isolation hole is excavated on the left side of the periphery of the tunnel to obtain a left isolation hole; an isolation hole is excavated on the right side of the periphery of the tunnel to obtain a right isolation hole.

[0014] In the second aspect, when the stress in the high stress area is high stress in one direction, only the isolation hole in the high stress direction is excavated.

[0015] The present invention also provides a method for construction of fault and dislocation prevention and control isolation for active fault zone tunnels, which is used for the construction of the above-mentioned deformation and fault and dislocation prevention and control isolation structure in the dislocation area of ​​the active fault zone. The method for construction of deformation and dislocation prevention and control isolation for active fault zone tunnels includes: excavating the rock mass in the dislocation area of ​​the active fault zone to obtain a tunnel; excavating an isolation tunnel just above the periphery of the tunnel to obtain a top isolation tunnel; excavating an isolation tunnel just below the periphery of the tunnel to obtain a bottom isolation tunnel; excavating an isolation tunnel on the left side of the periphery of the tunnel to obtain a left isolation tunnel; excavating an isolation tunnel on the right side of the periphery of the tunnel to obtain a right isolation tunnel.

[0016] In the third aspect, when the fault zone displacement in the active fault zone displacement area is in one direction, only the isolation hole in the one direction of the fault zone displacement is excavated.

[0017] Beneficial effects:

[0018] The present invention arranges isolation holes parallel to the tunnel at the top, bottom, left and right sides of the tunnel, which has a simple structure and is easy to construct; in high stress areas, the isolation holes set can fundamentally cut off the transmission of stress chains, reduce the stress of the tunnel surrounding rock and reduce the deformation of the tunnel, reduce the support and prevention and control costs of the tunnel, and reduce the long-term repair cost of the tunnel; in the dislocation area of ​​the active fault zone, the isolation holes set can fundamentally cut off the transmission of stress chains, buffer faults, reduce the influence of fault dislocation on the large deformation of the tunnel, reduce the support and prevention and control costs of the tunnel, and reduce the long-term repair cost of the tunnel; in summary, the prevention and control isolation structure of the present invention is simple, easy to construct, and has obvious effects, can fundamentally cut off the transmission of stress chains, reduce the large deformation of the tunnel caused by high stress and fault dislocation, reduce the support and prevention and control costs of the tunnel, and reduce the long-term repair cost of the tunnel. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] In order to more clearly illustrate the embodiments of this specification or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0020] Figure 1 It is a schematic diagram of the overall structure of the tunnel deformation and fault prevention and control isolation structure when the number of top isolation holes and the number of left isolation holes in the high stress area are both 1;

[0021] Figure 2 It is the front cross-sectional view of the tunnel deformation and fault prevention and control isolation structure when the number of top isolation holes and the number of left isolation holes in the high stress area are both 1;

[0022] Figure 3 It is the transverse cross-section diagram of the tunnel deformation and fault prevention and control isolation structure when the number of top isolation holes and the number of left isolation holes in the high stress area are both 1;

[0023] Figure 4 It is a side profile of the tunnel deformation and fault prevention and control isolation structure when the number of top isolation holes and the number of left isolation holes in the high stress area are both 1;

[0024] Figure 5 It is a schematic diagram of the overall structure of the tunnel deformation and fault dislocation prevention and control isolation structure when the number of top isolation tunnels and the number of left isolation tunnels in the dislocation area of ​​the active fault zone are both 1;

[0025] Figure 6 It is the front cross-sectional view of the tunnel deformation and fault dislocation prevention and control isolation structure when the number of top isolation tunnels and the number of left isolation tunnels in the dislocation area of ​​the active fault zone are both 1;

[0026] Figure 7 It is a transverse cross-sectional diagram of tunnel deformation and fault dislocation prevention and control isolation structure when the number of top isolation tunnels and the number of left isolation tunnels in the dislocation area of ​​the active fault zone are both 1;

[0027] Figure 8 It is a side profile of the tunnel deformation and fault dislocation prevention and control isolation structure when the number of top isolation tunnels and the number of left isolation tunnels in the dislocation area of ​​the active fault zone are both 1;

[0028] Reference numerals:

[0029] 1. Tunnel; 2. Top isolation tunnel; 3. Bottom isolation tunnel; 4. Left isolation tunnel; 5. Right isolation tunnel; 6. Vertical stress; 7. Horizontal stress; 8. Vertical dislocation force; 9. Horizontal dislocation force; 10. Dislocation surface. DETAILED DESCRIPTION

[0030] The following will be combined with the drawings in the embodiments of this specification to clearly and completely describe the technical solutions in the embodiments of this specification. Obviously, the described embodiments are only part of the embodiments of this specification, not all of the embodiments. Based on the embodiments in this specification, all other embodiments obtained by ordinary technicians in this field belong to the scope of protection of the present invention.

[0031] Embodiment 1

[0032] like Figures 1 to 8 As shown, the present embodiment 1 provides a tunnel deformation and fault prevention isolation structure, and the tunnel deformation and fault prevention isolation structure includes: a tunnel 1; a plurality of top isolation holes 2, and a plurality of the top isolation holes 2 are arranged just above the periphery of the tunnel 1; a plurality of bottom isolation holes 3, and a plurality of the bottom isolation holes 3 are arranged just below the periphery of the tunnel 1, and a plurality of the bottom isolation holes 3 and a plurality of the top isolation holes 2 are symmetrically distributed; a plurality of left isolation holes 4, and a plurality of the left isolation holes 4 are arranged on the left side of the periphery of the tunnel 1; a plurality of right isolation holes 5, and a plurality of the right isolation holes 5 are arranged on the left side of the periphery of the tunnel 1; On the right side of the outer periphery of the tunnel 1, several right isolation tunnels 5 and several left isolation tunnels 4 are symmetrically distributed; wherein, each of the top isolation tunnels 2, each of the bottom isolation tunnels 3, each of the left isolation tunnels 4 and each of the right isolation tunnels 5 are parallel to the tunnel 1; the line connecting several of the top isolation tunnels 2, the tunnel 1 and several of the bottom isolation tunnels 3 in the same plane is a vertical straight line, and the line connecting several of the left isolation tunnels 4, the tunnel 1 and several of the right isolation tunnels 5 in the same plane is a horizontal straight line, and the vertical straight line and the horizontal straight line are perpendicular to each other.

[0033] The present invention arranges isolation holes parallel to the tunnel at the top, bottom, left and right sides of the tunnel, which has a simple structure and is easy to construct; in high stress areas, the isolation holes set can fundamentally cut off the transmission of stress chains, reduce the stress of the tunnel surrounding rock and reduce the deformation of the tunnel, reduce the support and prevention and control costs of the tunnel, and reduce the long-term repair costs of the tunnel; in the dislocation area of ​​the active fault zone, the isolation holes set can fundamentally cut off the transmission of stress chains, buffer faults and dislocations, reduce the influence of fault dislocations on the large deformation of the tunnel, reduce the support and prevention and control costs of the tunnel, and reduce the long-term repair costs of the tunnel; in summary, the prevention and control isolation structure of the present invention is simple, easy to construct, and has obvious effects. It can fundamentally cut off the transmission of stress chains, reduce the large deformation of the tunnel caused by high stress and fault dislocation, reduce the support and prevention and control costs of the tunnel, and reduce the long-term repair costs of the tunnel; in addition, a tunnel deformation and fault dislocation prevention and control isolation structure of the present invention is also suitable for deformation and dislocation prevention and control isolation of high stress extrusion tunnels and active fault zone tunnels.

[0034] In some possible implementations, the number of the top isolation holes 2 is greater than or equal to 0; the number of the left isolation holes 3 is greater than or equal to 0, and the number of the top isolation holes 2 and the number of the left isolation holes 4 are not 0 at the same time; when the number of the top isolation holes 2 and the number of the left isolation holes 4 are both not 0, the number of the top isolation holes 2 and the number of the left isolation holes 4 are the same.

[0035] Specifically, the control isolation structure of the present invention can adjust the position of the isolation hole for unidirectional and multi-directional high stress, and unidirectional and multi-directional fault displacement. When the tunnel is subjected to unidirectional high stress or fault displacement, the isolation hole is arranged only in the unidirectional direction. For example, when the tunnel is only subjected to vertical stress or vertical displacement, the top isolation hole and the bottom isolation hole are arranged only in the vertical stress direction, and the number of the left isolation hole and the right isolation hole is 0. When the isolation effect of the arranged top isolation hole and the bottom isolation hole on the force is poor, the number of the top isolation hole and the bottom isolation hole can be increased accordingly to achieve the technical effect of cutting off the stress chain. If the tunnel is only subjected to horizontal stress or horizontal displacement, then If only the left isolation tunnel and the right isolation tunnel are arranged in the horizontal stress direction, the number of the top isolation tunnel and the bottom isolation tunnel is 0. When the force isolation effect of the arranged left isolation tunnel and the right isolation tunnel is poor, the number of the left isolation tunnel and the right isolation tunnel can be increased accordingly to achieve the technical effect of cutting off the stress chain; when the tunnel is subjected to multi-directional high stress or fault dislocation, isolation tunnels are arranged in the upper, lower, left and right directions of the tunnel. The number of the top isolation tunnel and the left isolation tunnel arranged initially is 1. When the isolation effect of the arranged four isolation tunnels on high stress or fault dislocation is poor, the number of isolation tunnels on the upper, lower, left and right sides can be increased accordingly to achieve the technical effect of cutting off the stress chain.

[0036] In some possible implementations, the diameter of each of the top isolation holes 2 , the diameter of each of the bottom isolation holes 3 , the diameter of each of the left isolation holes 4 , and the diameter of each of the right isolation holes 5 are the same as the diameter of the tunnel 1 .

[0037] Specifically, the diameter of the isolation tunnel arranged around the tunnel is the same as the diameter of the tunnel, which can better buffer the stress received by the tunnel surrounding rock and reduce the deformation of the tunnel.

[0038] In some possible implementations, the distances between the tunnel 1 and an adjacent top isolation tunnel 2, an adjacent bottom isolation tunnel 3, an adjacent left isolation tunnel 4 and an adjacent right isolation tunnel 5 are all the same and greater than three times the diameter of the tunnel 1; the distance between any two adjacent top isolation tunnels 2, the distance between any two adjacent bottom isolation tunnels 3, the distance between any two adjacent left isolation tunnels 4 and the distance between any two adjacent right isolation tunnels 5 are all the same and greater than three times the diameter of the tunnel 1.

[0039] Specifically, when the isolation effect of the arranged isolation tunnels on high stress or fault movement is poor, the number of isolation tunnels is increased accordingly, and the distance between the set tunnel and the adjacent isolation tunnel is greater than 3 times the tunnel diameter, and the distance between two adjacent isolation tunnels is greater than 3 times the tunnel diameter, which can effectively prevent the influence of high stress or fault movement on the tunnel.

[0040] In some possible implementations, each of the top isolation holes 2 , each of the bottom isolation holes 3 , each of the left isolation holes 4 , and each of the right isolation holes 5 are in a bare hole state.

[0041] Specifically, the top isolation tunnel, bottom isolation tunnel, left isolation tunnel and right isolation tunnel are not supported and remain in a bare tunnel state, which can improve the isolation tunnel's own buffering against high stress and fault movement, and avoid deformation of the tunnel due to the force transmitted to the surrounding rock through the supporting materials and then to the tunnel after the isolation tunnel is supported. In addition, the excavated isolation tunnels are not supported, which makes construction simpler and saves excavation costs.

[0042] Embodiment 2

[0043] like Figures 1 to 4 As shown, embodiment 2 of the present invention provides a deformation prevention and control isolation construction method suitable for high stress extrusion tunnels. In the high stress area, a tunnel deformation and fault prevention and control isolation structure described in embodiment 1 is used for the construction. The deformation prevention and control isolation construction method suitable for high stress extrusion tunnels includes: tunnel excavation of rock mass in the high stress area to obtain a tunnel; excavation of an isolation hole just above the periphery of the tunnel to obtain a top isolation hole; excavation of an isolation hole just below the periphery of the tunnel to obtain a bottom isolation hole; excavation of an isolation hole on the left side of the periphery of the tunnel to obtain a left isolation hole; excavation of an isolation hole on the right side of the periphery of the tunnel to obtain a right isolation hole; when the stress in the high stress area is unidirectional high stress, only high stress unidirectional isolation holes are excavated.

[0044] Specifically, in high stress areas, high stress will cause the tunnel to deform, increasing the cost of tunnel repair. The present invention excavates isolation tunnels on the upper, lower, left and right sides of the tunnel, and uses the isolation tunnels to buffer the high stress on the tunnel, cut off the stress chain, reduce the stress of the tunnel surrounding rock, avoid tunnel deformation, and reduce the cost of tunnel repair. When the high stress on the tunnel is in a single direction, the isolation tunnel is only excavated in the high stress direction, which saves the cost of excavating isolation tunnels in multiple directions while cutting off the stress chain. At the same time, the excavation position of the isolation tunnel is adjusted for high stress in one direction and in multiple directions, and the adaptability is strong. It should be noted that the deformation prevention and control isolation construction method suitable for high stress extrusion tunnels in the second embodiment is used for the construction of the deformation and fault prevention and control isolation structure of the tunnel in the first embodiment. Therefore, the performance principle of the deformation and fault prevention and control isolation structure of the tunnel is not repeated here. For the undetailed part, please refer to the first embodiment. At the same time, the deformation prevention and control isolation construction method suitable for high stress extrusion tunnels in the second embodiment is also applicable to the construction of deformation prevention and control isolation of high stress extrusion tunnels in high ground stress areas.

[0045] Embodiment 3

[0046] like Figures 5 to 8 As shown, embodiment three of the present invention provides a fault dislocation prevention and control isolation construction method applicable to active fault zone tunnels, in the active fault zone dislocation area, for the construction of a tunnel deformation and fault dislocation prevention and control isolation structure described in embodiment one, the deformation prevention and control isolation construction method applicable to active fault zone tunnels includes: tunnel excavation of rock mass in the active fault zone dislocation area to obtain a tunnel; excavation of an isolation tunnel just above the periphery of the tunnel to obtain a top isolation tunnel; excavation of an isolation tunnel just below the periphery of the tunnel to obtain a bottom isolation tunnel; excavation of an isolation tunnel on the left side of the periphery of the tunnel to obtain a left isolation tunnel; excavation of an isolation tunnel on the right side of the periphery of the tunnel to obtain a right isolation tunnel; when the fault zone dislocation in the active fault zone dislocation area is in a single direction, only excavation of the isolation tunnel in the single direction of the fault zone dislocation.

[0047] Specifically, in the dislocation area of ​​the active fault zone, a dislocation surface 10 will be formed due to the fault dislocation. The movement of the dislocation surface 10 will cause the tunnel to deform, increasing the cost of tunnel repair. The present invention excavates isolation tunnels on the upper, lower, left and right sides of the tunnel, and uses the isolation tunnels to buffer the fault dislocation of the active fault zone on the tunnel, cut off the stress chain, avoid the movement of the dislocation surface 10, reduce the stress of the tunnel surrounding rock, avoid tunnel deformation, and reduce the cost of tunnel repair. When the fault dislocation suffered by the tunnel is unidirectional, only the isolation tunnel is excavated in the direction of the fault dislocation, which cuts off the stress chain and saves the cost of excavating isolation tunnels in multiple directions. At the same time, the excavation position of the isolation tunnel is adjusted according to the unidirectional and multi-directional fault dislocations, and the adaptability is strong. It should be noted that the fault prevention and control isolation construction method applicable to active fault zone tunnels in the third embodiment is used for the construction of the tunnel deformation and fault prevention and control isolation structure in the first embodiment. Therefore, the performance principle of the tunnel deformation and fault prevention and control isolation structure will not be repeated here. For the undescribed part, please refer to the first embodiment. At the same time, the control and isolation construction method applicable to active fault zone tunnels in the third embodiment is also applicable to the construction of fault prevention and control isolation of active fault zone tunnels in the dislocation area of ​​the active fault zone.

[0048] The preferred specific embodiments of the present invention are described in detail above. It should be understood that a person skilled in the art can make many modifications and changes based on the concept of the present invention without creative work. Therefore, any technical solution that can be obtained by a person skilled in the art through logical analysis, reasoning or limited experiments based on the concept of the present invention on the basis of the prior art should be within the scope of protection determined by the claims.

Claims

1. A tunnel deformation and fault prevention isolation structure, It is characterized in that The tunnel deformation and fault prevention and control isolation structure includes: Tunnel (1); A plurality of top isolation holes (2), wherein the plurality of top isolation holes (2) are arranged directly above the periphery of the tunnel (1); A plurality of bottom isolation holes (3), wherein the plurality of bottom isolation holes (3) are arranged directly below the periphery of the tunnel (1), and the plurality of bottom isolation holes (3) and the plurality of top isolation holes (2) are symmetrically distributed; A plurality of left isolation tunnels (4), wherein the plurality of left isolation tunnels (4) are arranged on the left side of the periphery of the tunnel (1); A plurality of right isolation holes (5), wherein the plurality of right isolation holes (5) are arranged on the right side of the outer periphery of the tunnel (1), and the plurality of right isolation holes (5) and the plurality of left isolation holes (4) are symmetrically distributed; Each of the top isolation holes (2), each of the bottom isolation holes (3), each of the left isolation holes (4) and each of the right isolation holes (5) are parallel to the tunnel (1); a line connecting a plurality of the top isolation holes (2), the tunnel (1) and a plurality of the bottom isolation holes (3) in the same plane is a vertical straight line, a line connecting a plurality of the left isolation holes (4), the tunnel (1) and a plurality of the right isolation holes (5) in the same plane is a horizontal straight line, and the vertical straight line and the horizontal straight line are perpendicular to each other.

2. A tunnel deformation and fault prevention isolation structure as claimed in claim 1, Features: The number of the top isolation holes (2) is greater than or equal to 0; the number of the left isolation holes (3) is greater than or equal to 0, and the number of the top isolation holes (2) and the number of the left isolation holes (4) are not both 0; when the number of the top isolation holes (2) and the number of the left isolation holes (4) are both not 0, the number of the top isolation holes (2) and the number of the left isolation holes (4) are the same.

3. A tunnel deformation and fault prevention isolation structure as claimed in claim 1, Features: The diameter of each top isolation hole (2), the diameter of each bottom isolation hole (3), the diameter of each left isolation hole (4) and the diameter of each right isolation hole (5) are all the same as the diameter of the tunnel (1).

4. A tunnel deformation and fault prevention isolation structure as claimed in claim 1, Features: The distances between the tunnel (1) and an adjacent top isolation tunnel (2), an adjacent bottom isolation tunnel (3), an adjacent left isolation tunnel (4) and an adjacent right isolation tunnel (5) are all the same and greater than three times the diameter of the tunnel (1).

5. A tunnel deformation and fault prevention isolation structure as claimed in claim 1, Features: The distance between any two adjacent top isolation holes (2), the distance between any two adjacent bottom isolation holes (3), the distance between any two adjacent left isolation holes (4) and the distance between any two adjacent right isolation holes (5) are all the same and greater than three times the diameter of the tunnel (1).

6. A tunnel deformation and fault prevention isolation structure as claimed in claim 1, Features: Each of the top isolation holes (2), each of the bottom isolation holes (3), each of the left isolation holes (4) and each of the right isolation holes (5) are in a bare hole state.

7. A deformation prevention and control isolation construction method suitable for high stress extrusion tunnels, It is characterized in that In a high stress area, for the construction of a tunnel deformation and fault prevention and control isolation structure according to any one of claims 1 to 6, the deformation prevention and control isolation construction method applicable to a high stress extrusion tunnel comprises: Tunneling is performed on the rock mass in the high stress area to obtain a tunnel; Excavating an isolation hole just above the periphery of the tunnel to obtain a top isolation hole; excavating an isolation hole just below the periphery of the tunnel to obtain a bottom isolation hole; An isolation tunnel is excavated on the left side of the periphery of the tunnel to obtain a left isolation tunnel; and an isolation tunnel is excavated on the right side of the periphery of the tunnel to obtain a right isolation tunnel.

8. A deformation prevention and control isolation construction method suitable for high stress extrusion tunnels as claimed in claim 7, Features: When the stress in the high stress area is high stress in one direction, only the isolation hole in the one direction of high stress is excavated.

9. A fault fault prevention and control isolation construction method suitable for active fault zone tunnels. It is characterized in that In the dislocation area of ​​the active fault zone, the method for constructing a tunnel deformation and dislocation prevention and control isolation structure according to any one of claims 1 to 6, wherein the deformation prevention and control isolation construction method applicable to the active fault zone tunnel comprises: The tunnel is obtained by excavating the rock mass in the dislocation area of ​​the active fault zone; Excavating an isolation hole just above the periphery of the tunnel to obtain a top isolation hole; excavating an isolation hole just below the periphery of the tunnel to obtain a bottom isolation hole; An isolation tunnel is excavated on the left side of the periphery of the tunnel to obtain a left isolation tunnel; and an isolation tunnel is excavated on the right side of the periphery of the tunnel to obtain a right isolation tunnel.

10. A fault fault prevention and control isolation construction method applicable to active fault zone tunnels as claimed in claim 9, Features: When the fault zone in the active fault zone dislocation area moves in one direction, only the isolation hole in the one direction of the fault zone dislocation is excavated.

Citation Information

Patent Citations

  • Multistage cut-off method for underpass high-speed rail bridge opening deformation

    CN103114611A

  • Novel tunnel anti-seismic and anti-error structure penetrating through movable fault zone

    CN117231232A

  • Tunnel structure following up fault slip

    JP1992327693A

  • Underground cavity construction method and underground cavity construction thereby

    JP1999193689A

  • Fault-passing tunnel structure

    JP2000204891A