By designing a detachable launch tube and steel ball impact sleeve and an air-load crushed impact test device with an accurate alignment system, the problem of low equipment dispersion and control accuracy in the prior art is solved, and efficient impact of wooden blocks and steel balls is achieved 测试,提高了测试流程的便捷性和精度。
Patent Information
- Application Number
- CN202411369264.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-27
- Publication Date
- 2024-11-22
AI Technical Summary
The existing air-loaded crushed impact test device is difficult to accurately control the relationship between the pressure in the gas tank and the emission speed of the impact test object. Different equipment needs to be replaced when conducting impact tests of wooden blocks and steel balls, resulting in dispersion of the equipment system. The preparation procedures are complicated and the lack of accurate alignment system makes it difficult to meet the requirements of precise control.
A wind-load crushed impact test device is designed, including a power device, a speed measurement device, a launch device and a central control system. The launch device adopts a detachable launch tube and a steel ball impact sleeve, and the central control system, a power device and a speed measurement device are electrically installed. Connected, equipped with a distance sensor, inclination sensor and laser sight, to achieve accurate control of test distance, angle and position, suitable for impact testing of wooden blocks and steel balls.
Through an integrated launch device and precise alignment system, the problem of equipment replacement and control accuracy is solved, the efficiency and operational convenience of the test process are improved, manpower and material consumption is reduced, and the stability and accuracy of the test are enhanced. It is suitable for Large-scale promotion and use.
Smart Images

Figure CN119000371A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of impact testing, in particular to a wind-borne debris impact testing device. Background Art
[0002] In coastal and inland storm areas, building curtain walls, doors and windows are frequently damaged by the impact of wind-borne debris during storms. Therefore, in order to ensure that building curtain walls, doors and windows can effectively resist the impact of wind-borne debris, scientific evaluation standards and testing methods are particularly critical. To this end, my country has incorporated wind-borne debris impact testing into the safety performance evaluation system for building curtain walls, doors and windows, and has issued relevant standards and specifications, clarifying the corresponding testing methods and testing equipment.
[0003] The existing wind-borne debris impact test device usually uses a gas tank as the impact power source in structure, and controls the gas distribution through external pipes and simple operating switches. However, this structure makes it difficult to accurately control the relationship between the pressure in the gas tank and the launch speed of the impact test object; at the same time, when performing impact tests on wood blocks and steel balls, different equipment needs to be replaced, which also makes the equipment system scattered, the preparation procedures are cumbersome, and the disassembly and replacement of equipment also requires a lot of manpower and material resources. In addition, in order to improve the stability of the test, some adjustment equipment is added to some impact test devices, but it is limited to the rough control of the launch angle. For impact conditions such as the test distance, it depends on human subjective judgment and manual adjustment, which is difficult to meet the requirements of precise control. Summary of the invention
[0004] In view of the above problems, the present application is proposed to provide a wind-borne debris impact testing device which overcomes the above problems or at least partially solves the above problems.
[0005] A wind-borne debris impact test device comprises a power device, a speed measuring device, a launching device and a central control system; the launching device comprises a launching tube and a steel ball impact sleeve, and the diameter of the launching tube is different from the diameter of the steel ball impact sleeve; The power device is connected to the launch tube, the speed measuring device is arranged on the outer side of the launch tube near the launch port, and the steel ball impact sleeve is detachably arranged at the launch port of the launch tube; the central control system is electrically connected to the power device and the speed measuring device; When the impact test object is a wooden block, removing the steel ball impact sleeve at the launch port of the launch tube; When the impact test object is a steel ball, the steel ball impact sleeve is installed at the launch port of the launch tube.
[0006] Preferably, it also includes an adjustment device, which is arranged on the outside of the launch tube.
[0007] Preferably, the adjustment device comprises a distance sensor for measuring the test distance; the distance sensor is arranged on the outer side of the launch tube near the end of the launch port.
[0008] Preferably, the adjustment device comprises a tilt sensor for measuring the tilt angle of the launch tube; the tilt sensor is outside the launch tube.
[0009] Preferably, the adjustment device comprises a laser sight for aiming at the impact position; the laser sight is arranged outside the launch tube.
[0010] Preferably, the power device comprises an air compressor, an air storage tank, connecting pipelines and a gas valve; The air inlet end of the air storage tank is connected to the air compressor through the connecting pipeline, and the gas valve is arranged in the connecting pipeline; the air outlet end of the air storage tank is connected to the air inlet end of the launching tube.
[0011] Preferably, the power device further comprises a solenoid valve; the solenoid valve is arranged at the gas outlet end of the gas storage tank and is electrically connected to the central control system.
[0012] Preferably, the speed measuring device comprises a first inductive speed measuring device and a second inductive speed measuring device; The first inductive speed meter and the second inductive speed meter are sequentially arranged at intervals on the outer side of the launch tube close to the launch port; the first inductive speed meter and the second inductive speed meter are electrically connected to the central control system.
[0013] Preferably, it also includes a base, a handwheel adjustment device and casters; The power device and the central control system are fixedly mounted on the base; the hand wheel adjustment device is arranged on the base and connected to the launch tube; the caster is arranged at the bottom of the base.
[0014] Preferably, it also includes a support frame, the bottom end of which is fixed to the base, and the top end of which is connected to the power device.
[0015] This application has the following advantages: In the embodiments of the present application, with respect to the problem in the prior art that "the steel ball and wood block impact test requires the replacement of different test equipment, resulting in the dispersion of the equipment system and complicated and cumbersome preparation procedures", the present application provides an integrated launching device with a launching tube and a steel ball impact sleeve, specifically: the launching device includes a launching tube and a steel ball impact sleeve, the diameter of the launching tube is different from the diameter of the steel ball impact sleeve; the power device is connected to the launching tube, the speed measuring device is arranged on the outside of the launching tube close to the launching port, and the steel ball impact sleeve is detachably arranged at the launching port of the launching tube; the central control system is electrically connected to the power device and the speed measuring device; when the impact test object is a wood block, the steel ball impact sleeve is removed at the launching port of the launching tube; when the impact test object is a steel ball, the steel ball impact sleeve is installed at the launching port of the launching tube. The integrated launch device with a launch tube and a steel ball impact sleeve can meet the impact test scenarios of wood blocks and steel balls at the same time, solve the problem of needing to replace equipment during steel ball and wood block impact tests, avoid the inconvenience caused by complex docking between multiple devices, and enhance the efficiency of the impact test process and the convenience of operation. At the same time, the test device has a compact structure design, saves space resources, and is suitable for large-scale promotion and use. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In order to more clearly illustrate the technical solution of the present application, the following is a brief introduction to the drawings required for use in the description of the present application. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative labor.
[0017] Figure 1 It is a structural schematic diagram of a wind-borne debris impact testing device provided in one embodiment of the present application; 1. Power unit; 2. Launch tube; 3. Steel ball impact sleeve; 4. Central control system; 5. Distance sensor; 6. Tilt sensor; 7. Laser sight; 8. First induction speedometer; 9. Second induction speedometer; 10. Gas tank; 11. Air compressor; 12. Gas valve; 13. Solenoid valve; 14. Base; 15. Handwheel adjustment device; 16. Casters; 17. Support frame; 18. Transport slot. DETAILED DESCRIPTION
[0018] In order to make the objects, features and advantages of the present application more obvious and understandable, the present application is further described in detail below in conjunction with the accompanying drawings and specific implementation methods. Obviously, the described embodiments are part of the embodiments of the present application, rather than all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in the field without creative work are within the scope of protection of the present application.
[0019] The inventors found through analyzing the prior art that the existing wind-borne debris impact test devices generally use gas tanks as impact power sources to push wood blocks or steel balls to be launched, but the diameter of the launch tube is fixed. When performing impact tests on wood blocks and steel balls, due to the difference in the diameters of the launch tubes required for the two, the launch device needs to be replaced, which causes the equipment system to be dispersed and the preparation procedures to be cumbersome. At the same time, the existing test devices lack a precise adjustment system, which reduces the test accuracy and increases the error range.
[0020] Reference Figure 1 , showing a schematic structural diagram of the wind-borne debris impact testing device of the present invention, which may specifically include the following structures: including a power device 1, a speed measuring device, a launching device and a central control system 4; the launching device includes a launching tube 2 and a steel ball impact sleeve 3, and the diameter of the launching tube 2 is different from the diameter of the steel ball impact sleeve 3; the power device 1 is connected to the launching tube 2, the speed measuring device is arranged on the outer side of the launching tube 2 close to the launching port, and the steel ball impact sleeve 3 is detachably arranged at the launching port of the launching tube 2; the central control system 4 is electrically connected to the power device 1 and the speed measuring device; when the impact test object is a wooden block, the steel ball impact sleeve 3 is removed at the launching port of the launching tube 2; when the impact test object is a steel ball, the steel ball impact sleeve 3 is installed at the launching port of the launching tube 2.
[0021] In the embodiments of the present application, with respect to the problem in the prior art that "the steel ball and wood block impact test requires the replacement of different test equipment, resulting in the dispersion of the equipment system and complicated and cumbersome preparation procedures", the present application provides an integrated launching device with a launching tube and a steel ball impact sleeve, specifically: comprising a power device 1, a speed measuring device, a launching device and a central control system 4; the launching device comprises a launching tube 2 and a steel ball impact sleeve 3, the diameter of the launching tube 2 is different from the diameter of the steel ball impact sleeve 3; the power device 1 is connected to the launching tube 2, the speed measuring device is arranged on the outside of the launching tube 2 close to the launching port, and the steel ball impact sleeve 3 is detachably arranged at the launching port of the launching tube 2; the central control system 4 is electrically connected to the power device 1 and the speed measuring device; when the impact test object is a wood block, the steel ball impact sleeve 3 is removed at the launching port of the launching tube 2; when the impact test object is a steel ball, the steel ball impact sleeve 3 is installed at the launching port of the launching tube 2. The integrated launch device with a launch tube and a steel ball impact sleeve can meet the impact test scenarios of wood blocks and steel balls at the same time, solve the problem of needing to replace equipment during steel ball and wood block impact tests, avoid the inconvenience caused by complex docking between multiple devices, and enhance the efficiency of the impact test process and the convenience of operation. At the same time, the test device has a compact structure design, saves space resources, and is suitable for large-scale promotion and use.
[0022] Next, a wind-borne debris impact testing device in this exemplary embodiment will be further described.
[0023] In one embodiment of the present application, the wind-borne debris impact testing device includes a power device 1, a speed measuring device, a launching device and a central control system 4; the launching device includes a launching tube 2 and a steel ball impact sleeve 3, and the diameter of the launching tube 2 is different from the diameter of the steel ball impact sleeve 3; the power device 1 is connected to the launching tube 2, the speed measuring device is arranged on the outer side of the launching tube 2 close to the launching port, and the steel ball impact sleeve 3 is detachably arranged at the launching port of the launching tube 2; the central control system 4 is electrically connected to the power device 1 and the speed measuring device; when the impact test object is a wooden block, the steel ball impact sleeve 3 is removed at the launching port of the launching tube 2; when the impact test object is a steel ball, the steel ball impact sleeve 3 is installed at the launching port of the launching tube 2.
[0024] It should be noted that the power device 1 provides power for the impact test object, the speed measuring device measures the speed of the impact test object, and the central control system 4 serves as a core control unit to control the state parameters and execution actions of each device to ensure the efficiency and controllability of the entire test process.
[0025] As an example, the launching device includes a launching tube 2 and a steel ball impact sleeve 3, the diameter of the launching tube 2 is different from that of the steel ball impact sleeve 3, the diameter of the steel ball impact sleeve 3 is smaller than the diameter of the launching tube 2, and the steel ball impact sleeve 3 is detachably connected to the launching tube 2 by a fastening device; preferably, the fastening device may be a fastening bolt, the steel ball impact sleeve 3 is provided with a bolt hole, and the steel ball impact sleeve 3 is fastened and installed on the launching tube 2 by bolts.
[0026] In a specific embodiment, the steel ball impact sleeve is provided with 6 bolt holes around it, and the steel ball impact sleeve is fastened and installed on the launch tube by bolts; specifically, when performing a wood block impact test, the steel ball impact sleeve 3 is removed from the launch port of the launch tube 2, and the impact wood block with the bushing is pushed into the launch tube 2 until it reaches its bottom position, and the corresponding parameters are set by the central control system 4 to control the launch process, and the power device 1 drives the wood block to be ejected from the launch tube 2 at a high speed, and the speed measuring device and the central control system 4 calculate the ejection speed of the wood block, and the central control system 4 is responsible for collecting and Record various test data to complete the wood block impact test; when conducting the steel ball impact test, install the steel ball impact sleeve 3 at the launch port of the launch tube 2, press the steel ball on the sleeve and put it into the launch tube 2, and the power device 1 drives the wood block to be ejected from the launch tube 2 at high speed. After the steel ball sleeve is ejected, the sleeve will stop moving due to the restraining effect of the steel ball impact sleeve 3, and the steel ball will be ejected under inertia. The ejection speed of the steel ball is calculated by the speed measuring device and the central control system 4, and the central control system 4 is responsible for collecting and recording various test data to complete the steel ball impact test.
[0027] In one embodiment of the present application, an adjustment device is also included, and the adjustment device is arranged on the outside of the launch tube 2.
[0028] It should be noted that the adjustment device performs multi-directional calibration of the impact conditions to achieve precise control of the impact conditions; the adjustment device includes a distance adjustment device, an angle adjustment device and an impact position adjustment device for the impact test object. Through the above adjustment devices, the test data is ensured to be accurate and reliable, and the test accuracy is improved.
[0029] In one embodiment of the present application, the adjustment device includes a distance sensor 5 for measuring the test distance; the distance sensor 5 is arranged on the outer side of the launch tube 2 near the end of the launch port.
[0030] In a specific embodiment, the distance sensor 5 is fixedly installed on the outer side of the transmitting tube 2, and the test distance is measured by the distance sensor 5, and then the test distance is adjusted to meet the preset requirements.
[0031] In one embodiment of the present application, the adjustment device includes a tilt sensor 6 for measuring the tilt angle of the launch tube 2 ; the tilt sensor 6 is arranged on the outside of the launch tube 2 .
[0032] In a specific embodiment, the tilt sensor 6 is fixedly installed on the outside of the launch tube, and the launch angle of the launch tube 2 is adjusted to a specified angle by measuring the tilt angle of the launch tube 2 relative to the horizontal plane, so as to further improve the test accuracy.
[0033] In one embodiment of the present application, the adjustment device includes a laser sight 7 for aiming at the impact position; the laser sight 7 is arranged on the outside of the launch tube 2.
[0034] In a specific embodiment, the laser sight 7 is fixedly mounted on the outside of the transmitting tube 2. By rotating the laser sight 7, the infrared laser emitted by it is aimed at a preset impact test position, that is, the target impact position reached by the impact test object.
[0035] It should be noted that the various components of the alignment device work together to perform multi-directional verification of the impact conditions. When performing an impact test, firstly, the test distance is measured by the distance sensor 5 at the end of the launch tube 2 to verify whether the test distance meets the standard requirements, and the inclination of the launch tube 2 is measured by the inclination sensor 6 to verify whether the launch angle is at the specified angle, and then the laser sight 7 is rotated to aim the infrared laser at the impact position of the impact test object. After the above steps, it is ensured that the impact test can guarantee a sufficiently high accuracy and further improve the test accuracy.
[0036] In one embodiment of the present application, the power device 1 includes an air compressor 11, an air tank 10, a connecting pipeline and a gas valve 12; the air inlet end of the air tank 10 is connected to the air compressor 11 through the connecting pipeline, and the gas valve 12 is arranged in the connecting pipeline; the air outlet end of the air tank 10 is connected to the air inlet end of the launch tube 2.
[0037] In a specific embodiment, the air tank 10 is arranged above the air compressor 11, and the air inlet end of the air tank 10 is connected to the air compressor 11 through the connecting pipeline. The air compressor 11 provides compressed air to the air tank 10. In order to facilitate the observation of the pressure of the compressed air in the air tank 10, the air tank 10 is provided with a pressure gauge; the air tank 10 and the launch tube 2 are arranged along the same axis, and the air outlet end of the air tank 10 is connected to the air inlet end of the launch tube 2.
[0038] In one embodiment of the present application, the power device 1 further includes a solenoid valve 13 ; the solenoid valve 13 is disposed at the gas outlet end of the gas storage tank 10 and is electrically connected to the central control system 4 .
[0039] In a specific embodiment, the solenoid valve 13 is arranged at the gas outlet end of the gas tank 10. The solenoid valve 13 can close the gas outlet end of the gas tank 10 to isolate the gas or quickly open the gas outlet end of the gas tank 10 to communicate the gas tank 10 with the inner cavity of the launch tube 2. The PCL controller of the central control system 4 controls the opening or closing of the solenoid valve 13 switch; specifically, the compressed gas pressure in the gas tank 10 is different, and the launch speed of the impact test object is also different, and different pressure values can be set according to test needs; when performing an impact test, the central control system 4 controls the compressed gas pressure of the gas tank 10. When the pressure in the gas tank 10 reaches a preset value, the solenoid valve 13 is opened through the central control system 4, so that the gas in the gas tank 10 is ejected from the launch tube 2, acting on the impact test object in the launch tube 2, so that the impact test object is ejected at a high speed at a certain speed.
[0040] In one embodiment of the present application, the speed measuring device includes a first inductive speed meter 8 and a second inductive speed meter 9; the first inductive speed meter 8 and the second inductive speed meter 9 are arranged in sequence and spaced apart on the outer side of the launching tube 2 near the launching port; the first inductive speed meter 8 and the second inductive speed meter 9 are electrically connected to the central control system 4.
[0041] In a specific embodiment, the first inductive speed meter 8 and the second inductive speed meter 9 are electrically connected to the central control system 4, and the interval distance between the first inductive speed meter 8 and the second inductive speed meter 9 in the transmitting tube 2 is d. When the impact test object passes through the first inductive speed meter 8 and the second inductive speed meter 9 in sequence, the microsecond timer of the central control system 4 measures that the time required for the impact test object to pass through the interval distance between the two sets of speed meters is t, and then the average speed of the impact test object is calculated according to the formula v=d / t.
[0042] In one embodiment of the present application, it also includes a base 14, a handwheel adjustment device 15 and a caster 16; the power unit 1 and the central control system 4 are fixedly installed on the base 14; the handwheel adjustment device 15 is arranged on the base 14 and connected to the launch tube 2; the caster 16 is arranged at the bottom of the base 14.
[0043] In a specific embodiment, the power device 1 and the central control system 4 are fixedly mounted on the base 14, so that the impact testing device occupies a small area and occupies a compact space; the handwheel adjustment device 15 is arranged on the base 14, and one end of the handwheel device is connected to the launch tube 2, and the inclination angle of the launch tube 2 can be conveniently and quickly adjusted to a specified angle through the handwheel adjustment device 15; the base 14 is a movable rigid base 14 with lockable casters 16, and is equipped with a forklift transportation slot 18, and the casters 16 and the forklift transportation slot 18 are arranged at the bottom of the base 14. Through the above device, the test distance can be adjusted or the impact testing device can be moved as a whole conveniently and quickly, and it can also adapt to various application scenarios such as laboratories or factories, and is suitable for large-scale promotion.
[0044] In one embodiment of the present application, a support frame 17 is further included, wherein the bottom end of the support frame 17 is fixed to the base 14 , and the top end is connected to the power device 1 .
[0045] In a specific embodiment, the support frame 17 is vertically distributed on the base 14, the bottom end of the support frame 17 is fixedly connected to the base 14, and the upper end of the support is fixedly connected to the power device 1, so that the overall structure is safer and more reliable.
[0046] Although the preferred embodiments of the present application have been described, those skilled in the art may make additional changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications that fall within the scope of the embodiments of the present application.
[0047] Finally, it should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or terminal device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or terminal device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or terminal device including the elements.
[0048] The above is a detailed introduction to a wind-borne debris impact testing device provided by the present application. Specific examples are used in this article to illustrate the principles and implementation methods of the present application. The description of the above embodiments is only used to help understand the method of the present application and its core idea. At the same time, for general technicians in this field, according to the idea of the present application, there will be changes in the specific implementation method and application scope. In summary, the content of this specification should not be understood as a limitation on the present application.
Claims
1. A wind-borne debris impact test device, characterized in that: It includes a power device, a speed measuring device, a launching device and a central control system; the launching device includes a launching tube and a steel ball impact sleeve, and the diameter of the launching tube is different from the diameter of the steel ball impact sleeve; The power device is connected to the launch tube, the speed measuring device is arranged on the outer side of the launch tube near the launch port, and the steel ball impact sleeve is detachably arranged at the launch port of the launch tube; the central control system is electrically connected to the power device and the speed measuring device; When the impact test object is a wooden block, removing the steel ball impact sleeve at the launch port of the launch tube; When the impact test object is a steel ball, the steel ball impact sleeve is installed at the launch port of the launch tube.
2. The wind-borne debris impact testing device according to claim 1, characterized in that: It also includes an alignment device, which is arranged on the outside of the launch tube.
3. The wind-borne debris impact testing device according to claim 2, characterized in that: The alignment device comprises a distance sensor for measuring the test distance; the distance sensor is arranged on the outer side of the launch tube near the end of the launch port.
4. The wind-borne debris impact testing device according to claim 2, characterized in that: The alignment device comprises a tilt sensor for measuring the tilt angle of the launch tube; the tilt sensor is located outside the launch tube.
5. The wind-borne debris impact testing device according to claim 2, characterized in that: The alignment device comprises a laser sight for aiming at the impact position; the laser sight is arranged outside the launch tube.
6. The wind-borne debris impact testing device according to claim 1, characterized in that: The power device includes an air compressor, an air storage tank, connecting pipelines and a gas valve; The air inlet end of the air storage tank is connected to the air compressor through the connecting pipeline, and the gas valve is arranged in the connecting pipeline; the air outlet end of the air storage tank is connected to the air inlet end of the launching tube.
7. The wind-borne debris impact testing device according to claim 6, characterized in that: The power device also includes a solenoid valve; the solenoid valve is arranged at the gas outlet end of the gas storage tank and is electrically connected to the central control system.
8. The wind-borne debris impact testing device according to claim 1, characterized in that: The speed measuring device comprises a first inductive speed measuring device and a second inductive speed measuring device; The first inductive speed meter and the second inductive speed meter are sequentially arranged at intervals on the outer side of the launch tube close to the launch port; the first inductive speed meter and the second inductive speed meter are electrically connected to the central control system.
9. The wind-borne debris impact testing device according to claim 1, characterized in that: Also includes base, hand wheel adjustment and casters; The power device and the central control system are fixedly mounted on the base; the hand wheel adjustment device is arranged on the base and connected to the launch tube; the caster is arranged at the bottom of the base.
10. The wind-borne debris impact testing device according to claim 9, characterized in that: It also includes a support frame, the bottom end of which is fixed to the base, and the top end of which is connected to the power device.