The modular leg extension device enables convenient extension of the legs, solving the problems of high replacement cost and long installation time in existing technologies, and improving the efficiency and economy of marine engineering.
Patent Information
- Application Number
- CN202411221445.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-02
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2044-09-02
AI Technical Summary
Existing technologies are costly and time-consuming when replacing longer pile legs in marine engineering, and cannot be installed quickly, thus failing to meet the needs of deep-sea engineering.
The modular pile leg extension device includes a movable pile gripping assembly, a flipping transmission assembly, a pile leg connecting hoist, and a hoisting assembly. The detachable connection structure enables convenient extension of the pile legs, avoiding additional welding.
It reduces the cost of replacing and manufacturing pile legs, improves installation efficiency and stability, enhances the applicability and economy of pile legs, and adapts to engineering needs at different marine depths.
Smart Images

Figure CN119021231A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of marine engineering construction, and in particular to a modular pile leg lengthening device and an installation method. Background Art
[0002] In an offshore engineering platform, the role of the pile legs is to support the offshore engineering platform. With the development of offshore engineering towards deeper waters, during the use of the pile legs, it may happen that the original pile legs can no longer meet the depth requirements of the ocean. Currently, when replacing longer pile legs, the entire pile legs are usually replaced directly. The replacement cost and manufacturing cost of the pile legs are too high, and the process takes longer time and is less efficient, which cannot meet the needs of offshore engineering.
[0003] At present, modular assembly pile leg technology is used to extend the length of the pile leg. For example, Chinese patent publication (announcement) No. CN108374401A discloses a wind power installation ship pile leg extension device and its installation method. By designing a connection and lifting device, the pile leg is extended, so that it is suitable for deep-sea installation operations. However, during the installation process of the pile leg extension, it is necessary to add a lower flange for reinforcement on the top of the original pile leg, and at the same time add an upper flange and a top reinforcement component on the bottom of the extended pile leg. These components need to be pre-welded on the pile leg, which undoubtedly increases the workload and difficulty of extending the pile leg, and cannot achieve rapid installation, and cannot effectively reduce the construction cost and improve the economy and applicability of the pile leg. Summary of the invention
[0004] In order to overcome the shortcomings of the prior art, one of the purposes of the present invention is to provide a modular pile leg lengthening device. The present invention adopts the modular pile leg lengthening device to increase the length of the pile leg on the basis of the original pile leg. The lengthening installation process is convenient and does not require additional welding. The pile leg extension structure is a detachable connection structure, which enhances the adaptability of the pile leg and has potential innovative value in the field of marine engineering.
[0005] The second purpose of the present invention is to provide a modular pile leg lengthening installation method. The modular pile leg lengthening installation method can simplify the assembly process and has certain economic value and practical value for speeding up and increasing the efficiency of the pile leg extension project.
[0006] One of the purposes of the present invention is achieved by adopting the following technical solution: a modular pile leg lengthening device, comprising a movable pile holding assembly for placing pile legs, a flip transmission assembly for flipping the pile legs placed on the movable pile holding assembly from a horizontal state to a vertical state, a pile leg connecting hoop for fixing the connecting positions of two adjacent pile legs to each other, a hoisting assembly for hoisting the pile leg connecting hoop to the connecting position of two adjacent pile legs, and a top hoop assembly for supporting the pile leg connecting hoop on the inner wall of the connecting position of the two pile legs;
[0007] The flip transmission assembly is in transmission connection with the movable pile holding assembly, driving the movable pile holding assembly to switch between a horizontal state and a vertical state; the hoisting assembly is installed at the top of the movable pile holding assembly, the hoisting assembly is provided with a steel wire rope with a retractable function, the top hoop assembly is fixed at the end of the steel wire rope, and the lifting and lowering adjustment of the top hoop assembly is realized by the retractable hoisting assembly, and the pile leg connecting hoop is installed on the top hoop assembly;
[0008] When the pile leg is placed horizontally on the movable pile holding assembly, the flip transmission assembly lifts up the movable pile holding assembly, flips the pile leg from a horizontal state to a vertical state and aligns it with the pile leg at the lower section, and the hoisting assembly hoists the pile leg connecting hoop from the inside of the pile leg to the inner walls of the two adjacent pile legs through a steel wire rope, and the top hoop assembly supports the pile leg connecting hoop on the inner wall of the connecting position of the two pile legs.
[0009] Optionally, the movable pile holding assembly includes a movable pile holding frame and an articulated seat; the bottom end of the movable pile holding frame is hinged on the articulated seat, and the articulated seat is installed on the periphery of the moon pool of the working platform; the movable pile holding frame has a first accommodating groove for accommodating the pile leg, and at least one first guide groove is provided in the first accommodating groove, and a plurality of bearing groups for reducing sliding friction are embedded in the first guide groove.
[0010] Optionally, the flip transmission assembly includes a lifting cylinder and a horizontal slide, one end of the lifting cylinder is hinged to one side of the movable pile holding assembly, and the other end is hinged to the horizontal slide, and the horizontal slide slides horizontally on the offshore working platform.
[0011] Optionally, the pile leg connecting hoop includes a connecting ring and at least two groups of elastic locking members connected to the outer periphery of the connecting ring; each group of elastic locking members includes a first elastic locking member and a second elastic locking member symmetrically arranged above and below the first elastic locking member; the first elastic locking member is arranged on the outer periphery of the connecting ring, and is formed by the outer periphery extending upward and obliquely along the axial direction of the connecting ring; the second elastic locking member is arranged on the outer periphery of the connecting ring, and is formed by the outer periphery extending downward and obliquely along the axial direction of the connecting ring; the ends of each of the first elastic locking members are respectively fixed on the inner side wall of the pile leg located in the upper section, and the ends of each of the second elastic locking members are respectively fixed on the inner side wall of the pile leg located in the lower section, so as to fix the two adjacent sections of the pile legs to each other.
[0012] Optionally, each of the first elastic locking members comprises a first outwardly inclined portion and a first upright portion; one end of the first outwardly inclined portion is connected to the outer periphery of the connecting ring, and the other end is connected to the first upright portion; a plurality of first fastening holes are provided on the first upright portion; a locking hole adapted to the position of the first fastening hole is provided at the lower portion of the pile leg located at the upper section, and the first upright portion is locked and fixed to the inner wall of the pile leg located at the upper section by the fastener cooperating with the first fastening hole and the locking hole;
[0013] Each of the second elastic locking members includes a second outwardly inclined portion and a second upright portion; one end of the second outwardly inclined portion is connected to the outer periphery of the connecting ring, and the other end is connected to the second upright portion; a plurality of second fastening holes are provided on the second upright portion; the upper portion of the pile leg located in the lower section is provided with a locking hole adapted to the position of the second fastening hole, and the second upright portion is locked and fixed to the inner wall of the pile leg located in the lower section by means of a fastener cooperating with the second fastening hole and the locking hole.
[0014] Optionally, the pile leg located at the lower section has a recessed limit groove matching the shape of the second upright portion at its upper portion, and the second fastening hole is arranged in the recessed limit groove; the pile leg located at the upper section has a recessed limit groove matching the shape of the first upright portion at its lower portion, and the first fastening hole is arranged in the recessed limit groove;
[0015] At least one limit block is protruding outward from the outer periphery of the connecting ring, and the inner walls of the pile legs located at the upper section and the pile legs located at the lower section are recessed with axial guide grooves that match the shape of the limit block.
[0016] Optionally, the top hoop assembly includes a limiting seat for installing the connecting ring and a telescopic top tightening member for pressing the elastic locking member against the inner wall of the pile leg; the connecting ring is detachably mounted on the limiting seat, the telescopic top tightening member has a fan-shaped top tightening block, and the telescopic top tightening member is mounted on the limiting seat, and when the telescopic top tightening member performs a horizontal extension movement, the fan-shaped top tightening block is driven to open the elastic locking member outward so that each group of elastic locking members is pressed against the inner wall of the pile leg.
[0017] Optionally, the modular pile leg extension device also includes a fixed pile holding assembly arranged on one side of the movable pile holding assembly, the fixed pile holding assembly includes a fixed pile holding frame and a fixed seat; the bottom end of the fixed pile holding frame is fixed to the fixed seat, and the fixed seat is installed on the periphery of the moon pool of the working platform; the fixed pile holding frame has a second accommodating groove for accommodating the pile leg, the second accommodating groove is provided with at least one second guide groove, and the second guide groove is embedded with a plurality of bearing groups for reducing sliding friction.
[0018] Optionally, the lifting assembly also includes a lifting device mounting frame and a pulley member; the lifting device mounting frame is installed on the movable end of the movable pile holding assembly, the pulley member is installed on the lifting device mounting frame, the wire rope is wound around the pulley member, and the top hoop assembly equipped with a pile leg connecting hoop can be detachably installed on the wire rope.
[0019] The second object of the present invention is achieved by adopting the following technical solution: a modular pile leg lengthening installation method, characterized in that the modular pile leg lengthening device as described above is used to lengthen the original pile leg, specifically comprising the following steps:
[0020] (1) The initial position of the movable pile holding assembly is in a horizontal state, and the pile legs are fixed in the movable pile holding assembly, waiting to be turned over;
[0021] (2) Sleeve the pile leg connection hoop onto the top hoop assembly, fix the top hoop assembly with the pile leg connection hoop onto the lifting assembly via a steel wire rope, tighten the steel wire rope, and tighten the top hoop assembly onto one side of the pile leg;
[0022] (3) The turning transmission assembly lifts up the movable pile holding assembly, turning the movable pile holding assembly from a horizontal state to a vertical state, and the pile legs are synchronously turned from a horizontal state to a vertical state and aligned with the pile legs located at the lower section;
[0023] (4) The hoisting assembly releases the wire rope and lowers the top hoop assembly equipped with the pile leg connecting hoop from the inside of the pile leg to the connection between two adjacent pile legs;
[0024] (5) The top hoop assembly supports the pile leg connecting hoop on the inner wall of the connecting position of the two pile legs, and fixes the pile leg connecting hoop on the connecting position of the two pile legs through fasteners, thereby fixing the pile leg located at the upper section on the upper part of the original pile leg, thereby lengthening the pile leg.
[0025] Optionally, the modular pile leg extension installation method also includes step (6): continuing to install and extend pile legs on the lengthened pile legs; the specific process is as follows: a lifting device for adjusting the height of the pile legs is pre-arranged on the periphery of the moon pool, and the lifting device vertically transports the pile legs that have been lengthened in step (5) downward to a preset height position; and continuing to repeat steps (1)-(5) to flip and fix another section of the pile legs on the upper part of the pile legs that have been installed in step (5), and so on, until the entire pile leg meets the length required for various projects.
[0026] Compared with the prior art, the present invention has the following beneficial effects:
[0027] 1. The present invention adopts the modular pile leg lengthening device to increase the length of the pile leg on the basis of the original pile leg. The lengthening installation process is convenient and does not require additional welding. The pile leg extension structure is a detachable connection structure, which enhances the adaptability of the pile leg and has potential innovative value in the field of marine engineering.
[0028] 2. Reduce costs and improve efficiency: By designing a built-in pile leg connection hoop, the replacement of the entire pile leg is avoided, the manufacturing and replacement costs are reduced, and the rapid assembly of modular pile legs is achieved, making the extension process of the pile leg faster and shortening the process time.
[0029] 3. Improve connection stability and simplify installation process: through the built-in connecting ring and elastic locking parts, during installation, the pile leg connection structure will be hoisted from the inside of the pile leg to the required position, and the horizontally telescopic hydraulic jacking device will be used to expand the pile leg connection structure between the two pile legs, so that the upper and lower parts of the connecting ring structure can be connected to the upper pile leg and the lower pile leg respectively through fasteners, so as to achieve stable connection of the pile legs and reduce the welding workload and difficulty during the extension of the pile legs.
[0030] 4. Enhanced applicability: The design of the pile leg connection hoop allows multiple pile legs to be spliced and extended into a complete pile leg. The pile legs can meet the requirements of different lengths, improving the applicability of the pile legs in projects at different ocean depths.
[0031] 5. Easy maintenance: The modular design makes the maintenance and replacement of the pile legs more convenient, and local repairs or replacements can be carried out quickly without processing the entire pile leg.
[0032] 6. Improved economy: The economy of the pile legs is improved by reducing the overall cost of manufacturing and replacement and improving work efficiency.
[0033] 7. Strong environmental adaptability: The improved pile-leg connection structure can better adapt to complex marine environments such as the deep sea, improving the stability and reliability of the offshore engineering platform.
[0034] 8. Scalability: This technical solution may have good scalability and can be applied to a wider range of marine engineering projects in the future.
[0035] 9. This modular pile leg extension installation method can simplify the assembly process and has certain economic and practical value for speeding up and increasing the efficiency of the pile leg extension project. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] Figure 1 It is a schematic diagram of the state of the modular pile leg lengthening device after the two-stage pile leg lengthening is installed in a preferred embodiment of the present invention;
[0037] Figure 2This is a schematic structural diagram of a modular pile leg lengthening device according to a preferred embodiment of the present invention;
[0038] Figure 3 for Figure 2 The enlarged schematic diagram of point A in the middle;
[0039] Figure 4 for Figure 2 The enlarged schematic diagram of point B in the middle;
[0040] Figure 5 for Figure 4 The enlarged schematic diagram of the center C;
[0041] Figure 6 This is a structural schematic diagram of a fixed pile holding assembly according to a preferred embodiment of the present invention;
[0042] Figure 7 This is a schematic structural diagram of a pile leg connection hoop according to a preferred embodiment of the present invention;
[0043] Figure 8 It is a partial structural schematic diagram of a pile leg connection hoop of a preferred embodiment of the present invention;
[0044] Fig. 9 It is a schematic diagram of the hoisting state of the pile leg connecting hoop and the top hoop assembly in a preferred embodiment of the present invention;
[0045] Fig.10 It is a partial disassembled schematic diagram of a pile leg connection hoop and two pile legs in a preferred embodiment of the present invention;
[0046] Fig.11 It is a cross-sectional schematic diagram of a pile leg connecting hoop and two pile leg sections assembled in a preferred embodiment of the present invention;
[0047] Fig.12 It is a schematic diagram of partial disassembly of the pile leg connecting hoop and the top hoop assembly according to a preferred embodiment of the present invention.
[0048] In the figure:
[0049] 100. Modular pile leg extension device;
[0050] 1. movable pile holding assembly; 11. movable pile holding frame; 111. first accommodating groove; 112. first guide groove; 113. bearing assembly; 12. hinge seat;
[0051] 2. Turning transmission assembly; 21. Lifting cylinder; 22. Horizontal slide; 221. Pulley block;
[0052] 3. Pile leg connection hoop; 31. Connection ring; 311. Limit block; 32. First elastic locking member; 321. First outwardly inclined portion; 322. First upright portion; 323. First fastening hole; 33. Second elastic locking member; 331. Second outwardly inclined portion; 332. Second upright portion; 333. Second fastening hole;
[0053] 4. Hoisting assembly; 41. Hoisting device mounting frame; 42. Pulley; 43. Steel wire rope;
[0054] 5. Top hoop assembly; 51. Limit seat; 511. Fixed seat; 512. Horizontal telescopic support frame; 5121. Annular limit groove; 513. Mounting frame; 52. Telescopic top tightening member; 521. Fan-shaped top tightening block;
[0055] 6. Fixed pile holding assembly; 61. Fixed pile holding frame; 611. Second accommodating groove; 612. Second guide groove; 613. Bearing group; 62. Fixed seat;
[0056] 200, pile leg located at the upper section; 201, locking hole; 202, limiting groove; 203, axial guide groove;
[0057] 300, pile leg located at the lower section; 301, locking hole; 302, limiting groove; 303, axial guide groove;
[0058] 400. Lifting device. DETAILED DESCRIPTION
[0059] The present invention is further described below in conjunction with the accompanying drawings and specific implementation methods. It should be noted that, under the premise of no conflict, the various embodiments or technical features described below can be arbitrarily combined to form a new embodiment.
[0060] like Figure 1-12 As shown, the role of the modular pile leg extension device 100 of the present invention is to extend the length of the pile leg. For example, by increasing the length on the basis of the original pile leg, it can meet the depth requirements of the ocean and fully improve the utilization rate of the original pile leg. There is no need to replace the entire pile leg, thereby reducing the replacement cost of the pile leg. For example, in sea areas with different depths, the pile legs can be modularly assembled according to the different depths of the sea areas, which reduces the workload and difficulty of extending the pile legs, realizes rapid installation, effectively reduces construction costs, and improves the economy and applicability of the pile legs.
[0061] Specifically, the modular pile leg lengthening device 100 is installed on an offshore operating platform with a moon pool, specifically on the periphery of the moon pool. The pile legs at the lower section are located in the moon pool of the offshore operating platform. The modular pile leg lengthening device 100 is used to flip, align, and fix the newly added pile legs on the pile legs at the lower section in turn, and then the two adjacent pile legs are fixed together through the built-in pile leg connecting hoop 3, so as to realize the rapid assembly and extension of both the upper pile legs and the lower pile legs. This method is popularized and applied.
[0062] The modular pile leg lengthening device 100 includes a movable pile holding assembly 1 for placing pile legs, a flip transmission assembly 2 for flipping the pile legs placed on the movable pile holding assembly 1 from a horizontal state to a vertical state, a pile leg connecting hoop 3 for fixing the connecting positions of two adjacent pile legs to each other, a hoisting assembly 4 for hoisting the pile leg connecting hoop 3 to the connecting positions of two adjacent pile legs, and a top hoop assembly 5 for supporting the pile leg connecting hoop 3 on the inner wall of the connecting position of the two pile legs;
[0063] The flip transmission assembly 2 is in transmission connection with the movable pile holding assembly 1, driving the movable pile holding assembly 1 to switch between a horizontal state and a vertical state; the hoisting assembly 4 is installed at the top of the movable pile holding assembly 1, and the hoisting assembly 4 is provided with a steel wire rope 43 with a retractable function, and the top hoop assembly 5 is fixed at the end of the steel wire rope 43, and the lifting and lowering adjustment of the top hoop assembly 5 is realized by the hoisting assembly 4 being retracted and released, and the pile leg connecting hoop 3 is installed on the top hoop assembly 5;
[0064] When the pile leg is horizontally placed on the movable pile holding assembly 1, the flip transmission assembly 2 lifts up the movable pile holding assembly 1, flips the pile leg from a horizontal state to a vertical state and aligns it with the pile leg 300 located at the lower section, and the hoisting assembly 4 hoists the pile leg connecting hoop 3 from the inside of the pile leg to the inner walls of the two adjacent pile legs through the wire rope 43, and the top hoop assembly 5 supports the pile leg connecting hoop 3 on the inner walls of the connecting position of the two pile legs. At this time, the pile leg connecting hoop 3 is locked on the connecting position of the adjacent pile legs by a fastener (not shown in the figure).
[0065] As a further preferred embodiment, the movable pile holding assembly 1 includes a movable pile holding frame 11 and an articulated seat 12; the bottom end of the movable pile holding frame 11 is hinged on the articulated seat 12, and the articulated seat 12 is installed on the periphery of the moon pool of the working platform (not shown in the figure); the movable pile holding frame 11 has a first accommodating groove 111 for accommodating the pile leg, and at least one first guide groove 112 is provided in the first accommodating groove 111, and a plurality of bearing groups 113 for reducing sliding friction are embedded in the first guide groove 112.
[0066] The present application improves the flipping stability of the pile legs by designing the structure of the movable pile holding frame 11, and facilitates the rapid and accurate positioning of the pile legs at the lower section after flipping, which can improve the rapid positioning between the pile leg connecting hoop 3 and the two adjacent pile legs in the later stage. Specifically, by designing the first accommodating groove 111, it is convenient to horizontally position the pile legs, thereby improving the flipping stability of the pile legs. The design of the first guide groove 112 and the avoidance coordination of the transmission teeth on the outer surface of the pile legs can serve as a limiting structure to prevent movement during the flipping process. Secondly, the coordination design of the recessed first guide groove 112 and the bearing group 113 can also protect the transmission teeth, especially during the flipping process, reduce the sliding friction between the transmission teeth and the movable pile holding frame 11, and avoid deformation or wear of the transmission teeth.
[0067] As a further preferred embodiment, the flip transmission assembly 2 includes a lifting cylinder 21 and a horizontal slide 22. One end of the lifting cylinder 21 is hinged to one side of the movable pile holding assembly 1, and the other end is hinged to the horizontal slide 22. The horizontal slide 22 is enabled to slide horizontally on the offshore working platform by a pulley group 221 arranged at the bottom thereof.
[0068] As a further preferred embodiment, the pile leg connecting hoop 3 includes a connecting ring 31 and at least two groups of elastic locking members connected to the outer periphery of the connecting ring 31; each group of elastic locking members includes a first elastic locking member 32 and a second elastic locking member 33 symmetrically arranged above and below the first elastic locking member 32; the first elastic locking member 32 is arranged on the outer periphery of the connecting ring 31, and is formed by the outer periphery extending upward and obliquely along the axial direction of the connecting ring 31; the second elastic locking member 33 is arranged on the outer periphery of the connecting ring 31, and is formed by the outer periphery extending downward and obliquely along the axial direction of the connecting ring 31; the ends of each of the first elastic locking members 32 are respectively fixed on the inner side wall of the pile leg 200 located in the upper section, and the ends of each of the second elastic locking members 33 are respectively fixed on the inner side wall of the pile leg 300 located in the lower section, so as to fix the two adjacent pile legs to each other.
[0069] The present application avoids the replacement of the entire pile leg by designing a built-in pile leg connection hoop 3 as the pile leg connection structure, reduces the cost of manufacturing and replacement, realizes the rapid assembly of modular pile legs, makes the extension process of the pile leg faster, and shortens the process time. Specifically, by designing the first elastic locking member 32 and the second elastic locking member 33 that are symmetrical up and down, the mold processing cost of the pile leg connection structure can be reduced and optimized, the assembly process is simplified, and it has certain economic value and practical value for speeding up and increasing the efficiency of the pile leg extension project.
[0070] As a further preferred embodiment, each of the first elastic locking members 32 includes a first outwardly inclined portion 321 and a first upright portion 322; one end of the first outwardly inclined portion 321 is connected to the outer periphery of the connecting ring 31, and the other end is connected to the first upright portion 322; a plurality of first fastening holes 323 are provided on the first upright portion 322; a locking hole 201 adapted to the position of the first fastening hole 323 is provided at the lower portion of the pile leg 200 located at the upper section, and the first upright portion 322 is locked and fixed to the inner wall of the pile leg 200 located at the upper section by a fastener cooperating with the first fastening hole 323 and the locking hole 201;
[0071] Each of the second elastic locking members 33 includes a second outwardly inclined portion 331 and a second upright portion 332; one end of the second outwardly inclined portion 331 is connected to the outer periphery of the connecting ring 31, and the other end is connected to the second upright portion 332; a plurality of second fastening holes 333 are provided on the second upright portion 332; the upper portion of the pile leg 300 located at the lower section is provided with a locking hole 301 adapted to the position of the second fastening hole 333, and the second upright portion 332 is locked and fixed to the inner wall of the pile leg located at the lower section by a fastener (not shown) cooperating with the second fastening hole 333 and the locking hole 301.
[0072] Specifically, the present application uses a built-in connecting ring 31 and an elastic locking piece to lift the pile leg connecting structure from the inside of the pile leg to the desired position during installation, and uses a horizontally retractable hydraulic jacking device to expand the pile leg connecting structure between the two sections of the pile legs (specifically the first upright portion 322 and the second upright portion 332), so that the first upright portion 322 and the second upright portion 332 of the connecting ring structure are connected to the pile legs located at the upper and lower sections respectively through fasteners, thereby achieving a stable connection of the pile legs and reducing the welding workload and difficulty during the pile leg extension process.
[0073] As a further preferred solution, the pile leg 300 located at the lower section has a recessed limit groove 302 at its upper portion that matches the shape of the second upright portion 332, and the second fastening hole 333 is arranged in the restricting groove 302; the pile leg located at the upper section has a recessed limit groove 202 at its lower portion that matches the shape of the first upright portion 322, and the first fastening hole 323 is arranged in the restricting groove 202;
[0074] At least one limit block 311 is protruded outwardly from the outer periphery of the connecting ring 31 , and the inner walls of the pile legs located at the upper section and the pile legs located at the lower section are recessed with axial guide grooves 203 / 303 that match the shape of the limit block 311 .
[0075] The present application designs a limit block 311 in the pile leg connection structure and an axial guide groove on the inner wall of the pile leg. The two cooperate and slide so that when the pile leg connection structure is hoisted, the pile leg connection structure can move up and down along a preset moving trajectory in the pile leg. This is beneficial to the precise alignment between the locking hole and the first and second fastening holes, realizes the rapid installation of fasteners, and improves the installation efficiency and quality.
[0076] As a further preferred embodiment, the top hoop assembly 5 includes a limiting seat 51 for installing the connecting ring 31 and a telescopic top tightening member 52 for pressing the elastic locking member against the inner wall of the pile leg; the connecting ring 31 is detachably mounted on the limiting seat 51, and the telescopic top tightening member 52 has a fan-shaped top tightening block 521, and the telescopic top tightening member 52 is mounted on the limiting seat 51. When the telescopic top tightening member 52 makes a horizontal extension movement, it drives the fan-shaped top tightening block 521 to open the elastic locking member outward so that each group of elastic locking members is pressed against the inner wall of the pile leg.
[0077] The limiting seat 51 includes a fixed seat 511, a horizontal telescopic support frame 512 installed on the fixed seat 511, and mounting frames 513 respectively arranged at the upper and lower parts of the fixed seat 511 for mounting the telescopic top tightening member 52; each of the mounting frames 513 is installed with a telescopic top tightening member 52; the horizontal telescopic support frame 512 has an annular limiting groove 5121 adapted to the shape of the connecting ring 31.
[0078] As a further preferred embodiment, the modular pile leg extension device 100 also includes a fixed pile holding assembly 6 arranged on one side of the movable pile holding assembly 1, and the fixed pile holding assembly 6 includes a fixed pile holding frame 61 and a fixed seat 62; the bottom end of the fixed pile holding frame 61 is fixed on the fixed seat 62, and the fixed seat 62 is installed on the periphery of the moon pool of the working platform; the fixed pile holding frame 61 has a second accommodating groove 611 for accommodating the pile leg, and at least one second guide groove 612 is provided in the second accommodating groove 611, and a plurality of bearing groups 613 for reducing sliding friction are embedded in the second guide groove 612.
[0079] As a further preferred embodiment, the hoisting assembly 4 includes a hoisting device mounting frame 41, a pulley member 42, and a steel wire rope 43; the hoisting device mounting frame 41 is installed on the movable end of the movable pile holding assembly 1, the pulley member 42 is installed on the hoisting device mounting frame 41, the steel wire rope 43 is wound around the pulley member 42, and the top hoop assembly equipped with a pile leg connecting hoop can be detachably installed on the steel wire rope.
[0080] The present invention also provides a modular pile leg lengthening installation method, which uses the modular pile leg lengthening device 100 as described above to lengthen the original pile leg, and specifically includes the following steps:
[0081] (1) The initial position of the movable pile holding assembly 1 is in a horizontal state, and the pile legs are fixed in the movable pile holding assembly 1, waiting to be turned over; optionally, the pile legs can be fixed to the movable pile holding assembly by ropes.
[0082] (2) The pile leg connection hoop 3 is mounted on the top hoop assembly 5, and the top hoop assembly 5 with the pile leg connection hoop 3 installed is fixed to the lifting assembly 4 through the wire rope 43, and the wire rope 43 is tightened to tighten the top hoop assembly 5 on one side of the pile leg;
[0083] (3) The turning transmission assembly 2 lifts up the movable pile holding assembly 1, turning the movable pile holding assembly 1 from a horizontal state to a vertical state, and the pile legs are synchronously turned from a horizontal state to a vertical state and aligned with the pile legs 300 located at the lower section;
[0084] (4) The hoisting assembly 4 releases the steel wire rope 43, and lowers the top hoop assembly 5 equipped with the pile leg connecting hoop 3 from the inside of the pile leg to the connection point between two adjacent pile legs;
[0085] (5) The top hoop assembly 5 supports the pile leg connecting hoop 3 on the inner wall of the connecting position of the two pile legs, and fixes the pile leg connecting hoop 3 on the connecting position of the two pile legs through fasteners, thereby fixing the pile leg 200 located at the upper section on the upper part of the original pile leg, thereby lengthening the pile leg.
[0086] (6) Continue to install and extend the pile legs on the lengthened pile legs; the specific process is as follows: a lifting device 400 for adjusting the height of the pile legs is fixedly set at the periphery of the moon pool in advance, and the lifting device vertically transports the pile legs that have been lengthened in step (5) downward to a preset height position; continue to repeat steps (1)-(5) to flip and fix another section of the pile legs on the upper part of the pile legs that have been installed in step (5), and so on, until the entire pile leg meets the length required by various projects. Optionally, the lifting device can be a self-elevating lifting device, and the lifting operation of the pile legs is realized by the mutual engagement of the gears on the lifting device and the teeth on the pile legs.
[0087] The modular pile leg extension installation method of the present invention can increase the length of the original pile leg multiple times on the basis of the original pile leg, which can meet the different depth requirements of the ocean and fully improve the utilization rate of the original pile leg. There is no need to replace the entire pile leg, thereby reducing the replacement cost of the pile leg. The pile leg can also be modularly assembled and extended according to the different depths of the sea area, which reduces the workload and difficulty of extending the pile leg, realizes rapid installation, effectively reduces the construction cost, and improves the economy and applicability of the pile leg.
[0088] The above-mentioned embodiments are only preferred embodiments of the present invention and cannot be used to limit the scope of protection of the present invention. Any non-substantial changes and substitutions made by technicians in this field on the basis of the present invention shall fall within the scope of protection required by the present invention.
Claims
1. A modular pile leg extension device, characterized in that: It includes a movable pile holding assembly for placing pile legs, a flip transmission assembly for flipping the pile legs placed on the movable pile holding assembly from a horizontal state to a vertical state, a pile leg connecting hoop for fixing the connecting positions of two adjacent pile legs to each other, a hoisting assembly for hoisting the pile leg connecting hoop to the connecting position of two adjacent pile legs, and a top hoop assembly for supporting the pile leg connecting hoop on the inner wall of the connecting position of the two pile legs; The flip transmission assembly is in transmission connection with the movable pile holding assembly, driving the movable pile holding assembly to switch between a horizontal state and a vertical state; the hoisting assembly is installed at the top of the movable pile holding assembly, the hoisting assembly is provided with a steel wire rope with a retractable function, the top hoop assembly is fixed at the end of the steel wire rope, and the lifting and lowering adjustment of the top hoop assembly is realized by the retractable hoisting assembly, and the pile leg connecting hoop is installed on the top hoop assembly; When the pile leg is placed horizontally on the movable pile holding assembly, the flip transmission assembly lifts up the movable pile holding assembly, flips the pile leg from a horizontal state to a vertical state and aligns it with the pile leg at the lower section, and the hoisting assembly hoists the pile leg connecting hoop from the inside of the pile leg to the inner walls of the two adjacent pile legs through a steel wire rope, and the top hoop assembly supports the pile leg connecting hoop on the inner wall of the connecting position of the two pile legs.
2. The modular leg extension device according to claim 1, characterized in that: The movable pile holding assembly includes a movable pile holding frame and an articulated seat; the bottom end of the movable pile holding frame is hinged on the articulated seat, and the articulated seat is installed on the periphery of the moon pool of the working platform; the movable pile holding frame has a first accommodating groove for accommodating the pile leg, and at least one first guide groove is provided in the first accommodating groove, and a plurality of bearing groups for reducing sliding friction are embedded in the first guide groove.
3. The modular leg extension device according to claim 1, characterized in that: The overturning transmission assembly comprises a lifting cylinder and a horizontal slide. One end of the lifting cylinder is hinged to one side of the movable pile holding assembly, and the other end is hinged to the horizontal slide. The horizontal slide slides horizontally on the offshore working platform.
4. The modular leg extension device according to claim 1, characterized in that: The pile leg connecting hoop comprises a connecting ring and at least two groups of elastic locking members connected to the outer periphery of the connecting ring; each group of elastic locking members comprises a first elastic locking member and a second elastic locking member symmetrically arranged above and below the first elastic locking member; the first elastic locking member is arranged at the outer periphery of the connecting ring, and is formed by the outer periphery extending upwardly and obliquely along the axial direction of the connecting ring; the second elastic locking member is arranged at the outer periphery of the connecting ring, and is formed by the outer periphery extending downwardly and obliquely along the axial direction of the connecting ring; the ends of each of the first elastic locking members are respectively fixed on the inner side wall of the pile leg located in the upper section, and the ends of each of the second elastic locking members are respectively fixed on the inner side wall of the pile leg located in the lower section, so as to fix the two adjacent pile legs to each other.
5. The modular leg extension device according to claim 4, characterized in that: Each of the first elastic locking members comprises a first outwardly inclined portion and a first upright portion; one end of the first outwardly inclined portion is connected to the outer periphery of the connecting ring, and the other end is connected to the first upright portion; a plurality of first fastening holes are provided on the first upright portion; a locking hole adapted to the position of the first fastening hole is provided at the lower portion of the pile leg located at the upper section, and the first upright portion is locked and fixed to the inner wall of the pile leg located at the upper section by the fastener cooperating with the first fastening hole and the locking hole; Each of the second elastic locking members includes a second outwardly inclined portion and a second upright portion; one end of the second outwardly inclined portion is connected to the outer periphery of the connecting ring, and the other end is connected to the second upright portion; a plurality of second fastening holes are provided on the second upright portion; the upper portion of the pile leg located in the lower section is provided with a locking hole adapted to the position of the second fastening hole, and the second upright portion is locked and fixed to the inner wall of the pile leg located in the lower section by means of a fastener cooperating with the second fastening hole and the locking hole.
6. The modular leg extension device according to claim 5, characterized in that: The pile leg located at the lower section has a concave limiting groove matched with the shape of the second upright part at its upper part, and the second fastening hole is arranged in the concave limiting groove; the pile leg located at the upper section has a concave limiting groove matched with the shape of the first upright part at its lower part, and the first fastening hole is arranged in the concave limiting groove; At least one limit block is protruding outward from the outer periphery of the connecting ring, and the inner walls of the pile legs located at the upper section and the pile legs located at the lower section are recessed with axial guide grooves that match the shape of the limit block.
7. The modular leg extension device according to claim 4, characterized in that: The top hoop assembly includes a limiting seat for installing the connecting ring and a telescopic top tightening member for pressing the elastic locking member against the inner wall of the pile leg; the connecting ring is detachably mounted on the limiting seat, the telescopic top tightening member has a fan-shaped top tightening block, and the telescopic top tightening member is mounted on the limiting seat, and when the telescopic top tightening member performs horizontal extension movement, the fan-shaped top tightening block is driven to open the elastic locking member outward, so that each group of elastic locking members is pressed against the inner wall of the pile leg.
8. The modular leg extension device according to claim 7, characterized in that: The modular pile leg extension device also includes a fixed pile holding assembly arranged on one side of the movable pile holding assembly, and the fixed pile holding assembly includes a fixed pile holding frame and a fixed seat; the bottom end of the fixed pile holding frame is fixed to the fixed seat, and the fixed seat is installed on the periphery of the moon pool of the working platform; the fixed pile holding frame has a second accommodating groove for accommodating the pile leg, and at least one second guide groove is provided in the second accommodating groove, and a plurality of bearing groups for reducing sliding friction are embedded in the second guide groove.
9. A modular pile leg extension installation method, characterized in that: The modular pile leg lengthening device according to any one of claims 1 to 8 is used to lengthen the original pile leg, which specifically comprises the following steps: (1) The initial position of the movable pile holding assembly is in a horizontal state, and the pile legs are fixed in the movable pile holding assembly, waiting to be turned over; (2) Sleeve the pile leg connection hoop onto the top hoop assembly, fix the top hoop assembly with the pile leg connection hoop onto the lifting assembly via a steel wire rope, tighten the steel wire rope, and tighten the top hoop assembly onto one side of the pile leg; (3) The turning transmission assembly lifts up the movable pile holding assembly, turning the movable pile holding assembly from a horizontal state to a vertical state, and the pile legs are synchronously turned from a horizontal state to a vertical state and aligned with the pile legs located at the lower section; (4) The hoisting assembly releases the wire rope and lowers the top hoop assembly equipped with the pile leg connecting hoop from the inside of the pile leg to the connection between two adjacent pile legs; (5) The top hoop assembly supports the pile leg connecting hoop on the inner wall of the connecting position of the two pile legs, and fixes the pile leg connecting hoop on the connecting position of the two pile legs through fasteners, thereby fixing the pile leg located at the upper section on the upper part of the original pile leg, thereby lengthening the pile leg.
10. A modular pile leg lengthening installation method as claimed in claim 9, characterized in that: The method further includes step (6) of continuing to install and extend pile legs on the lengthened pile legs. The specific process is as follows: a lifting device for adjusting the height of the pile legs is pre-arranged at the periphery of the moon pool, and the lifting device vertically transports the pile legs that have been lengthened in step (5) downward to a preset height position; and steps (1) to (5) are continuously repeated to flip and fix another section of the pile legs on the upper part of the pile legs that have been installed in step (5), and so on, until the entire pile leg meets the length required for various projects.