Decorative mortar as well as preparation method and construction method of decorative mortar

By optimizing the raw material ratio of decorative mortar and using components such as silicate cement, the problems of cracking and peeling of traditional decorative mortar have been solved, the adhesion and weather resistance have been improved, and the service life has been extended.

CN119038930AInactive Publication Date: 2024-11-29JIANGXI TIANTAI NEW MATERIAL TECHNOLOGY CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411235595.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-04
Publication Date
2024-11-29
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Traditional decorative mortar is prone to cracking and peeling under the influence of the external environment, resulting in poor weather resistance.

Method used

By optimizing the raw material ratio, using components such as silicate cement, heavy calcium carbonate powder, quartz sand, metakaolin, HPMC cellulose ether, and redispersible latex powder, combined with sulfoaluminate cement, starch ether, and water-repellent agent, the bonding strength, compressive strength, and weather resistance are improved.

Benefits of technology

It enhances the adhesion, compressive strength, and weather resistance of decorative mortar, reduces the risk of cracking, and extends its service life.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119038930A_ABST
    Figure CN119038930A_ABST
Patent Text Reader

Abstract

The invention is applicable to the technical field of decoration, and particularly relates to decorative mortar, a preparation method and a construction method of the decorative mortar, the decorative mortar comprises the following raw materials: 82.1-89.5% of a basic construction raw material, 2.2-7.2% of a performance regulator, 1-11.2% of a functional additive and 0.2-3% of inorganic toner; the basic construction raw materials comprise 20 to 23 percent of Portland cement, 46.1 to 48.5 percent of 325-mesh heavy calcium powder and 16 to 18 percent of 80 to 120-mesh quartz sand; the performance regulator is prepared from 1 to 3 percent of 1000-mesh metakaolin, 0.1 to 0.2 percent of HPMC (Hydroxy Propyl Methyl Cellulose) cellulose ether, 1 to 3 percent of redispersible latex powder and 0.1 to 1 percent of bentonite; the functional additive is prepared from 0.55 to 10 percent of sulphoaluminate cement, 0.15 to 0.5 percent of starch ether, 0.05 to 0.2 percent of alkali inhibitor and 0.25 to 0.5 percent of water repellent; the decorative mortar construction method comprises the following steps: constructing decorative mortar on a required construction area to form a decorative mortar layer; a silica gel film is laid on the decorative mortar layer, and the surface of the silica gel film is extruded to be flat; and after the decorative mortar layer is solidified, the silica gel film is removed. The decorative mortar provided by the invention can solve the problems of cracking, falling, poor weather resistance and the like in the traditional decorative mortar.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application belongs to the field of decoration technology, and in particular relates to a decorative mortar, a decorative mortar preparation method and a construction method. Background Art

[0002] Decorative mortar is a special building material, mainly used for wall decoration and protection. It is usually mixed with cement, fine aggregate, pigment, additives and other materials, and has good physical properties for decorative effect. Common types of decorative mortar include real stone paint, texture paint, artistic paint, etc.

[0003] After the traditional decorative mortar prepared in the related art is applied to the wall and / or the ground, it is prone to cracking and falling off under the influence of the external environment (such as light temperature, humidity or corrosion conditions, etc.), resulting in poor weather resistance of the decorative mortar. Summary of the invention

[0004] The embodiments of the present application provide a decorative mortar, a preparation method of the decorative mortar and a construction method, which can solve the problem that the traditional decorative mortar is easy to crack and fall off, resulting in poor weather resistance of the decorative mortar.

[0005] In a first aspect, an embodiment of the present application provides a decorative mortar, wherein the raw materials of the decorative mortar include the following components by weight:

[0006] Basic building materials 82.1-89.5%;

[0007] Performance regulator 2.2-7.2%;

[0008] Functional additives 1~11.2%;

[0009] Inorganic color powder 0.2-3%;

[0010] Wherein, the basic building materials include the following components:

[0011] Portland cement 20-23%;

[0012] 325 mesh heavy calcium powder 46.1~48.5%;

[0013] 80-120 mesh quartz sand 16-18%;

[0014] The performance moderator comprises the following components:

[0015] 1000 mesh metakaolin 1-3%;

[0016] HPMC cellulose ether 0.1-0.2%;

[0017] Redispersible latex powder 1-3%;

[0018] Bentonite 0.1-1%;

[0019] The functional additives include the following components:

[0020] Sulphoaluminate cement 0.55-10%;

[0021] Starch ether 0.15-0.5%;

[0022] Alkali inhibitor 0.05-0.2%;

[0023] Water repellent 0.25~0.5%.

[0024] The above technical solutions in the embodiments of the present application have at least the following technical effects:

[0025] The decorative mortar provided in the present application improves the construction performance of the decorative mortar by means of the basic construction raw material ratio. Portland cement is used as the main bonding material in combination with 325 mesh heavy calcium powder and 80-120 mesh quartz sand, which not only gives the mortar good bonding force and compressive strength and reduces the cracking of the decorative mortar, but also optimizes the construction performance and surface texture of the mortar through the reasonable matching of particle sizes. The addition of performance regulator further improves the comprehensive performance of mortar. The addition of 1000 mesh metakaolin and HPMC cellulose ether can effectively improve the shedding of mortar and enhance the weather resistance of the final product. The use of redispersible latex powder not only improves the bonding strength of mortar, but also gives it a certain flexibility, thereby effectively preventing cracks and shedding. The addition of functional additive sulphoaluminate cement enhances the anti-seepage performance of mortar and improves its stability in a humid environment. Powder ether as a thickener helps to increase the viscosity of mortar and improve its construction performance. The use of alkali inhibitor and hydrophobic agent effectively prevents the occurrence of alkali efflux, and gives mortar good waterproof performance, extending the service life of decorative mortar. Finally, the addition of inorganic color powder meets the needs of different styles. By accurately controlling the ratio of each component, the decorative mortar of this application not only has excellent decorative effect, but also has good weather resistance, durability and environmental protection.

[0026] In a second aspect, an embodiment of the present application provides a method for preparing a decorative mortar, which is used to prepare the decorative mortar of any embodiment of the first aspect above, and the method for preparing the decorative mortar comprises:

[0027] Add silicate cement into the mixer, then add 325 mesh heavy calcium powder, and continue stirring for 5 minutes at the preset stirring speed;

[0028] 80-120 mesh quartz sand is gradually added into the mixer, and stirred for 10 minutes according to a preset stirring speed to form a mortar mixture, and then 1000 mesh metakaolin, HPMC cellulose ether, redispersible latex powder and bentonite are added in sequence for stirring; wherein, after the mortar mixture is formed, each raw material is stirred for 5 minutes;

[0029] Add sulphoaluminate cement, starch ether, alkali inhibitor and water repellent into the mixer in sequence; stir for 10 minutes after adding each raw material;

[0030] The inorganic color powder is added into the mixer and stirred for 5-10 minutes. After all components are added, the mixture is stirred for 20 minutes to obtain the decorative mortar.

[0031] The above technical solutions in the embodiments of the present application have at least the following technical effects:

[0032] The decorative mortar preparation method provided by the present application comprises the following steps: firstly adding silicate cement into a mixer, then adding 325 mesh heavy calcium powder, and continuously stirring for 5 minutes according to a preset stirring speed, which can improve the density and compressive strength of the mortar. Meanwhile, the addition of heavy calcium powder helps to improve the construction performance of the mortar, making it easier to spread and level. Then, 80-120 mesh quartz sand is gradually added into the mixer, and stirred for 10 minutes according to a preset stirring speed. After forming a mortar mixture, 1000 mesh metakaolin, HPMC cellulose ether, redispersible latex powder and bentonite are sequentially added and stirred. After forming the mortar mixture, each raw material is stirred for 5 minutes, which can fully combine the quartz sand with the cement matrix. And enhance the wear resistance and crack resistance of the mortar. At the same time, the particle size distribution of quartz sand helps to form a dense mortar structure. Then add sulphoaluminate cement, starch ether, alkali inhibitor and water repellent to the mixer in sequence; wherein, after each raw material is added, stir for 10 minutes, which can further improve the adhesion, flexibility and durability of the mortar. Finally, add inorganic color powder to the mixer and stir for 5-10 minutes. After all components are added, stir for 20 minutes to obtain decorative mortar. Stirring for a long time can make the color evenly distributed, thereby giving the decorative mortar a beautiful appearance. It can ensure that various materials are fully mixed, and finally form a homogeneous decorative mortar, thereby improving the overall performance and decorative effect of the decorative mortar.

[0033] In a third aspect, an embodiment of the present application provides a decorative mortar construction method, which is used to construct the decorative mortar of any embodiment of the first aspect or the decorative mortar prepared by the decorative mortar preparation method of any embodiment of the second aspect, and the decorative mortar construction method comprises:

[0034] Applying decorative mortar on a desired construction area to form a decorative mortar layer; wherein the construction area includes a wall surface and / or a ground surface;

[0035] Laying a silicone film on the decorative mortar layer, and squeezing the surface of the silicone film flat;

[0036] When the decorative mortar layer is solidified, the silicone film is removed.

[0037] The above technical solutions in the embodiments of the present application have at least the following technical effects:

[0038] The decorative mortar preparation method provided in the present application comprises the following steps: first, applying the decorative mortar on the required construction area to form a decorative mortar layer; since the silicone film has good flexibility, construction workers can easily adhere it to surfaces of various complex shapes, thereby greatly shortening the construction time; and by laying the silicone film on the decorative mortar layer and squeezing the surface of the silicone film flat, the smoothness and uniformity of the surface of the decorative mortar layer can be improved, which not only improves the overall aesthetics of the decoration, but also reduces subsequent polishing and repair work, thereby reducing construction costs; finally, when the decorative mortar layer is solidified, the silicone film is removed to present a delicate and uniform texture, which not only improves the overall aesthetics of the wall, but also enhances its durability. BRIEF DESCRIPTION OF THE DRAWINGS

[0039] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0040] Figure 1 It is a schematic diagram of a process for preparing decorative mortar provided in one embodiment of the present application;

[0041] Figure 2 It is a schematic diagram of the process of a decorative mortar construction method provided in one embodiment of the present application;

[0042] Figure 3 It is a schematic diagram of the process before step S100B in the decorative mortar construction method provided in one embodiment of the present application;

[0043] Figure 4 It is a schematic diagram of the implementation process of step S200C in the decorative mortar construction method provided in one embodiment of the present application;

[0044] Figure 5 It is a schematic diagram of the implementation process of step S300C in the decorative mortar construction method provided in one embodiment of the present application;

[0045] Figure 6It is a schematic diagram of the implementation process of step S380C in the decorative mortar construction method provided in one embodiment of the present application;

[0046] Figure 7 It is a schematic diagram of the implementation process of step S382C in the decorative mortar construction method provided in one embodiment of the present application;

[0047] Figure 8 It is a structural schematic diagram of a decorative mortar construction system provided in an embodiment of the present application;

[0048] Fig. 9 It is a structural schematic diagram of a control device for decorative mortar construction equipment provided in an embodiment of the present application. DETAILED DESCRIPTION

[0049] In the following description, specific details such as specific system structures, technologies, etc. are provided for the purpose of illustration rather than limitation, so as to provide a thorough understanding of the embodiments of the present application. However, it should be clear to those skilled in the art that the present application may also be implemented in other embodiments without these specific details. In other cases, detailed descriptions of well-known systems, devices, circuits, and methods are omitted to prevent unnecessary details from obstructing the description of the present application.

[0050] It should be understood that when used in the present specification and the appended claims, the term "comprising" indicates the presence of described features, wholes, steps, operations, elements and / or components, but does not exclude the presence or addition of one or more other features, wholes, steps, operations, elements, components and / or combinations thereof.

[0051] It should also be understood that the term “and / or” used in the specification and appended claims refers to any and all possible combinations of one or more of the associated listed items, and includes these combinations.

[0052] As used in the specification and appended claims of this application, the term "if" can be interpreted as "when" or "uponce" or "in response to determining" or "in response to detecting", depending on the context. Similarly, the phrase "if it is determined" or "if [described condition or event] is detected" can be interpreted as meaning "uponce it is determined" or "in response to determining" or "uponce [described condition or event] is detected" or "in response to detecting [described condition or event]", depending on the context.

[0053] In addition, in the description of the present application specification and the appended claims, the terms "first", "second", "third", etc. are only used to distinguish the descriptions and cannot be understood as indicating or implying relative importance.

[0054] References to "one embodiment" or "some embodiments" etc. described in the specification of this application mean that one or more embodiments of the present application include specific features, structures or characteristics described in conjunction with the embodiment. Therefore, the statements "in one embodiment", "in some embodiments", "in some other embodiments", "in some other embodiments", etc. that appear in different places in this specification do not necessarily refer to the same embodiment, but mean "one or more but not all embodiments", unless otherwise specifically emphasized in other ways. The terms "including", "comprising", "having" and their variations all mean "including but not limited to", unless otherwise specifically emphasized in other ways.

[0055] Decorative mortar is a special building material, mainly used for wall decoration and protection. It is usually mixed with cement, fine aggregate, pigment, additives and other materials, and has good physical properties for decorative effect. Common types of decorative mortar include real stone paint, texture paint, artistic paint, etc.

[0056] After the traditional decorative mortar prepared in the related art is applied to the wall and / or the ground, it is prone to cracking and falling off under the influence of the external environment (such as light temperature, humidity or corrosion conditions, etc.), resulting in poor weather resistance of the decorative mortar.

[0057] Based on this, in order to solve the problem that the traditional decorative mortar is easy to crack and fall off, resulting in poor weather resistance of the decorative mortar, the embodiment of the present application provides the following solution.

[0058] In a first aspect, an embodiment of the present application provides a decorative mortar, wherein the raw materials of the decorative mortar include 82.1-89.5% of basic building raw materials, 2.2-7.2% of performance regulator, 1-11.2% of functional additives and 0.2-3% of inorganic color powder, calculated by weight 100%, wherein:

[0059] The raw materials for foundation construction include 20-23% of silicate cement, 46.1-48.5% of 325-mesh heavy calcium powder and 16-18% of 80-120-mesh quartz sand.

[0060] The performance regulator comprises 1-3% of 1000-mesh metakaolin, 0.1-0.2% of HPMC cellulose ether, 1-3% of redispersible latex powder and 0.1-1% of bentonite.

[0061] The functional additives include 0.55-10% of sulphoaluminate cement, 0.15-0.5% of starch ether, 0.05-0.2% of alkali inhibitor and 0.25-0.5% of water repellent.

[0062] It can be understood that Portland cement is a cementitious material that provides strength and adhesion to ensure that the mortar can be firmly attached to the surface of various substrates. 325 mesh heavy calcium powder is a calcium carbonate powder that helps to improve the surface texture and make the effect more delicate and beautiful. 80-120 mesh quartz sand is a mineral filler with moderate coarseness and fineness, which can increase the mechanical strength of the mortar and provide a certain decorative effect, giving the surface a certain texture and three-dimensional sense. 1000 mesh metakaolin is a mineral powder that can improve the adhesion and crack resistance of the mortar. HPMC cellulose ether is a water-soluble polymer. HPMC cellulose ether can improve the construction performance of the mortar, make it have better adhesion and ductility, and help reduce the shrinkage and cracking of the mortar. Redispersible latex powder is a powder dried from a polymer emulsion, which can improve the bonding strength and durability of the mortar, give the decorative mortar a certain elasticity, and can adapt to the slight deformation of the substrate. Bentonite is a clay mineral that can improve the water retention and construction performance of the mortar, and has a certain thickening effect, which is easy to apply and polish. Sulphoaluminate cement is a fast-hardening cement that can cure quickly, shorten the construction period, and improve the durability and impermeability of the mortar. Starch ether is a water-soluble high molecular polymer that can improve the construction performance of the mortar and help reduce the shrinkage and cracking of the mortar. Alkali inhibitor is a chemical substance that can inhibit the precipitation of alkaline substances, which can improve the durability and aesthetics of the mortar. Water repellent is a chemical substance that can make the surface of the material hydrophobic, which can improve the waterproof performance of the mortar, make it more weather-resistant and anti-pollution, and extend the service life of the decorative surface.

[0063] The decorative mortar provided in the present application improves the construction performance of the decorative mortar by means of the basic construction raw material ratio. Portland cement is used as the main bonding material in combination with 325 mesh heavy calcium powder and 80-120 mesh quartz sand, which not only gives the mortar good bonding force and compressive strength and reduces the cracking of the decorative mortar, but also optimizes the construction performance and surface texture of the mortar through the reasonable matching of particle sizes. The addition of performance regulator further improves the comprehensive performance of mortar. The addition of 1000 mesh metakaolin and HPMC cellulose ether can effectively improve the shedding of mortar and enhance the weather resistance of the final product. The use of redispersible latex powder not only improves the bonding strength of mortar, but also gives it a certain flexibility, thereby effectively preventing cracks and shedding. The addition of functional additive sulphoaluminate cement enhances the anti-seepage performance of mortar and improves its stability in a humid environment. Powder ether as a thickener helps to increase the viscosity of mortar and improve its construction performance. The use of alkali inhibitor and hydrophobic agent effectively prevents the occurrence of alkali efflux, and gives mortar good waterproof performance, extending the service life of decorative mortar. Finally, the addition of inorganic color powder meets the needs of different styles. By accurately controlling the ratio of each component, the decorative mortar of this application not only has excellent decorative effect, but also has good weather resistance, durability and environmental protection.

[0064] In the second aspect, the embodiment of the present application provides a decorative mortar construction method, in which silicate cement is first added to a mixer, and then 325 mesh heavy calcium powder is added, and stirring is continued for 5 minutes according to a preset stirring speed, which can improve the density and compressive strength of the mortar. At the same time, the addition of heavy calcium powder helps to improve the construction performance of the mortar, making it easier to apply and level. 80-120 mesh quartz sand is gradually added to the mixer, and stirred for 10 minutes according to a preset stirring speed. After the mortar mixture is formed, 1000 mesh kaolin, HPMC cellulose ether, redispersible latex powder and bentonite are added in sequence for stirring; wherein, after the mortar mixture is formed, each raw material is stirred for 5 minutes, so that the quartz sand and cement can be mixed. The matrix is ​​fully combined, thereby enhancing the wear resistance and crack resistance of the mortar. At the same time, the particle size distribution of quartz sand helps to form a dense mortar structure. Then sulphoaluminate cement, starch ether, alkali inhibitor and water repellent are added to the mixer in sequence; wherein, after each raw material is added, it is stirred for 10 minutes, which can further improve the adhesion, flexibility and durability of the mortar. Finally, the inorganic color powder is added to the mixer and stirred for 5-10 minutes. After all components are added, stir for 20 minutes to obtain decorative mortar. Stirring for a long time can make the color evenly distributed, thereby giving the decorative mortar a beautiful appearance. It can ensure that various materials are fully mixed, and finally form a homogeneous decorative mortar, thereby improving the overall performance and decorative effect of the decorative mortar.

[0065] In order to better understand the decorative mortar preparation method provided in the embodiment of the present application, the specific implementation process of the decorative mortar preparation method provided in the embodiment of the present application is exemplarily introduced below.

[0066] Figure 1 A schematic flow chart of a method for preparing decorative mortar provided in an embodiment of the present application is shown, and the method for preparing decorative mortar comprises:

[0067] S100A, add silicate cement into the mixer, then add 325 mesh heavy calcium powder, and continue stirring for 5 minutes according to the preset stirring speed.

[0068] It can be understood that a mixer is a machine for mixing raw materials, such as a horizontal mixer, a vertical mixer or a twin-shaft forced mixer, but is not limited to this; the preset mixing speed is a mixing speed determined according to the addition of different raw materials. For example, considering the physical and chemical properties of each raw material, the basic building raw materials usually have a higher viscosity and particle size, so the required mixing speed is determined to avoid generating too many bubbles and destroying the particle structure. The mixing speed can be set at 40-50±4 rpm, and the mixing speed of the performance regulator is usually set at 50-70±4 rpm, which can quickly achieve uniform mixing without destroying its activity; in this embodiment, rpm can be used to apply the preset mixing speed, and torque can also be used, but is not limited to this.

[0069] First, keep the mixer clean and dry, without residue or moisture, to avoid affecting the quality of the decorative mortar to be mixed later. Then, according to the preset ratio, slowly pour the silicate cement into the mixer, and turn on the mixer to stir, so that the cement is evenly spread in the mixer to avoid caking. While keeping the mixer running, gradually add the screened 325 mesh heavy calcium powder. The selection of 325 mesh heavy calcium powder can improve the fineness and make it more uniform, which helps to mix better with cement and improve the overall performance of the mortar. During the addition process, the addition speed can be appropriately adjusted by observing the feed port or stirring of the mixer to ensure that the two materials can be evenly mixed. After all the materials are added, the speed of the mixer is gradually adjusted according to the actual situation to ensure that the materials can fully react and mix. The stirring time is set to 5 minutes, 40-50±2 rpm. This time can be obtained through multiple experiments and practical application experience, which can ensure that the chemical reaction between silicate cement and heavy calcium powder is fully carried out, while avoiding the degradation of mortar performance caused by excessive stirring. During the mixing process, check the uniformity and consistency of the mortar regularly, add appropriate amount of water or adjust the mixing speed to achieve the ideal mixing effect. After the mixing is completed, turn off the mixer and wait for the mortar to stand for a while so that its internal reaction is more complete and lays the foundation for the next step.

[0070] S200A, gradually add 80-120 mesh quartz sand into the mixer, stir for 10 minutes according to the preset stirring speed, and after forming a mortar mixture, add 1000 mesh metakaolin, HPMC cellulose ether, redispersible latex powder and bentonite in sequence for stirring; wherein, after forming the mortar mixture, each raw material added is stirred for 5 minutes.

[0071] Exemplarily, after the mortar base material in step S100A has been fully mixed and left to stand for an appropriate time (which can be 30 minutes, 60 minutes or the standing time is determined according to the actual total amount), quartz sand is prepared to be added to the mixer, and the particle size range of quartz sand is between 80-120 mesh, which not only improves the strength and durability of the mortar, but also contributes to its smoothness and surface texture during construction. When adding, a gradual addition method can be adopted, that is, the quartz sand is slowly poured into the mixer in batches, while the mixer is kept running at a preset medium or high speed to ensure that the quartz sand can be evenly dispersed and fully integrated into the mortar base material. After all the quartz sand is added and stirred at 47-60±2 rpm for about 5 minutes, the uniformity and fluidity of the mortar mixture are checked. After confirmation, an appropriate amount of 1000 mesh metakaolin is slowly added to the mixer. The metakaolin can significantly improve the strength and durability of the mortar with its high activity and good adhesion. After adding, continue stirring for 5 minutes, 50-70±2 rpm, to fully blend the metakaolin with the mortar mixture, and then add HPMC cellulose ether in turn. Also pay attention to controlling the addition speed, and continue stirring for 5 minutes, 55-70±4 rpm after adding, to ensure that it is evenly dispersed, and add redispersible latex powder. The latex powder can be redispersed into an emulsion in water, which can enhance the adhesion and flexibility of the mortar and improve the weather resistance and crack resistance of the mortar. After adding the latex powder, continue stirring for 5 minutes, 60-70±2 rpm, until it is completely dissolved and evenly distributed in the mortar. Finally, add bentonite and continue stirring for 5 minutes, 65-70±2 rpm, to ensure that it is fully mixed with the mortar mixture.

[0072] S300A, add sulphoaluminate cement, starch ether, alkali inhibitor and water repellent into the mixer in sequence; wherein each raw material is stirred for 10 minutes after being added.

[0073] Exemplarily, sulphoaluminate cement is slowly poured into a mixer according to the ratio, and stirring is started after the sulphoaluminate cement is evenly spread on the bottom of the mixer to prevent cement splashing or caking. During the stirring process, starch ether is gradually added. Starch ether, as a natural thickener, can improve the adhesion and construction performance of the mortar, and at the same time help control the consistency and fluidity of the mortar. After adding starch ether, continue stirring for 10 minutes, 40-60 rpm to ensure that it is fully mixed with sulphoaluminate cement. Subsequently, alkali inhibitor and water repellent are added in sequence. The role of the alkali inhibitor is to reduce the alkaline substances produced during the hardening process of the mortar, thereby avoiding alkali-aggregate reaction and extending the life of the decorative surface layer. After the water repellent is added, continue stirring for 10 minutes, 45-60 rpm to ensure that it is evenly dispersed and fully reacted.

[0074] S400A, add the inorganic color powder into the mixer and stir for 5-10 minutes. After all the components are added, stir for 20 minutes to obtain the decorative mortar.

[0075] Exemplarily, inorganic color powder is weighed according to the formula of the desired color. Inorganic color powder is selected for its weather resistance, light resistance and chemical stability, which can improve the color durability of decorative mortar during long-term use. The weighed inorganic color powder is slowly poured into the mixer for stirring, so that the inorganic color powder is evenly dispersed in the mortar to avoid color spots or color differences. During the stirring process, check the color change of the decorative mortar to ensure that the color powder and the mortar are evenly mixed. Usually, the stirring time is controlled between 5 and 10 minutes, 20-40±4 rpm, and the specific time can be adjusted according to the type of color powder and the depth of color. After the inorganic color powder and mortar are evenly mixed, add them to the basic mortar mixture in turn and mix them thoroughly with the inorganic color powder. After all components are added, continue stirring for 20 minutes, 60-80±4 rpm, to ensure that the newly added basic mortar mixture is fully integrated with the mortar with color powder to form a uniform decorative mortar.

[0076] On the third aspect, an embodiment of the present application provides a decorative mortar construction method, in which the decorative mortar is first constructed on the required construction area to form a decorative mortar layer. Since the silicone film has good flexibility, construction workers can easily stick it on surfaces of various complex shapes, thereby greatly shortening the construction time. By laying the silicone film on the decorative mortar layer and squeezing the surface of the silicone film flat, the smoothness and uniformity of the surface of the decorative mortar layer can be improved, which not only improves the overall aesthetics of the decoration, but also reduces subsequent polishing and repair work, thereby reducing construction costs; finally, when the decorative mortar layer is solidified, the silicone film is removed to present a delicate and uniform texture, which not only improves the overall aesthetics of the wall, but also enhances its durability.

[0077] Part or all of the steps of the decorative mortar construction method provided in the embodiment of the present application can be applied to the decorative mortar construction equipment, such as steps S100C, S200C, and S300C below. In this case, the decorative mortar construction equipment is the execution subject of the decorative mortar construction method provided in the embodiment of the present application. The embodiment of the present application does not impose any restrictions on the specific type of the decorative mortar construction equipment. Of course, in addition to being completed by equipment, some steps of the decorative mortar construction method can also be completed manually, such as steps S100B, S200B, and S300B below.

[0078] For example, the decorative mortar construction equipment may include a control device and a construction device; the control device and the construction device are communicatively connected. The construction device may be any device capable of applying decorative mortar (e.g., scraping, spraying, etc.) to the construction area, and may adopt a device capable of scraping or spraying mortar on the wall in the prior art. For example, the construction device may include a mixer driven by an electric motor, a mortar applicator, and a delivery pump. The mixer driven by an electric motor is a machine for mixing raw materials so that the raw materials form a uniform decorative mortar, such as a vertical mixer and a horizontal mixer, but not limited thereto. The mortar applicator is a machine for spraying mortar uniformly onto a wall or ground, such as a screw sprayer, a piston sprayer, or a pneumatic sprayer; the delivery pump is a mortar applicator for delivering the decorative mortar mixed by the mixer to the construction area, such as a plunger pump or a screw pump. The control device may be a tablet computer, a laptop computer, a netbook, a desktop computer, a smart large screen, a computer, a laptop computer, a handheld computing device, and the like.

[0079] In order to better understand the decorative mortar construction method provided in the embodiment of the present application, the specific implementation process of the decorative mortar construction method provided in the embodiment of the present application is exemplarily introduced below.

[0080] Figure 2 A schematic flow chart of a decorative mortar construction method provided in an embodiment of the present application is shown, and the decorative mortar construction method comprises:

[0081] S100B, applying decorative mortar on a desired construction area to form a decorative mortar layer; wherein the construction area includes a wall surface and / or a ground surface.

[0082] For example, determine the construction surface. Before construction, make sure that the wall or floor is clean, flat and oil-free. Then stir the prepared decorative mortar to a uniform paste without particles. Use an electric stirrer to ensure uniform mixing. Use a scraper or trowel to evenly apply the mixed decorative mortar on the construction area. According to actual construction requirements, it can be applied all at once or in layers to form a decorative mortar layer.

[0083] S200B, lay the silicone film on the decorative mortar layer and squeeze the surface of the silicone film flat.

[0084] For example, select a suitable silicone film with corresponding color, thickness and transparency according to the actual decoration design requirements. According to the size of the construction area, make the silicone film slightly larger than the construction area to facilitate paving. Place the cut silicone film gently on the decorative mortar layer, press and flatten it evenly from the center to the surrounding areas. The silicone film fits tightly on the mortar layer to make the surface of the silicone film flat and smooth.

[0085] In a possible implementation, the thickness of the silicone mold is 1 mm-2 mm.

[0086] For example, when selecting a silicone film, an accurate thickness measuring tool or an accurate automated tool can be used to accurately select the thickness of the silicone mold to ensure that the thickness of each silicone film is between 1 mm and 2 mm to meet the precise requirements of the decorative design.

[0087] Optionally, the silicone film is laid on the surface of the decorative mortar layer and is provided with a texture structure.

[0088] For example, when preparing silicone film, products with specific texture structures are determined to match the visual effect of the decorative design; the texture can be natural stone texture, wood grain or other patterns that the designer wants to present to enhance the aesthetics and texture of the decorative surface. Before laying the silicone film, check the direction and alignment of the texture to ensure that the texture is visually coherent and meets the design requirements. After the silicone film is laid, specific tools or methods can be used to enhance the texture effect. For example, a texture roller can be used to gently roll the surface of the silicone film to make the texture more prominent and three-dimensional, thereby enhancing the decorative effect.

[0089] Such an arrangement can improve the precise arrangement and presentation of the texture structure of the silicone film on the decorative mortar layer, thereby adding a unique visual effect and texture to the decorative surface and improving the overall decorative quality.

[0090] S300B, when the decorative mortar layer solidifies, remove the silicone film.

[0091] Exemplarily, confirm the bonding strength of the silicone film. Before removing the silicone film, first check the bonding between the silicone film and the decorative mortar layer. Make sure that the silicone film has been fully cured and tightly bonded to the mortar layer to avoid damage to the decorative mortar layer during the demolding process. Slowly and evenly peel off the silicone film along the surface of the decorative mortar layer. During the peeling process, maintain a steady force to avoid tearing too quickly, which may cause damage to the silicone film or the decorative mortar layer. If there are minor flaws or damage that may occur during the demolding process, such as slight scratches or dents, use repair materials that match the decorative mortar layer to repair them so that the repair area has a smooth transition with the surrounding surface without obvious marks.

[0092] In one possible implementation, see Figure 3 , S100B, before applying the decorative mortar on the desired construction area to form a decorative mortar layer, the decorative mortar construction method further includes;

[0093] S100C, obtaining position information of the construction equipment in the construction area; wherein the position information is used to reflect the specific position of the construction equipment in the construction area.

[0094] For example, laser scanning technology can be used to create an accurate three-dimensional model by setting up laser scanners around the construction area, and the position of construction equipment in the model can be monitored and recorded in real time. Laser scanning technology can provide high-precision location information, especially for complex or large construction areas; wireless radio frequency identification technology can be used to obtain location information. RFID tags are installed on construction equipment, and RFID readers are set up in the construction area. When the equipment enters the reader's sensing range, the reader can identify the tag and record the location information of the equipment; the location information of construction equipment on the construction area can also be obtained manually.

[0095] With such arrangement, through the above-mentioned various technical means, the position information of the construction equipment in the construction area can be effectively obtained, thereby improving the accuracy and efficiency of the decorative mortar construction.

[0096] S200C, performing feature recognition on the construction area to obtain feature information; wherein the feature information is used to reflect the surface conditions of the wall and / or ground that needs to be constructed.

[0097] It is understood that feature recognition can be achieved by using high-resolution image capture devices, such as high-definition cameras or laser scanners. First, a comprehensive image acquisition is performed on the construction area to capture the detailed surface conditions of the wall and / or the ground. The collected images are analyzed using computer vision technology to identify different surface features, such as cracks, unevenness, stains, wet areas, etc. The image data is then processed using a deep learning algorithm to identify and classify various surface features. Multispectral imaging technology can also be used to obtain feature information of the construction area. Multispectral imaging can capture spectral information of different wavelengths, thereby revealing the chemical composition and physical state of the material and obtaining feature information on the construction area.

[0098] In one possible implementation, see Figure 4 , S200C, performs feature recognition on the construction area and obtains feature information, including:

[0099] S210C, obtaining first preset information and second preset information; wherein the first preset information is used to indicate a preset numerical range of flatness, and the second preset information is used to indicate a preset numerical range of concavity.

[0100] Exemplarily, the first preset information and the second preset information can be obtained by using a laser flatness meter to scan the walls and the ground in the construction area to obtain accurate surface flatness data. The laser flatness meter can emit a laser beam and receive a reflected signal, and generate high-precision flatness data by calculating the contact point between the laser beam and the surface. Ultrasonic ranging technology can be used. The ultrasonic sensor emits high-frequency sound waves and receives its reflected signal. The surface concavity and convexity are determined by measuring the round-trip time of the sound waves, and accurate concavity and convexity data are provided; in order to further improve the accuracy and reliability of the data, the data obtained by the laser flatness meter and the ultrasonic ranging technology can be analyzed. The software uses the least squares method to fit to determine the preset numerical ranges of the flatness and concavity of the wall and the ground; in this embodiment, the preset numerical range of the flatness indicated by the first preset information and the preset numerical range of the concavity indicated by the second preset information are variable, and the preset numerical range of the flatness and the preset numerical range of the concavity are different according to the actual wall and / or ground. Each time a different wall and / or ground is constructed, the status of the wall and / or ground this time will be recorded or uploaded to the database (which can be a record of the situation information of the historical construction of the wall and / or ground), so that direct matching can be performed during the subsequent construction of other walls and / or ground, which can save time.

[0101] S220C, identify and divide the construction area according to the first preset information. If the construction area includes one or more sub-areas that meet the first preset information, obtain the corresponding one or more first surface frame information; wherein the first surface frame information is used to indicate an identification circle, and the identification circle has a sub-area that meets the first preset information.

[0102] Exemplarily, the process of identifying and dividing the construction area by the first preset information uses image processing technology and machine learning algorithms. First, a high-resolution image capture device, such as a high-definition camera, is used to obtain detailed information about the construction area, and image data of the wall and the ground are obtained. Then, these image data are converted into a digital format for analysis through image processing software, and the converted image is processed using the image segmentation technology in the machine learning algorithm. Image segmentation technology can distinguish different areas in the image according to color, texture or other visual features. In this process, the sub-area that meets the flatness standard defined in the first preset information is identified, and feature learning is performed using a convolutional neural network (CNN) in deep learning. CNN can automatically learn the features of identifying flatness from a large amount of image data, and accurately classify new image data, so that it can identify the sub-area that meets the first preset information, and draw an identification circle in the image, thereby obtaining the first surface frame information; wherein, the identification circle indicated by the first surface frame information can be circular, rectangular or elliptical, etc.

[0103] S230C, identifying and dividing the construction area according to the second preset information, if the construction area includes one or more sub-areas that meet the second preset information, obtaining one or more corresponding second surface frame information; wherein the second surface frame information is used to indicate an identification frame, and the identification frame has a sub-area that meets the second preset information.

[0104] Exemplarily, first, a remote sensing device, such as a multispectral camera carried by a drone, is used to comprehensively scan the construction area to obtain multi-dimensional data of the wall and the ground. These data include but are not limited to visible light, infrared and thermal imaging information, which can provide detailed information about material type, temperature distribution and potential defects. The multi-dimensional data obtained by the remote sensing device is processed by using the clustering analysis technology in the pattern recognition algorithm. The clustering analysis technology can divide the construction area into different sub-areas according to the similarity of the data. In this process, the algorithm will identify the sub-areas that meet these conditions according to the specific conditions defined in the second preset information, such as material type or temperature threshold. These sub-areas are distinguished in the data with different clustering markers to further improve the accuracy of recognition. The deep reinforcement learning algorithm in artificial intelligence can be used to learn the optimal strategy through interaction with the environment and automatically adjust the recognition parameters to adapt to the complexity of the construction area. By training the deep reinforcement learning model, it can identify the sub-areas that meet the second preset information and draw a recognition frame in the data, thereby obtaining the second surface frame information; wherein, the recognition circle indicated by the first surface frame information can be circular, rectangular or elliptical.

[0105] S240C: Obtain feature information according to all first surface frame information and all second surface frame information.

[0106] Exemplarily, first, the first surface frame information and the second surface frame information are integrated to form a comprehensive data set containing all relevant features. This data set includes not only images and remote sensing data, but also other relevant information such as time series data and environmental parameters. Multimodal data fusion technology is used to integrate and process data from different sources and types. Information such as image data, remote sensing data and environmental parameters are synchronized and aligned to ensure their consistency in time and space. Through this fusion, a richer and more comprehensive data representation can be created, providing a more accurate basis for feature extraction. The feature extraction algorithm in machine learning, such as principal component analysis, linear discriminant analysis or autoencoder, is used to reduce the dimension and extract features of the fused data. These algorithms can extract the most representative and distinguishing features from high-dimensional data, and then extract and optimize the features using a pre-trained deep neural network model through transfer learning technology. Through the analysis and processing of feature information, a comprehensive feature description can be obtained, which includes the flatness indicated by all first surface frame information on the wall and the ground and the concave-convexity information indicated by all second surface frame information, thereby obtaining feature information.

[0107] S300C, determining construction control information based on the orientation information and the feature information; wherein the construction control information is used to control construction equipment to perform construction on the wall and / or ground that needs to be constructed.

[0108] Exemplarily, the collected position information and feature information need to be fused first. This step usually involves data synchronization and calibration to ensure the consistency of position information and feature information in time and space, and to fuse the data using advanced algorithms, such as Kalman filters or particle filters, to improve the accuracy and reliability of the information. In order to control the construction equipment, the three-dimensional model is integrated with the control system of the construction equipment, and the motion trajectory and construction parameters of the equipment are generated in real time through the control algorithm in the control system to obtain the construction control information. For example, for an automated mortar laying machine, the control algorithm calculates the direction, path, paving speed and paving amount of the mortar laying machine to ensure that the flatness and thickness of the road surface meet the design requirements.

[0109] In one possible implementation, see Figure 5 , S300C, determining construction control information based on the position information and the feature information, including:

[0110] S310C, obtaining construction parameter information and a preset identification range of the construction equipment; wherein the construction parameter information is used to indicate the original construction parameters in the construction equipment before it is working, and the preset identification range is a range extending from the construction equipment to a direction away from the construction equipment as the center.

[0111] Exemplarily, to obtain the construction parameter information of the construction equipment, it is first necessary to communicate with the interface of the construction equipment, which may include the use of wired or wireless technology, such as serial communication, Bluetooth or Wi-Fi. These parameter information include but are not limited to the model, size, power, speed, angle, etc. of the equipment. The construction parameter information is the initial configuration data of the equipment before construction. To obtain these parameter information, the system will perform the initialization step. The system will send a query instruction through the device interface to request the device to provide the original construction parameters stored internally. After the device responds, the system records and stores these parameter information in the database for subsequent analysis and processing. Determine the preset recognition range, which is set based on the characteristics of the construction equipment and the requirements of the construction task. The system simulates the motion trajectory of the construction equipment during the construction process and determines the preset recognition range according to the size and construction parameters of the construction equipment. The preset recognition range can be a range formed by extending from the equipment to the direction away from the construction equipment. The range size can be the position of an identification circle or identification frame extending from the edge of the construction equipment to the direction away from the edge of the construction equipment, or it can be determined according to the area of ​​the wall and / or the ground, but it cannot be less than the size range of the construction equipment.

[0112] S320C, identify the identification circle within the preset identification range according to the orientation information, and then compare the first preset information within the identified one or more identification circles according to the construction parameter information to obtain one or more first matching information; wherein the first matching information is used to reflect the matching value obtained after comparing the first preset information within the identification circle with the construction parameter information.

[0113] Exemplarily, first, identify the identification circle within the preset identification range. The preset identification circle may have one or more identification circles, but at least one. For example, when there are two identification circles within the preset identification range, compare the first preset information in the two identified identification circles with the construction parameter information, and compare the similarity between the first preset information and the construction parameter information (the construction parameter information is the initial equipment parameters of the construction equipment. The initial equipment parameters of the construction equipment are compared with the equipment parameters of the construction parameter information. The similarity can be understood by comparison, such as how many construction parameters are the same and how many construction parameters are different. The same situation of the construction parameters is the similarity). Then, a matching value is obtained based on the similarity. The higher the matching value, the closer the construction conditions in the identification circle are to the initial construction parameters. The time for modifying the initial parameters will be reduced, thereby improving the construction efficiency of the construction equipment and avoiding damage to the construction equipment due to frequent modification of parameter values.

[0114] S330C, based on the orientation information, the identification box within the preset identification range is identified, and the second preset information in the identified one or more identification boxes is compared according to the construction parameter information to obtain one or more second matching information; wherein the second matching information is used to reflect the matching value obtained after comparing the second preset information in the identification box with the construction parameter information.

[0115] First, identify the identification frame within the preset identification range. There may be one or more identification frames within the preset identification range, but there must be at least one. For example, when there are two identification frames within the preset identification range, compare the first preset information in the two identified identification frames with the construction parameter information, and compare the similarity between the first preset information and the construction parameter information (the construction parameter information is the initial equipment parameters of the construction equipment. The initial equipment parameters of the construction equipment are compared with the equipment parameters of the construction parameter information. The similarity can be understood through comparison, such as how many construction parameters are the same and how many construction parameters are different. The same situation of the construction parameters is the similarity). Then, a matching value is obtained based on the similarity. The higher the matching value, the closer the construction conditions in the identification frame are to the initial construction parameters. The time for modifying the initial parameters will be reduced, thereby improving the construction efficiency of the construction equipment and avoiding damage to the construction equipment due to frequent modification of parameter values.

[0116] S340C, compare the matching values ​​of one or more first matching information and one or more second matching information. If, after the first matching information and the second matching information are matched and compared, the matching degree of the first matching information is higher than the matching degree of the second matching information, and there is only one first matching information, the first matching information is prioritized.

[0117] Exemplarily, if the matching degree of the first matching information is higher than that of the second matching information, the system will further check the number of first matching information. According to the description of step S340C, if there is only one first matching information, the system will preferentially select this matching information as the final matching result, that is, the priority matching information.

[0118] S350C: if after the first matching information and the second matching information are matched and compared, the matching degree of the first matching information is higher than that of the second matching information, and if there are multiple first matching information, the priority matching information is the one with the highest matching value among the multiple first matching information.

[0119] Exemplarily, if the matching degree of the first matching information is higher than that of the second matching information, the system will further check the number of first matching information. According to the description of step S340C, because there are multiple first matching information, the matching degree values ​​of the multiple first matching information are compared, and the highest matching degree value will be preferentially selected by the system, and the first matching information with the highest matching degree value is used as the final matching result, that is, the priority matching information.

[0120] S360C: if after the first matching information and the second matching information are matched and compared, the first matching information is lower than the matching degree of the second matching information, and there is only one second matching information, the priority matching information is the second matching information.

[0121] For example, if the matching degree of the first matching information is lower than that of the second matching information, the system will further check the number of second matching information. According to the description of step S340C, since there is only one second matching information, the system will preferentially select this matching information as the final matching result, i.e., the priority matching information.

[0122] S370C: If there are multiple pieces of second matching information, the priority matching information is the one with the highest matching value among the multiple pieces of second matching information.

[0123] Exemplarily, if the matching degree of the first matching information is lower than the matching degree of the second matching information, the system will further check the number of first matching information. According to the description of step S340C, because there are multiple first matching information, the matching degree values ​​of the multiple first matching information are compared, and the highest matching degree value will be preferentially selected by the system, and the second matching information with the highest matching degree value is used as the final matching result, that is, the priority matching information.

[0124] S380C, obtain construction control information according to the priority matching information.

[0125] Exemplarily, firstly, the priority matching information is extracted from the database, which contains the detailed data that best matches the construction parameters, and the adaptive control algorithm is started. The algorithm first initializes the construction control parameters to ensure the real-time and accuracy of the construction control information. By adopting the method of real-time feedback correction technology, various sensors are installed on the construction equipment, and the system can monitor various parameters in the construction process in real time, such as pressure, temperature, vibration, etc. These data are fed back to the system in real time, and the adaptive control algorithm will dynamically adjust the construction control parameters according to these feedback data to ensure that the construction process is always in the optimal state, and then use the genetic algorithm to further optimize the construction control parameters. After determining the optimal construction control parameters, it is converted into specific construction control information. This information is sent to the construction equipment through the control interface to guide it to perform precise construction operations. For example, for an automated mortar laying machine, the construction control information will guide its laying depth, current laying amount and total laying amount, which are both efficient and meet the design requirements.

[0126] This setting can not only obtain accurate construction control information based on priority matching information, but also cope with various complex situations that may arise during the construction process, ensure the continuity and stability of the construction process, and conduct comprehensive analysis and processing of priority matching information. The comprehensive application of these technologies ensures the precise control and efficient operation of construction equipment during the construction process, thereby improving construction quality and efficiency.

[0127] In one possible implementation, see Figure 6 , S380C, based on the priority matching information, obtains the construction control information, including:

[0128] S381C, optimizing and correcting the construction parameter information according to the priority matching information to obtain first construction information; wherein the first construction information is used to indicate the construction parameters after the original construction parameters on the construction equipment are corrected according to the first matching information or the second matching information.

[0129] Exemplarily, first, influencing factors are extracted from historical construction data, and a preliminary construction parameter optimization model is constructed. The model is trained and verified using machine learning algorithms, such as random forests or support vector machines, to ensure the accuracy of its predictions. The priority matching information is input into the optimization model, and the model will automatically adjust the construction parameters to adapt to the current construction conditions. In order to ensure the accuracy of the construction information, a real-time feedback mechanism is introduced. When the construction equipment executes the parameters indicated by the first construction information, it monitors the construction effect in real time and feeds the data back to the optimization model. The model dynamically adjusts the construction parameters according to the feedback data to form a closed-loop control system to ensure that the construction process is always in the best state.

[0130] S382C, simulate the construction of the construction area based on the first construction information, optimize the first construction information, and obtain second construction information.

[0131] Exemplarily, advanced simulation technology is used to simulate the construction of the construction area. First, a precise three-dimensional model of the construction area is constructed based on the first construction information using computer-aided design software. Then, the three-dimensional model is dynamically simulated through integrated simulation software, such as Bentley Systems' ProjectWise or Autodesk's Navisworks, to evaluate the performance of the construction parameters in the actual environment. During the simulation process, various environmental factors and construction conditions, such as weather changes, material supply, labor allocation, etc., are considered to ensure the comprehensiveness and accuracy of the simulation results. Through simulation, problems that may arise during the construction process can be predicted, and the first construction information can be adjusted to optimize the construction process and improve resource utilization efficiency. Further, the particle swarm optimization algorithm is used to analyze the simulation results. These algorithms can handle complex optimization problems, and fine-tune the construction parameters through iterative search for the optimal solution to achieve the best balance in terms of cost, time, quality, etc., so as to obtain the second construction information; wherein, the obtained second construction parameters also have construction parameters for filling the flatness and unevenness of the wall and / or the ground. For example, if there is a pit on the wall, the construction equipment fills a certain amount of decorative mortar in the pit and fills it with decorative mortar until it is flush with the smooth wall surface. If the flatness of the wall is uneven, the construction equipment fills the unevenness with decorative mortar until it is flush with the smooth wall surface. If there is a protrusion, it can be filled with decorative mortar, or other tools (which can be a shovel or an automatic cleaning device in the prior art for automatic shoveling) can be used to remove the protruding part.

[0132] In one possible implementation, see Figure 7 , S382C, based on the first construction information, simulate the construction of the construction area, optimize the first construction information, and obtain second construction information, including:

[0133] S3821C, obtain construction requirements; wherein the construction requirements are used to reflect the total batch thickness value required for the construction area.

[0134] For example, advanced 3D scanning technology can be used to accurately scan the construction area and generate a detailed 3D model. By analyzing the model data, the flatness of the wall or the ground can be accurately calculated, and the area and thickness that need to be scraped can be determined; or the wall information can be input into a prediction model (the prediction model can be obtained by training with the input wall information as a sample) to predict the total scraping thickness value required in the construction requirements.

[0135] S3822C, simulate the construction of the construction area according to the construction requirements and the repaired construction parameters indicated by the first construction information, and obtain the first construction thickness information; wherein the first construction thickness information is used to indicate the scraping thickness value of the decorative mortar on the construction area in the simulation state, the scraping thickness value indicated by the first construction thickness information is less than the required total scraping thickness value indicated by the construction requirements, and the simulated construction is to construct the defects indicated by the flatness and unevenness on the wall and / or the ground, and the scraping thickness value is the amount of decorative mortar used to fill the wall and / or the ground.

[0136] Exemplarily, a detailed construction model is first constructed based on the construction requirements and the first construction information. This model not only includes the initial flatness and concavity data of the wall and the ground, but also integrates the material properties and environmental conditions of the construction area. The construction area is simulated using physically based rendering technology. PBR technology can provide more realistic lighting and material effects, thereby ensuring the accuracy of the simulation results. Through PBR technology, the performance of decorative mortar in the construction area under different scraping thicknesses can be simulated, including effects such as reflection, refraction and shadow. In order to further improve the accuracy of the simulation, a machine learning algorithm is introduced. By training a machine learning model, the final effect of the decorative mortar under different construction parameters is predicted. This includes the optimization of factors such as scraping thickness, construction speed and material mixing ratio to ensure that the final construction effect is consistent with the design requirements. In the simulation process, multi-physics coupling analysis technology is used. This technology can simultaneously consider the influence of multiple physical fields such as heat, force, and fluid on the construction process. For example, the influence of temperature changes on the curing process of decorative mortar and the stress concentration problems that may occur during the construction process are analyzed.

[0137] Finally, the simulation results are visualized, and the construction parameters can be adjusted to optimize the construction plan, and finally the first construction thickness information is obtained, which not only meets the design requirements but also has practical operability.

[0138] S3823C, compare the total scraping thickness value required by the construction requirements with the scraping thickness value indicated by the first construction thickness information to obtain thickness difference information.

[0139] Exemplarily, it is first necessary to ensure that the data format and unit of the construction requirements and the simulated construction results are consistent. Format the thickness data in the construction requirements and the simulated construction results to ensure that they have the same units (such as millimeters or inches), and ensure that the thickness data in the construction requirements and the simulated construction results correspond to the same construction area. It may be necessary to spatially align the data to ensure that the thickness values ​​at the same position are compared. For the required total scraping thickness value for each position in the construction requirements, subtract the scraping thickness value indicated by the first construction thickness information at the corresponding position in the simulated construction results to obtain the thickness difference information. This step can also be implemented by programming, for example, using programming languages ​​such as Python or MATLAB to calculate and obtain the thickness difference information. The calculated thickness difference information is analyzed to determine whether it is within an acceptable error range.

[0140] S3824C, optimizing and correcting the construction parameter information according to the thickness difference information to obtain second construction information; wherein the second construction information is used to indicate the construction thickness value parameter obtained by optimizing the construction parameter information after simulating construction on the construction area.

[0141] Exemplarily, multiple optimization objectives are first defined, including minimizing thickness difference, maximizing construction efficiency and minimizing material waste. An optimization model is constructed, which takes thickness difference information as input and combines the geometric characteristics, material properties and environmental conditions of the construction area. Through this model, the construction parameters can be dynamically adjusted to adapt to different construction scenarios and requirements. In order to further improve the accuracy of optimization, a genetic algorithm is used for parameter optimization, and new parameter combinations are generated through operations such as selection, crossover and mutation, and finally the best parameter combination that meets all optimization objectives is screened out. In order to ensure the practicality and reliability of the optimization results, the Monte Carlo simulation technology is used to evaluate the performance of the optimization parameters in various situations by simulating different construction scenarios and random variables, and calculate the confidence interval of the construction thickness value parameters, which helps to make reasonable decisions in the face of uncertain factors. In the optimization process, by comparing the results of the simulated construction with the actual construction data, the optimization model can be adjusted to ensure the accuracy and applicability of the second construction information, which not only improves the efficiency of the construction parameter optimization, but also enhances the controllability of the construction process, and finally, the second construction information is obtained.

[0142] S383C, obtain construction control information based on the first construction information and the second construction information.

[0143] Exemplarily, the first construction information and the second construction information are integrated by data fusion technology. The first construction information contains the original construction requirements and design parameters, while the second construction information contains the optimized construction thickness value parameters. The real-time monitoring technology is used to continuously track the simulated construction process, and key data such as construction thickness, speed, and temperature can be collected in real time. The data is transmitted to the control system and compared with the construction control model for analysis. In order to further improve the accuracy of construction control, a predictive maintenance algorithm is adopted. By analyzing historical data and real-time data, the predictive maintenance algorithm can predict possible problems and deviations and make adjustments in advance. For example, if the system detects that the construction thickness is about to exceed the allowable range, it will automatically adjust the parameters of the construction equipment to ensure that the thickness value remains within the predetermined range, making the construction parameters more stable. After the simulated construction is completed, the construction parameters are fine-tuned to make the construction parameters more accurate and stable, and then the construction control information is obtained, which contains real-time construction parameter adjustment instructions, which not only ensures the precise control of the construction process, but also improves the construction efficiency and quality, and realizes the intelligence and refinement of the construction process.

[0144] In a possible implementation, the method further includes:

[0145] S3101, if the optimized and corrected construction parameters indicated by the first construction information are modified according to the first matching information, when simulating the construction of the construction area according to the construction requirements and the modified construction parameters indicated by the first construction information, simulated construction is performed on all sub-areas within the identification circle on the construction area.

[0146] Exemplarily, when the optimized and corrected construction parameters indicated by the first construction information are modified according to the first matching information, when the construction area is simulated according to the construction requirements and the trimmed construction parameters indicated by the first construction information, firstly, all sub-areas within the identification circle in the construction area are simulated, and the uneven positions on all sub-areas within the identification circle are filled and leveled. In this way, the initial construction parameters of the construction equipment need to be modified less or not, which can increase the service life of the equipment and improve the construction speed. For example, if the identification circle is in a flatness condition, the construction equipment will fill and level all sub-areas within the identification circle in the construction area.

[0147] S3102, after the simulated construction is completed, the optimized and corrected construction parameters indicated by the first construction information are modified according to the second matching information. When the construction area is simulated according to the construction requirements and the modified construction parameters indicated by the first construction information, construction is performed on all sub-areas within the identification box on the construction area.

[0148] Exemplarily, after filling and leveling the uneven positions on all sub-areas within the identification circle, the optimized and corrected construction parameters indicated by the first construction information are modified according to the second matching information. When the construction area is simulated according to the construction requirements and the modified construction parameters indicated by the first construction information, construction is performed on all sub-areas within the identification boxes on the construction area, and all pits and / or protrusions on the sub-areas within the identification boxes are filled and leveled.

[0149] In a possible implementation, the method further includes:

[0150] S3103, if the optimized and corrected construction parameters indicated by the first construction information are modified according to the second matching information, when simulating the construction of the construction area according to the construction requirements and the modified construction parameters indicated by the first construction information, simulated construction is performed on all sub-areas within the identification box on the construction area.

[0151] Exemplarily, when the optimized and corrected construction parameters indicated by the first construction information are modified according to the second matching information, when the construction area is simulated according to the construction requirements and the modified construction parameters indicated by the first construction information, firstly, simulated construction is performed on all sub-areas within the identification box in the construction area, and the pits and / or protrusions on all sub-areas within the identification box are filled and leveled. Because the optimized and corrected construction parameters indicated by the first construction information are modified according to the second matching information, the initial construction parameters of the construction equipment need to be modified less or not, which can increase the service life of the equipment and the construction speed; for example, if the identification box shows concavity, the construction equipment will fill and level all sub-areas within the identification box on the construction area.

[0152] S3104, after the simulated construction is completed, the optimized and corrected construction parameters indicated by the first construction information are modified according to the first matching information. When the construction area is simulated according to the construction requirements and the modified construction parameters indicated by the first construction information, construction is performed on all sub-areas within the identification circle on the construction area.

[0153] After filling and leveling all the pits and / or protrusions on the sub-areas within the identification frame, the optimized and corrected construction parameters indicated by the first construction information are modified according to the first matching information. When the construction area is simulated according to the construction requirements and the modified construction parameters indicated by the first construction information, construction is performed on all the sub-areas within the identification frame circles on the construction area, and all the uneven positions on the sub-areas within the identification circle are filled and leveled.

[0154] Such a setting, through the above situation, can increase the service life of the equipment, improve the convenience of the construction equipment, reduce the frequency of modification of construction parameters on the construction equipment, and thus improve the construction speed and efficiency.

[0155] It should be understood that the size of the serial numbers of the steps in the above embodiments does not mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present application.

[0156] Corresponding to the decorative mortar construction method described in the above embodiment, the embodiment of the present application also provides a decorative mortar construction system, each unit of which can implement steps S100C, S200C, S300C of the decorative mortar construction method and its specific implementation steps. Figure 8 A structural block diagram of a decorative mortar construction system provided in an embodiment of the present application is shown. For ease of explanation, only the parts related to the embodiment of the present application are shown.

[0157] Reference Figure 8 , the decorative mortar construction system includes:

[0158] An acquisition unit is used to acquire the position information of the construction equipment in the construction area; wherein the position information is used to reflect the specific position of the construction equipment in the construction area;

[0159] A processing unit, used to perform feature recognition on the construction area to obtain feature information; wherein the feature information is used to reflect the surface conditions of the wall and / or ground that need to be constructed;

[0160] A control unit is used to determine construction control information based on the orientation information and the feature information; wherein the construction control information is used to control the construction equipment to perform construction on the wall and / or ground that needs to be constructed.

[0161] It should be noted that the information interaction, execution process, etc. between the above-mentioned systems / units are based on the same concept as the method embodiment of the present application. Their specific functions and technical effects can be found in the method embodiment part and will not be repeated here.

[0162] Those skilled in the art can clearly understand that, for the convenience and simplicity of description, only the division of the above-mentioned functional units is used as an example for illustration. In practical applications, the above-mentioned functions can be assigned to different functional units as needed, that is, the internal structure of the device can be divided into different functional units to complete all or part of the functions described above. The functional units in the embodiment can be integrated into a processing unit, or each unit can exist physically separately, or two or more units can be integrated into one unit. The above-mentioned integrated unit can be implemented in the form of hardware or in the form of software functional units. In addition, the specific names of the functional units are only for the convenience of distinguishing each other, and are not used to limit the scope of protection of this application. The specific working process of the units in the above-mentioned system can refer to the corresponding process in the aforementioned method embodiment, which will not be repeated here.

[0163] The present application also provides a decorative mortar construction device, Fig. 9 This is a schematic diagram of the structure of the decorative mortar construction equipment provided in one embodiment of the present application. Fig. 9 As shown, the decorative mortar construction equipment 6 of this embodiment includes: at least one processor 60 ( Fig. 9 Only one is shown), at least one memory 61 ( Fig. 9 Only one is shown in the figure) and a computer program 62 stored in the at least one memory 61 and executable on the at least one processor 60. When the processor 60 executes the computer program 62, the decorative mortar construction equipment 6 implements the steps in any of the above-mentioned decorative mortar construction method embodiments, or implements the functions of the various units in the above-mentioned system embodiments.

[0164] Exemplarily, the computer program 62 may be divided into one or more units, which are stored in the memory 61 and executed by the processor 60 to complete the present application. The one or more units may be a series of computer program instruction segments capable of completing specific functions, which are used to describe the execution process of the computer program 62 in the decorative mortar construction device 6.

[0165] The control device 6 of the decorative mortar construction equipment can be a computing device such as a desktop computer, a notebook, a palm computer, etc. The control device may include, but is not limited to, a processor 60 and a memory 61. Those skilled in the art will understand that Fig. 9 It is only an example of the control device 6 and does not constitute a limitation on the control device 6. It may include more or fewer components than shown in the figure, or a combination of certain components, or different components. For example, it may also include input and output devices, network access devices, buses, etc.

[0166] The processor 60 may be a central processing unit (CPU), or other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. A general-purpose processor may be a microprocessor or any conventional processor, etc.

[0167] In some embodiments, the memory 61 may be an internal storage unit of the control device 6, such as a hard disk or memory of the control device 6. In other embodiments, the memory 61 may also be an external storage device of the control device 6, such as a plug-in hard disk, a smart media card (SMC), a secure digital (SD) card, a flash card, etc. equipped on the control device 6. Further, the memory 61 may also include both an internal storage unit and an external storage device of the control device 6. The memory 61 is used to store an operating system, an application program, a boot loader (BootLoader), data, and other programs, such as the program code of the computer program. The memory 61 may also be used to temporarily store data that has been output or is to be output.

[0168] An embodiment of the present application further provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps in any of the above method embodiments are implemented.

[0169] An embodiment of the present application provides a computer program product. When the computer program product runs on a decorative mortar construction device, the decorative mortar construction device implements the steps in any of the above-mentioned method embodiments.

[0170] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the present application implements all or part of the processes in the above-mentioned embodiment method, which can be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a computer-readable storage medium. When the computer program is executed by the processor, the steps of the above-mentioned various method embodiments can be implemented. Among them, the computer program includes computer program code, and the computer program code can be in source code form, object code form, executable file or some intermediate form. The computer-readable medium may at least include: any entity or device that can carry the computer program code to the decorative mortar construction equipment, recording medium, computer memory, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), electric carrier signal, telecommunication signal and software distribution medium. For example, a USB flash drive, a mobile hard disk, a magnetic disk or an optical disk. In some jurisdictions, according to legislation and patent practice, computer-readable media cannot be electric carrier signals and telecommunication signals.

[0171] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described or recorded in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.

[0172] Those of ordinary skill in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of this application.

[0173] In the embodiments provided in the present application, it should be understood that the disclosed decorative mortar construction system, equipment and method can be implemented in other ways. For example, the decorative mortar construction system and equipment embodiments described above are merely schematic. For example, the division of the units is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be an indirect coupling or communication connection through some interfaces, devices or units, which can be electrical, mechanical or other forms.

[0174] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0175] The embodiments described above are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, a person skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. Such modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application, and should all be included in the protection scope of the present application.

Claims

1. A decorative mortar, characterized in that: The raw materials of the decorative mortar include the following components by weight: Basic building materials 82.1-89.5%; Performance regulator 2.2-7.2%; Functional additives 1~11.2%; Inorganic color powder 0.2-3%; Wherein, the basic building materials include the following components: Portland cement 20-23%; 325 mesh heavy calcium powder 46.1~48.5%; 80-120 mesh quartz sand 16-18%; The performance moderator comprises the following components: 1000 mesh metakaolin 1-3%; HPMC cellulose ether 0.1-0.2%; Redispersible latex powder 1-3%; Bentonite 0.1-1%; The functional additives include the following components: Sulphoaluminate cement 0.55-10%; Starch ether 0.15-0.5%; Alkali inhibitor 0.05-0.2%; Water repellent 0.25~0.5%.

2. A method for preparing decorative mortar, characterized in that: Used to prepare the decorative mortar according to claim 1, the decorative mortar preparation method comprises: Add silicate cement into the mixer, then add 325 mesh heavy calcium powder, and continue stirring for 5 minutes at the preset stirring speed; 80-120 mesh quartz sand is gradually added into the mixer, and stirred for 10 minutes according to a preset stirring speed to form a mortar mixture, and then 1000 mesh metakaolin, HPMC cellulose ether, redispersible latex powder and bentonite are added in sequence for stirring; wherein, after the mortar mixture is formed, each raw material is stirred for 5 minutes; Add sulphoaluminate cement, starch ether, alkali inhibitor and water repellent into the mixer in sequence; stir for 10 minutes after adding each raw material; The inorganic color powder is added into the mixer and stirred for 5-10 minutes. After all components are added, the mixture is stirred for 20 minutes to obtain the decorative mortar.

3. A decorative mortar construction method, characterized in that: The decorative mortar prepared by the decorative mortar according to claim 1 or the decorative mortar preparation method according to claim 2, the decorative mortar construction method comprising: Applying decorative mortar on a desired construction area to form a decorative mortar layer; wherein the construction area includes a wall surface and / or a ground surface; Laying a silicone film on the decorative mortar layer, and squeezing the surface of the silicone film flat; When the decorative mortar layer is solidified, the silicone film is removed.

4. The decorative mortar construction method according to claim 3, characterized in that: The thickness of the silicone film is 1mm-2mm; and / or The silicone film is paved on the surface of the decorative mortar layer and is provided with a texture structure.

5. The decorative mortar construction method according to claim 3, characterized in that: Before the decorative mortar is applied on the desired construction area to form a decorative mortar layer, the decorative mortar construction method further comprises: Acquire the position information of the construction equipment in the construction area; wherein the position information is used to reflect the specific position of the construction equipment in the construction area; Performing feature recognition on the construction area to obtain feature information; wherein the feature information is used to reflect the surface conditions of the wall and / or ground that needs to be constructed; The construction control information is determined based on the orientation information and the characteristic information; wherein the construction control information is used to control the construction equipment to perform construction on the wall and / or ground that needs to be constructed.

6. The decorative mortar construction method according to claim 5, characterized in that: The feature identification of the construction area to obtain feature information includes: Acquire first preset information and second preset information; wherein the first preset information is used to indicate a preset numerical range of flatness, and the second preset information is used to indicate a preset numerical range of concavity; The construction area is identified and divided according to the first preset information, and if the construction area includes one or more sub-areas that meet the first preset information, one or more corresponding first surface frame information is obtained; wherein the first surface frame information is used to indicate an identification circle, and a sub-area that meets the first preset information is included in the identification circle; Identify and divide the construction area according to the second preset information, and if the construction area includes one or more sub-areas that meet the second preset information, obtain corresponding one or more second surface frame information; wherein the second surface frame information is used to indicate an identification frame, and the identification frame includes a sub-area that meets the second preset information; Characteristic information is obtained according to all the first surface frame information and all the second surface frame information.

7. The decorative mortar construction method according to claim 6, characterized in that: Determining construction control information based on the position information and the feature information includes: Acquire construction parameter information and a preset identification range of the construction equipment; wherein the construction parameter information is used to indicate the original construction parameters in the construction equipment before it is working, and the preset identification range is a range formed by taking the construction equipment as the center and extending in a direction away from the construction equipment; The identification circle within the preset identification range is identified according to the orientation information, and then one or more first preset information within the identified identification circle is compared according to the construction parameter information to obtain one or more first matching information; wherein the first matching information is used to reflect the matching value obtained after comparing the first preset information within the identification circle with the construction parameter information; The identification frame within the preset identification range is identified according to the orientation information, and the second preset information within one or more identified identification frames is compared according to the construction parameter information to obtain one or more second matching information; wherein the second matching information is used to reflect the matching value obtained after comparing the second preset information within the identification frame with the construction parameter information; Comparing the matching values ​​of one or more of the first matching information and one or more of the second matching information, if the matching degree of the first matching information is higher than the matching degree of the second matching information, and there is only one first matching information, determining the first matching information as the priority matching information; If the matching degree of the first matching information is higher than that of the second matching information, and there are multiple first matching information, determine the first matching information with the highest matching value among the multiple first matching information as the priority matching information; If the matching degree of the first matching information is lower than the matching degree of the second matching information, and there is only one second matching information, determining the second matching information as the priority matching information; If there are multiple pieces of second matching information, determine the second matching information with the highest matching value among the multiple pieces of second matching information as the priority matching information; The construction control information is obtained according to the priority matching information.

8. The decorative mortar construction method according to claim 7, characterized in that: The obtaining of construction control information according to the priority matching information includes: The construction parameter information is optimized and corrected according to the priority matching information to obtain first construction information; wherein the first construction information is used to indicate the construction parameters after the original construction parameters on the construction equipment are corrected according to the first matching information or the second matching information; Performing simulated construction on the construction area based on the first construction information, optimizing the first construction information, and obtaining second construction information; The construction control information is obtained according to the first construction information and the second construction information.

9. The decorative mortar construction method according to claim 8, characterized in that: The simulating construction on the construction area based on the first construction information and optimizing the first construction information to obtain second construction information includes: Obtaining construction requirements; wherein the construction requirements are used to reflect the total scraping thickness value required for the construction area; The construction area is simulated for construction according to the construction requirements and the repaired construction parameters indicated by the first construction information to obtain first construction thickness information; wherein the first construction thickness information is used to indicate the scraping thickness value of the decorative mortar on the construction area in the simulation state, the scraping thickness value indicated by the first construction thickness information is less than the required total scraping thickness value indicated by the construction requirements, the simulated construction is performed on the defects indicated by the flatness and unevenness on the wall and / or the ground, and the scraping thickness value is the amount of decorative mortar used to fill the wall and / or the ground; Compare the total scraping thickness value required by the construction requirement with the scraping thickness value indicated by the first construction thickness information to obtain thickness difference information; The construction parameter information is optimized and corrected according to the thickness difference information to obtain second construction information; wherein the second construction information is used to indicate the construction thickness value parameter obtained by optimizing the construction parameter information after simulated construction of the construction area.

10. The decorative mortar construction method according to claim 9, characterized in that: The method further comprises: If the optimized and corrected construction parameters indicated by the first construction information are modified according to the first matching information, when simulating construction on the construction area according to the construction requirements and the modified construction parameters indicated by the first construction information, simulated construction is performed on all sub-areas within the identification circle on the construction area; After the simulated construction is completed, the optimized and corrected construction parameters indicated by the first construction information are modified according to the second matching information, and when the simulated construction is performed on the construction area according to the construction requirements and the modified construction parameters indicated by the first construction information, the sub-areas within the identification box on the construction area are constructed; And / or, the method further comprises: If the optimized and corrected construction parameters indicated by the first construction information are modified according to the second matching information, when simulating construction on the construction area according to the construction requirements and the modified construction parameters indicated by the first construction information, simulated construction is performed on all sub-areas within the identification box on the construction area; After the simulated construction is completed, the optimized and corrected construction parameters indicated by the first construction information are modified according to the first matching information. When the construction area is simulated according to the construction requirements and the trimmed construction parameters indicated by the first construction information, construction is performed on all sub-areas within the identification circle on the construction area.

Citation Information

Cited By

  • Cement-based building material without alkali efflorescence performance

    CN120247469A