Method for excavating deep foundation pit in strongly developed limestone area

Through drilling survey and grouting treatment of caves, combined with water exploration hole monitoring, the problem of the impact of caves and groundwater during foundation pit excavation in strongly developed limestone areas is solved, the construction stability and safety are improved, and emergencies are avoided.

CN119041444APending Publication Date: 2024-11-29CHINA RAILWAY 12TH BUREAU GRP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411448465.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-17
Publication Date
2024-11-29

AI Technical Summary

Technical Problem

In strongly developed limestone areas, there are a large number of dissolution cracks and caves during the excavation of foundation pits, resulting in construction uncertainty and safety hazards. It is difficult for traditional methods to effectively predict and deal with the impact of groundwater on foundation pit stability.

Method used

Drilling survey and exploration hole construction are used to judge and treat the cave through drilling depth and grouting, fill the cave with cement slurry or cement water glass double-liquid grouting, and monitor the base seepage through water exploration holes and pumping tests to ensure Foundation pit stability and safety.

Benefits of technology

It improves the stability of foundation pit excavation, reduces safety hazards, effectively blocks the cave, avoids sudden water surge incidents, and ensures the smooth progress of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119041444A_ABST
    Figure CN119041444A_ABST
Patent Text Reader

Abstract

The invention provides a method for excavating a deep foundation pit in a strong development limestone area, which belongs to the technical field of foundation pit construction, and is characterized in that cement paste or cement-water glass double-liquid slurry is adopted to finely fill a karst cave in an enclosure structure, so that the construction quality of an underground diaphragm wall is guaranteed, and a project is more stable and reliable. Meanwhile, the limestone layer is subjected to encrypted grouting, the karst cave in the limestone area of the foundation pit can be effectively blocked, then the water seepage condition of the base is monitored in real time in combination with a water pumping test, it is ensured that the foundation pit is safe, the sudden water gushing event is avoided, and smooth proceeding of a project is protected. Besides, when the drilling and cracking all-in-one machine is used for limestone crushing operation, compared with a crushing hammer, the drilling and cracking all-in-one machine is small in vibration in the crushing process, the influence on the stratum is smaller, and the construction safety and quality can be better guaranteed. The stability of foundation pit excavation can be effectively improved, and potential safety hazards are reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of foundation pit construction, and specifically discloses a deep foundation pit excavation method in a strongly developed limestone area. Background Art

[0002] The geological conditions in the limestone area are quite special. There are a large number of dissolution cracks and caves in the strongly developed limestone area, which brings great uncertainty and safety hazards to the excavation of the foundation pit. The water-rich environment further increases the difficulty of construction. The presence of groundwater not only affects the stability of the foundation pit, but also may cause sudden situations such as water gushing and mud bursting.

[0003] In this context, traditional construction methods often fail to work. Detailed geological surveys are required before construction to fully understand the distribution and characteristics of the underground rock formations, but even so, it is still difficult to fully predict possible problems. During the excavation process, effective support measures need to be taken to ensure the stability of the foundation pit wall and prevent collapse accidents. At the same time, the treatment of groundwater is also key, and appropriate water-stopping and drainage measures need to be adopted to avoid water interference and damage to construction.

[0004] In addition, during the construction process, it is necessary to closely monitor the changes in the foundation pit and the surrounding environment, and promptly discover and deal with possible abnormal situations. Various advanced monitoring technologies and equipment need to be widely used to grasp the status of the foundation pit in real time. Summary of the invention

[0005] Aiming at the special conditions of the strongly developed limestone area, the present invention provides a deep foundation pit excavation method to improve the stability of the foundation pit excavation and reduce safety hazards.

[0006] The deep foundation pit excavation method in a strongly developed limestone area provided by the present invention comprises the following steps:

[0007] S1, exploration hole construction

[0008] Drill holes at preset locations of ground-connected walls, foundation pits, and bored piles, with the drilling depth exceeding the preset depth of the ground-connected walls, the preset depth of the foundation pits, and the preset depth of the bored piles, to complete the construction of the survey holes, and determine whether there are karst caves at the preset locations of the ground-connected walls, foundation pits, and bored piles through the survey holes;

[0009] S2, exploration hole construction

[0010] If the exploration holes determine that there are karst caves at the preset locations of the ground-anchored wall, foundation pit, and bored piles, the first drilling will be carried out based on the exploration holes at the preset distances;

[0011] If no cave is found in the first drilling, the exploration hole construction is completed;

[0012] If a cave is found during the first drilling, drill again at a preset distance outwards and continue to expand until the edge or the area without cave development is processed;

[0013] The drilling depth exceeds the preset depth of the ground-anchored wall, the preset depth of the foundation pit, and the preset depth of the bored piles. If the cave is at the bottom of the exploration hole, continue drilling through the cave to the intact rock layer below the cave;

[0014] S3, grouting of exploration holes;

[0015] S4, enclosure construction

[0016] The retaining structure includes ground-connected walls and bored cast-in-place piles in the foundation pit;

[0017] S5, excavation of the upper soil layer of the foundation pit;

[0018] S6, construction of grouting holes inside the foundation pit;

[0019] S7, grouting background preparation and slurry configuration;

[0020] S8, grouting in grouting holes;

[0021] S9, water exploration hole construction and pumping test;

[0022] S10, excavation of the lower layer of stone in the foundation pit.

[0023] In step S1, a one-slot two-drilling method is used for the ground-connected wall, and holes are drilled at three equal intervals on the center line of the ground-connected wall as exploration holes;

[0024] For bored cast-in-place piles, one pile one drill method is adopted, and a hole is drilled in the center of the bored cast-in-place pile as an exploration hole.

[0025] In step S2, multiple rows of exploration holes are symmetrically arranged on both sides of the ground-connected wall, the distance between adjacent holes in a single row of exploration holes is a preset distance d, and the distance between the innermost row of exploration holes adjacent to the ground-connected wall and the exploration holes on the ground-connected wall is a preset distance d; the innermost row of exploration holes is arranged with the single-end exploration holes of the ground-connected wall as the basic holes, and the first hole and the second hole are symmetrically arranged on both sides of the basic holes; among the multiple rows of exploration holes located on a single side of the ground-connected wall, the distance between two adjacent rows of exploration holes is equal and is a preset distance d, and the two adjacent rows of exploration holes are staggered and the staggered distance is d / 2;

[0026] The multiple layers of exploration holes are arranged from the inside to the outside with the bored cast-in-place pile as the center. Each layer of exploration holes is arranged in a circular shape. The distance between adjacent holes in each layer of exploration holes is equal. The distance between the innermost exploration hole adjacent to the bored cast-in-place pile and the exploration hole on the bored cast-in-place pile is the preset distance d. The distance between two adjacent layers of exploration holes is the preset distance d. In two adjacent layers of exploration holes, the degree of the center angle of adjacent holes in the inner exploration hole is twice the degree of the center angle of adjacent holes in the outer exploration hole.

[0027] For the exploration holes in the foundation pit, multiple layers of exploration holes are arranged from the inside to the outside with the exploration hole as the center. Each layer of exploration holes is arranged in a regular polygon. The distance between adjacent holes in each layer of exploration holes is a preset distance d. The distance between the innermost exploration hole adjacent to the exploration hole and the exploration hole is the preset distance d. The distance between two adjacent layers of exploration holes is the preset distance d.

[0028] In step S3, when the water output of the exploration hole exceeds the preset value Q1 or the drilled core is in a broken state, cement-water-glass double slurry is used for grouting;

[0029] When there is no water in the exploration hole or the drilled core is intact, cement slurry is used for grouting.

[0030] In step S5, the excavation boundary line of the upper soil layer of the foundation pit is a preset depth h1 below the bottom elevation of the first support layer on the rock-soil boundary line.

[0031] In step S6, when the cave is located at the bottom of the grouting hole, drilling continues through the cave to the intact rock layer below the cave;

[0032] If the grouting holes conflict with the position of the retaining structure, they need to be staggered.

[0033] In step S6, the drilling operation uses a geological drilling rig to drill holes;

[0034] In step S8, the grouting holes are constructed by the skip row method, and the grouting is performed by sleeve valve pipe grouting;

[0035] When the water output of the grouting hole exceeds the preset value Q2 or the drilled core is in a broken state, cement-water-glass double liquid slurry is used for grouting;

[0036] When there is no water in the grouting hole or the drilled core is intact, cement slurry is used for grouting.

[0037] Step S9 includes the following steps:

[0038] t1, construct water exploration holes in the foundation pit;

[0039] t2, group the water exploration holes;

[0040] t3, conduct group well tests on each group of water exploration holes in the foundation pit in turn, observe and record the water levels of all water exploration holes in the group and the water level observation holes outside the foundation pit. After data collection is completed, analyze and calculate the stable water level after precipitation, the recharge amount after precipitation, and the recharge direction, and determine the suspicious water exploration holes in the foundation pit;

[0041] t4, conduct a single well test on the suspected water exploration holes in step t3, and increase the number of exploration holes and reinforce them with grouting according to the return water velocity of the suspected water exploration holes, the connectivity between the suspected water exploration holes and the surrounding water exploration holes, and the connectivity between the suspected water exploration holes and the water level observation holes outside the foundation pit.

[0042] In step t1, the depth of the water exploration hole in the foundation pit is a preset depth h2 below the foundation pit base, and a PVC flower pipe is placed, and a water pump is installed in the PVC flower pipe for pumping water;

[0043] In step t3, the group well test refers to first using a water pump to control the water level of the water exploration hole at a preset depth h3 below the base of the foundation pit and stopping pumping after a preset time t1, or stopping pumping when the total pumping volume is less than a preset value Q3 and after a preset time t2, and immediately starting observation after stopping pumping, and performing n1 water level observations and records within the first measurement unit T1, and the interval time of water level observations and records is T1 / n1, and the interval time of water level observations and records after the first measurement unit T1 is changed to T1 / 2, until the water level rises to a stable water level;

[0044] In step t4, the water level of the suspected water exploration hole is continuously lowered to keep the water level at a preset depth h4 below the base of the foundation pit. At the same time, the water level of the surrounding water exploration holes is observed and recorded n2 times. The water level observation and recording time is T2, and the drainage volume of the surrounding water exploration holes is recorded.

[0045] When the water levels in all the water exploration holes are stable at a preset depth h5 below the foundation pit bottom, and the return water speed is less than the preset value Q4, it can be determined that there is no risk of sudden water inrush in the foundation pit, and step S10 is performed;

[0046] In step S10, a construction method in which a drilling and cracking machine, a blasting hammer, an excavator and a dock crane cooperate with each other is adopted in the excavation of the lower layer of the foundation pit.

[0047] Compared with the prior art, the present invention has the following beneficial effects.

[0048] The present invention shows many advantages in construction. By using cement slurry or cement-water glass double liquid slurry to finely fill the karst caves in the enclosure structure, not only the construction quality of the ground-connected wall is guaranteed, but also the project is made more stable and reliable. At the same time, dense grouting of the limestone layer can effectively block the karst caves in the limestone area of ​​the foundation pit, and then combined with the pumping test to monitor the base water seepage in real time, ensure the safety of the foundation pit, avoid the occurrence of sudden water gushing, and escort the smooth progress of the project. In addition, the use of a drilling and cracking machine for limestone crushing operations, compared with a breaker, has less vibration during the crushing process, and has less impact on the stratum, which is more conducive to ensuring construction safety and quality. The present invention can effectively improve the stability of foundation pit excavation and reduce safety hazards. BRIEF DESCRIPTION OF THE DRAWINGS

[0049] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0050] Figure 1 is a flowchart of the method of the present invention;

[0051] Figure 2 This is the layout diagram of the exploration holes.

[0052] Figure 3 Layout of exploration holes for ground-connected walls;

[0053] Figure 4 Layout of exploration holes for bored piles;

[0054] Figure 5 It is the layout diagram of the exploration holes in the foundation pit;

[0055] Figure 6 This is the position relationship diagram between the geotechnical boundary line and the first excavation boundary line;

[0056] Figure 7 This is the layout diagram of the water exploration holes.

[0057] In the figure: 1. Exploration hole; 2. Exploration hole; 3. Ground-anchored wall; 4. Bored piles; 5. Foundation pit; 6. Water exploration hole. DETAILED DESCRIPTION

[0058] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0059] This embodiment takes the excavation of a deep foundation pit in a limestone area close to an existing line as an example to explain in detail the specific process of the deep foundation pit excavation method in a highly developed limestone area.

[0060] The total length of the foundation pit is 287m, of which the limestone area within 126m near one end of the existing line has strong karst development and a cave rate of 82.52%. The foundation pit is 42.9m wide and 30.36m deep. The foundation pit retaining structure adopts an underground continuous wall + internal support system, with a total of 5 concrete supports.

[0061] The deep foundation pit excavation method in a strongly developed limestone area provided in this embodiment comprises a total of 10 steps, including S1, construction of exploration holes; S2, construction of exploration holes; S3, grouting of exploration holes; S4, construction of retaining structures; S5, excavation of the upper earthwork of the foundation pit; S6, construction of grouting holes inside the foundation pit; S7, background preparation for grouting and configuration of slurry; S8, grouting of grouting holes in separate holes; S9, construction of water exploration holes and pumping test; and S10, excavation of the lower stonework of the foundation pit.

[0062] The first step is to drill holes at the preset positions of the ground-connected wall 3, foundation pit 5 and bored piles 4 to complete the construction of the exploration hole 1, and determine whether there are caves at the preset positions of the ground-connected wall 2, foundation pit 5 and bored piles 4 through the exploration hole 1. Figure 2 As shown, for the ground-anchored wall 3, a one-slot-two-drilling method is adopted, and holes are drilled at three equal intervals on the center line of the ground-anchored wall 3, and the hole depth reaches 3m below the preset depth of the ground-anchored wall 3; and for the bored cast-in-place pile 4, a one-pile-one-drilling method is adopted, and a hole is drilled in the center of the bored cast-in-place pile 4, and the hole depth is 3m below the preset depth of the bored cast-in-place pile 4; the hole depth of the exploration hole 1 in the foundation pit 5 is 5m below the base of the foundation pit.

[0063] The second step is to construct the exploration hole 2. The exploration hole 2 is drilled for the first time at a preset distance of 2m based on the exploration hole 1 that reveals the cave.

[0064] like Figure 3 The figure shows the arrangement of the exploration holes 2 on both sides of the ground-connected wall 3. Multiple rows of exploration holes 2 are symmetrically arranged on both sides of the ground-connected wall 3. The distance between adjacent holes in a single row of exploration holes 2 is 2m. The distance between the innermost row of exploration holes adjacent to the ground-connected wall 3 and the exploration hole 1 on the ground-connected wall 3 is 2m. The innermost row of exploration holes is arranged with the exploration hole at the left end of the ground-connected wall 3 as the basic hole. The first hole and the second hole of the innermost row of exploration holes are symmetrically arranged on both sides of the basic hole. Among the multiple rows of exploration holes 2 on one side of the ground-connected wall 3, the distance between two adjacent rows of exploration holes 2 is equal and 2m. The two adjacent rows of exploration holes 2 are staggered and the staggered distance is 1m. The depth of the exploration hole 2 reaches 3m below the preset depth of the ground-connected wall 3.

[0065] like Figure 4 The figure shows the arrangement of the exploration holes 2 around the bored pile 4. The multiple layers of exploration holes 2 are arranged from the inside to the outside with the bored pile 1 as the center. Each layer of exploration holes 2 is arranged in a circular shape. The distance between adjacent holes in each layer of exploration holes 2 is equal. The distance between the innermost exploration hole adjacent to the bored pile 4 and the exploration hole 1 on the bored pile 4 is 2m. The number of holes in the innermost exploration hole is 6. The distance between adjacent holes in the innermost exploration hole is 2m. The distance between two adjacent layers of exploration holes 2 is 2m. In two adjacent layers of exploration holes 2, the degree of the center angle of adjacent holes in the inner exploration hole is twice the degree of the center angle of adjacent holes in the outer exploration hole. Figure 4The center angle between adjacent holes in the innermost exploration hole is 60°, and the center angle between adjacent holes in the second exploration hole is 30°. The depth of the exploration hole 2 is 3m below the preset depth of the bored pile 4.

[0066] like Figure 5 The diagram shows the arrangement of the exploration holes 2 in the foundation pit 5. The multiple layers of exploration holes 2 are arranged from the inside to the outside with the exploration hole 1 as the center. Each layer of exploration holes 2 is arranged in a regular hexagon. The distance between adjacent holes in each layer of exploration holes 2 is 2m. The distance between the innermost exploration hole adjacent to the exploration hole 1 and the exploration hole is 2m, and the distance between two adjacent layers of exploration holes 2 is 2m. The depth of the exploration hole 1 is 5m below the foundation pit base.

[0067] If no cave is found during the first drilling, the exploration hole construction is completed; if a cave is found during the first drilling, drilling is performed again at a preset distance of 2m outward, and the expansion is continued until the edge line or the area without cave development is processed; if the cave is at the bottom of exploration hole 2, drilling continues to pass through the cave to 2m inside the intact rock layer below the cave.

[0068] The third step is to inject grout into the exploration hole. The grouting uses cement slurry (water: cement = 1:1) and cement-water glass double slurry (water: cement: water glass = 1:0.38:0.3). The grouting pressure is controlled at 0.8MPa. When the water output of the exploration hole exceeds the preset value (2.5m 3 / h) or the drilled core is in a broken state, cement-water-glass double-liquid slurry is used for grouting; when there is no water in the exploration hole or the drilled core is intact, cement slurry is used for grouting.

[0069] The fourth step, the construction of the retaining structure refers to the construction of the ground-connected wall 3 and the bored cast-in-place piles 4 in the foundation pit 5.

[0070] The fifth step is to excavate the upper layer of soil in the foundation pit. During excavation, the strata must be carefully analyzed, and the relationship between the rock-soil boundary line and the support must be combined to determine the first excavation depth. The general excavation boundary line is determined at the bottom of the first layer of support on the rock-soil boundary line.

[0071] Since the later stone grouting process will cause the base of the foundation pit to bulge, which will have a great impact on the support, the actual excavation depth needs to lower the excavation surface by 10cm after the support construction is completed.

[0072] Step 6: Construction of grouting holes inside foundation pit 5. The density of grouting holes is arranged at a spacing of 2.5m×3m, and the drilling depth needs to reach 5m below the foundation pit base. When the cave is at the bottom of the grouting hole, it should be drilled to 2m inside the intact rock layer under the cave. If the grouting hole conflicts with the position of the retaining structure, it needs to be fine-tuned according to the actual situation.

[0073] The drilling operation uses a geological drill rig to drill holes, and the grouting operation uses the sleeve valve pipe grouting method.

[0074] Step 8: Grouting holes are divided into different holes for grouting. When the water output of the grouting holes exceeds the preset value (2.5m 3 / h) or the drilled core is in a broken state, cement-water-glass double liquid slurry (initial setting time is about 30s) should be used for grouting; when there is no water in the grouting hole or the core is intact, cement slurry is used for grouting. In order to avoid excessive impact on the soil, the grouting hole is constructed using the skipping method, and the grouting lifting pipe pressure is controlled at about 0.8MPa.

[0075] The ninth step is the construction of water exploration holes and water pumping test. The density of water exploration hole 6 is 15m×10m. A geological drilling rig is used for drilling. The hole depth is 3m below the base of the foundation pit. The hole diameter is φ130. A φA110PVC flower pipe is used as the lower pipe. A water pump is installed in the pipe for water pumping test.

[0076] The pumping test includes group well test and single well test. The water exploration holes 6 are grouped according to their locations, with each group covering an area of ​​about 1,500 m2. Each group first undergoes a group well test and then a single well test.

[0077] The group well test means that the water level of the water exploration hole 6 is controlled at 1m below the bottom of the foundation pit by using an automatic water pump for 5-6 days, or when the total pumping volume is less than 30m 3 / h for 2 days and then stop pumping. Start observation immediately after stopping pumping. Observe and record the water level every 10 minutes in the first hour. After 1 hour, observe the water level every 30 minutes until the water level rises to a stable level.

[0078] During the group well test, water level observation and recording are performed for all water exploration holes 6 in the group and water level observation holes outside the foundation pit. After data collection is completed, detailed data analysis is required, mainly to analyze and calculate the stable water level after precipitation, the recharge volume after precipitation (water inflow per unit hour), the recharge direction, etc., so as to accurately determine the location of the suspected water exploration hole in the foundation pit.

[0079] The single well test is mainly carried out on the suspected water exploration holes. The suspected water exploration holes are continuously dewatered to keep the water level at 1m below the base of the foundation pit. At the same time, the surrounding water exploration holes of the suspected water exploration holes (the water exploration holes surrounding the suspected water exploration holes) are monitored once every 30 minutes for a total of 6 hours, and the drainage volume of the surrounding water exploration holes is recorded. After the data collection is completed, an in-depth analysis is carried out. According to the return water speed of the suspected water exploration holes, the connectivity between the suspected water exploration holes and the surrounding water exploration holes, and the connectivity between the suspected water exploration holes and the water level observation holes outside the foundation pit, the suspected water exploration holes are reinforced with grouting to ensure the safety and stability of the foundation pit.

[0080] The grouting effect of the foundation pit can be checked by observing and calculating the water level recovery speed in the water exploration hole 6. 3 / h, it indicates that the location is safe and there is no risk of water gushing in subsequent excavation. If it is greater than this value, the hole position will be recorded and handled uniformly later.

[0081] The water level in all water exploration holes 6 is stable at 1m below the bottom of the foundation pit, and the return water speed is less than 0.25m 3 / h, it can be determined that there is basically no risk of sudden water inrush in the foundation pit, and the next excavation work can be carried out.

[0082] The tenth step is to excavate the lower layer of stone in the foundation pit, using a construction method that uses a drilling and cracking machine, a blasting hammer, an excavator and a dock crane to cooperate with each other.

[0083] The construction principle of the drilling and splitting machine is to first drill a hole and then split the rock layer using hydraulic pressure. When excavating in limestone areas, the drilling and splitting machine has many advantages. Its construction drilling holes can not only serve as water exploration holes 6, timely discover water gushing and handle it, but also each drilling can reach a depth of 2m, split 1m deep, and the drilling spacing is 2m×2m. This construction method can effectively improve construction efficiency and ensure construction safety.

[0084] The above-mentioned deep foundation pit excavation method in the highly developed limestone area ensures the safety of the existing line. During the construction process, no risk events such as speed reduction or even suspension of the existing line were caused, which ensures the safety of the majority of travelers. The excavation of the foundation pit was completed safely and efficiently, saving 60 days of construction time compared with the original method, avoiding the interference of water gushing on the existing line, and avoiding the increased construction risks caused by blasting. It is safer, greener and more environmentally friendly, and has served as a model for deep foundation pit excavation construction near existing lines.

[0085] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.

Claims

1. A deep foundation pit excavation method in a strongly developed limestone area, characterized in that: The steps include: S1, exploration hole construction Drill holes at preset locations of ground-connected walls, foundation pits, and bored piles, with the drilling depth exceeding the preset depth of the ground-connected walls, the preset depth of the foundation pits, and the preset depth of the bored piles, to complete the construction of the survey holes, and determine whether there are karst caves at the preset locations of the ground-connected walls, foundation pits, and bored piles through the survey holes; S2, exploration hole construction If the exploration holes determine that there are karst caves at the preset locations of the ground-anchored wall, foundation pit, and bored piles, the first drilling will be carried out based on the exploration holes at the preset distances; If no cave is found in the first drilling, the exploration hole construction is completed; If a cave is found during the first drilling, drill again outward at a preset distance and continue to expand until the edge or the area without cave development is processed; The drilling depth exceeds the preset depth of the ground-anchored wall, the preset depth of the foundation pit, and the preset depth of the bored piles. If the cave is at the bottom of the exploration hole, continue drilling through the cave to the intact rock layer below the cave; S3, grouting of exploration holes; S4, enclosure construction The retaining structure includes ground-connected walls and bored cast-in-place piles in the foundation pit; S5, excavation of the upper soil layer of the foundation pit; S6, construction of grouting holes inside the foundation pit; S7, grouting background preparation and slurry configuration; S8, grouting in grouting holes; S9, water exploration hole construction and pumping test; S10, excavation of the lower layer of stone in the foundation pit.

2. The deep foundation pit excavation method in a strongly developed limestone area according to claim 1 is characterized in that: In step S1, a one-slot two-drilling method is used for the ground-connected wall, and holes are drilled at three equal intervals on the center line of the ground-connected wall as exploration holes; For bored cast-in-place piles, one pile one drill method is adopted, and a hole is drilled in the center of the bored cast-in-place pile as an exploration hole.

3. The deep foundation pit excavation method in a strongly developed limestone area according to claim 2 is characterized in that: In step S2, multiple rows of exploration holes are symmetrically arranged on both sides of the ground-connected wall, the distance between adjacent holes in a single row of exploration holes is a preset distance d, and the distance between the innermost row of exploration holes adjacent to the ground-connected wall and the exploration holes on the ground-connected wall is a preset distance d; the innermost row of exploration holes is arranged with the single-end exploration holes of the ground-connected wall as the basic holes, and the first hole and the second hole are symmetrically arranged on both sides of the basic holes; among the multiple rows of exploration holes located on a single side of the ground-connected wall, the distance between two adjacent rows of exploration holes is equal and is a preset distance d, and the two adjacent rows of exploration holes are staggered and the staggered distance is d / 2; The multiple layers of exploration holes are arranged from the inside to the outside with the bored cast-in-place pile as the center. Each layer of exploration holes is arranged in a circular shape. The distance between adjacent holes in each layer of exploration holes is equal. The distance between the innermost exploration hole adjacent to the bored cast-in-place pile and the exploration hole on the bored cast-in-place pile is the preset distance d. The distance between two adjacent layers of exploration holes is the preset distance d. In two adjacent layers of exploration holes, the degree of the center angle of adjacent holes in the inner exploration hole is twice the degree of the center angle of adjacent holes in the outer exploration hole. For the exploration holes in the foundation pit, multiple layers of exploration holes are arranged from the inside to the outside with the exploration hole as the center. Each layer of exploration holes is arranged in a regular polygon. The distance between adjacent holes in each layer of exploration holes is a preset distance d. The distance between the innermost exploration hole adjacent to the exploration hole and the exploration hole is the preset distance d. The distance between two adjacent layers of exploration holes is the preset distance d.

4. The deep foundation pit excavation method in a strongly developed limestone area according to claim 3 is characterized in that: In step S3, when the water output of the exploration hole exceeds the preset value Q1 or the drilled core is in a broken state, cement-water-glass double slurry is used for grouting; When there is no water in the exploration hole or the drilled core is intact, cement slurry is used for grouting.

5. The deep foundation pit excavation method in a strongly developed limestone area according to claim 4 is characterized in that: In step S5, the excavation boundary line of the upper soil layer of the foundation pit is a preset depth h1 below the bottom elevation of the first support layer on the rock-soil boundary line.

6. The deep foundation pit excavation method in a strongly developed limestone area according to claim 5 is characterized in that: In step S6, when the cave is located at the bottom of the grouting hole, drilling continues through the cave to the intact rock layer below the cave; If the grouting holes conflict with the position of the retaining structure, they need to be staggered.

7. The deep foundation pit excavation method in a strongly developed limestone area according to claim 6, characterized in that: In step S6, the drilling operation uses a geological drilling rig to drill holes; In step S8, the grouting holes are constructed by the skip row method, and the grouting is performed by sleeve valve pipe grouting; When the water output of the grouting hole exceeds the preset value Q2 or the drilled core is in a broken state, cement-water-glass double liquid slurry is used for grouting; When there is no water in the grouting hole or the drilled core is intact, cement slurry is used for grouting.

8. The deep foundation pit excavation method in a strongly developed limestone area according to claim 7, characterized in that: Step S9 includes the following steps: t1, construct water exploration holes in the foundation pit; t2, group the water exploration holes; t3, conduct group well tests on each group of water exploration holes in the foundation pit in turn, observe and record the water levels of all water exploration holes in the group and the water level observation holes outside the foundation pit. After data collection is completed, analyze and calculate the stable water level after precipitation, the recharge amount after precipitation, and the recharge direction, and determine the suspicious water exploration holes in the foundation pit; t4, conduct a single well test on the suspected water exploration holes in step t3, and increase the number of exploration holes and reinforce them with grouting according to the return water velocity of the suspected water exploration holes, the connectivity between the suspected water exploration holes and the surrounding water exploration holes, and the connectivity between the suspected water exploration holes and the water level observation holes outside the foundation pit.

9. The deep foundation pit excavation method in a strongly developed limestone area according to claim 8, characterized in that: In step t1, the depth of the water exploration hole in the foundation pit is a preset depth h2 below the foundation pit base, and a PVC flower pipe is installed in the PVC flower pipe. Water Pump For pumping water; In step t3, the group well test refers to first using a water pump to control the water level of the water exploration hole at a preset depth h3 below the base of the foundation pit and stopping pumping after a preset time t1, or stopping pumping when the total pumping volume is less than a preset value Q3 and after a preset time t2, and immediately starting observation after stopping pumping, and performing n1 water level observations and records within the first measurement unit T1, and the interval time of water level observations and records is T1 / n1, and the interval time of water level observations and records after the first measurement unit T1 is changed to T1 / 2, until the water level rises to a stable water level; In step t4, the water level of the suspected water exploration hole is continuously lowered to keep the water level at a preset depth h4 below the base of the foundation pit. At the same time, the water level of the surrounding water exploration holes is observed and recorded n2 times. The water level observation and recording time is T2, and the drainage volume of the surrounding water exploration holes is recorded.

10. The deep foundation pit excavation method in a strongly developed limestone area according to claim 9, characterized in that: When the water levels in all the water exploration holes are stable at a preset depth h5 below the foundation pit bottom, and the return water speed is less than the preset value Q4, it can be determined that there is no risk of sudden water inrush in the foundation pit, and step S10 is performed; In step S10, a construction method in which a drilling and cracking machine, a blasting hammer, an excavator and a dock crane cooperate with each other is adopted in the excavation of the lower layer of the foundation pit.