Construction method pile reinforcing structure and construction method
By combining steel pipe piles with reinforcement sections and anchor sections in the working piles, the reinforcement sections and anchor sections of the reaming cement mixing piles are solved, and material saving is achieved , shorten construction period and improve structural durability.
Patent Information
- Application Number
- CN202411472233.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-22
- Publication Date
- 2024-11-29
AI Technical Summary
When existing working piles are in weak strata areas, the weakness of the formation affects its stability, resulting in sinking, tilting or overall instability. The material usage is large when reinforced by cement mixing piles, increasing construction costs and cycles.
Multiple steel pipe piles are used to combine with the reinforcement section and anchor section of the reaming cement mixing pile. The structure is strengthened by reinforcement of steel bars and self-healing capsules, and the stability is improved by using locks and Larsen steel sheet piles, and ensured by pressing the top beam and drainage ditch. Overall fixity.
The amount of material used for reaming cement mixing piles is reduced, the construction period is shortened, the stability and tensile resistance of the working piles are improved, the durability is enhanced, and crack repair is achieved through self-healing capsules, reducing construction costs.
Smart Images

Figure CN119041450A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of construction method piles, and in particular relates to a construction method pile reinforcement structure and a construction method. Background Art
[0002] As an important structural form widely used in foundation reinforcement and civil engineering infrastructure construction, construction piles have become one of the more economical support methods in foundation pit support. Types of construction piles include PC construction piles, HW construction piles, etc. Among them, PC construction piles adopt a structural method that combines steel pipe piles and Larsen steel sheet piles, showing multiple advantages such as flexible construction, strong bending resistance, superior economy and environmental friendliness. In addition, the Larsen steel sheet piles set in the structure also have the function of a water-stop curtain, which can not only reduce the occupation of the surrounding structure space during construction, but also significantly improve the construction efficiency of construction piles.
[0003] As shown in the patent document with publication number CN208618395U, the construction pile is a structure combining steel pipes and Larsen steel plates. The construction pile is mainly used in the fields of foundation pit support, foundation reinforcement and civil engineering foundation construction.
[0004] In the related art, when the construction method pile is located in a soft stratum area, the weakness of the stratum will affect the stability of the construction method pile, especially under long-term load, the construction method pile may sink, tilt or become unstable as a whole. Therefore, when constructing the construction method pile, it is usually necessary to use cement mixing piles to reinforce the construction method pile to improve the bearing capacity and stability of the construction method pile. Cement mixing piles are a commonly used reinforcement method, which can significantly improve the stability of the construction method pile by improving and strengthening the stratum. However, the amount of materials required for the construction of cement mixing piles is large, which may increase the construction cost and prolong the construction period. Therefore, the existing technology requires a construction method pile reinforcement structure that can save material consumption. Summary of the invention
[0005] The purpose of the present invention is to provide a construction pile reinforcement structure and a construction method to solve the technical problem that a large amount of waste materials are required during construction in the above-mentioned background technology of reinforcing construction piles by cement mixing piles.
[0006] The above technical objectives of the present invention are achieved through the following technical solutions: A construction pile reinforcement structure and construction method, including: a plurality of steel pipe piles, wherein the outer wall of the steel pipe pile is provided with an expanded hole cement mixing pile, the expanded hole cement mixing pile includes an expanded hole cement mixing pile reinforcement section and an expanded hole cement mixing pile anchoring section, the expanded hole cement mixing pile reinforcement section is located in the middle of the steel pipe pile, the expanded hole cement mixing pile anchoring section is located at the bottom of the steel pipe pile, a plurality of reinforcing steel bars are provided, the plurality of reinforcing steel bars are evenly located on the outside of the steel pipe pile, and the top end of the reinforcing steel bar is located inside the expanded hole cement mixing pile reinforcement section, and the bottom end of the reinforcing steel bar is located inside the expanded hole cement mixing pile anchoring section, and a plurality of self-healing capsules are provided, the plurality of self-healing capsules are evenly located inside the expanded hole cement mixing pile.
[0007] Furthermore: in order to enhance the structural strength of the hole-enlarging cement mixing pile, reinforcing fiber filaments are arranged inside the hole-enlarging cement mixing pile.
[0008] Furthermore: in order to limit the position between adjacent steel pipe piles, lock buckles are fixedly connected to both sides of the outer wall of the steel pipe piles, and Larsen steel sheet piles are arranged between the connected steel pipe piles, and one side of the Larsen steel sheet piles is mutually engaged with the lock buckles.
[0009] Furthermore: in order to improve the stability of the top ends of the plurality of steel pipe piles, the top ends of the plurality of steel pipe piles are fixedly connected with a top pressure beam, and a drainage ditch is provided on one side of the top pressure beam.
[0010] Furthermore: a basement cap is arranged above the reinforcement section of the enlarged cement mixing pile.
[0011] Furthermore: In order to improve the stability of the reinforcing steel bars during use, a first reinforcing ring is fixedly connected to the interior of the reinforcement section of the expanded hole cement mixing pile, and the upper surface of the reinforcing steel bar is fixedly connected to the bottom of the first reinforcing ring; a second reinforcing ring is fixedly connected to the interior of the anchor section of the expanded hole cement mixing pile, and the lower end surface of the reinforcing steel bar is fixedly connected to the top of the second reinforcing ring.
[0012] Furthermore: the self-healing capsule comprises a wrapping layer, and a repair agent is stored inside the wrapping layer.
[0013] Furthermore: in order to ensure the tearing effect of the wrapping layer, the wrapping layer is evenly and fixedly connected with pulling fiber threads, the inner wall of the wrapping layer is fixedly connected with a pulling net, and one end of the pulling fiber threads passes through the wrapping layer and is fixedly connected with the pulling net.
[0014] A construction method for a pile reinforcement structure, the specific steps of the construction method are: Step 1: Use the construction equipment of the expanded cement mixing pile to drill into the bottom of the designed position of the steel pipe pile, open the expanded tail wing of the construction equipment, and construct the expanded cement mixing pile anchoring section at the bottom elevation position of the designed position of the steel pipe pile. After the construction is completed, retract the expanded tail wing and lift it to the middle of the designed position of the steel pipe pile; Step 2: In the middle of the designed position of the steel pipe pile, below the basement cap, open the expansion tail again to construct the expansion cement mixing pile reinforcement section. After the construction is completed, retract the expansion tail and lift it to the ground to prepare for the construction of the next expansion cement mixing pile; Step 3: Evenly insert the reinforcing steel bars on the hole-enlarged cement mixing pile so that the top of the reinforcing steel bars is located in the reinforcement section of the hole-enlarged cement mixing pile and the bottom is located in the anchoring section of the hole-enlarged cement mixing pile; Step 4: After the construction of the expanded hole cement mixing pile is completed, the construction of the method pile is carried out in time. The method pile is composed of multiple steel pipe piles and multiple Larsen steel sheet piles. The method pile is passed through the expanded hole cement mixing pile reinforcement section and the expanded hole cement mixing pile anchoring section to ensure that the lower end of the method pile is embedded in the expanded hole cement mixing pile anchoring section to provide sufficient bearing capacity and stability; Step 5: After completing the construction of the construction method piles, construct a capping beam on the upper end of the construction method piles to form the construction method piles into a whole to ensure the fixation of the upper end of the construction method piles, and construct a drainage ditch on one side of the capping beam.
[0015] In summary, the present invention has the following beneficial effects: ① It can reduce the amount of materials used in the expanded hole cement mixing pile and shorten the construction period: multiple steel pipe piles and multiple Larsen steel sheet piles can be arranged to form a construction pile, and the expanded hole cement mixing pile can be divided into two parts: the expanded hole cement mixing pile reinforcement section and the expanded hole cement mixing pile anchoring section. The expanded hole cement mixing pile reinforcement section can be used to reinforce the middle part of the steel pipe pile, and the expanded hole cement mixing pile anchoring section can be used to reinforce the bottom of the steel pipe pile, which can reduce the amount of materials used in the expanded hole cement mixing pile, thereby saving costs and shortening the construction period; ② It can improve the stability of the expanded hole cement mixing pile: the tensile and crack resistance of the expanded hole cement mixing pile can be further improved by reinforcing the fiber filaments. Multiple reinforcing steel bars can reinforce the position between the reinforcement section and the anchor section of the expanded hole cement mixing pile to improve the integrity and tensile resistance of the entire expanded hole cement mixing pile reinforcement structure. The first reinforcement ring can limit the stability of the top of the reinforcing steel bar inside the reinforcement section of the expanded hole cement mixing pile, and the second reinforcement ring can limit the stability of the bottom of the reinforcing steel bar inside the anchor section of the expanded hole cement mixing pile, thereby enhancing the use effect of the reinforcing steel bar; ③ It can self-heal the cracks in the enlarged hole cement mixing pile: by mixing a number of self-healing capsules inside the enlarged hole cement mixing pile, the self-healing capsules are composed of a wrapping layer wrapping a repair agent. When the enlarged hole cement mixing pile cracks, the cracked part can drive the pulling fiber filaments to move, and the movement of the pulling fiber filaments can involve the pulling net. The wrapping layer can be torn open through the movement of the pulling net, so that the repair agent can flow out from the north and south of the wrapping layer, thereby ensuring the effective use of the self-healing capsules. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a schematic diagram of the overall structure of a construction pile reinforcement structure and a construction method in an embodiment of the present invention; Figure 2 It is a schematic diagram of the elevation structure of a construction pile reinforcement structure and a construction method in an embodiment of the present invention; Figure 3 It is a schematic diagram of the planar structure of a construction pile reinforcement structure and a construction method in an embodiment of the present invention; Figure 4 A construction pile reinforcement structure and construction method in an embodiment of the present invention Figure 3 A schematic diagram of the structure enlargement at point A; Figure 5 It is a schematic diagram of a steel pipe pile and Larsen steel sheet pile structure of a construction pile reinforcement structure and a construction method in an embodiment of the present invention; Figure 6 It is a schematic diagram of a reinforcing steel bar and a reinforcing ring structure of a construction pile reinforcement structure and a construction method in an embodiment of the present invention; Figure 7 It is a schematic cross-sectional structure diagram of a self-healing capsule of a construction pile reinforcement structure and a construction method in an embodiment of the present invention; In the figure, 1. steel pipe pile; 2. enlarged cement mixing pile; 201. enlarged cement mixing pile reinforcement section; 202. enlarged cement mixing pile anchor section; 3. reinforced steel bars; 4. self-healing capsule; 401. wrapping layer; 402. repair agent; 5. top beam; 6. drainage ditch; 7. basement pedestal; 8. lock; 9. Larsen steel sheet pile; 10. reinforcing fiber filament; 11. pulling fiber filament; 12. pulling net; 13. first reinforcement ring; 14. second reinforcement ring. DETAILED DESCRIPTION
[0017] The present invention is further described in detail below in conjunction with the accompanying drawings.
[0018] See also Figure 1-Figure 7 , the present invention provides a technical solution: Example 1 The embodiment of the present invention discloses a method pile reinforcement structure. Figure 1 and Figure 2The construction pile reinforcement structure includes a plurality of steel pipe piles 1, which are the core bearing elements of the construction piles. The main function of the steel pipe piles 1 is to provide vertical support force, which can carry the building load above and transfer it to the stratum below. Figure 3 , Figure 4 and Figure 5 As shown, lock buckles 8 are fixedly connected to both sides of the outer wall of the steel pipe pile 1, and the lock buckles 8 and the steel pipe pile 1 are welded and fixed, and the lock buckles 8 on both sides of the outer wall of the steel pipe pile 1 are symmetrically located on the same diameter line of the steel pipe pile 1, and Larsen steel sheet piles 9 are arranged between the connected steel pipe piles 1, and one side of the Larsen steel sheet pile 9 is mutually engaged with the lock buckle 8, and the Larsen steel sheet pile 9 can be installed between adjacent steel pipe piles 1 through the arranged lock buckle 8, and the direction of the lock buckle 8 can be the same direction or the reverse direction according to the combination form between the steel pipe pile 1 and the Larsen steel sheet pile 9. The arranged Larsen steel sheet pile 9 can improve the stability between adjacent steel pipe piles 1 when in use, and also has a water-stopping function to prevent groundwater leakage.
[0019] Further, such as Figure 1 and Figure 2 As shown, the top ends of the plurality of steel pipe piles 1 are fixedly connected with a capping beam 5, and the top ends of the plurality of steel pipe piles 1 can be fixed by the capping beam 5, so that the construction method piles form a whole, and the stability of the upper structure of the pile body can be ensured. A drainage ditch 6 is arranged on one side of the capping beam 5, and the drainage ditch 6 is made of bricks. The groundwater or rainwater generated during or after the construction process can be drained through the drainage ditch 6 to prevent moisture from accumulating around the construction method piles and affecting the stability of the pile body.
[0020] In a further preferred embodiment of the present invention, Figure 1 , Figure 2 and Figure 3 The outer wall of the steel pipe pile 1 is provided with an expanded cement mixing pile 2, which can reinforce the steel pipe pile 1 and provide good support and restraint for the steel pipe pile 1, so as to reduce the deformation and displacement of the steel pipe pile 1 under the load at the foundation pit edge. The expanded cement mixing pile 2 can replace the reinforcement method of respectively providing active reinforcement zone and passive reinforcement zone on the outer side and inner side of the steel pipe pile 1. The expanded cement mixing pile 2 forms a pile body with higher strength through mechanical mixing and cement slurry injection, which can improve the bearing capacity of the stratum and the overall stability of the construction pile.
[0021] Specifically, refer to Figure 1 , Figure 2 and Figure 3The expanded hole cement mixing pile 2 includes an expanded hole cement mixing pile reinforcement section 201 and an expanded hole cement mixing pile anchoring section 202. The expanded hole cement mixing pile reinforcement section 201 is located in the middle of the steel pipe pile 1, and the middle of the steel pipe pile 1 can be reinforced by the expanded hole cement mixing pile reinforcement section 201. The length of the expanded hole cement mixing pile reinforcement section 201 is not less than 2 meters, and the diameter is not less than 1.6 meters. The expanded hole cement mixing pile anchoring section 202 is located at the bottom of the steel pipe pile 1, and the bottom of the steel pipe pile 1 can be reinforced by the expanded hole cement mixing pile anchoring section 202. The length of the expanded hole cement mixing pile anchoring section 202 is not less than 2 meters, and the diameter is not less than 1.6 meters. The present application divides the expanded hole cement mixing pile 2 into two main parts, namely the expanded hole cement mixing pile reinforcement section 201 and the expanded hole cement mixing pile anchoring section 202, which can reduce the amount of materials used, thereby saving costs, shortening construction period, and making the pile body stable and reliable in force, safe and efficient.
[0022] Further, such as Figure 1 and Figure 2 As shown, a basement cap 7 is arranged above the hole-enlarged cement mixing pile reinforcement section 201 . The hole-enlarged cement mixing pile reinforcement section 201 can help strengthen the support and constraint of the basement cap 7 by the nearby soil, so as to improve the stability of the basement cap 7 .
[0023] In a further preferred embodiment of the present invention, Figure 1 , Figure 2 and Figure 3 A plurality of reinforcing steel bars 3 are provided, and the plurality of reinforcing steel bars 3 are evenly located on the outside of the steel pipe pile 1, and the top end of the reinforcing steel bars 3 is located inside the reinforcing section 201 of the expanded cement mixing pile, and the bottom end of the reinforcing steel bars 3 is located inside the anchoring section 202 of the expanded cement mixing pile. The reinforcing steel bars 3 can enhance the stability of the position between the reinforcement section 201 of the expanded cement mixing pile and the anchoring section 202 of the expanded cement mixing pile, so as to improve the integrity and tensile strength of the entire reinforcement structure.
[0024] In a further preferred embodiment of the present invention, Figure 3 , Figure 4 and Figure 7As shown, a plurality of self-healing capsules 4 are provided, and the plurality of self-healing capsules 4 are evenly located inside the expanded hole cement mixing pile 2. The self-healing capsule 4 includes a wrapping layer 401. The wrapping layer 401 may be made of a high molecular polymer material such as urea-formaldehyde resin, polylactic acid or polyvinyl alcohol. A repair agent 402 is stored inside the wrapping layer 401, and the repair agent 402 can be preserved by the wrapping layer 401. The repair agent 402 may be made of materials such as epoxy resin, polymer monomer or calcium carbonate particle suspension. After being released, these materials can quickly react chemically with the surrounding cement-based materials or fill cracks to restore the density of the structure. When the expanded hole cement mixing pile 2 cracks after long-term use, the cracks can be filled and repaired by the self-healing capsules 4 to restore the integrity of the expanded hole cement mixing pile 2 and enhance the durability and stability of the expanded hole cement mixing pile 2.
[0025] Example 2 This embodiment is an improvement made on the basis of embodiment 1. Figure 4 As shown, in order to enhance the structural strength of the expanded hole cement mixing pile 2, the interior of the expanded hole cement mixing pile 2 is provided with reinforcing fiber filaments 10, and the reinforcing fiber filaments 10 are evenly arranged inside the expanded hole cement mixing pile 2, which can further improve the tensile and crack resistance of the expanded hole cement mixing pile 2, and the reinforcing fiber filaments 10 can be made of high-strength glass fiber or carbon fiber, which can play a reinforcing effect inside the expanded hole cement mixing pile 2.
[0026] Example 3 This embodiment is an improvement made on the basis of embodiment 1. Figure 2 and Figure 6 As shown, in order to improve the stability of the reinforcing steel bar 3 during use, a first reinforcing ring 13 is fixedly connected to the interior of the expansion hole cement mixing pile reinforcement section 201, and the upper surface of the reinforcing steel bar 3 is fixedly connected to the bottom of the first reinforcing ring 13, and the first reinforcing ring 13 can limit the stability of the top end of the reinforcing steel bar 3 inside the expansion hole cement mixing pile reinforcement section 201, and a second reinforcing ring 14 is fixedly connected to the interior of the expansion hole cement mixing pile anchor section 202, and the lower end surface of the reinforcing steel bar 3 is fixedly connected to the top of the second reinforcing ring 14, and the second reinforcing ring 14 can limit the stability of the bottom end of the reinforcing steel bar 3 inside the expansion hole cement mixing pile anchor section 202, thereby enhancing the use effect of the reinforcing steel bar 3.
[0027] Example 4 This embodiment is an improvement made on the basis of embodiment 1. Figure 3 , Figure 4 and Figure 7As shown, in order to ensure the tearing effect of the wrapping layer 401, the wrapping layer 401 is evenly and fixedly connected with a pulling fiber filament 11. When the expanded cement mixing pile 2 is cracked, the cracked part can drive the pulling fiber filament 11 to move. The inner wall of the wrapping layer 401 is fixedly connected with a pulling net 12. One end of the pulling fiber filament 11 passes through the wrapping layer 401 and is fixedly connected with the pulling net 12. The pulling net 12 can be involved by the movement of the pulling fiber filament 11. The wrapping layer 401 can be torn by the movement of the pulling net 12, so that the repair agent 402 can flow out from the north and south of the wrapping layer 401, thereby ensuring the effective use of the self-healing capsule 4.
[0028] A construction method for a construction pile reinforcement structure, the specific steps of the construction method are: Step 1: Use the construction equipment of the expanded cement mixing pile 2 to drill into the bottom of the designed position of the steel pipe pile 1, open the expanded tail wing of the construction equipment, and construct the expanded cement mixing pile anchoring section 202 at the bottom elevation position of the designed position of the steel pipe pile 1. After the construction is completed, retract the expanded tail wing and lift the expanded tail wing to the middle of the designed position of the steel pipe pile 1; Step 2: In the middle of the designed position of the steel pipe pile 1, below the basement cap 7, the expansion tail wing is opened again to construct the expansion cement mixing pile reinforcement section 201. After the construction is completed, the expansion tail wing is folded and lifted to the ground to prepare for the construction of the next expansion cement mixing pile 2; Step 3: Evenly insert the reinforcing steel bars 3 on the hole-enlarging cement mixing pile 2, so that the top end of the reinforcing steel bars 3 is located in the reinforcement section 201 of the hole-enlarging cement mixing pile, and the bottom end is located in the anchoring section 202 of the hole-enlarging cement mixing pile; Step 4: After the construction of the expanded hole cement mixing pile 2 is completed, the construction of the method pile is carried out in time. The method pile is composed of a plurality of steel pipe piles 1 and a plurality of Larsen steel sheet piles 9 arranged in an arranged manner. The method pile is passed through the expanded hole cement mixing pile reinforcement section 201 and the expanded hole cement mixing pile anchoring section 202 to ensure that the lower end of the method pile is embedded in the expanded hole cement mixing pile anchoring section 202 to provide sufficient bearing capacity and stability; Step 5: After the construction of the construction method pile is completed, a capping beam 5 is constructed on the upper end of the construction method pile to form the construction method pile into a whole to ensure the fixation of the upper end of the construction method pile, and a drainage ditch 6 is constructed on one side of the capping beam 5.
[0029] Through the operations of step one, step two, step three, step four and step five, the amount of material used in the hole-enlarging cement mixing pile 2 can be reduced, which is beneficial to saving costs and shortening construction period.
[0030] The implementation principle of the construction pile reinforcement structure and construction method of the embodiment of the present invention is: When in use, the construction method pile is composed of a plurality of steel pipe piles 1 and a plurality of Larsen steel sheet piles 9 arranged in an arranged manner. The expanded hole cement mixing pile 2 used to reinforce the steel pipe pile 1 is divided into two parts for construction, namely, the expanded hole cement mixing pile reinforcement section 201 and the expanded hole cement mixing pile anchoring section 202. The expanded hole cement mixing pile reinforcement section 201 can be used to reinforce the middle part of the steel pipe pile 1, and the expanded hole cement mixing pile anchoring section 202 can be used to reinforce the bottom of the steel pipe pile 1, thereby reducing the amount of material used for the expanded hole cement mixing pile 2, thereby being beneficial to saving costs, shortening construction period, and making the force of the construction method pile stable and reliable. By reinforcing the position between the reinforcement section 201 of the expanded hole cement mixing pile and the anchor section 202 of the expanded hole cement mixing pile by multiple reinforcing steel bars 3, the integrity and tensile strength of the entire expanded hole cement mixing pile 2 reinforcement structure can be improved, and a number of self-healing capsules 4 are mixed inside the expanded hole cement mixing pile 2. When the expanded hole cement mixing pile 2 cracks after long-term use, the cracks can be filled and repaired by the self-healing capsules 4 to restore the integrity of the expanded hole cement mixing pile 2 and enhance the durability and stability of the expanded hole cement mixing pile 2, thereby making the pile reinforcement structure of this method more conducive to practical use.
[0031] This specific embodiment is merely an explanation of the present invention and is not a limitation of the present invention. After reading this specification, those skilled in the art may make non-creative modifications to the present embodiment as needed. However, as long as they are within the scope of the claims of the present invention, they are protected by the patent law.
Claims
1. A construction pile reinforcement structure, comprising a plurality of steel pipe piles (1), characterized in that: The outer wall of the steel pipe pile (1) is provided with a hole-enlarging cement mixing pile (2), the hole-enlarging cement mixing pile (2) comprising a hole-enlarging cement mixing pile reinforcement section (201) and a hole-enlarging cement mixing pile anchoring section (202), the hole-enlarging cement mixing pile reinforcement section (201) being located in the middle of the steel pipe pile (1), and the hole-enlarging cement mixing pile anchoring section (202) being located at the bottom of the steel pipe pile (1); A plurality of reinforcing steel bars (3) are provided, wherein the plurality of reinforcing steel bars (3) are evenly located outside the steel pipe pile (1), and the top ends of the reinforcing steel bars (3) are located inside the reinforcement section (201) of the enlarged hole cement mixing pile, and the bottom ends of the reinforcing steel bars (3) are located inside the anchor section (202) of the enlarged hole cement mixing pile; and A plurality of self-healing capsules (4) are provided, and the plurality of self-healing capsules (4) are evenly located inside the hole-enlarging cement mixing pile (2).
2. A construction pile reinforcement structure according to claim 1, characterized in that: Reinforcement fiber filaments (10) are arranged inside the hole-enlarging cement mixing pile (2).
3. A construction pile reinforcement structure according to claim 1, characterized in that: Lock buckles (8) are fixedly connected to both sides of the outer wall of the steel pipe pile (1), and Larsen steel sheet piles (9) are arranged between the connected steel pipe piles (1), and one side of the Larsen steel sheet pile (9) is mutually engaged with the lock buckle (8).
4. A construction pile reinforcement structure according to claim 1, characterized in that: The top ends of the plurality of steel pipe piles (1) are all fixedly connected to a top pressure beam (5), and a drainage ditch (6) is provided on one side of the top pressure beam (5).
5. The method pile reinforcement structure according to claim 1, characterized in that: A basement cap (7) is arranged above the hole-enlarged cement mixing pile reinforcement section (201).
6. The method pile reinforcement structure according to claim 1, characterized in that: A first reinforcement ring (13) is fixedly connected to the interior of the hole-enlarging cement mixing pile reinforcement section (201), the upper surface of the reinforcement steel bar (3) is fixedly connected to the bottom of the first reinforcement ring (13), and a second reinforcement ring (14) is fixedly connected to the interior of the hole-enlarging cement mixing pile anchoring section (202), and the lower end surface of the reinforcement steel bar (3) is fixedly connected to the top of the second reinforcement ring (14).
7. The method pile reinforcement structure according to claim 1, characterized in that: The self-healing capsule (4) comprises a wrapping layer (401), wherein a repair agent (402) is stored inside the wrapping layer (401).
8. A construction pile reinforcement structure according to claim 7, characterized in that: The wrapping layer (401) is evenly and fixedly connected with pulling fiber threads (11), the inner wall of the wrapping layer (401) is fixedly connected with a pulling net (12), and one end of the pulling fiber threads (11) passes through the wrapping layer (401) and is fixedly connected to the pulling net (12).
9. A construction method for a pile reinforcement structure, characterized in that: The specific steps of the construction method are: Step 1: Use construction equipment for expanding the hole cement mixing pile (2) to drill into the bottom of the designed position of the steel pipe pile (1), open the expansion tail of the construction equipment, and construct the expansion cement mixing pile anchoring section (202) at the bottom elevation position of the designed position of the steel pipe pile (1). After the construction is completed, retract the expansion tail and lift the expansion tail to the middle of the designed position of the steel pipe pile (1); Step 2: In the middle of the designed position of the steel pipe pile (1), below the basement cap (7), the expansion tail wing is opened again to construct the expansion cement mixing pile reinforcement section (201). After the construction is completed, the expansion tail wing is folded and lifted to the ground to prepare for the construction of the next expansion cement mixing pile (2); Step 3: Evenly insert the reinforcing steel bars (3) on the hole-enlarging cement mixing pile (2), so that the top end of the reinforcing steel bars (3) is located in the reinforcement section (201) of the hole-enlarging cement mixing pile, and the bottom end is located in the anchoring section (202) of the hole-enlarging cement mixing pile; Step 4: After the construction of the enlarged cement mixing pile (2) is completed, the construction of the method pile is carried out in a timely manner. The method pile is composed of a plurality of steel pipe piles (1) and a plurality of Larsen steel sheet piles (9) arranged in an arranged manner. The method pile is passed through the enlarged cement mixing pile reinforcement section (201) and the enlarged cement mixing pile anchoring section (202), ensuring that the lower end of the method pile is embedded in the enlarged cement mixing pile anchoring section (202) to provide sufficient bearing capacity and stability; Step 5: After the construction of the construction method pile is completed, a top beam (5) is constructed on the upper end of the construction method pile to form the construction method pile into a whole to ensure the fixation of the upper end of the construction method pile, and a drainage ditch (6) is constructed on one side of the top beam (5).