Blind shot judgment and accurate positioning method based on traditional blasting vibration measurement system
By setting seismic wave monitoring points at the blasting site, calculating the seismic wave speed and the detonation time of the blind gun, and determining the position of the blind gun, the problem of traditional methods being unable to identify and locate blind guns, and the accurate identification and positioning of blind guns in complex blasting environments is achieved. , improve construction safety and efficiency.
Patent Information
- Application Number
- CN202411029784.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-30
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2044-07-30
AI Technical Summary
In complex multi-layer and rows of open-air rock blasts and underground or underwater blasts that cannot be directly observed, traditional methods cannot effectively identify and locate blind guns, resulting in construction safety hazards and potential serious casualties and equipment losses.
Using a method based on the traditional blasting vibration measurement system, the vibration time curve of the seismic wave is recorded by setting multiple seismic wave monitoring points around the blast source, the vibration time curve of the seismic wave is calculated, and the position and distance of the monitoring point are combined to calculate the blind The location area of the gun is selected and calculated repeatedly to ensure that the area overlap reaches 80% to determine the exact location of the blind gun.
Accurate identification and positioning of blind guns has been achieved, construction safety and efficiency have been improved, construction risks have been reduced, and safety hazards and equipment losses have been avoided due to blind guns.
Smart Images

Figure CN119063594A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of blasting, and in particular to a blind shot determination and precise positioning method based on a traditional blasting vibration measurement system. Background Art
[0002] At home and abroad, the identification of blind shots in open-pit rock blasting is still mainly based on direct observation of the blasting process and empirical comparison of the blast pile morphology after blasting. For complex large-scale blasting with multiple holes and rows and other underground or underwater blasting where the blasting process cannot be directly observed, traditional methods are obviously unable to identify and locate blind shots. In engineering, blasting design precedes drilling, charging, and networking construction, but in actual construction, it will change dynamically in combination with the on-site conditions, which leads to the fact that the pre-blasting design and the actual on-site construction cannot be completely guaranteed to be consistent. For example, there are large differences between the actual networking and the designed networking in the blasting area, there are differences between the actual number of blastholes and the designed number of blastholes, and there are often errors or even large deviations in the actual situation, which is different from the regular and accurate arrangement of the blasting area and blastholes on the design drawings. After blasting, considering the complexity of the on-site environment, it is often impossible to determine the position of the blind shot based on the terrain before blasting. Therefore, the location of the rejected blasthole cannot be accurately located by only following the drawings and waveforms. In addition, traditional visual inspection and empirical judgment itself bring certain safety hazards to construction personnel, and will also leave great safety hazards for subsequent slag removal and blasting operations. In the subsequent slag removal or blasting operation, the explosive packs left by the previous blasting failure are likely to be detonated, resulting in serious casualties and equipment and property losses. At present, there is no relatively accurate quantitative analysis method for the identification and positioning of blind shots in complex underground or underwater blasting processes at home and abroad. Summary of the invention
[0003] In view of the above problems, the present invention provides a method for blind shot determination and precise positioning based on a traditional blasting vibration measurement system.
[0004] The present invention adopts the following technical solutions:
[0005] A blind shot determination and precise positioning method based on a traditional blasting vibration measurement system comprises the following steps:
[0006] Step 1: Set up multiple seismic wave monitoring points in the rock mass or on the surface around the explosion source and install corresponding vibration monitoring instruments. Suppose there are m monitoring points in total, and perform joint timing for the vibration monitoring instruments at all monitoring points;
[0007] Step 2: Measure the straight-line distance from the first blasthole to each monitoring point. The distance from the ith monitoring point to the center of the explosive package is Li, where i∈(1,2,…,m), and record the position of the monitoring point relative to the blasting area.
[0008] Step 3: During the blasting process, the vibration time history curve of the blasting-induced seismic wave at each monitoring point is recorded by a vibration monitoring instrument. Combined with the adopted detonation design scheme and the detonation interval between holes, it is determined whether there is a missing wave crest. If there is a missing wave crest, it is determined that there is a blind shot, and a blind shot warning is issued. The detonation time before and after the blind shot is determined according to the corresponding time of the peak before and after the vacant position of the wave crest;
[0009] Step 4: Calculate the velocities of multiple groups of seismic waves by the distance between the first blasthole and the monitoring points and the time difference between the peak values of the vibration time history curves. The average seismic wave velocity of all groups is obtained by averaging the seismic wave velocities.
[0010] Step 5: Obtain the midpoint of the detonation time before and after the blind shot corresponding to each monitoring point, and obtain the detonation time of the blind shot corresponding to each monitoring point. Suppose the detonation time of the blind shot of the ith monitoring point is t i ;
[0011] Step 6: Calculate the distance from the blind shot to each monitoring point by the propagation time of the seismic wave at the blind shot. The distance calculation formula from the blind shot to the i-th monitoring point is:
[0012]
[0013] Among them, Δt is the delayed detonation time between holes, and T0 is the detonation time;
[0014] Step 7: Draw a circle with each monitoring point as the center and the distance from the corresponding monitoring point to the blind shot as the radius. The intersection area of the circles corresponding to all monitoring points is the location area of the blind shot.
[0015] Furthermore, assuming that the blind shot location area calculated in step 8 is S1, step 8 also includes step 9: selecting multiple new monitoring points and repeating steps 1-8 to obtain the blind shot location area S2 during the second calculation, and calculating the area overlap of the two results:
[0016]
[0017] If the area overlap P ≥ 80%, the calculation result can be considered reliable, and the overlapping area of S1 and S2 is taken as a more accurate blind shot position; if the area overlap P < 80%, it is necessary to select a new monitoring point to calculate the blind shot position again until the location area results of the two groups of blind shots that meet the area overlap requirements are obtained, and the overlapping area is taken as the final reliable blind shot position.
[0018] Furthermore, in step 1, m≥3.
[0019] Furthermore, in step 4, the velocity C of the pth group of seismic waves is calculated based on the i-th and j-th monitoring points. RpThe calculation formula is:
[0020]
[0021] t j1 , t i1 are the first blast hole detonation moments recorded at the j-th and i-th monitoring points respectively.
[0022] After adopting the above technical solution, the present invention has the following advantages compared with the prior art:
[0023] 1) Compared with the identification of blind shots in open-pit rock blasting at home and abroad, which still mainly adopts the method of direct observation of the blasting process and empirical comparison of the blast pile morphology after blasting, the present invention can realize the identification and positioning of blind shots in complex multi-layer and multi-row chamber blasting and other underground or underwater blasting where the blasting process cannot be directly observed, which is obviously impossible for traditional methods.
[0024] 2) Traditional visual inspection and empirical judgment cannot accurately determine the occurrence of blind shots, which in itself brings certain safety hazards to the observer and will also leave great safety hazards for subsequent slag removal or blasting operations. In the subsequent slag removal or blasting construction process, it is very likely that the explosive bags left by the previous blasting will be detonated, resulting in serious casualties and equipment and property losses. The present invention realizes the remote monitoring and positioning of blind shots, which can better ensure the safety of construction personnel and improve the efficiency of the construction process. Security .
[0025] 3) The present invention utilizes detection instruments to collect seismic wave data, and adopts a set of effective methods to calculate the location of the blind shot, thereby achieving more accurate positioning of the blind shot, eliminating construction risks, and also improving the efficiency and accuracy of the construction inspection process.
[0026] The present invention is described in detail below with reference to the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 is a flow chart of the method of the present invention;
[0028] Figure 2 Schematic diagram of monitoring point layout;
[0029] Figure 3 It is a schematic diagram of hole-by-hole detonation and blind shot generation in the blasting area;
[0030] Figure 4 This is the seismic wave vibration time history curve obtained by monitoring point #1 after joint timing;
[0031] Figure 5 Schematic diagram of blind shot positioning on a plane. DETAILED DESCRIPTION
[0032] The principles and features of the present invention are described below in conjunction with the accompanying drawings. The examples given are only used to explain the present invention and are not used to limit the scope of the present invention.
[0033] The principles and features of the present invention are described below in conjunction with the accompanying drawings. The implementation scheme is explained using a single blind shot and the same inter-hole delayed detonation time Δt as an example. The accuracy of the calculation result requires that the area overlap reaches 80%. The examples given are only used to explain the present invention and are not used to limit the scope of the present invention.
[0034] like Figure 1 As shown, the method of the present invention comprises the following steps:
[0035] 1. Arrangement and distance measurement of monitoring points before blasting;
[0036] 1) If Figure 2 As shown in the figure, monitoring points for blasting seismic waves are set in the rock mass or on the surface around the blasting source and corresponding vibration monitoring instruments are installed, and they should be distributed around the blasting area as much as possible to avoid monitoring points being too close;
[0037] 2) Jointly time the detection instruments at the monitoring point (i.e. calibrate the internal time of the detonator and the detection instrument to a unified standard time), i.e. adjust the time setting inside the detector so that the horizontal axis time of the obtained vibration time history curve is the standard time or consistent with the detonator time. Similarly, taking the first detonation hole B1 as an example, set the detonation time of B1 to T0, then the initial time in each detection instrument is T0;
[0038] 3) After arranging the monitoring points and detection instruments, measure the straight-line distance (including height difference) from the center of the explosive package to the seismic wave monitoring point, and record the location of the monitoring point relative to the explosion area. Figure 3 Taking the first blast hole B1 as an example, the distances from monitoring points #1, #2, and #3 are L1, L2, and L3 respectively;
[0039] 2. Measurement, observation and judgment of seismic waves during blasting;
[0040] 1) During the blasting process, the vibration monitoring instrument installed at the monitoring point records the vibration time history curve of the blasting-induced seismic wave, and the peak time corresponding to each blast hole n in the monitoring instrument is t in , for example, the peak time t in the curve of monitoring point #1 11 -t 16 Corresponding to 1-6 blast holes respectively, such as Figure 4 As shown;
[0041] 2) During the blasting process, the vibration time history curve of the seismic wave obtained by the vibration monitoring instrument was observed, and it was found that t 12 With t 14There is a time interval between two normal hole-by-hole detonations, so it is possible to quickly determine the occurrence of dangerous blind shots, which should be marked and notified in time to ensure the safety of the construction site;
[0042] 3. Processing of vibration time history curve after blasting and positioning of blind shots;
[0043] 1) The wave velocities of three groups of seismic waves are calculated by using the distance of the same detonation point relative to each monitoring point after joint timing and the time difference of the peak value of the vibration time history curve. In this embodiment, there are 3 monitoring points in total, and three groups of data can be measured by calculating two monitoring points separately:
[0044]
[0045] Three similar seismic wave velocities can be obtained from three monitoring points. If a more accurate velocity value is needed, the three can be averaged:
[0046] 2) The detonation time of the front and rear blast holes of the blind shot is known. According to the original blasting design and the detonation interval between holes, the time when the detonator at the blind shot should be detonated and the time of the corresponding vibration peak in the monitor are calculated. Under the same condition of delayed detonation between holes, the original detonation time of the blind hole is:
[0047]
[0048] where t 23 With t 33 They are the blind shot detonation times obtained at monitoring points #2 and #3 respectively;
[0049] 3) Calculate the distance from the blind shot to each monitoring point through the propagation time of the seismic wave at the blind shot:
[0050]
[0051] Where Δt is the delayed detonation time between holes;
[0052] 4) Use the distance from the blind shot to each monitoring point to establish the blind shot position relative to the monitoring point position and draw an image in plane coordinates, such as Figure 5 As shown, circles are drawn with the monitoring point as the center and the distance from the monitoring point to the blind shot as the radius. The intersection area of multiple circles is the blind shot location area S1 (x, y).
[0053] 5) Select a new set of monitoring point data and repeat the above steps to obtain the new blind shot distance R in formula (3): 43 , R 53 , R 63 , and get S2(x,y), then calculate the area overlap of the two results:
[0054]
[0055] If the area overlap P ≥ 80%, the calculation result can be considered reliable, and the overlapping area of S1(x, y) and S2(x, y) is taken as a more accurate blind shot position; if the area overlap P < 80%, it is necessary to select new monitoring points to calculate the blind shot position until the location area results of the two groups of blind shots that meet the area overlap requirements are obtained as the final reliable blind shot position.
[0056] The above is an example of the best implementation of the present invention, and the parts not described in detail are common knowledge of ordinary technicians in the field. The protection scope of the present invention shall be based on the content of the claims, and any equivalent transformation based on the technical enlightenment of the present invention is also within the protection scope of the present invention.
Claims
1. A blind shot determination and precise positioning method based on a traditional blasting vibration measurement system, characterized in that: The following steps are involved: Step 1: Set up multiple seismic wave monitoring points in the rock mass or on the surface around the explosion source and install corresponding vibration monitoring instruments. Suppose there are m monitoring points in total, and perform joint timing for the vibration monitoring instruments at all monitoring points; Step 2: Measure the straight-line distance from the first blasthole to each monitoring point. The distance from the ith monitoring point to the center of the explosive package is Li, where i∈(1,2,…,m), and record the position of the monitoring point relative to the blasting area. Step 3: During the blasting process, the vibration time history curve of the blasting-induced seismic wave at each monitoring point is recorded by a vibration monitoring instrument. Combined with the adopted detonation design scheme and the detonation interval between holes, it is determined whether there is a missing wave crest. If there is a missing wave crest, it is determined that there is a blind shot, and a blind shot warning is issued. The detonation time before and after the blind shot is determined according to the corresponding time of the peak before and after the vacant position of the wave crest; Step 4: Calculate the velocities of multiple groups of seismic waves by the distance between the first blasthole and the monitoring points and the time difference between the peak values of the vibration time history curves. The average seismic wave velocity of all groups is obtained by averaging the seismic wave velocities. Step 5: Obtain the midpoint of the detonation time before and after the blind shot corresponding to each monitoring point, and obtain the detonation time of the blind shot corresponding to each monitoring point. Suppose the detonation time of the blind shot of the ith monitoring point is t i ; Step 6: Calculate the distance from the blind shot to each monitoring point by the propagation time of the seismic wave at the blind shot. The distance calculation formula from the blind shot to the i-th monitoring point is: Among them, Δt is the delayed detonation time between holes, and T0 is the detonation time; Step 7: Draw a circle with each monitoring point as the center and the distance from the corresponding monitoring point to the blind shot as the radius. The intersection area of the circles corresponding to all monitoring points is the location area of the blind shot.
2. The blind shot determination and precise positioning method based on the traditional blasting vibration measurement system according to claim 1 is characterized in that: Assume that the blind shot location area calculated in step 8 is S1, and step 8 also includes step 9: select multiple new monitoring points and repeat steps 1-8 to obtain the blind shot location area S2 in the second calculation, and calculate the area overlap of the two results: If the area overlap P ≥ 80%, the calculation result can be considered reliable, and the overlapping area of S1 and S2 is taken as a more accurate blind shot position; if the area overlap P < 80%, it is necessary to select a new monitoring point to calculate the blind shot position again until the location area results of the two groups of blind shots that meet the area overlap requirements are obtained, and the overlapping area is taken as the final reliable blind shot position.
3. The blind shot determination and precise positioning method based on the traditional blasting vibration measurement system according to claim 1 is characterized in that: In step 1, m ≥ 3.
4. The blind shot determination and precise positioning method based on the traditional blasting vibration measurement system according to claim 1 is characterized in that: In step 4, the velocity C of the pth group of seismic waves is calculated based on the i-th and j-th monitoring points. Rp The calculation formula is: t j1 , t i1 are the first blast hole detonation moments recorded at the j-th and i-th monitoring points respectively.
Citation Information
Patent Citations
Misfire detecting method by means of blast vibration waves
CN103256874A
Method for analyzing and identifying misfire by utilizing electronic chip detonator blast vibration waves
CN107401958A
Method and system for determining the location of a seismic event
WO2023023750A2
Cited By
Cross-border mining identification and accurate positioning method based on all-weather wireless blasting vibration system
CN120742404A
Blasting effect evaluation method and system based on GNSS high-precision space-time reference
CN122041689A
Rapid identification method for blasthole blind shots in tunnel blasting excavation
CN122510523A