BIM (Building Information Modeling)-based high-speed railway precast beam steel bar optimization processing method and application
Through BIM technology, the three-dimensional model and processing process of railway prefabricated beam reinforcement is optimized, and the problems of waste of resources and insufficient safety in traditional design are solved, achieving more efficient construction and lower cost steel frame production.
Patent Information
- Application Number
- CN202411122726.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-15
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2044-08-15
AI Technical Summary
The design of traditional railway prefabricated beam reinforcement bars lacks optimization for specific geographical environments and load conditions, resulting in excessive resource consumption, insufficient structural durability and safety, and high design complexity and construction costs.
Using BIM technology to create a three-dimensional model of steel bars, optimize the layout and quantity of steel bars through structural response and stress analysis, and use intelligent welding equipment and CNC bending center for fine processing and splicing to optimize the position of steel bars, top plate, bottom web, longitudinal and transverse steel bars Design to reduce interference and resource consumption.
It improves construction efficiency, reduces resource consumption and construction costs, enhances the durability and safety of the steel frame, and simplifies the design and installation process.
Smart Images

Figure CN119066746A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of building construction, and in particular to a BIM-based high-speed railway prefabricated beam reinforcement optimization processing method and application. Background Art
[0002] Railway precast beams are key structural components in modern railway construction. In traditional precast beam production, the components mainly include the beam body itself, which is composed of a steel skeleton and concrete. The steel skeleton is the core component of precast beams, and its design and manufacturing quality directly affect the safety and economy of railway lines. The production process of the steel skeleton includes cutting, bending and welding of steel bars to form steel components of predetermined shapes and sizes, and assembling them into a complete steel skeleton on the assembly platform according to the design drawings.
[0003] When designing traditional railway prefabricated beams, the arrangement and amount of steel bars often follow a fixed standard model, lacking refined optimization for specific geographical environments, load conditions, and material properties, which leads to excessive consumption of resources and may also affect the durability and safety of the structure due to insufficient design redundancy. In addition, the steel skeleton of railway prefabricated beams uses a two-dimensional design, with a large number of steel bars and a complex structure. It is very easy for steel bar components to interfere with each other. The design optimization process of the steel skeleton is relatively difficult, and the steel bar binding and installation process is time-consuming and labor-intensive, with high construction costs. Summary of the invention
[0004] The purpose of the present invention is to provide a BIM-based high-speed railway prefabricated beam reinforcement optimization processing method to solve the problems raised in the above background technology.
[0005] To achieve the above object, the present invention provides the following technical solutions:
[0006] A method for optimizing reinforcement processing of high-speed railway prefabricated beams based on BIM, comprising the following steps:
[0007] S1, based on BMI technology, a three-dimensional model of precast beam reinforcement is created, and various output files are calculated by setting SATWE pre-processing parameters, and the overall calculation indicators are compared, such as structural response, stress and strain analysis under different loads, and an optimization design calculation model for the reinforcement skeleton is proposed;
[0008] S2, optimizing the design, construction and application of the three-dimensional model, wherein the optimization method includes: adjusting the position of the steel bars, optimizing the top plate steel bars, optimizing the bottom web steel bars, optimizing the longitudinal and transverse steel bars, and optimizing the positioning mesh;
[0009] S3, design and process prefabricated components according to the optimization plan, make steel bars into prefabricated steel bars of different specifications, and splice and install the prefabricated components.
[0010] As a preferred solution of the present invention, the SATWE pre-processing parameters in step S1 include setting basic information, earthquake information, wind load information and global analysis parameters.
[0011] As a preferred solution of the present invention, the optimization of the top plate reinforcement in S2 includes: connecting the bottom plate longitudinal reinforcement into one piece, or changing it into three-piece connection.
[0012] As a preferred embodiment of the present invention, the bottom web reinforcement optimization in step S2 includes: inserting reinforcing bars one by one at the upper and lower corners of the small U-shaped bars.
[0013] As a preferred embodiment of the present invention, the optimization of longitudinal and transverse reinforcement in step S2 includes: the longitudinal reinforcement of the outer ring of the box girder is continuous and has no hooks, the longitudinal reinforcement of the inner ring of the box girder is divided into three pieces and is set as hooks, and the hook of the inner stirrup of the web is changed from 135° to a flat hook.
[0014] As a preferred embodiment of the present invention, the positioning mesh optimization in step S2 includes: connecting the positioning mesh steel bars and the inner circle steel cage into a whole.
[0015] As a preferred embodiment of the present invention, the steel bar optimization equipment includes: intelligent steel strip mesh welding equipment, steel mesh welding equipment, box girder positioning mesh intelligent welding equipment, CNC steel bar hydraulic shearing equipment, and large U-shaped steel bar bending center.
[0016] As a preferred embodiment of the present invention, the large U-shaped steel bar bending center comprises: a stepped feeding structure, a steel bar positioning structure, and a large U-shaped steel bar bending structure;
[0017] The steel bar positioning structure includes a photoelectric sensor and a feeding positioning fixture, the feeding positioning fixture includes a base, a clamping block is fixedly installed on one side of the base, a cylinder shell is installed on the other side of the base, an inner push cylinder is installed inside the cylinder shell, the front end of the inner push cylinder is fixedly connected to the inner push block, the space formed by the base, the clamping block and the inner push block is a clamping groove, a rodless cylinder arranged perpendicular to the movement direction of the inner push block is fixedly connected below the base, a support seat for supporting the feeding positioning fixture is connected to the bottom of the rodless cylinder, a connecting seat is fixedly installed on the inner push cylinder side of the support seat, and the support seat is fixedly connected to the mechanical arm through the connecting seat, there are at least three feeding positioning fixtures, which are evenly arranged to clamp the center and both ends of the steel bar respectively, there are two photoelectric sensors, which are symmetrically installed on both sides of the positioning structure, and the photoelectric sensor positioning and identification is at the bottom of the clamping groove and close to the clamping block side;
[0018] The large U-shaped steel bar bending structure includes a bending positioning fixture, a first bending mechanism, and a second bending mechanism. The bending positioning fixture is fixedly connected to a mechanical arm, a small bending head is fixedly installed above the first bending mechanism, and a large bending head is fixedly installed above the second bending mechanism.
[0019] Another object of the present invention is to provide a BIM-based high-speed railway prefabricated beam reinforcement optimization processing method for application in the construction of railway prefabricated box girders.
[0020] Compared with the prior art, the present invention has the following beneficial effects:
[0021] In the present invention, the BIM technology is used to perform all-round three-dimensional modeling of the steel skeleton of the railway prefabricated beam, and the feasibility analysis and optimization of the steel skeleton are carried out during the design, the steel interference problem is eliminated in advance, the steel skeleton assembly construction process is simulated, the installation is carefully planned, and the construction efficiency is improved. For the large U-shaped steel bar bending center, the fixed-length shear structure in the prior art is eliminated, which reduces resource consumption and construction costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] By reading the following detailed description with reference to the accompanying drawings, the above and other objects, features and advantages of the exemplary embodiments of the present invention will become readily understood. In the accompanying drawings, several embodiments of the present invention are shown in an exemplary and non-limiting manner, and the same or corresponding reference numerals represent the same or corresponding parts, wherein:
[0023] Figure 1 This is an example diagram of steel bar position optimization provided in Example 1 of the present invention;
[0024] Figure 2 An example diagram of steel bar top plate optimization provided in Example 1 of the present invention;
[0025] Figure 3 This is an example diagram of bottom web reinforcement optimization provided in Example 1 of the present invention;
[0026] Figure 4 This is an example diagram of longitudinal reinforcement optimization provided in Example 1 of the present invention;
[0027] Figure 5 This is an example diagram of the optimization of the web inner stirrup N15 provided in Example 1 of the present invention;
[0028] Figure 6 This is an example diagram of the optimization of the upper reinforcement N35 of the bottom plate provided in Example 1 of the present invention;
[0029] Figure 7 This is an example diagram of positioning mesh optimization provided in Example 1 of the present invention;
[0030] Figure 8This is an example diagram of the three-dimensional structure of the loading and positioning fixture provided in Example 1 of the present invention;
[0031] Description of reference numerals:
[0032] 1. Base; 2. Clamping block; 3. Cylinder housing; 4. Inner push cylinder; 5. Inner push block; 6. Rodless cylinder; 7. Support seat; 8. Connecting seat; 9. Clamping groove. DETAILED DESCRIPTION
[0033] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Those skilled in the art should know that the embodiments described below are part of the embodiments of the present disclosure, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present invention.
[0034] In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "top / bottom" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific position, be constructed and operated in a specific position, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.
[0035] Embodiment 1, the present invention provides a technical solution:
[0036] The present invention accurately creates a three-dimensional model of precast beam steel bars based on BMI technology. BMI technology allows for detailed definition of building material properties, so that the three-dimensional model of the steel bars can accurately reflect their material properties, dimensions and position information. Structural analysis and calculation are performed by setting SATWE pre-processing parameters. SATWE pre-processing parameters include but are not limited to basic information, earthquake information, wind load information and global analysis parameters, etc., and then multiple files are output. The files include structural responses, stress and strain analysis under various loads. These output files can be compared and analyzed in detail, and the performance of the precast beam steel bar skeleton under various working conditions can be comprehensively evaluated, and the layout, structure, quantity or connection method of the steel bar skeleton can be optimized and adjusted based on this.
[0037] By optimizing the design, construction and application of the three-dimensional model, the optimization methods include: adjusting the position of the steel bars, optimizing the top plate steel bars, optimizing the bottom web steel bars, optimizing the longitudinal and transverse steel bars, and optimizing the positioning mesh.
[0038] like Figure 1As shown, the method for optimizing the position of steel bars provided by the embodiment of the present invention includes: placing the longitudinal full-length steel bars of the top plate of the steel skeleton when assembling the mesh, wherein the original steel bars N5 and the steel bars N7 are placed side by side, and the full-length steel bars N14 are located below the two, and now the steel bars N7 are shortened so that the original position relationship becomes the steel bars N5, the full-length steel bars N14, and the steel bars N7, and in addition, the bottom full-length steel bars N16 are placed outside the hooks of the inner stirrups N15 of the web and the upper steel bars N35 of the bottom plate;
[0039] The steel bar position optimization method can avoid interference caused during the assembly of the steel skeleton mesh. By adjusting the length of steel bar N7 and the positions of full-length steel bars 14 and N16, the problem that the full-length steel bars cannot be hooked in is solved, the mesh assembly requirements are met, and the construction difficulty is reduced.
[0040] like Figure 2 As shown, the steel bar top plate optimization method provided by the embodiment of the present invention includes: Figure 2 As shown in 2b, connect the steel bars of each section of the bottom plate into one, or as shown in Figure 2 As shown in 2c, the steel bars of each section of the bottom plate are connected in three sections;
[0041] like Figure 2 As shown in Figure 2a, since the bottom of the precast beam bridge deck needs to have a gradual thickness according to the cross-section, its bottom layer of steel bars is mostly arranged along its gradual cross-section. Therefore, the above steel bar top plate optimization method can reduce the lap length of the relevant steel bars and reduce production costs.
[0042] like Figure 3 As shown, the bottom web reinforcement optimization provided by the embodiment of the present invention includes: inserting reinforcing bars one by one at the upper and lower corners of the small U-shaped bars;
[0043] The bottom web reinforcement optimization method strengthens the local strength and stiffness of the beam by inserting the reinforcement bars one by one. At the same time, the method of inserting one by one during assembly also avoids the interference between the steel bars caused by the assembly of steel bars in pieces. This optimization method can more accurately control the position and number of reinforcement bars.
[0044] like Figure 4-Figure 6 As shown, the longitudinal and transverse reinforcement optimization provided by the embodiment of the present invention includes: the longitudinal reinforcement of the outer ring of the box beam is continuous and has no hooks, the longitudinal reinforcement of the inner ring of the box beam is divided into three pieces, and the inner ring longitudinal reinforcement is provided with hooks. At the same time, the hooks of the bent reinforcement at the end of the top plate beam can be cancelled according to actual conditions, and the bottom plate and the web plate still maintain the original design with hooks. This optimization method avoids the interference of the lengthened reinforcement with the prestressed pipe;
[0045] For a single monolithic frame, the hook of the inner stirrup of the web can be changed from 135° to a flat hook. This optimization method facilitates the welding or binding of the flat hook of the inner stirrup N15 of the web with the upper steel bar N35 of the bottom plate to form an integral frame. For the upper steel bar N35 of the bottom plate, the anchorage length can be shortened, and a straight end scheme can be considered for the upper steel bar N35 of the bottom plate, which is convenient for construction. However, the upper steel bar N35 of the bottom plate needs to be welded or firmly bound to the inner stirrup N15 of the web and the longitudinal steel bars. The upper steel bar N35 of the bottom plate is a transverse force-bearing steel bar, and the anchorage length should meet 35d.
[0046] like Figure 7 As shown, the positioning mesh optimization provided by the embodiment of the present invention includes: connecting the positioning mesh steel bars and the inner ring steel cage to form a stable overall structure, and the connection can be made by welding, tying or other effective connection methods to ensure that the connection between the two is firm and reliable;
[0047] If the installation of the precast beam reinforcement skeleton is carried out in the order of arranging the large U-bar and longitudinal bars on the outside of the web, inserting the positioning mesh reinforcement, installing the inner ring reinforcement cage, and installing the upper layer of the reinforcement mesh, the transverse reinforcement in the positioning mesh reinforcement is welded to the inner and outer steel stirrups of the web. When the inner ring reinforcement cage is hoisted and installed from above with the longitudinal reinforcement, the spacing between the transverse reinforcement of the positioning mesh and the longitudinal reinforcement of the inner ring reinforcement cage is theoretically only 12 mm. Considering the deformation of the reinforcement cage, interference will occur. The positioning mesh optimization method can avoid the interference problem between the reinforcement mesh and the reinforcement cage.
[0048] like Figure 8 As shown, the large U-shaped steel bar bending center provided by the embodiment of the present invention includes: a stepped feeding structure, a steel bar positioning structure, and a large U-shaped steel bar bending structure;
[0049] The steel bar positioning structure includes a photoelectric sensor and a feeding positioning fixture. The feeding positioning fixture includes a base 1. A clamping block 2 is fixedly installed on one side of the base 1. A cylinder shell 3 is correspondingly installed on the other side of the base 1. The cylinder shell 3 is fixedly connected to the base 1. An inner push cylinder 4 is fixedly installed inside the cylinder shell 3. An inner push block 5 is fixedly connected to the front end of the inner push cylinder 4. The inner push cylinder 4 can drive the inner push block 5 to move toward the clamping block 2 to complete the preliminary positioning of the steel bar. The space formed between the base 1, the clamping block 2 and the inner push block 5 is a clamping groove 9. A clamping groove 9 is fixedly connected to the bottom of the base 1 and is arranged perpendicular to the movement direction of the inner push block 5. A rodless cylinder 6, a support seat 7 for supporting a loading positioning fixture is fixedly connected to the bottom of the rodless cylinder 6, a connecting seat 8 is fixedly installed on one side of the inner push cylinder 4 on the support seat 7, and the support seat 7 is fixedly connected to the mechanical arm through the connecting seat 8. There are at least three loading positioning fixtures, which are evenly arranged to clamp the center and both ends of the steel bar respectively. There are two photoelectric sensors, which are symmetrically installed on both sides of the positioning structure. The photoelectric sensor is positioned and identified at the bottom of the clamping groove 9 and close to the side of the clamp block 2. When the steel bar is initially positioned, the photoelectric sensor can be used to identify the distance between the end point of the steel bar and the photoelectric sensor;
[0050] The large U-shaped steel bar bending structure includes a bending positioning fixture, a first bending mechanism, and a second bending mechanism. The bending positioning fixture is fixedly connected to a mechanical arm, a small bending machine head is fixedly installed above the first bending mechanism, and a large bending machine head is fixedly installed above the second bending mechanism.
[0051] In the description of the operational process of the implementation stage of the present invention, after the device is activated, the first step involves the orderly conveying and lifting of the steel bars by the stepped feeding structure. When the conveying process reaches the predetermined high position, the steel bars will smoothly transition and accurately slide into the clamping groove 9 of the feeding positioning fixture. Then, the rodless cylinder 6 component in the system is activated, and the initial accurate positioning of the steel bars is completed by driving the inner push block 5 to move along the predetermined trajectory. After this stage, the configured high-sensitivity photoelectric sensor group intervenes, and by accurately measuring the distance from the two ends of the steel bar to the sensor, and converting this displacement information into an electrical signal, the rodless cylinder 6 is immediately instructed to make fine adjustments to ensure that the distance between the two ends of the steel bar is completely consistent, that is, the positioning of the steel bar is completed;
[0052] After the positioning program is completed, the pre-programmed robotic arm system starts, and controls the loading and positioning fixture to smoothly transfer the positioned steel bars to the first bending mechanism. At this time, the bending and positioning fixture is immediately connected to firmly clamp the steel bars. At the same time, the loading and positioning fixture is automatically released and reset to the initial state. Next, the first bending mechanism program starts, and a small bend is formed at both ends of the steel bar. Then the bending and positioning fixture works together again to transfer the steel bar to the second bending mechanism, and the steel bar is formed into a large U-shaped bar as a whole.
[0053] In the prior art, the large U-shaped steel bar bending center includes a fixed-length shearing structure, and a certain margin needs to be reserved for the steel bars during processing. After the steel bars pass through the stepped feeding structure, the fixed-length shearing structure performs fixed-length positioning shearing on the steel bars, and then sends them to the clamp structure, thereby realizing the positioning production of the steel bars by the clamp. The large U-shaped steel bar bending center provided in this embodiment improves the steel bar positioning structure, and no margin needs to be reserved for the steel bars during production, thereby avoiding steel bar cutting and recycling the cut steel bar heads, reducing energy consumption and saving construction costs.
[0054] Embodiment 2 is different from Embodiment 1 mainly in that:
[0055] The transverse reinforcement optimization method provided in Example 2 of the present invention sets a hook or anchor plate scheme for the upper reinforcement N35 of the bottom plate. This scheme reduces the used length of the reinforcement by 320 mm and can avoid interference with the outer reinforcement of the web.
[0056] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A method for optimizing the steel bars of high-speed railway prefabricated beams based on BIM, characterized in that: The following steps are involved: S1, based on BMI technology, a three-dimensional model of precast beam reinforcement is created, and various output files are calculated by setting SATWE pre-processing parameters, and the overall calculation indicators are compared, such as structural response, stress and strain analysis under different loads, and an optimization design calculation model for the reinforcement skeleton is proposed; S2, optimizing the design, construction and application of the three-dimensional model, wherein the optimization method includes: adjusting the position of the steel bars, optimizing the top plate steel bars, optimizing the bottom web steel bars, optimizing the longitudinal and transverse steel bars, and optimizing the positioning mesh; S3, design and process prefabricated components according to the optimization plan, make steel bars into prefabricated steel bars of different specifications, and splice and install the prefabricated components.
2. The BIM-based high-speed railway prefabricated beam reinforcement optimization processing method according to claim 1 is characterized in that: The SATWE pre-processing parameters in step S1 include setting basic information, earthquake information, wind load information and global analysis parameters.
3. The BIM-based high-speed railway prefabricated beam reinforcement optimization processing method according to claim 1 is characterized in that: The optimization of the top plate reinforcement in S2 includes: connecting the bottom plate longitudinal reinforcement into one piece, or changing it into three-piece connection.
4. The BIM-based high-speed railway prefabricated beam reinforcement optimization processing method according to claim 1 is characterized in that: The bottom web reinforcement optimization in step S2 includes: inserting reinforcing bars one by one at the upper and lower corners of the small U-shaped bars.
5. The BIM-based high-speed railway prefabricated beam reinforcement optimization processing method according to claim 1 is characterized in that: The optimization of longitudinal and transverse reinforcement in step S2 includes: the longitudinal reinforcement of the outer ring of the box girder is continuous and has no hooks, the longitudinal reinforcement of the inner ring of the box girder is divided into three pieces and is set as hooks, and the hook of the inner stirrup of the web is changed from 135° to a flat hook.
6. The BIM-based high-speed railway prefabricated beam reinforcement optimization processing method according to claim 1 is characterized in that: The positioning mesh optimization in step S2 includes: connecting the positioning mesh steel bars and the inner circle steel cage into a whole.
7. The BIM-based high-speed railway prefabricated beam reinforcement optimization processing method according to claim 1 is characterized in that: The steel bar optimization equipment includes: intelligent steel strip mesh welding equipment, steel mesh welding equipment, box girder positioning mesh intelligent welding equipment, CNC steel bar hydraulic shearing equipment, and large U-shaped steel bar bending center.
8. The BIM-based high-speed railway prefabricated beam reinforcement optimization processing method according to claim 1 is characterized in that: The large U-shaped steel bar bending center includes: a stepped feeding structure, a steel bar positioning structure, and a large U-shaped steel bar bending structure; The steel bar positioning structure includes a photoelectric sensor and a feeding positioning fixture, the feeding positioning fixture includes a base, a clamping block is fixedly installed on one side of the base, a cylinder shell is installed on the other side of the base, an inner push cylinder is installed inside the cylinder shell, the front end of the inner push cylinder is fixedly connected to the inner push block, the space formed by the base, the clamping block and the inner push block is a clamping groove, a rodless cylinder arranged perpendicular to the movement direction of the inner push block is fixedly connected below the base, a support seat for supporting the feeding positioning fixture is connected to the bottom of the rodless cylinder, a connecting seat is fixedly installed on the inner push cylinder side of the support seat, and the support seat is fixedly connected to the mechanical arm through the connecting seat, there are at least three feeding positioning fixtures, which are evenly arranged to clamp the center and both ends of the steel bar respectively, there are two photoelectric sensors, which are symmetrically installed on both sides of the positioning structure, and the photoelectric sensor positioning and identification is at the bottom of the clamping groove and close to the clamping block side; The large U-shaped steel bar bending structure includes a bending positioning fixture, a first bending mechanism, and a second bending mechanism. The bending positioning fixture is fixedly connected to a mechanical arm, a small bending head is fixedly installed above the first bending mechanism, and a large bending head is fixedly installed above the second bending mechanism.
9. Application of the BIM-based high-speed railway prefabricated beam reinforcement optimization processing method according to any one of claims 1 to 8 in the construction of railway prefabricated box girders.
Citation Information
Patent Citations
BIM-based steel reinforced concrete joint construction method
CN112854758A
Railway prefabricated box girder U-shaped rib machining method
CN113477835A
Component splitting method suitable for intelligent construction of railway precast beam reinforcement cage and application
CN114919061A
Industrial intelligent manufacturing method and equipment for cast-in-place box girder reinforcing steel bar component
CN118237514A
Reinforcing bar delivery support system and reinforcing bar delivery support method
JP2023171112A