Coal power unit scheduling method considering carbon-electricity coupling

The coal-fired power unit scheduling method integrates economic and environmental objectives through piecewise functions and Euclidean distance optimization, addressing the challenge of balancing profit and emissions in coal-fired power plants.

CN119070280APending Publication Date: 2024-12-03STATE GRID ANHUI ELECTRIC POWER CO LTD ELECTRIC POWER SCI RES INST +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411122413.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-15
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

Existing coal-fired power plants face challenges in balancing economic benefits with environmental protection goals, particularly in reducing coal consumption and carbon emissions while optimizing scheduling to meet profit and emission reduction requirements.

Method used

A coal-fired power unit scheduling method considering carbon-electricity coupling, utilizing piecewise cubic and sine sum functions for coal consumption, profit maximization, and carbon emission minimization, combined with a multi-objective Euclidean distance optimization to integrate these objectives into a single objective function.

Benefits of technology

The method provides a balanced solution that minimizes coal consumption, maximizes profits, and reduces carbon emissions, offering a comprehensive analysis of revenue changes under dual market operations, thus alleviating market pressures.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119070280A_ABST
    Figure CN119070280A_ABST
Patent Text Reader

Abstract

The invention discloses a coal power unit scheduling method considering carbon-electricity coupling. The method comprises two parts of optimization target setting and constraint condition setting, wherein the optimization target setting comprises minimum total coal consumption of the coal power plant, maximum profit of the coal power plant and minimum carbon emission of the coal power plant. According to the method, the income change characteristics of the coal power unit under the carbon power double-market operation condition are analyzed through a multi-dimensional analysis method, and the method can be used for group income change characteristic analysis of different types of coal power units on the provincial power supply side under the double-market operation condition; the operation mode and the cost income condition of the coal power unit are evaluated under the carbon power double-market parallel condition, and reference is provided for relieving multi-aspect pressure faced by the power market.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of economic dispatching of the thermal power generation industry under the condition of coexistence of carbon market expansion and electricity market, and in particular to a method for dispatching coal-fired power units taking into account carbon-electricity coupling. Background Art

[0002] With the expansion of the carbon market, reducing the amount of coal used for power generation is very important for China's coal-fired power plants, which mainly use coal for power generation.

[0003] Due to the large total base of greenhouse gas emissions, global greenhouse gases have increased. The power system is the most important factor in producing greenhouse gases. Since the greenhouse gases produced by the power system mainly come from coal-fired power plants, the carbon dioxide emissions of power plants are mainly determined by coal consumption. How to reduce the cost of power generation, reduce coal use and pollutant emissions while taking into account the benefits of coal-fired power plants and environmental benefits is an issue that needs to be discussed. Coal-fired power generation units can achieve the best power generation efficiency and economic benefits by selecting a design charcoal type that is usually not suitable for power plants.

[0004] Traditional planning is a unilateral decision aimed at minimizing the use or production cost of coal, without considering the negative impact of energy markets or power plant emissions on the environment, just for profit. Now, my country has clear emission reduction requirements in energy to reduce energy emissions for energy efficiency, which requires careful consideration of how to optimize the use of multiple objectives for optimal scheduling to promote economic benefits and protect the environment.

[0005] In multi-objective decision-making, many objective phenomena and behaviors are contradictory, so some realistic methods are needed to seek the global optimal solution under multiple objective functions. The multi-objective optimization of the time domain model is used to solve the problem, find a balance between economic benefits and many key environmental protection goals of the economic environment of coal-fired power plants, and evaluate the role of Euclidean distance construction. By analyzing the impact of coal consumption in power plants and the efficiency and superiority of optimal timing multi-objectives, a multi-objective optimal scheduling model for the economic environment of coal-fired power plants is established, and the multi-objective problem of balancing the economic benefits of power plants and multiple environmental protection goals is solved by using the Euclidean distance estimation function. Summary of the invention

[0006] The technical problem to be solved by the present invention is to provide a coal-fired power unit scheduling method taking carbon-electricity coupling into consideration.

[0007] In order to solve the above technical problems, the technical solution adopted by the present invention is a coal-fired power unit scheduling method considering carbon-electricity coupling, comprising the following steps:

[0008] 1. Optimize goal setting

[0009] 1) The total coal consumption of coal-fired power plants is minimal

[0010] The coal consumption and unit output of coal-fired power units are piecewise functions composed of cubic curves and sine sum functions:

[0011]

[0012] Where: f1 is the total coal consumption of all coal-fired power units in one year, Ton; T is the total number of weeks in a year; N is the number of coal-fired power units; P it is the output (MWh) of the coal-fired power unit numbered i in period t; a1, a2, a3 are the amplitudes of the sine function, b1, b2 are the angular frequency coefficients of the sine sum function, c1, c2 are the phase angles; p1, p2, p3, p4 are the coal consumption coefficients of coal-fired power unit i, and the units are Ton / MWh respectively 3 , Ton / MWh 2 , Ton / MWh, Ton.

[0013] 2) Coal-fired power plants have the highest profits

[0014] The profit of a coal-fired power plant is the total electricity sales revenue of the coal-fired power unit minus its total power generation cost; the electricity sales revenue is the product of the electricity sales price and power generation of each power plant in the power market, and the power generation cost is the coal consumption cost and carbon cost. The specific functional relationship is:

[0015]

[0016] Where: f2 is the total profit of the power grid for coal-fired power units in one year, in yuan; ρ i is the on-grid electricity price of unit i (yuan / MWh); C we is the unit price of coal used, C tj is the carbon price;

[0017] 3) Coal-fired power plants have the lowest carbon emissions

[0018] The minimum carbon emissions from coal-fired power plants can be expressed by a cubic polynomial:

[0019] f3=q1P it 3 +q2P it 2 +q3P it +q4 (3)

[0020] Where: f3 is the total carbon emissions in a year (t); T is the total number of time periods in a year; N is the number of coal-fired power units i; P it is the active power output of unit i in period t (MWh); q1, q2, q3, q4 are the carbon emission coefficients of unit i, and the units are Ton / MWh respectively. 3 , Ton / MWh 2, Ton / MWh, Ton.

[0021] 4) Multi-target Euclidean distance

[0022] To solve the multi-objective optimization problem, the key is to consider the requirements of each objective; generally speaking, the optimal solution of one objective is almost impossible, or there is a small probability that it is the optimal solution of other objectives; under the condition of sacrificing the optimal decision to achieve all objectives, the relationship between the various objectives is coordinated to achieve an overall solution; in the present invention, a standard Euclidean function is constructed to convert multiple objectives into a single objective to be solved for solving;

[0023] Consider the multi-objective decision problem (MOP):

[0024]

[0025] Where: F(x), G(x) are the respective objective functions, and are continuous functions on their domain X;

[0026] For multi-objective decision-making problems, we can reconstruct the multi-objective evaluation function and regard the multi-objective function as a single-objective problem; based on the single objective, we can get an evaluation function to solve the multi-objective decision-making problem, namely, the multi-objective Euclidean distance

[0027]

[0028] Where: z(x) is the Euclidean distance between the target functions; is the optimal solution of the single objective normalized function, i.e., d i (x); Find the minimum value of the Euclidean distance z(x) to get the optimal solution x under the multi-objective decision function * , this optimal solution is one of the Pareto optimal solutions under multi-objective decision making.

[0029] 2. Constraints

[0030] 5) System power balance constraints

[0031]

[0032] Where: P it is the active power output of coal-fired power unit i in period t; P ddi is the dispatching power between the i-th coal-fired power unit and other coal-fired power units; P si The power of line loss during dispatch between No. i coal-fired power unit and other coal-fired power units; P Li is the total system load at time t;

[0033] 6) Upper and lower limits of coal-fired power unit output power

[0034] P imin ≤P i ≤P imax (7)

[0035] Where: P imin is the lower limit of power generation of coal-fired power unit i; P imax is the upper limit of power generation of coal-fired power unit i;

[0036] 7) Upper and lower limits of dispatching power

[0037]

[0038] Where: P dd is the dispatching power of the line, is the maximum power allowed on the transmission line.

[0039] The beneficial effects of the present invention are:

[0040] The multi-dimensional analysis method is used to analyze the changing characteristics of coal-fired power unit revenues under the operation of the carbon-electricity dual market. It can be used to analyze the changing characteristics of unit revenues of different types of coal-fired power units on the provincial power supply side under the operation of the dual market, and to evaluate the operation mode and cost-benefit of coal-fired power units under the parallel operation of the carbon-electricity dual market, providing a reference for alleviating the various pressures faced by the electricity market. BRIEF DESCRIPTION OF THE DRAWINGS

[0041] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.

[0042] Figure 1 It is a flowchart of the entire program of an embodiment of the present invention.

[0043] Figure 2 This is a schematic diagram of the scheduling of three coal-fired power units in an embodiment of the present invention.

[0044] Figure 3 This is the home page interface of the embodiment of the present invention.

[0045] Figure 4 It is an interface display of the coal consumption coefficient and carbon emission coefficient of an embodiment of the present invention.

[0046] Figure 5 This is a display of the unit load parameter interface of an embodiment of the present invention.

[0047] Figure 6 It is a display of the power supply coal consumption parameter interface under different load rates of an embodiment of the present invention.

[0048] Figure 7 This is a display of the dispatch distance parameter interface of an embodiment of the present invention.

[0049] Figure 8This is the result interface under the objective function of minimum carbon emission and minimum coal consumption of the embodiment of the present invention. DETAILED DESCRIPTION

[0050] A method for dispatching coal-fired power units considering carbon-electricity coupling comprises the following steps:

[0051] 1. Optimize goal setting

[0052] The dispatch optimization objectives include three parts: minimizing the total coal consumption of coal-fired power plants, maximizing the profits of coal-fired power plants, and minimizing the carbon emissions of coal-fired power plants.

[0053] 1) The total coal consumption of coal-fired power plants is minimal

[0054] The coal consumption and unit output of coal-fired power units are piecewise functions composed of cubic curves and sine sum functions:

[0055]

[0056] Where: f1 is the total coal consumption of all coal-fired power units in one year, t; T is the total number of weeks in a year; N is the number of coal-fired power units; P it is the output (MWh) of the coal-fired power unit numbered i in period t; a1, a2, a3 are the amplitudes of the sine function, b1, b2 are the angular frequency coefficients of the sine sum function, c1, c2 are the phase angles; p1, p2, p3, p4 are the coal consumption coefficients of coal-fired power unit i, and the units are Ton / MWh respectively 3 , Ton / MWh 2 , Ton / MWh, Ton;

[0057] 2) Coal-fired power plants have the highest profits

[0058] The profit of a coal-fired power plant is the total electricity sales revenue of the coal-fired power unit minus its total power generation cost; the electricity sales revenue is the product of the electricity sales price and power generation of each power plant in the power market, and the power generation cost is the coal consumption cost and carbon cost. The specific functional relationship is:

[0059]

[0060] Where: f2 is the total profit of the power grid for coal-fired power units in one year, in yuan; ρ i is the on-grid electricity price of unit i (yuan / MWh); C we is the unit price of coal used, C tj is the carbon price;

[0061] 3) Coal-fired power plants have the lowest carbon emissions

[0062] The minimum carbon emissions from coal-fired power plants can be expressed by a cubic polynomial:

[0063] f3=q1P it 3+q2P it 2 +q3P it +q4 (3)

[0064] Where: f3 is the total carbon emissions in a year (t); T is the total number of time periods in a year; N is the number of coal-fired power units i; P it is the active power output of unit i in period t (MWh); q1, q2, q3, q4 are the carbon emission coefficients of unit i, and the units are Ton / MWh respectively. 3 , Ton / MWh 2 , Ton / MWh, Ton.

[0065] 4) Multi-target Euclidean distance

[0066] To solve the multi-objective optimization problem, the key is to consider the requirements of each objective; generally speaking, the optimal solution of one objective is almost impossible, or there is a small probability that it is the optimal solution of other objectives; under the condition of sacrificing the optimal decision to achieve all objectives, the relationship between the various objectives is coordinated to achieve an overall solution; in this embodiment, a standard Euclidean function is constructed to convert multiple objectives into a single objective to be solved for solution;

[0067] Consider the multi-objective decision problem (MOP):

[0068]

[0069] Where: F(x), G(x) are the respective objective functions, and are continuous functions on their domain X;

[0070] For multi-objective decision-making problems, we can reconstruct the multi-objective evaluation function and regard the multi-objective function as a single-objective problem; based on the single objective, we can get an evaluation function to solve the multi-objective decision-making problem, namely, the multi-objective Euclidean distance

[0071]

[0072] Where: z(x) is the Euclidean distance between the target functions; is the optimal solution of the single objective normalized function, i.e., d i (x); Find the minimum value of the Euclidean distance z(x) to get the optimal solution x under the multi-objective decision function * , this optimal solution is one of the Pareto optimal solutions under multi-objective decision-making;

[0073] 2. Constraints

[0074] 5) System power balance constraints

[0075]

[0076] Where: P it is the active power output of coal-fired power unit i in period t; P ddi is the dispatching power between the i-th coal-fired power unit and other coal-fired power units; P si The power of line loss during dispatch between No. i coal-fired power unit and other coal-fired power units; P Li is the total system load at time t;

[0077] 6) Upper and lower limits of coal-fired power unit output power

[0078] P imin ≤P i ≤P imax (7)

[0079] Where: P imin is the lower limit of power generation of coal-fired power unit i; P imax is the upper limit of power generation of coal-fired power unit i;

[0080] 7) Upper and lower limits of dispatching power

[0081]

[0082] Where: P dd is the dispatching power of the line, is the maximum power allowed on the transmission line.

[0083] Figure 1 It is a flowchart of the entire program of this embodiment.

[0084] In this embodiment, necessary constants and related data are first defined, such as coal consumption coefficient, carbon emission coefficient, coal unit price, annual carbon price, number of units, load of each coal-fired power unit, etc. Decision variables to be solved are set, such as the output of each coal-fired power unit, the dispatching power between each coal-fired power unit, and the line loss power.

[0085] Secondly, set constraints on the decision variables. Constraints are divided into equality constraints and inequality constraints:

[0086] The equality constraint includes the unit system power balance constraint. Before the equality constraint, the dispatch direction needs to be judged. If the dispatch direction is from the unit with a smaller number to the unit with a larger number, the intermediate variable at this time (that is, the sum of the dispatch power and the line loss power) is positive. If the dispatch direction is from the unit with a larger number to the unit with a smaller number, the intermediate variable is negative. After the judgment is completed, the equality constraint of the unit system power balance is performed. Inequality constraints include the upper and lower limit constraints of the unit output and the maximum constraint of the line dispatch power.

[0087] After setting the constraints, establish the objective function.

[0088] Finally, multiple objective functions are optimized and solved by using Euclidean distance, and the optimal solution is finally obtained, including the output of each unit, dispatching power, and line loss power.

[0089] exist Figure 2 In this paper, taking three types of coal-fired power units as an example, the dispatching mode among the three under the carbon-electricity dual market and the impact of carbon price on the dispatching of the three are explored. By analyzing the annual dispatching of the three units, the cost-benefit and carbon reduction effect of different dispatching operation modes of coal-fired power units under the conditions of parallel electricity-carbon dual markets are evaluated.

[0090] The following is an interface display of the results of the above scheduling model. Click "Home" to display the topological diagram of the coal-fired power unit configuration ( Figure 3 ), click the "Parameters" interface to display the various parameters needed to build the model for calculation: including coal consumption and carbon emission coefficient, the load carried by the unit, the power supply coal consumption under different load rates, and the scheduling distance between each unit.

[0091] Figure 4 It is the interface display of coal consumption coefficient and carbon emission coefficient.

[0092] Figure 5 It is the unit load parameter interface display.

[0093] Figure 6 It is an interface display of power supply coal consumption parameters under different load rates.

[0094] Figure 7 It is the interface display of the dispatch distance parameter. Click "Optimize" to see the optimization results under different objectives, including minimum carbon emission, minimum coal consumption, and maximum profit. You can select multiple targets. The multiple targets are optimized according to the Euclidean distance method, and the results of each optimal solution under different objective functions will be displayed, including the output, dispatch power, line loss power and corresponding carbon emissions between coal-fired power units.

[0095] For example Figure 8 It is the result interface under the objective function of minimum carbon emission and minimum coal consumption.

[0096] This embodiment proposes a coal-fired power unit scheduling method considering carbon-electricity coupling, constructs the scheduling optimization objectives, constraints and optimal Euclidean distance, as well as the corresponding system functional architecture.

Claims

1. Coal-fired power unit dispatching method considering carbon-electricity coupling, The following steps are involved:

1. Optimize goal setting 1) The total coal consumption of coal-fired power plants is minimal The coal consumption and unit output of coal-fired power units are piecewise functions composed of cubic curves and sine sum functions: Where: f 1 is the total coal consumption of all coal-fired power units in one year, in tons (Ton); T is the total number of weeks in a year; N is the number of coal-fired power units; P it is the output of coal-fired power unit numbered i in period t (MWh); a 1 、a 2 、a 3 is the amplitude of the sine function, b 1 、b 2 are the angular frequency coefficients of the sine sum function, c 1 、c 2 is the phase angle; p 1 、p 2 、p 3 、p 4 is the coal consumption coefficient of coal-fired power unit i, in units of Ton / MWh 3 , Ton / MWh 2 , Ton / MWh, Ton; 2) Coal-fired power plants have the highest profits The profit of a coal-fired power plant is the total electricity sales revenue of the coal-fired power unit minus its total power generation cost; the electricity sales revenue is the product of the electricity sales price and power generation of each power plant in the power market, and the power generation cost is the coal consumption cost and carbon cost. The specific functional relationship is: Where: f 2 is the total profit of the power grid for coal-fired power units in one year, in yuan; ρ i is the on-grid electricity price of unit i (yuan / MWh); C we is the unit price of coal used, C tj is the carbon price; 3) Coal-fired power plants have the lowest carbon emissions The minimum carbon emissions from coal-fired power plants can be expressed by a cubic polynomial: f 3 =q 1 P it 3 +q 2 P it 2 +q 3 P it +q 4 (3) Where: f3 is the total carbon emissions in a year (t); T is the total number of time periods in a year; N is the number of coal-fired power units i; P it is the active power output of unit i in period t (MWh); q 1 ,q 2 ,q 3 ,q 4 is the carbon emission coefficient of unit i, in units of Ton / MWh 3 , Ton / MWh 2 , Ton / MWh, Ton; 4) Multi-target Euclidean distance Construct a standard Euclidean function to convert multiple objectives into a single objective to be solved; Consider the multi-objective decision problem (MOP): Where: F(x), G(x) are the respective objective functions, and are continuous functions on their domain X; For multi-objective decision-making problems, we can reconstruct the multi-objective evaluation function and regard the multi-objective function as a single-objective problem. Based on the single objective, we can get an evaluation function to solve the multi-objective decision-making problem, namely, the multi-objective Euclidean distance: Where: z(x) is the Euclidean distance between the target functions; is the optimal solution of the single objective normalized function, i.e., d i (x); Find the minimum value of the Euclidean distance z(x) to get the optimal solution x under the multi-objective decision function * , this optimal solution is one of the Pareto optimal solutions under multi-objective decision-making; 2. Constraints 5) System power balance constraints Where: P it is the active power output of coal-fired power unit i in period t; P ddi is the dispatching power between the i-th coal-fired power unit and other coal-fired power units; P si The power of line loss during dispatch between No. i coal-fired power unit and other coal-fired power units; P Li is the total system load at time t; 6) Upper and lower limits of coal-fired power unit output power P imin ≤P i ≤P imax (7) Where: P imin is the lower limit of power generation of coal-fired power unit i; P imax is the upper limit of power generation of coal-fired power unit i; 7) Upper and lower limits of dispatching power Where: P dd is the dispatching power of the line, is the maximum power allowed on the transmission line.