Roof structure construction method
Through the methods of pre-assembly of roof skeletons and fixing points of embedded parts, the difficulty and safety of lifting and high-altitude operations in roof structure construction are solved, and efficient and safe roof structure construction is achieved, reducing costs and construction periods.
Patent Information
- Application Number
- CN202411444854.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-16
- Publication Date
- 2025-01-03
AI Technical Summary
The existing roof structure construction has the problem of long interval between the lifting and the installation of the insulation layer, which is prone to deformation and damage, inconvenient operation at high altitudes, high safety risks, and cumbersome processes, resulting in long construction periods and high costs.
The roof skeleton is pre-assembled and embedded parts fixing points are adopted to hoist the roof skeleton through a crane and fix it on the main body of the building to reduce high-altitude operations and use integrated ground construction to reduce construction difficulty and cost.
It improves construction efficiency and safety, reduces the risks of high-altitude operations, reduces construction costs, shortens construction periods, and ensures construction quality.
Smart Images

Figure CN119243999A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a roof structure construction method. Background Art
[0002] At present, with the development of urbanization, more and more urban landmark buildings are rising from the ground, and the designs of these buildings are becoming more and more diverse. In order to improve the overall aesthetics of the building, many buildings have adopted complex roof structures, which are generally made of concrete. Therefore, the existing roof modeling construction has the following problems: 1. The interval between the hoisting of the modeling structure and the installation of the insulation layer is long, which is prone to deformation and damage; 2. Scaffolding is required for high-altitude operations, which is inconvenient for construction operations and inconvenient and unsafe for personnel to go up and down; 3. The on-site construction process is cumbersome, the construction organization is complex, and the construction period is long; 4. The force analysis and calculation of the modeling structure is difficult, the amount of steel used in the structural parts is large, and the cost is high.
[0003] Based on the above situation, it is urgent to develop a roof structure construction method that can solve the problem. Summary of the invention
[0004] The present invention is made to solve the above-mentioned technical problems, and its purpose is to provide a roof structure construction method that can effectively solve the problem that the roof structure is complex and diverse, and has a large volume, resulting in great construction difficulty and high cost.
[0005] In order to achieve the above object, the present invention provides a roof structure construction method, comprising: S1: embedding an embedded part on a building main body and serving as a fixing point for connecting the building main body with a roof frame;
[0006] S2: hoisting the pre-assembled roof frame to a preset position of the building main body, wherein the roof frame is installed on a part of the outer surface of the roof frame;
[0007] S3: fixing the roof frame to the building body through the embedded parts;
[0008] S4: installing panels on the other outer surfaces of the roof frame to complete the construction of the roof structure.
[0009] Preferably, in step S1, the embedded part is a pre-embedded part or a post-embedded part.
[0010] When the building main body is cast, the embedded parts are embedded in the building main body as the fixing points for connecting the building main body with the roof frame; or,
[0011] After the main building is completed, the post-embedded parts are arranged on the main building as fixing points for connecting the main building with the roof frame.
[0012] Preferably, before step S2, the method further includes:
[0013] Making various components of the roof frame;
[0014] The various components of the processed roof frame are assembled into a whole on a pre-built workbench.
[0015] Preferably, in step S2, hoisting the pre-assembled roof frame to a preset position of the building main body includes:
[0016] The assembled roof frame is hoisted as a whole by a crane;
[0017] Flipping the suspended roof frame in the air to adjust the installation angle between the roof frame and the building main body;
[0018] The roof frame with the installation angle adjusted is attached to the preset position of the building body.
[0019] Preferably, after step S3 and before step S4, the method further includes:
[0020] Acceptance inspection of the roof frame fixed to the main building;
[0021] After acceptance, proceed to step S4.
[0022] Preferably, the panel is an aluminum plate.
[0023] Preferably, the panel is fixed to the roof frame by riveting.
[0024] Preferably, an anti-corrosion layer is provided on the surface of the roof frame.
[0025] Preferably, the roof frame is a steel frame.
[0026] Preferably, the embedded parts are embedded steel plates.
[0027] According to the above description and practice, the roof structure construction method of the present invention has the following advantages:
[0028] 1. Ground integrated construction is adopted for high-altitude components. The production, assembly, welding and installation of decorative panels of all components are completed on the ground. The construction is convenient, the construction difficulty is reduced, the operation efficiency is improved and the construction quality is guaranteed.
[0029] 2. During the construction process, crane hoisting technology was introduced to achieve a high degree of mechanization of construction operations, effectively reduce the physical burden of workers, and greatly reduce the demand for high-altitude operations, thereby significantly reducing safety risks in the construction process and providing a more solid safety guarantee for the project advancement.
[0030] 3. It avoids the need to set up aerial work platforms, which not only saves material resources, but also significantly reduces labor costs, makes a positive contribution to project cost control, and further reduces construction costs.
[0031] 4. It provides a stable and efficient working surface for operations in key areas such as roofs and exterior walls, effectively accelerating the progress of the project. At the same time, it also achieves reasonable control of project costs while ensuring quality, laying a solid foundation for the smooth completion of the project and subsequent operations. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] Figure 1 The present invention is a flowchart of a roof structure construction method according to an embodiment of the present invention.
[0033] Figure 2 This is a cross-sectional view of a roof frame installed on a main structure in one embodiment of the present invention.
[0034] Figure 3 It is a cross-sectional view of an embedded part involved in one embodiment of the present invention.
[0035] The reference numerals in the figure are:
[0036] 1. Roof frame; 11. First frame; 12. Second frame; 13. Diagonal braces; 2. Main structure; 3. Embedded parts. DETAILED DESCRIPTION
[0037] The exemplary embodiments will now be described more fully with reference to the accompanying drawings. However, the exemplary embodiments can be implemented in many forms and should not be construed as limited to the examples set forth herein; rather, these embodiments are provided so that the disclosure will be more comprehensive and complete and fully convey the concepts of the exemplary embodiments to those skilled in the art. The described features, structures, or characteristics may be combined in any suitable manner in one or more embodiments.
[0038] In addition, the accompanying drawings are only schematic illustrations of the present disclosure and are not necessarily drawn to scale. The same reference numerals in the figures represent the same or similar parts, and thus their repeated descriptions will be omitted. It should be noted that in the present disclosure, the terms "including", "configured with", and "set in" are used to express the meaning of open-ended inclusion, and mean that in addition to the listed elements / components / etc., there may be other elements / components / etc.; the terms "first", "second", etc. are only used as marks, and are not restrictions on the number or order of their objects; the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside", etc. indicate the orientation or position relationship based on the orientation or position relationship shown in the accompanying drawings, which is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0039] Unless otherwise clearly specified and limited, the terms "installed", "connected" and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0040] In this embodiment, a roof structure construction method is disclosed. Figure 1 The whole process of the roof structure construction method is shown. Figure 2 The side structure in which the roof frame involved in the roof structure construction method is installed on the main structure is shown; Figure 3 The cross-sectional structure of the roof frame is shown.
[0041] Please refer to Figures 1 to 3 , the roof structure construction method of the present invention includes: In order to achieve the above-mentioned purpose, the present invention provides a roof structure construction method, including: S1: embedding the embedded parts on the building main body and serving as the fixing points connecting the building main body with the roof frame;
[0042] S2: installing some panels on the roof frame, and hoisting the pre-assembled roof frame to a preset position of the building body;
[0043] S3: fixing the roof frame to the building body through the embedded parts;
[0044] S4: Install the panel on the lower surface of the roof frame to complete the construction of the roof structure.
[0045] In step S1, the embedded parts are pre-embedded parts or post-embedded parts. When the building body is poured, the pre-embedded parts are buried in the building body as fixed points connecting the building body with the roof frame 1; or, after the building body is completed, the post-embedded parts are set on the building body as fixed points connecting the building body with the roof frame 1.
[0046] Before step S2, a workbench can be built on the construction ground, and the roof frame 1 can be built on the ground, which can ensure the assembly quality of the roof frame 1, facilitate inspection, and make assembly simpler, reduce the construction difficulty, improve work efficiency, and omit the construction of an aerial work platform, saving a lot of materials and labor, and reducing construction costs. In addition, there is no need to set up a scaffolding or a floor-standing scaffolding as a construction operation platform, which reduces the occupation of the work surface, provides a work surface for roof and exterior wall operations, speeds up the construction period, and reduces costs.
[0047] Among them, in this embodiment, the roof frame 1 includes: a first frame 11, a second frame 12 arranged on one side of the first frame 11, wherein the first frame 11 and the second frame 12 include a plurality of horizontal beams and a plurality of vertical beams vertically arranged on the plurality of horizontal beams; the panel is arranged on the first frame 11; one side of the second frame 12 and one side of the first frame 11 are respectively connected to the embedded parts 3. The vertical beams not only enhance the longitudinal stability of the frame, but also form a stable grid structure with the horizontal beams, effectively dispersing various loads from above. In this embodiment, the first frame 11, the second frame 12 and the outer edge of the main structure 2 form a triangle, and the size of the angle between the first frame 11 and the second frame 12 can be adjusted according to actual needs.
[0048] In step S2, when installing panels on the surface of the roof frame 1, in order to maintain the flexibility of construction, a layer without installing panels will be reserved on the roof frame. In this embodiment, any layer is selected from the first frame 11 and the second frame 12, that is, the distance between any horizontal beam and the horizontal beam adjacent to it. Panels are not installed within this range, leaving space for welding and installation of the roof frame 1, which is convenient for construction personnel to install and fix the roof frame 1. In specific construction operations, the bottom layer of the first frame 11 and the second frame 12 is generally selected without installing panels. The pre-assembled roof frame 1 is hoisted to the preset position of the building main body, including: hoisting the assembled roof frame 1 as a whole by a crane; flipping the hoisted roof frame 1 in the air to adjust the installation angle between the roof frame 1 and the building main body; and fitting the roof frame 1 with the adjusted installation angle to the preset position of the building main body. The crane can adjust the structure of the roof frame 1 as needed. Due to different construction requirements, the roof frame 1 has various shapes, which are not only large in size but also complex in structure. Therefore, the position of the roof frame 1 is adjusted in the air by a crane, and mechanized construction is performed, which reduces the labor intensity of workers, reduces high-altitude operations, and reduces safety risks.
[0049] After step S3 and before step S4, the method further includes: inspecting the roof frame 1 fixed on the main body of the building; and executing step S4 after the inspection is qualified. In step S4, after the inspection of the roof frame 1 is completed, the panels are installed on the outer surface of the roof frame 1 where the panels are not installed, so as to ensure the integrity and beauty of the roof.
[0050] Among them, in this embodiment, the second frame 12 in the roof frame 1 is fixed to the first frame 11 by welding. The welding connection performance is good, which ensures the integrity of the first frame 11 and the second frame 12, making the roof frame 1 more solid and firm. Diagonal braces 13 are evenly arranged between the first frame 11 and the second frame 12. The diagonal braces 13 are used to support the first frame 11 and the second frame 12, effectively dispersing the stress that may be generated between the frames, and enhancing the stability and wind pressure resistance of the overall structure. One end of the diagonal brace 13 is fixed to the end of the first frame 11, and the other end is fixed to the middle of the second frame 12, providing additional support for the frame.
[0051] The panel is an aluminum plate. With its advantages of light weight, corrosion resistance and easy processing, the aluminum plate not only provides good waterproof and thermal insulation performance for the building, but also adds a beautiful scenery to the building with its unique texture and color. The panel is fixed to the roof frame 1 by riveting. This connection method not only ensures the close connection between the panel and the frame, but also avoids the thermal stress problem that may be caused by traditional welding, further improving the safety and durability of the structure. At the same time, the surface of the aluminum plate can be sprayed as needed to achieve a visual effect that is coordinated with the overall architectural style.
[0052] Among them, an anti-corrosion layer is arranged on the surface of the roof frame 1, which can effectively resist the erosion of harmful factors such as acid rain and ultraviolet rays in the natural environment, ensuring that the frame can still maintain its original strength and stability in harsh environments.
[0053] The roof frame 1 is a steel frame, which not only meets the building's requirements for bearing capacity, but also provides the possibility of realizing complex and varied building forms. In the embodiment of the present invention, the specific structure of the roof frame can be set to different structures according to the situation.
[0054] The embedded part 3 is a steel plate, which is reliably connected to the roof frame 1 during the construction process to ensure the continuity and stability of the roof frame 1 as a whole.
[0055] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.
Claims
1. A roof structure construction method, characterized in that: include: S1: embedding the embedded parts in the building main body and serving as the fixing points for connecting the building main body with the roof frame; S2: hoisting the pre-assembled roof frame to a preset position of the building main body, wherein the roof frame is installed on a part of the outer surface of the roof frame; S3: fixing the roof frame to the building body through the embedded parts; S4: installing panels on the other outer surfaces of the roof frame to complete the construction of the roof structure.
2. The roof structure construction method according to claim 1, characterized in that: In step S1, the embedded part is a pre-embedded part or a post-embedded part. When the building main body is cast, the embedded parts are embedded in the building main body as the fixing points for connecting the building main body with the roof frame; or, After the main building is completed, the post-embedded parts are arranged on the main building as fixing points for connecting the main building with the roof frame.
3. The roof structure construction method according to claim 1, characterized in that: Before step S2, the method further includes: Making various components of the roof frame; The various components of the processed roof frame are assembled into a whole on a pre-built workbench.
4. The roof structure construction method according to claim 1, characterized in that: In step S2, the pre-assembled roof frame is hoisted to a preset position of the building body, including: The assembled roof frame is hoisted as a whole by a crane; Flipping the suspended roof frame in the air to adjust the installation angle between the roof frame and the building main body; The roof frame with the installation angle adjusted is attached to the preset position of the building body.
5. The roof structure construction method according to claim 1, characterized in that: After step S3 and before step S4, the method further includes: Acceptance inspection of the roof frame fixed to the main building; After acceptance, proceed to step S4.
6. The roof structure construction method according to claim 1, characterized in that: The panel is an aluminum plate.
7. The roof structure construction method according to claim 1, characterized in that: The panel is fixed on the roof frame by riveting.
8. The roof structure construction method according to claim 1, characterized in that: An anti-corrosion layer is arranged on the surface of the roof frame.
9. The roof structure construction method according to claim 1, characterized in that: The roof frame is a steel frame.
10. The roof structure construction method according to claim 1, characterized in that: The embedded part is a steel plate.