Concrete prefabricated wallboard demolding and pouring device

By using conveyor belts and bridge systems in the production of concrete precast wall panels, the continuous conveying and pouring of molds is realized, the problem of low production efficiency in the existing technology is solved, and efficient wall panel production is achieved.

CN221912544UActive Publication Date: 2024-10-29HENAN ZHUGONG CONSCTRUCTION TECH LTD CO
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420528530.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-19
Publication Date
2024-10-29
Estimated Expiration
2034-03-19

AI Technical Summary

Technical Problem

The existing demoulding and pouring device for precast concrete wall panels has the bottom plate fixed on the table, which makes it impossible to achieve continuous operation during the production process, resulting in low processing efficiency.

Method used

Two conveyor belts and multiple bridges are used to realize the continuous transportation of molds and concrete injection through hydraulic rods and driving devices, ensuring that the molds are poured and formed on the bridges, allowing multiple groups of equipment to operate at the same time and improving production efficiency.

Benefits of technology

It realizes the continuous and uninterrupted production of concrete precast wall panels, improves processing efficiency, avoids downtime waiting for molding, and improves production efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221912544U_ABST
    Figure CN221912544U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of prefabricated wallboard production equipment, in particular to a concrete prefabricated wallboard demolding and pouring device which comprises two conveying belts which are used for conveying empty molds and molds injected with concrete respectively, a plurality of bridge frames are distributed between the two conveying belts at intervals, and hydraulic rods in one-to-one correspondence with the bridge frames are arranged on one sides of the conveying belts. A push plate abutting against the surface of the conveying belt is fixed to the movable end of the hydraulic rod, and a spray head is suspended above the bridge. During use, empty molds are placed on the first conveying belt at intervals, and when the molds are conveyed to the corresponding positions of the bridge frame, the molds are pushed into the bridge frame through the push plate and then transferred to the position below the spray head for grouting; then the mold injected with the concrete is transferred to a second conveying belt and conveyed to a wallboard condensation area; a plurality of sets of equipment work simultaneously, after injection molding, a mold is transferred to a congelation area to be formed, a next empty mold is conveyed to a grouting position, continuous operation can be achieved, shutdown and waiting are not needed, and the production and machining efficiency is greatly improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of prefabricated wallboard production equipment, in particular to a demoulding and pouring device for a concrete prefabricated wallboard. Background Art

[0002] Precast concrete wall panels are reinforced concrete plate-type components processed in precast plants or construction sites for building assembly. A reinforcement cage with steel bars is laid in the mold, and then concrete with a proportion based on different needs is poured. After cooling and forming, the wall panels are taken out to complete the process.

[0003] In the patent document with the announcement number CN220008170U, a demoulding and casting device for prefabricated concrete wall panels is disclosed. A base plate is arranged on a table body, and rotating plates are hinged on both sides of the base plate. The two rotating plates and the base plate are assembled into a mold with an upper end opening. After concrete is injected from the upper end opening and cooled, the mold is disassembled to take out the manufactured wall.

[0004] However, there is an obvious problem in the above patent: the bottom plate is fixed on the table body, so that the mold is fixed to the table body. At this time, the next wall panel can only be made after the wall panel inside the mold is formed. Continuous operation is not possible and the processing efficiency is low.

[0005] To this end, the utility model provides a demoulding and pouring device for a prefabricated concrete wall panel, which can continuously and uninterruptedly manufacture the wall panel and improve the processing efficiency. Utility Model Content

[0006] The utility model aims to solve the problems existing in the prior art and proposes a demoulding and pouring device for a prefabricated concrete wall panel.

[0007] In order to achieve the above purpose, the utility model adopts the following technical solutions:

[0008] A demoulding and pouring device for prefabricated concrete wall panels comprises two conveyor belts, which are respectively used to convey empty molds and molds after concrete is injected. A plurality of bridge frames are spaced apart between the two conveyor belts. A hydraulic rod corresponding to the bridge frames is arranged on the side of the conveyor belt for conveying the empty molds away from the bridge frames. A push plate resting on the surface of the conveyor belt is fixed to the movable end of the hydraulic rod. A plurality of rollers are rotatably mounted on each bridge frame. The plurality of rollers are driven by a driving device to rotate synchronously. A gantry is suspended above the bridge frame. A spray pump is fixed on the gantry. The feed inlet of the spray pump is connected to a concrete supply system, and the discharge outlet is connected to a nozzle.

[0009] Preferably, the concrete supply system comprises a barrel, the barrel is connected to a hard feeding pipe via a delivery pump, and the feeding pipe is connected to a feeding port of the injection pump.

[0010] Preferably, an electric telescopic rod is fixed on the gantry, a support plate is fixed to the protruding end of the electric telescopic rod, the spray pump is clamped on the support plate, and a hose is connected between the feed port of the spray pump and the feed pipe.

[0011] Preferably, a first vertical plate is fixed to the upper end face of the gantry, and a second vertical plate is arranged on the side, the feed pipe is clamped on the upper end of the second vertical plate, two rollers are vertically installed on the upper end of the first vertical plate for rotation at intervals, the hose passes through between the two rollers and is connected to the injection pump, and the gap between the two rollers is larger than the outer diameter of the hose.

[0012] Preferably, a movable plate is vertically slidably mounted on one opposite side of the first vertical plate and the second vertical plate, a pull rope is fixed to one end of the movable plate close to the first vertical plate, and the other end of the pull rope passes around the upper end of the first vertical plate and is fixedly connected to the support plate.

[0013] Preferably, a guide roller is rotatably installed on the first vertical plate below the two rollers, one end of the pull rope is connected to the movable plate, and the other end passes around the guide roller and is connected to the support plate.

[0014] Preferably, inclined baffles are provided on both sides of the movable plate.

[0015] Preferably, a notch is provided at the upper end of the gantry for the pull rope to pass through.

[0016] Preferably, guide rails are fixed on both sides of the upper end of the bridge, and the two guide rails are flared at one end close to the conveyor belt for conveying the empty mold.

[0017] Preferably, the nozzle is a fan-shaped duckbill nozzle.

[0018] Compared with the prior art, the utility model provides a demoulding and pouring device for prefabricated concrete wall panels, which has the following beneficial effects:

[0019] 1. When in use, empty molds are placed at intervals on the first conveyor belt. When the mold is transferred to the corresponding position of the bridge, the first conveyor belt stops, the hydraulic rod starts, and the mold is pushed onto the bridge through the push plate. Then the roller is driven by the driving device to rotate, thereby driving the mold to be transferred to the bottom of the nozzle. The driving device stops, the mold is left to stand, and concrete is injected into the mold. After that, the driving device is started to transfer the mold injected with concrete to the second conveyor belt, and it is transported to the wall panel condensation area through the second conveyor belt to wait for the wall panel to be formed. Multiple groups of bridges and their supporting facilities are arranged at intervals, and multiple groups of equipment operate at the same time. After injection, the mold is transferred to the condensation area for molding, and the next empty mold is transported to the grouting position. Continuous operation is possible without stopping work and waiting, which greatly improves the production and processing efficiency.

[0020] 2. An electric telescopic rod is fixed on the gantry, a support plate is fixed on the protruding end of the electric telescopic rod, the spray pump is clamped on the support plate, and a hose is connected between the feed port of the spray pump and the feed pipe, so that the nozzle can be raised and lowered, so that the height between the nozzle and the mold remains unchanged at all times, preventing concrete from leaking from the nozzle to the mold.

[0021] 3. A limiting component is also provided so that the hose can be deflected as the nozzle is raised or lowered, while the hose will not fall down at will and affect the operation of the equipment.

[0022] Other advantages, objectives and features of the present invention will be described in the following description to some extent; and will be apparent to those skilled in the art based on the following examination and study to some extent; or, may be taught from the practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 It is an overall three-dimensional schematic diagram of the utility model.

[0024] Figure 2 For the utility model Figure 1 Schematic diagram of the central bridge and gantry.

[0025] Figure 3 It is a front view of the utility model when assembled on the gantry.

[0026] Figure 4 For the utility model Figure 2 Top view of the .

[0027] In the figure: 1. first conveyor belt; 2. second conveyor belt; 3. bridge; 4. roller; 5. guide rail; 6. hydraulic rod; 7. push plate; 8. gantry; 9. electric telescopic rod; 10. support plate; 11. spray pump; 12. nozzle; 13. hose; 14. first vertical plate; 15. second vertical plate; 16. roller; 17. moving plate; 18. pull rope; 19. baffle. DETAILED DESCRIPTION

[0028] The following will be combined with the attached embodiment of the utility model Figure 1-4 , the technical solutions in the embodiments of the utility model are described clearly and completely. Obviously, the described embodiments are only part of the embodiments of the utility model, rather than all the embodiments.

[0029] Embodiment 1, in order to solve the problems existing in the prior art, this embodiment provides a demoulding and pouring device for prefabricated concrete wall panels, comprising two conveyor belts, namely a first conveyor belt 1 and a second conveyor belt 2, the first conveyor belt 1 is used to transport empty molds, and the second conveyor belt 2 is used to transport molds after concrete is injected. The first conveyor belt 1 and the second conveyor belt 2 in the accompanying drawings are only schematic diagrams and do not represent specific structures and dimensions; bridges 3 are spaced between the two conveyor belts, and a hydraulic rod 6 corresponding to the bridge 3 is arranged on the side of the conveyor belt for transporting empty molds away from the bridge 3, and a push plate 7 is fixed to the movable end of the hydraulic rod 6 against the surface of the conveyor belt, and a plurality of rollers 4 are rotatably mounted on each bridge 3, and the ends of the plurality of rollers 4 are connected by chain transmission and rotate synchronously and in the same direction, and the chain transmission is driven by a motor fixed on the bridge 3, and a gantry 8 is suspended above the bridge 3, and a spray pump 11 is fixed on the gantry 8, and the feed inlet of the spray pump 11 is connected to the concrete supply system, and the discharge port is connected to the nozzle 12;

[0030] The concrete supply system includes a barrel, which is used to mix the required concrete. The barrel is equipped with a heating element and a stirring element to prevent the concrete from solidifying. The barrel is connected to a hard feeding pipe through a delivery pump, and the feeding pipe is connected to the feed port of the injection pump 11.

[0031] Guide rails 5 are fixed on both sides of the upper end of the bridge 3. The two guide rails 5 are expanded at one end close to the conveyor belt for conveying the empty mold to guide the mold to enter the bridge 3.

[0032] The nozzle 12 is a fan-shaped duckbill-shaped nozzle 12, which enlarges the spraying size of the nozzle 12 so that the concrete slurry is injected into the mold more evenly.

[0033] The mold is the same as the patent document in the background technology, and the side walls are all detachable, so that the wall panel can be taken out after being formed.

[0034] The specific use process of this embodiment is as follows:

[0035] Empty molds are placed at intervals on the first conveyor belt 1. When the mold is transferred to the corresponding position of the bridge frame 3, the first conveyor belt 1 stops, the hydraulic rod 6 starts, and the mold is pushed onto the bridge frame 3 through the push plate 7. Then the roller 16 is driven to rotate by the driving device, thereby driving the mold to move on the bridge frame 3. When the mold is transferred to the bottom of the nozzle 12, the driving device stops, the mold is left to stand, and the delivery pump and the spray pump 11 are started at the same time to inject concrete into the mold until it is full, and the delivery pump and the spray pump 11 are turned off. Then the driving device is started to transfer the mold injected with concrete to the second conveyor belt 2, and it is centrally transported to the wall panel condensation area through the second conveyor belt 2, waiting for the wall panel to be formed.

[0036] Multiple groups of bridge frames 3 and their supporting facilities are arranged at intervals, and multiple groups of equipment operate simultaneously. After injection molding, the mold is transferred to the coagulation zone for molding, and the next empty mold is transported to the grouting position. Sustainable operation is possible without stopping work and waiting, which greatly improves the production and processing efficiency.

[0037] Embodiment 2: Since the wall panels have different sizes and thicknesses, in order to keep the height of the nozzle 12 and the mold unchanged at all times and prevent concrete from leaking out of the mold from the nozzle 12, an electric telescopic rod 9 is fixed on the gantry 8, and a support plate 10 is fixed to the protruding end of the electric telescopic rod 9. A spray pump 11 is clamped on the support plate 10, and a hose 13 is connected between the feed port of the spray pump 11 and the feed pipe, so that the nozzle 12 can be raised and lowered to adapt to grouting operations of molds of different heights.

[0038] Embodiment 3: As the nozzle 12 rises and falls, the hose 13 bends and contracts. In order to prevent the hose 13 from falling down and affecting the operation of the equipment, in this embodiment, a hose 13 limiting component is provided, so that the hose 13 can be offset with the nozzle 12 rising and falling while maintaining relative stability.

[0039] The limiting component includes: a first vertical plate 14 is fixed to the upper end surface of the gantry 8, a second vertical plate 15 is arranged on the side, the feed pipe is clamped on the upper end of the second vertical plate 15, two rollers 16 are installed on the upper end of the first vertical plate 14 for vertical rotation at intervals, the hose 13 passes through between the two rollers 16 and is connected to the injection pump 11, the gap between the two rollers 16 is larger than the outer diameter of the hose 13, thereby guiding and limiting the hose 13 so that the hose 13 will not fall off at will.

[0040] Embodiment 4, when the nozzle 12 is raised or lowered, the hose 13 is pulled and moved synchronously. At this time, the stress is concentrated at the connection between the hose 13 and the feed port of the spray pipe. After a long time, the hose 13 is easy to fall off or tear. Therefore, in this embodiment, a movable plate 17 is vertically slidably installed on the opposite sides of the first vertical plate 14 and the second vertical plate 15. A pull rope 18 is fixed to one end of the movable plate 17 close to the first vertical plate 14. A guide roller is rotatably installed on the first vertical plate 14 below the two rotating rollers 16. A notch is provided at the upper end of the gantry 8 for the pull rope 18 to pass through. The other end of the pull rope 18 passes around the guide roller, and then passes through the notch to be fixedly connected to the support plate 10.

[0041] The movable end of the electric telescopic rod 9 drives the support plate 10 to rise and fall, and the support plate 10 drives the spray pump 11 to rise and fall, thereby driving the nozzle 12 to rise and fall. When the support plate 10 is raised and lowered, the movable plate 17 is pulled up and down by the pull rope 18, and the movable plate 17 rises and falls against the hanging part of the hose 13 to provide auxiliary support for the hose 13, thereby reducing the burden on the feed port connection of the spray pump 11 and improving the service life of the equipment.

[0042] Inclined baffles 19 are provided on both sides of the moving plate 17 , so that the hose 13 is covered on the moving plate 17 , further restricting the hose 13 .

[0043] The above are only preferred specific implementation methods of the utility model, but the protection scope of the utility model is not limited to this. Any technician familiar with the technical field within the technical scope disclosed by the utility model, who makes equivalent replacements or changes based on the technical scheme and utility model concept of the utility model, should be covered by the protection scope of the utility model.

[0044] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the utility model. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

[0045] Although the embodiments of the present invention have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limitations of the present invention. Ordinary technicians in the field can change, modify, replace and modify the above embodiments within the scope of the present invention.

Claims

1. A demoulding and pouring device for prefabricated concrete wall panels, characterized in that: The invention comprises two conveyor belts, which are used to convey empty moulds and moulds after concrete is injected, respectively. A plurality of bridge frames (3) are arranged at intervals between the two conveyor belts. A hydraulic rod (6) corresponding to the bridge frames (3) is arranged on the side of the conveyor belt for conveying empty moulds away from the bridge frames (3). A push plate (7) is fixed to the movable end of the hydraulic rod (6) and abuts against the surface of the conveyor belt. A plurality of rollers (4) are rotatably mounted on each bridge frame (3). The plurality of rollers (4) are driven by a driving device to rotate synchronously. A gantry frame (8) is suspended above the bridge frame (3). A spraying pump (11) is fixed on the gantry frame (8). The feed inlet of the spraying pump (11) is connected to a concrete supply system, and the discharge outlet is connected to a spray head (12).

2. A demoulding and pouring device for prefabricated concrete wall panels according to claim 1, characterized in that: The concrete supply system comprises a material barrel, which is connected to a hard feeding pipe via a delivery pump, and the feeding pipe is connected to a feeding port of a spraying pump (11).

3. A demoulding and pouring device for prefabricated concrete wall panels according to claim 2, characterized in that: An electric telescopic rod (9) is fixed on the gantry (8), a support plate (10) is fixed to the extended end of the electric telescopic rod (9), a spray pump (11) is clamped on the support plate (10), and a hose (13) is connected between the feed port of the spray pump (11) and the feed pipe.

4. A demoulding and pouring device for prefabricated concrete wall panels according to claim 3, characterized in that: A first vertical plate (14) is fixed to the upper end surface of the gantry (8), and a second vertical plate (15) is arranged on the side. The feeding pipe is clamped on the upper end of the second vertical plate (15). Two rollers (16) are vertically and rotatably installed at intervals on the upper end of the first vertical plate (14). The hose (13) passes through between the two rollers (16) and is connected to the injection pump (11). The gap between the two rollers (16) is larger than the outer diameter of the hose (13).

5. A demoulding and pouring device for prefabricated concrete wall panels according to claim 4, characterized in that: A movable plate (17) is vertically slidably mounted on opposite sides of the first vertical plate (14) and the second vertical plate (15), a pull rope (18) is fixed to one end of the movable plate (17) close to the first vertical plate (14), and the other end of the pull rope (18) is passed around the upper end of the first vertical plate (14) and is fixedly connected to the support plate (10).

6. A demoulding and pouring device for prefabricated concrete wall panels according to claim 4, characterized in that: A guide roller is rotatably mounted on the first vertical plate (14) below the two rotating rollers (16); one end of a pull rope (18) is connected to the movable plate (17) and the other end passes around the guide roller and is connected to the support plate (10).

7. A demoulding and pouring device for prefabricated concrete wall panels according to claim 6, characterized in that: Inclined baffles (19) are provided on both sides of the movable plate (17).

8. The demoulding and pouring device for prefabricated concrete wall panels according to claim 4, characterized in that: The upper end of the gantry (8) is provided with a notch for the pull rope (18) to pass through.

9. The demoulding and pouring device for prefabricated concrete wall panels according to claim 1, characterized in that: Guide rails (5) are fixed on both sides of the upper end of the bridge frame (3), and the two guide rails (5) are in a flared shape at one end close to the conveyor belt for conveying the empty mold.

10. The demoulding and pouring device for prefabricated concrete wall panels according to claim 1, characterized in that: The nozzle (12) is a fan-shaped duckbill-shaped nozzle (12).