Pressure steel pipe manufacturing and mounting integrated arrangement system
By setting up hoisting channels and gantry cranes directly from the surface to the high-pressure shaft in the hydropower station project, the manufacturing in the steel pipe processing plant and the installation in the high-pressure shaft are integrated, which solves the problems of high investment and low efficiency in steel pipe transportation and installation equipment in the hydropower station project. , improving construction efficiency and safety.
Patent Information
- Application Number
- CN202323418400.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-14
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2033-12-14
AI Technical Summary
In existing hydropower station projects, there are problems such as high equipment investment, low efficiency, high safety risks, and low construction efficiency during the transportation and installation of pressure steel pipes. In particular, the large size of steel pipes, difficulty in transportation, and multiple transfers of hoisting equipment lead to reduced efficiency.
Set up a construction area outside the pressure regulating shaft, set up a hoisting channel from the surface directly to the high-pressure shaft, and arrange a gantry crane in the steel pipe processing plant to realize the integration of manufacturing of finished steel pipes in the steel pipe processing plant and installation in the high-pressure shaft, and reduce the need for transportation equipment and track investment to extend the length of a single section of steel pipe.
The steel pipe transportation investment is reduced, the construction efficiency and safety are improved, the equipment investment is reduced, the construction efficiency and safety are enhanced, and the problem of low transportation efficiency in the existing technology is solved.
Smart Images

Figure CN221919296U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of hydropower station engineering design and construction, and in particular to a pressure steel pipe manufacturing and installation integrated layout system. Background Art
[0002] Pumped storage power stations or conventional water diversion power stations generally have the characteristic of high water head. In order to protect the safety of the structure and prevent internal water from seeping out, the water diversion high-pressure shaft is usually lined with steel plates (referred to as steel lining), and concrete backfill is used between the steel plates and the rocks to make them dense.
[0003] Usually, after the steel plates are transported to the site, they are manufactured into steel pipes of various types and sizes that meet the needs of the project through the steel pipe processing plant arranged in the construction area. The finished steel pipes are then transported by car to the entrance of the construction branch tunnel of the horizontal tunnel, and then transferred to the rail flatbed car in the tunnel and transported to the top of the high-pressure shaft for lifting.
[0004] From the perspective of engineering practice, the above arrangement has the following problems:
[0005] (1) The size of steel pipes is often large, which requires increasing the width of the roads along the steel pipe transportation route and the construction branch tunnels, which increases a lot of investment.
[0006] (2) When steel pipes are transported in construction branch tunnels and horizontal tunnels, they need to be transferred to rail flatbed trucks. The layout of tracks along the tunnel and the purchase of rail flatbed trucks require a large amount of additional investment.
[0007] (3) Steel pipes are transported from cars to rail flatbed trucks at the entrance of the construction branch tunnel, and lifting equipment needs to be arranged for transfer, which increases equipment investment and reduces work efficiency.
[0008] (4) After the rail flatbed car is transported to the top of the high-pressure shaft, it is necessary to arrange lifting equipment to lift the steel pipe, which increases equipment investment and reduces work efficiency.
[0009] (5) Due to the limitations of factors such as the cross-sectional size of the transportation road and the vehicle load, steel pipes can usually only be transported in sections of 3 meters, and then welded and assembled after reaching the installation work surface. The welding environment is harsh, the safety risk is high, and the construction efficiency is low. Utility Model Content
[0010] The purpose of the utility model is to provide a manufacturing and installation integrated layout system that can avoid the inconvenience of conventional pressure steel pipe manufacturing, installation and transportation methods and improve efficiency. To this end, the utility model adopts the following technical solutions:
[0011] A pressure steel pipe manufacturing and installation integrated layout system, a construction area is set up in the upper site outside the pressure regulating shaft, a steel pipe processing plant is arranged in the construction area, a guide section is set on the top of the pressure regulating shaft and is dug through the ground in the vertical direction, and the end of the guide section connected to the ground is led to the construction area to form a lifting channel from the ground to the high-pressure shaft. Lifting equipment is arranged in the construction area, and the lifting equipment takes into account the manufacturing of finished steel pipes in the steel pipe processing plant and the installation on the working surface in the high-pressure shaft, so that the steel lining and the rock mass of the high-pressure shaft are in a dense state.
[0012] Furthermore: the processing site of the steel pipe processing plant covers the pressure regulating shaft and its guide section.
[0013] Furthermore: the hoisting equipment adopts a gantry crane, and a track matching the gantry crane is arranged in the steel pipe processing plant.
[0014] Furthermore: the layout direction of the steel pipe processing plant is vertically arranged with the water diversion line.
[0015] Furthermore: the steel pipe processing plant is divided into steel plate stacking area and finished steel pipe stacking area, and the distance between the finished steel pipe stacking area and the pressure regulating well is smaller than the distance between the steel plate stacking area and the pressure regulating well.
[0016] Furthermore, the length of the finished steel pipe hoisted and transported through the hoisting channel can reach more than 6m.
[0017] Compared with the prior art, the utility model has the following beneficial effects:
[0018] The utility model arranges a steel pipe processing plant at the top of the shaft, thereby forming a hoisting channel for the finished steel pipe to directly reach the inside of the high-pressure shaft, and realizes the integration of the pressure steel pipe manufacturing in the steel pipe processing plant and the installation in the high-pressure shaft through the hoisting equipment, thereby reducing the overall investment required for steel pipe transportation. There is no need to add additional tracks and other hoisting equipment required for transportation, solving the problem of low efficiency of existing steel pipe transportation; at the same time, due to the existence of the hoisting channel, the single section length of the finished steel pipe can also be increased accordingly, so as to improve the safety factor of construction in the high-pressure shaft and improve the construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a schematic diagram of the plane layout of the utility model;
[0020] Figure 2 For this utility model Figure 1 Sectional view of AA. DETAILED DESCRIPTION
[0021] The present invention is further described below in conjunction with the accompanying drawings and embodiments, but they are not intended to limit the present invention.
[0022] like Figure 1-2 As shown, a pressure steel pipe manufacturing and installation integrated layout system is provided. A high-pressure shaft 1 is arranged at a location with suitable topographic and geological conditions (small upper rock mass coverage thickness and gentle terrain) on the water diversion line of the power station. A construction area 8 is set on the gentle slope above the high-pressure shaft 1 and the surge shaft 2. A steel pipe processing plant 5 is arranged in the construction area 8. The top of the surge shaft 2 is provided with a guide section that is dug through the ground in the vertical direction. The end of the guide section that is connected to the ground is connected to the construction area 8 to form a lifting channel 9 that directly connects the ground to the high-pressure shaft 1. Lifting equipment is arranged in the construction area 8. The lifting equipment takes into account the manufacturing of the finished steel pipe 4 in the steel pipe processing plant 5 and the installation on the working surface in the high-pressure shaft 1. At the same time, before the steel lining 3 of the working surface of the high-pressure shaft 1 is constructed, the excavation and support of the water diversion and surge chamber at the top of the high-pressure shaft 1 and the section to the surface are completed to make the steel lining 3 and the rock mass of the high-pressure shaft 1 dense.
[0023] Specifically, the processing site of the steel pipe processing plant 5 covers the pressure regulating shaft 2 and its guide section, so that the hook range of the lifting equipment of the steel pipe processing plant 5 can cover the top of the high-pressure shaft 1 while meeting the manufacturing of the finished steel pipe 4, thereby facilitating the installation of the finished steel pipe 4.
[0024] Specifically, the lifting equipment uses a gantry crane 6, and a track 7 that cooperates with the gantry crane 6 is arranged in the steel pipe processing plant 5. The track 7 of the gantry crane 6 is arranged along the length direction of the steel pipe processing plant 5, and the lifting range of the gantry crane 6 covers the entire steel pipe processing plant 5 and the pressure regulating shaft 2.
[0025] The arrangement direction of the steel pipe processing plant 5 is vertical to the water diversion line, and the steel plate stacking area and the finished steel pipe stacking area are arranged in the steel pipe processing plant 5 in different areas, and the distance between the finished steel pipe stacking area and the surge tank 2 is less than the distance between the steel plate stacking area and the surge tank 2. In this embodiment, the steel pipe processing plant 5 is arranged from the far end of the surge tank 2 to the near end of the finished steel pipe stacking area, and the flow operation area is arranged between the steel plate stacking area and the finished steel pipe stacking area according to the steel pipe manufacturing process (the specific process of steel pipe forming in the flow operation area is as follows Figure 1 ).
[0026] In this embodiment, the length of the finished steel pipe 4 hoisted and transported through the hoisting channel 9 can reach more than 6 meters.
[0027] See also Figure 1-2 When arranging and constructing the integrated layout system for penstock manufacturing and installation, the specific implementation steps are as follows:
[0028] S1: Optimize the layout of the water diversion line of the power station, and arrange the high-pressure shaft 1 at a location where the overlying rock mass is moderately thick and the top terrain is relatively flat, so as to facilitate digging through the top rock mass of the surge shaft 2 and to facilitate the arrangement of the steel pipe processing plant 5 on the gentle slope;
[0029] S2: First, excavate and level the site at the top of surge shaft 2, then excavate the caverns of surge shaft 2 and high-pressure shaft 1 from top to bottom, and complete the initial support;
[0030] S3: After the excavation and support of the surge tank 2 is completed, the steel pipe processing plant 5 building construction and equipment installation can be carried out;
[0031] S4: While the high-pressure shaft 1 is being excavated, the finished steel pipe 4 is being manufactured and processed simultaneously, and the lifting work during the steel pipe manufacturing is all completed by the gantry crane 6;
[0032] S5: After the excavation of the high-pressure shaft 1 is completed, the construction of the steel lining 3 can be carried out. During installation, the gantry crane 6 in the steel pipe processing plant 5 is used to lift the finished steel pipe 4 to the installation working surface for installation. After the installation of the finished steel pipe 4 is completed, the space between the steel lining 3 and the rock mass is backfilled with concrete to make it dense.
[0033] The above embodiment is only a preferred technical solution of the present invention. Those skilled in the art should understand that the technical solutions or parameters in the embodiments can be modified or replaced without departing from the principle and essence of the present invention, and all should be included in the protection scope of the present invention.
Claims
1. An integrated layout system for penstock manufacturing and installation, characterized in that: A construction area (8) is arranged above the outside of the pressure regulating shaft (2), a steel pipe processing plant (5) is arranged in the construction area (8), a guide section which is dug through the ground in the vertical direction is arranged at the top of the pressure regulating shaft (2), and the end of the guide section which is connected to the ground is connected to the construction area (8) to form a lifting channel (9) which is directly connected to the high-pressure shaft (1) from the ground. Lifting equipment is arranged in the construction area (8), and the lifting equipment takes into account both the manufacturing of the finished steel pipe (4) in the steel pipe processing plant (5) and the installation on the working surface in the high-pressure shaft (1).
2. The integrated layout system for manufacturing and installing a pressure steel pipe according to claim 1, characterized in that: The processing site of the steel pipe processing plant (5) covers the pressure regulating shaft (2) and its guide section.
3. The integrated layout system for manufacturing and installing a pressure steel pipe according to claim 2, characterized in that: The hoisting equipment is a gantry crane (6), and a track (7) matching the gantry crane (6) is arranged in the steel pipe processing plant (5).
4. The integrated layout system for manufacturing and installing a pressure steel pipe according to claim 2, characterized in that: The layout direction of the steel pipe processing plant (5) is vertical to the water diversion line.
5. The integrated layout system for manufacturing and installing a pressure steel pipe according to claim 4, characterized in that: The steel pipe processing plant (5) is divided into a steel plate stacking area and a finished steel pipe stacking area, and the distance between the finished steel pipe stacking area and the pressure regulating well (2) is smaller than the distance between the steel plate stacking area and the pressure regulating well (2).
6. The integrated layout system for manufacturing and installing a pressure steel pipe according to claim 1, characterized in that: The length of the finished steel pipe (4) hoisted and transported through the hoisting channel (9) can reach more than 6 meters.