Flue gas denitration and dust removal equipment for tunnel kiln

By designing flue gas denitrition and dust removal equipment suitable for high-temperature tunnel kilns, multiple heat exchangers and conical covers are used to transfer the flue gas heat to the exhaust gas, and combined power output, the problem of insufficient flue gas purification in the tunnel kilns is solved and improved Denitrification efficiency and energy-saving effect.

CN221959296UActive Publication Date: 2024-11-05HEBEI HONGTAI ENVIRONMENTAL PROTECTION ENG CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420584914.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-25
Publication Date
2024-11-05
Estimated Expiration
2034-03-25

AI Technical Summary

Technical Problem

The flue gas emission temperature of the tunnel kiln is higher than the normal working temperature of the SCR denitrification reactor, resulting in low denitrification rate and inability to adapt to the high-temperature tunnel kiln, resulting in insufficient flue gas purification.

Method used

A tunnel kiln flue gas denitrition equipment is designed, including a denitrification reactor, dust collector, desulfurization tower, fan and chimney. By setting up multiple heat exchangers and conical covers, the heat of the flue gas is transferred to the purified exhaust gas. , and use the power combined output of the fan and motor to reduce power consumption and adapt to SCR denitrification reactor.

Benefits of technology

It effectively reduces the flue gas temperature to a suitable denitrification reactor state, improves the denitrification efficiency, reduces the emission of nitrogen oxides, reduces environmental pollution, and reduces the motor load through kinetic energy conversion, saving electricity.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221959296U_ABST
    Figure CN221959296U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of industrial waste gas treatment, and discloses flue gas denitration and dust removal equipment for a tunnel kiln, which comprises a denitration reactor, a dust remover, a desulfurizing tower, a fan and a chimney, and is characterized in that a second heat exchanger and a conical cover are communicated with the bottom of the chimney, and a fifth flue gas pipe is arranged at an outlet of the fan and communicated with the bottom end of the conical cover; compared with the prior art, the denitration reactor has the advantages that before flue gas enters the denitration reactor, the temperature of the flue gas is reduced through the first heat exchanger, and the flue gas is cooled through the second heat exchanger; the heat released by the flue gas is fed into the second heat exchanger and transmitted to the purified tail gas, the tail gas expands after being heated to accelerate emission, the overall purification speed of the device is increased, a set of simple turbine structure is arranged in the chimney, the flue gas heat energy is converted into kinetic energy, the turbine structure and a motor synchronously drive a fan in the device, the load of the motor can be reduced, and the power consumption is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of industrial waste gas treatment, in particular to tunnel kiln flue gas denitrification and dust removal equipment. Background Art

[0002] Tunnel kiln flue gas denitrification and dust removal equipment is used to treat flue gas generated during cement production. Tunnel kiln is a commonly used clinker calcining equipment, but its flue gas usually contains a large amount of pollutants such as nitrogen oxides (NOx), sulfur-containing gases and dust. In order to avoid tunnel kiln flue gas polluting the environment, it is often necessary to select a denitrification device, a dust removal device and a desulfurization device in series to purify the flue gas before discharging it from the chimney. Among the current mainstream denitrification devices, the SCR denitrification reactor has been widely used due to its high denitrification rate.

[0003] However, tunnel kilns have different operating temperatures depending on the materials they process. The temperature of some tunnel kilns can reach thousands of degrees Celsius, which will cause the flue gas emission temperature to be much higher than the normal operating temperature of the SCR denitrification reactor. This type of tunnel kiln can only select other reactors with high operating temperatures but low denitrification rates, resulting in insufficient flue gas purification. Utility Model Content

[0004] 1. Technical Problems Solved

[0005] The technical problem to be solved by the utility model is that regardless of the high-temperature tunnel kiln, an SCR denitration reactor cannot be adapted, and a tunnel kiln flue gas denitration and dust removal device is provided.

[0006] 2. Technical Solution

[0007] In order to solve the above technical problems, the technical solution provided by the utility model is: a tunnel kiln flue gas denitrification and dust removal equipment, which includes a denitrification reactor, a dust collector, a desulfurization tower, a fan and a chimney. A flue gas collection pipe is arranged at the inlet of the denitrification reactor and connected to the tunnel kiln. A second flue gas pipe is arranged between the denitrification reactor and the dust collector, a third flue gas pipe is arranged between the dust collector and the desulfurization tower, a fourth flue gas pipe is arranged between the desulfurization tower and the fan, and the fan and the chimney are connected.

[0008] The bottom of the chimney is connected to the second heat exchanger and the conical hood, the fan outlet is provided with a fifth smoke pipe connected to the bottom of the conical hood, the tip of the conical hood is connected to the cold end inlet of the second heat exchanger, and the cold end outlet of the second heat exchanger is connected to the bottom of the chimney.

[0009] Furthermore, a flue gas collecting pipe is connected to a first heat exchanger, a circulating water inlet pipe is connected to the cold end inlet of the first heat exchanger, a waste heat transport pipe is connected to the cold end outlet, a flue gas collecting pipe is connected to the hot end inlet of the first heat exchanger, a first flue gas pipe is arranged at the hot end outlet, and the first flue gas pipe is connected to the denitrification reactor inlet to transfer excess heat of the flue gas to the purified exhaust gas.

[0010] Furthermore, a plurality of water exchange channel plates are arranged inside the second heat exchanger, and the water exchange channel plates are arranged parallel to the flue gas flow direction in the second heat exchanger. The top inlet of the water exchange channel plate is connected to a first ring pipe, and the bottom outlet is connected to a second ring pipe. The first ring pipe is connected to the waste heat transport pipeline, and the second ring pipe is connected to a circulating water outlet pipeline.

[0011] Furthermore, the outlet pipe diameter of the cold end of the second heat exchanger is smaller than the pipe diameter of the bottom of the chimney. The stator fan and the rotor fan are arranged at the bottom of the chimney from bottom to top. The blades of the stator fan and the rotor fan are arranged in opposite directions to convert the thermal energy of the flue gas into kinetic energy.

[0012] Furthermore, a transmission box is connected to the bottom of the conical cover, and a variable frequency motor is connected to the bottom of the transmission box. An output shaft is provided at the output end of the transmission box and is connected to the fan power. A first gear is provided inside the transmission box, and the output shaft is provided with a second gear meshing with the first gear. The top surface of the first gear is fixedly connected to a gear frame, and the gear frame is hollow. A third gear and a fourth gear are respectively provided on both sides of the gear frame parallel to the axis of the first gear. Planetary gears are provided on both sides of the gear frame perpendicular to the axis of the first gear. The third gear is meshed with the planetary gears, and the fourth gear is meshed with the planetary gears. The third gear passes through the gear frame and is connected to the variable frequency motor power. The fourth gear passes through the gear frame and is provided with a transmission shaft, and the transmission shaft is connected to the rotor fan power, so that the motor power and the above-mentioned turbine power are combined and output to the fan to reduce power consumption.

[0013] Furthermore, the transmission shaft is located at one end of the gear frame and is fixedly sleeved with a first locking ring, the transmission shaft is located inside the transmission box and is slidingly sleeved with a second locking ring, a key transmission is arranged between the second locking ring and the transmission shaft, a connecting rod is rotatably connected to the outer side of the second locking ring, the side of the connecting rod extends to the outside of the transmission box, a servo electric cylinder is arranged outside the transmission box, the extension and retraction direction of the servo electric cylinder is parallel to the sliding direction of the second locking ring, the power end of the servo electric cylinder is connected to the connecting rod, and when the device is started cold, the structure can allow the motor to temporarily drive the turbine until the heat exchanger reaches thermal equilibrium.

[0014] 3. Beneficial Effects

[0015] The advantages of the utility model compared with the prior art are:

[0016] 1. Before the flue gas enters the denitrification reactor, it first passes through the first heat exchanger to reduce the temperature to a state suitable for the operation of the denitrification reactor. The heat released by the flue gas is sent to the second heat exchanger and transferred to the purified tail gas. After being heated, the tail gas expands and is discharged faster, thereby improving the overall purification speed of the device.

[0017] 2. This device sets up a simple turbine structure in the chimney to convert the heat energy of the flue gas into kinetic energy, and drives the fan in the device synchronously with the motor. Since additional power input is provided to the fan, the load of the motor can be reduced, and the working frequency of the motor can be reduced to save electricity. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a structural schematic diagram of tunnel kiln flue gas denitrification and dust removal equipment.

[0019] Figure 2 It is a structural schematic diagram of tunnel kiln flue gas denitrification and dust removal equipment.

[0020] Figure 3 The present invention is a schematic diagram of the cross-sectional structure of the second heat exchanger of the tunnel kiln flue gas denitrification and dust removal equipment.

[0021] Figure 4 The present invention is a schematic diagram of the cross-sectional structure of a transmission box of a tunnel kiln flue gas denitrification and dust removal equipment.

[0022] As shown in the figure: 1. Flue gas collection pipe, 2. First heat exchanger, 3. First flue gas pipe, 4. Denitrification reactor, 5. Second flue gas pipe, 6. Dust collector, 7. Third flue gas pipe, 8. Desulfurization tower, 9. Fourth flue gas pipe, 10. Fan, 11. Fifth flue gas pipe, 12. Frequency conversion motor, 13. Conical hood, 14. Second heat exchanger, 15. Chimney, 16. Circulating water inlet pipe, 17. Waste heat transport pipe, 18. Circulating water outlet pipe, 19. Transmission box, 20. Output shaft, 21. Transmission shaft, 22. Second ring pipe, 23. Heat exchange channel plate, 24. First ring pipe, 25. Stator fan, 26. Rotor fan, 27. First gear, 28. Gear rack, 29. Planetary gear, 30. Third gear, 31. Fourth gear, 32. First locking ring, 33. Second locking ring, 34. Connecting rod, 35. Servo cylinder. DETAILED DESCRIPTION

[0023] The utility model is further described in detail below in conjunction with the accompanying drawings.

[0024] Embodiment 1

[0025] Combined with Figure 1A tunnel kiln flue gas denitrification and dust removal device comprises a denitrification reactor 4, a dust collector 6, a desulfurization tower 8, a fan 10 and a chimney 15. A flue gas collecting pipe 1 is arranged at the entrance of the denitrification reactor 4 and connected to the tunnel kiln. A second flue gas pipe 5 is arranged between the denitrification reactor 4 and the dust collector 6. A third flue gas pipe 7 is arranged between the dust collector 6 and the desulfurization tower 8. A fourth flue gas pipe 9 is arranged between the desulfurization tower 8 and the fan 10. The fan 10 and the chimney 15 are arranged in communication.

[0026] The second heat exchanger 14 and the conical cover 13 are connected at the bottom of the chimney 15, the fifth flue gas pipe 11 is connected to the bottom of the conical cover 13 at the outlet of the fan 10, the tip of the conical cover 13 is connected to the cold end inlet of the second heat exchanger 14, and the cold end outlet of the second heat exchanger 14 is connected to the bottom of the chimney 15.

[0027] Combined with Figure 1 and attached Figure 3 The flue gas collecting pipe 1 is connected with the first heat exchanger 2, the cold end inlet of the first heat exchanger 2 is connected with the circulating water inlet pipe 16, the cold end outlet is connected with the waste heat delivery pipe 17, the hot end inlet of the first heat exchanger 2 is connected with the flue gas collecting pipe 1, the hot end outlet is provided with the first flue gas pipe 3, and the first flue gas pipe 3 is connected with the inlet of the denitration reactor 4. A plurality of heat exchange channel plates 23 are arranged inside the second heat exchanger 14, and the heat exchange channel plates 23 are arranged parallel to the flue gas flow direction in the second heat exchanger 14. The top inlet of the heat exchange channel plate 23 is connected with the first annular pipe 24, and the bottom outlet is connected with the second annular pipe 22. The first annular pipe 24 is connected with the waste heat delivery pipe 17, and the second annular pipe 22 is connected with the circulating water outlet pipe 18.

[0028] The above-mentioned device can utilize the circulating water system within the factory to transfer the heat of the tunnel kiln flue gas to the purified exhaust gas emission section, and can reduce the flue gas temperature to a temperature suitable for the denitrification reactor for denitrification treatment. It is suitable for the SCR denitrification reactor with higher denitrification efficiency, thereby improving the denitrification effect of the tunnel kiln flue gas, reducing the emission of nitrogen oxides, and reducing environmental pollution.

[0029] Embodiment 2

[0030] Combined with Figure 3 The outlet diameter of the cold end of the second heat exchanger 14 is smaller than the bottom diameter of the chimney 15. The stator fan 25 and the rotor fan 26 are arranged at the bottom of the chimney 15 from bottom to top, and the blades of the stator fan 25 and the rotor fan 26 are arranged in reverse.

[0031] The above-mentioned device cooperates with the heat transfer effect in Example 1 to further utilize the waste heat of the flue gas. The purified flue gas is sent to the conical hood through the fan, and the airflow is compressed under the influence of its internal contour. The compressed exhaust gas enters the heat exchanger to absorb heat. After the high-temperature and high-pressure exhaust gas enters the chimney, it begins to expand because the inner diameter of the chimney is larger than the inner diameter of the second heat exchanger. At this time, the airflow is first deflected by the stator fan, and then the rotor fan is pushed to rotate at a larger angle of attack, thereby converting the excess waste heat of the flue gas into kinetic energy.

[0032] Combined with Figure 4 A transmission box 19 is connected to the bottom of the conical cover 13, and a frequency conversion motor 12 is connected to the bottom of the transmission box 19. An output shaft 20 is provided at the output end of the transmission box 19 to be powered by the fan 10. A first gear 27 is provided inside the transmission box 19, and a second gear is provided on the output shaft 20 to mesh with the first gear 27. The top surface of the first gear 27 is fixedly connected to a gear frame 28, and the gear frame 28 is hollow. A third gear 30 and a fourth gear 31 are respectively provided on both sides of the gear frame 28 parallel to the axis of the first gear 27. Planetary gears 29 are provided on both sides of the gear frame 28 perpendicular to the axis of the first gear 27. The third gear 30 is meshed with the planetary gears 29, and the fourth gear 31 is meshed with the planetary gears 29. The third gear 30 passes through the gear frame 28 to be powered by the frequency conversion motor 12, and the fourth gear 31 passes through the gear frame 28 to be provided with a transmission shaft 21, and the transmission shaft 21 is powered by the rotor fan 26.

[0033] The power for the flow of smoke in this device is provided by the fan as a whole. The transmission box can combine the power of the variable frequency motor and the power of the rotor fan with the above structure and output them to the fan. Compared with the fan driven by the motor alone, the power of the rotor fan can reduce the load of the motor part. Therefore, the variable frequency motor is selected as the power. The frequency of the variable frequency motor can be appropriately reduced according to the power output of the rotor fan to reduce power consumption and save energy.

[0034] Combined with Figure 4 The transmission shaft 21 is located at one end of the gear frame 28 and is fixedly sleeved with a first locking ring 32. The transmission shaft 21 is located inside the transmission box 19 and is slidingly sleeved with a second locking ring 33. A key transmission is set between the second locking ring 33 and the transmission shaft 21. The second locking ring 33 is rotatably connected to the outer side of the second locking ring 33. The side of the second locking ring 33 extends to the outside of the transmission box 19. A servo electric cylinder 35 is set outside the transmission box 19. The extension direction of the servo electric cylinder 35 is parallel to the sliding direction of the second locking ring 33. The power end of the servo electric cylinder 35 is connected to the connecting rod 34.

[0035] When the device is started up cold, the first and second heat exchangers cannot reach thermal equilibrium in a short time, and there is not enough heat to drive the rotor fan. At this time, the drive shaft connected to the rotor fan can be converted into the second output shaft of the transmission box through the above device, and the fan and the rotor fan are driven by the variable frequency motor at the same time. The motor is temporarily used as a power source to drive before the heat exchanger reaches thermal equilibrium.

[0036] The above description of the utility model and its implementation methods is not restrictive. The drawings show only one implementation method of the utility model, and the actual structure is not limited thereto. In short, if ordinary technicians in this field are inspired by it and design structural methods and embodiments similar to the technical solution without creativity without departing from the purpose of the invention of the utility model, they should all fall within the protection scope of the utility model.

Claims

1. A tunnel kiln flue gas denitration and dust removal device, comprising a denitration reactor (4), a dust collector (6), a desulfurization tower (8), a fan (10) and a chimney (15), wherein a flue gas collecting pipe (1) is arranged at the inlet of the denitration reactor (4) and connected to the tunnel kiln, a second flue gas pipe (5) is arranged in communication between the denitration reactor (4) and the dust collector (6), a third flue gas pipe (7) is arranged in communication between the dust collector (6) and the desulfurization tower (8), a fourth flue gas pipe (9) is arranged in communication between the desulfurization tower (8) and the fan (10), and the fan (10) and the chimney (15) are arranged in communication, characterized in that: The bottom of the chimney (15) is connected to the second heat exchanger (14) and the conical cover (13); the outlet of the fan (10) is provided with a fifth smoke pipe (11) connected to the bottom of the conical cover (13); the tip of the conical cover (13) is connected to the cold end inlet of the second heat exchanger (14); and the cold end outlet of the second heat exchanger (14) is connected to the bottom of the chimney (15).

2. The tunnel kiln flue gas denitrification and dust removal equipment according to claim 1, characterized in that: The flue gas collection pipe (1) is connected to a first heat exchanger (2); a circulating water inlet pipe (16) is connected to the cold end inlet of the first heat exchanger (2); a waste heat transport pipe (17) is connected to the cold end outlet; a flue gas collection pipe (1) is connected to the hot end inlet of the first heat exchanger (2); a first flue gas pipe (3) is provided at the hot end outlet; and the first flue gas pipe (3) is connected to the inlet of a denitration reactor (4).

3. The tunnel kiln flue gas denitrification and dust removal equipment according to claim 2, characterized in that: A plurality of heat exchange channel plates (23) are arranged inside the second heat exchanger (14), and the heat exchange channel plates (23) are arranged parallel to the direction of smoke flow in the second heat exchanger (14). The top inlet of the heat exchange channel plate (23) is connected to a first annular pipe (24), and the bottom outlet is connected to a second annular pipe (22). The first annular pipe (24) is connected to a waste heat transport pipeline (17), and the second annular pipe (22) is connected to a circulating water outlet pipeline (18).

4. The tunnel kiln flue gas denitrification and dust removal equipment according to claim 1, characterized in that: The diameter of the cold end outlet pipe of the second heat exchanger (14) is smaller than the diameter of the bottom pipe of the chimney (15), and a stator fan (25) and a rotor fan (26) are arranged at the bottom of the chimney (15) from bottom to top, and the blades of the stator fan (25) and the rotor fan (26) are arranged in opposite directions.

5. The tunnel kiln flue gas denitrification and dust removal equipment according to claim 4, characterized in that: The bottom of the conical cover (13) is connected to a transmission box (19), the bottom of the transmission box (19) is connected to a variable frequency motor (12), an output shaft (20) is provided at the output end of the transmission box (19) for power connection with the fan (10), a first gear (27) is provided inside the transmission box (19), the output shaft (20) is provided with a second gear meshing with the first gear (27), the top surface of the first gear (27) is fixedly connected to a gear rack (28), the gear rack (28) is hollow, and the inside of the gear rack (28) is parallel to the axis of the first gear (27) and has two A third gear (30) and a fourth gear (31) are respectively arranged on the sides; planetary gears (29) are arranged inside the gear frame (28) perpendicular to the axis of the first gear (27) on both sides; the third gear (30) is meshed with the planetary gears (29); the fourth gear (31) is meshed with the planetary gears (29); the third gear (30) passes through the gear frame (28) and is connected to the variable frequency motor (12); the fourth gear (31) passes through the gear frame (28) and is provided with a transmission shaft (21); the transmission shaft (21) is connected to the rotor fan (26) by power.

6. The tunnel kiln flue gas denitrification and dust removal equipment according to claim 5, characterized in that: The transmission shaft (21) is located at one end of the gear frame (28) and is fixedly sleeved with a first locking ring (32); the transmission shaft (21) is located inside the transmission box (19) and is slidably sleeved with a second locking ring (33); a key transmission is arranged between the second locking ring (33) and the transmission shaft (21); a second locking ring (33) is rotatably connected to the outer side of the second locking ring (33); the side of the second locking ring (33) extends to the outside of the transmission box (19); a servo electric cylinder (35) is arranged outside the transmission box (19); the extension direction of the servo electric cylinder (35) is parallel to the sliding direction of the second locking ring (33); and the power end of the servo electric cylinder (35) is connected to the connecting rod (34).

Citation Information

Cited By

  • Industrial furnace flue gas carbon reduction, desulfurization and denitrification system

    CN120868780A