Fabricated soil retaining structure for municipal engineering construction

By setting reinforcement ribs and steel wires on the foundation of the retaining wall, and using docking plates and connecting blocks to achieve stable connection between the walls, the construction restricted on weak foundations of gravity retaining walls in the prior art is solved. The problem of unstable horizontal docking improves construction quality and safety.

CN221989385UActive Publication Date: 2024-11-12HUNAN ZHONGCHENG CONSTR ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420011821.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-03
Publication Date
2024-11-12
Estimated Expiration
2034-01-03

AI Technical Summary

Technical Problem

The existing gravity retaining walls are limited by load capacity when constructed on weak foundations, have slow construction speed, poor environmental coordination, and unstable horizontal docking of prefabricated retaining walls.

Method used

Adopt a prefabricated retaining structure, including the retaining wall foundation and connecting structure. By setting grooves and baffles at the top of the wall, reinforcing ribs and steel wires are installed on the back of the wall, and stable connection between the wall is achieved by using docking plates and connecting blocks. , ensure the firm fixation between the wall and the soil.

Benefits of technology

The lateral connection stability and fixation with the soil of the prefabricated retaining wall are improved, the construction quality and safety are enhanced, and the problems of slow construction speed and poor environmental coordination in the prior art are solved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221989385U_ABST
    Figure CN221989385U_ABST
Patent Text Reader

Abstract

The utility model relates to the related field of retaining walls, in particular to a fabricated retaining structure for municipal engineering construction, which comprises a retaining wall foundation, a wall body, a mounting groove, a baffle, a reinforcing frame and a connecting structure 6. The connecting structure is arranged, two adjacent wall bodies can be in butt joint through the butt joint plates arranged on the back of the first mounting plate in the connecting structure in a bilateral symmetry mode, the connecting stability of the left sides and the right sides of the wall bodies is guaranteed, and the problem that in the prior art, the connecting stability of the two adjacent wall bodies is insufficient is solved; mounting steel wires penetrate through the interiors of the mounting plates I, so that the connection stability of the two adjacent wall bodies is further enhanced; the reinforcing ribs are installed at the upper end and the lower end of the front face of the first installation plate and penetrate through the wall body to be embedded into the soil body, connection stability of the fabricated wall body and the soil body can be guaranteed, soil filling or deformation and instability of the soil body can be better prevented, safety is guaranteed, and construction quality is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of retaining walls, in particular to an assembled retaining structure for municipal engineering construction. Background Art

[0002] A retaining wall refers to a structure that supports roadbed fill or hillside soil and prevents the fill or soil from deforming and becoming unstable. It is usually used in projects such as slopes, roadbeds, and rivers. The existing technology generally uses cast-in-place concrete retaining walls, namely gravity retaining walls. Gravity retaining walls use the retaining wall's own gravity to maintain the stability of the retaining wall under the action of soil pressure.

[0003] The problems with the prior art are as follows: since the gravity retaining wall relies on its own weight to maintain balance and stability, it is large in size and weight. When built on a soft foundation, it is often limited by its bearing capacity and has poor coordination with the surrounding environment. In addition, the project volume is large, the construction speed is slow, and a large amount of manpower is required; and the prefabricated retaining wall of the prior art has unstable lateral docking.

[0004] To this end, we propose a prefabricated retaining structure for municipal engineering construction to solve the above problems. Utility Model Content

[0005] The utility model provides an assembled earth retaining structure for municipal engineering construction to solve the technical problems raised in the above-mentioned background technology.

[0006] In order to achieve the above-mentioned purpose, the utility model adopts the following technical scheme: an assembled retaining structure for municipal engineering construction, including a retaining wall foundation and a connecting structure, a wall body is installed on the top of the retaining wall foundation, a groove is formed in the wall body, installation grooves are symmetrically arranged on both sides of the top surface of the wall body, a baffle is arranged on the contact surface between the groove in the wall body and the soil body, and a reinforcing frame is arranged on the back of the baffle plate; the connecting structure is installed on the lower part of the back of the wall body, the connecting structure includes a mounting plate 1, reinforcing ribs, a docking plate, a steel wire and a connecting block, the mounting plate 1 is installed on the lower part of the back of the wall body, and reinforcing ribs are installed on the upper and lower ends of the front side, the reinforcing ribs pass through the wall body and are embedded in the soil body, the docking plate is installed on the left and right sides of the back of the mounting plate 1, the mounting plate 1 has a steel wire installed inside, the steel wire passes through the left and right sides of the wall, a connecting block is installed in the middle of the front side of the mounting plate 1, and the connecting block is embedded in the lower part of the back of the wall.

[0007] Preferably, the docking plate includes a second mounting plate, mounting holes and fixing bolts, the second mounting plate is installed on the left and right sides of the back of the first mounting plate, and mounting holes are provided on its corners, and the fixing bolts are embedded in the mounting holes and connected to the first mounting plate.

[0008] Preferably, two mounting plates 2 are provided and are symmetrically installed on the left and right sides of the back of the mounting plate 1.

[0009] Preferably, there are no less than two mounting holes, which can be arranged vertically and diagonally on one corner of the mounting plate.

[0010] Preferably, the mounting plate 1 is a square structure.

[0011] Preferably, at least two reinforcing ribs are provided and are symmetrically installed on a front side of the mounting plate.

[0012] Preferably, there are no less than two steel wires, and they are installed in a longitudinal array.

[0013] Preferably, the connecting block is a square structure.

[0014] Beneficial effects of the utility model:

[0015] The utility model is provided with a connection structure, and two adjacent walls can be butted together by a butt joint plate symmetrically arranged on the back of a mounting plate in the connection structure, thereby ensuring the connection stability of the left and right sides of the wall, and solving the problem of insufficient connection stability of two adjacent walls in the prior art; and the connection stability of the two adjacent walls is further strengthened by passing the installation wire through the inside of the mounting plate.

[0016] The utility model can ensure the connection stability between the assembled wall and the soil by installing reinforcing ribs on the upper and lower ends of the front side of the installation plate, and the reinforcing ribs pass through the wall and embed into the soil, which can better prevent the filling or soil from deforming and becoming unstable, ensure safety, and improve construction quality. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a schematic diagram of the structure of the utility model;

[0018] Figure 2 It is a structural schematic diagram of the cross section of the utility model;

[0019] Figure 3 It is a structural schematic diagram of the connection structure of the utility model;

[0020] Figure 4 It is a structural schematic diagram of the front side of the mounting plate of the utility model;

[0021] Figure 5 It is a structural schematic diagram of a docking plate of the utility model.

[0022] Among them: retaining wall foundation-1, wall-2, installation groove-3, baffle-4, reinforcement frame-5, connection structure-6, installation plate 1-61, reinforcement rib-62, docking plate-63, steel wire-64, connection block-65, installation plate 2-631, installation hole-632, fixing bolt-633. DETAILED DESCRIPTION

[0023] In order to further explain the technical solution of the present utility model, it is described in detail through specific embodiments below.

[0024] like Figure 1 , 2 As shown, the utility model provides an assembled retaining structure for municipal engineering construction, including a retaining wall foundation 1, which is used as a basis for construction and installation. A wall body 2 is installed on the top of the retaining wall foundation 1 to prevent the fill or soil from deforming and becoming unstable. A groove is formed in the wall body 2, and installation grooves 3 are symmetrically arranged on both sides of the top surface of the wall body 2 for the upper and lower assembly of the wall body 2. A baffle 4 is arranged on the contact surface between the groove in the wall 2 and the soil to strengthen the support for the fill or soil. A reinforcing frame 5 is arranged on the back of the baffle 4, and the reinforcing frame 5 is used to enhance stability and strengthen the rigidity of the wall body 2 at the same time.

[0025] like Figure 3 , 4 As shown, the connection structure 6 of the utility model is used to connect two adjacent walls 2 and strengthen the connection stability between the wall 2 and the soil. The connection structure 6 is installed at the lower back of the wall 2. The connection structure 6 includes a mounting plate 61, a reinforcing rib 62, a docking plate 63, a steel wire 64 and a connection block 65. The mounting plate 61 is installed at the lower back of the wall 2 for installation and connection, and reinforcing ribs 62 are installed at the upper and lower ends of the front. The reinforcing rib 62 passes through the wall 2 and is embedded in the soil to strengthen the connection stability. At the same time, the wall 2 can be better fixed on the soil. The docking plate 63 is installed on the left and right sides of the back of the mounting plate 61 to connect the two adjacent walls 2 and improve the lateral stability and installation stability. The mounting steel wire 64 runs through the inside of the mounting plate 61. The mounting steel wire 64 can further strengthen the connection stability of the two adjacent walls. The steel wire 64 passes through the left and right sides of the wall 2. A connection block 65 is installed in the middle of the front of the mounting plate 61. The connection block 65 is embedded in the lower back of the wall 2 to ensure the connection stability between the connection structure 6 and the wall 2.

[0026] Among them, the mounting plate 1 61 is a square structure, and the directional structure has better connection stability, ensuring the overall installation stability of the structure;

[0027] In this embodiment, ten reinforcing ribs 62 are provided, and are symmetrically installed on the front of the mounting plate 1 61. The provision of ten reinforcing ribs can better ensure the connection stability between the assembled wall and the soil, and prevent the fill or soil from deforming and becoming unstable.

[0028] In this embodiment, five steel wires 64 are provided and installed in a longitudinal array. The provision of five steel wires can further enhance the connection stability of two adjacent walls.

[0029] Among them, the connecting block 65 is a square structure, which has the same principle as the above-mentioned mounting plate 61. The directional structure has better connection stability, ensuring the overall installation stability of the structure.

[0030] like Figure 5 As shown, the docking plate 63 of the utility model includes a second mounting plate 631, a mounting hole 632 and a fixing bolt 633. The second mounting plate 631 is installed on the left and right sides of the back of the first mounting plate 61 for installation and connection, and the mounting hole 632 is provided on the corner thereof, and the fixing bolt 633 is inserted into the mounting hole 632 to connect with the first mounting plate 61, and the two adjacent walls 2 are connected by the fixing bolt 633;

[0031] Among them, there are two mounting plates 631, which are symmetrically installed on the left and right sides of the back of the mounting plate 61, and two can be connected to other walls on the left and right sides of the wall 2 at the same time, ensuring the overall stability of the connection;

[0032] In this embodiment, four mounting holes 632 are provided, which can be arranged up and down and diagonally on the corners of the mounting plate 61. The four mounting holes 632 can better fix the walls on both sides and reduce the occurrence of falling off due to unstable connection.

[0033] Working principle: The retaining wall foundation 1 is used as the foundation for construction and installation. The wall 2 installed on the top of the retaining wall foundation 1 is used to prevent the fill or soil from deforming and becoming unstable. The wall 2 can be assembled up and down through the installation groove 3. The baffle 4 is used to strengthen the support for the fill or soil. The stability is further enhanced through the reinforcement frame 5, and the rigidity of the wall 2 is strengthened. Then, the two adjacent walls 2 are connected through the connection structure 6;

[0034] The connection structure 6 includes a mounting plate 61, which is installed on the wall 2 through the mounting plate 61, and then the reinforcing ribs 62 installed on the front of the mounting plate 61 are embedded in the soil to strengthen the connection stability, so that the wall 2 is better fixed on the soil. Two adjacent walls 2 are connected through a docking plate 63, and a steel wire 64 is passed through one side of the wall 2 to be installed in the mounting plate 1 to strengthen the stability of the two adjacent walls 2. The connection block 65 can ensure the connection stability between the entire structure and the wall 2;

[0035] The docking plate 63 includes a second mounting plate 631 , a mounting hole 632 and a fixing bolt 633 . The second mounting plate 631 is installed on the adjacent wall 2 by passing the fixing bolt 633 through the mounting hole 632 , so that two adjacent walls are connected.

[0036] The above description is only a preferred example of the present invention and is not intended to limit the present invention. Although the present invention is described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions described in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. An assembled retaining structure for municipal engineering construction, comprising a retaining wall foundation (1), a wall body (2) being installed at the top of the retaining wall foundation (1), a groove being formed in the wall body (2), mounting grooves (3) being symmetrically arranged on both sides of the top surface of the wall body (2), a baffle (4) being arranged on the contact surface between the groove in the wall body (2) and the soil body, and a reinforcing frame (5) being arranged on the back of the baffle (4); Features: The invention also comprises a connection structure (6), wherein the connection structure (6) is installed at the lower back of the wall (2), and the connection structure (6) comprises a mounting plate (61), a reinforcing rib (62), a butt joint plate (63), a steel wire (64) and a connection block (65). The mounting plate (61) is installed at the lower back of the wall (2), and reinforcing ribs (62) are installed at the upper and lower ends of the front face, and the reinforcing ribs (62) pass through the wall (2) and are embedded in the soil. The butt joint plate (63) is installed at the left and right sides of the back of the mounting plate (61). The mounting steel wire (64) passes through the inside of the mounting plate (61), and the steel wire (64) passes through the left and right sides of the wall (2). A connection block (65) is installed at the middle of the front face of the mounting plate (61), and the connection block (65) is embedded in the lower back of the wall (2).

2. The assembled earth retaining structure for municipal engineering construction according to claim 1, characterized in that: The docking plate (63) comprises a second mounting plate (631), a mounting hole (632) and a fixing bolt (633); the second mounting plate (631) is mounted on the left and right sides of the back of the first mounting plate (61), and the mounting holes (632) are arranged on the corners; the fixing bolt (633) is embedded in the mounting hole (632) and connected to the first mounting plate (61).

3. The assembled earth retaining structure for municipal engineering construction according to claim 2 is characterized in that: The second mounting plate (631) is provided with two and is symmetrically mounted on the left and right sides of the back of the first mounting plate (61).

4. The assembled earth retaining structure for municipal engineering construction according to claim 2, characterized in that: The mounting holes (632) are provided with no less than two and can be arranged vertically and diagonally on the corners of the mounting plate (61).

5. The assembled earth retaining structure for municipal engineering construction according to claim 1, characterized in that: The mounting plate 1 (61) is a square structure.

6. The assembled earth retaining structure for municipal engineering construction according to claim 1, characterized in that: The reinforcing ribs (62) are provided in no less than two pieces and are symmetrically mounted on the front side of the first mounting plate (61) in an upper and lower manner.

7. The assembled earth retaining structure for municipal engineering construction according to claim 1, characterized in that: The steel wires (64) are provided in a number of not less than two and are installed in a longitudinal array.

8. The assembled earth retaining structure for municipal engineering construction according to claim 1, characterized in that: The connecting block (65) is a square structure.