Rapid supporting device for fractured stratum tunnel
By using initial spray ruler and steel bar hanging structure in broken formation tunnels, combined with grouting steel frame and drainage pipelines, the problems of untimely support and irregular groundwater flow in the initial stage are solved, and fast and accurate support and Improve construction efficiency.
Patent Information
- Application Number
- CN202323480757.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-20
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2033-12-20
AI Technical Summary
In the excavation of broken formation tunnels, the existing technology is difficult to achieve rapid and accurate initial support, resulting in a high risk of collapse accidents, and irregular groundwater flow leads to construction suspension, affecting efficiency.
The first layer of steel bar hanging net is formed by using the initial spraying ruler and steel bar hanging net structure, through anchors, drilling holes on the rock surface and spraying concrete to form a first layer of steel bar hanging net, combining the grouting steel frame and drainage pipeline to ensure the rapid installation of support and the effective groundwater drain.
It has achieved rapid and precise installation of initial support, reduced the risk of collapse, reduced construction downtime, and improved construction efficiency and safety.
Smart Images

Figure CN221990388U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of road and bridge construction, and specifically relates to a rapid supporting device for a broken stratum tunnel. Background Art
[0002] Fractured ground is a geological condition that usually includes fault zones, joint development, rock fragmentation, and unformed cores. Therefore, tunneling in fractured ground is a challenging task because these formations usually have poor rock quality and / or unstable geological conditions, which makes tunnel excavation and support difficult because many factors need to be considered, such as:
[0003] Water and mud inrush: In areas with abundant groundwater, the excavation of underground projects will destroy the original stratum structure and break the mechanical balance of the soil and water in the stratum. Collapse: It is mainly caused by improper operation or other reasons that lead to untimely and unstable support, resulting in the engineering framework exceeding its own strength limit under the action of external force or gravity, or causing collapse accidents due to the destruction of structural stability.
[0004] In the prior art, in order to overcome the various problems caused by geological factors in the broken strata, the support measures taken include pre-grouting reinforcement: before tunnel excavation, the strata can be reinforced by pre-grouting to improve the stability and strength of the strata; or anchor rods and anchor cables are used to drill holes in the walls and top plates of the tunnel, insert anchor rods and anchor cables, and fix them in the soil layer by grouting to increase the stability of the tunnel; or shotcrete, etc. However, these support methods still have the problem of untimely initial support. Once the broken strata collapse, it is easy to cause production safety accidents. Utility Model Content
[0005] The utility model aims to provide a rapid support device for a broken stratum tunnel, which can quickly support the broken stratum in the early stage of tunnel excavation to avoid serious production safety accidents caused by collapse of the broken stratum.
[0006] In order to achieve the above purpose, the technical solution adopted by the utility model is specifically as follows:
[0007] A rapid support device for a tunnel in a broken stratum comprises a primary spraying ruler nailed into the rock surface of the tunnel, a first layer of steel mesh connected to the primary spraying ruler, a grouting steel frame and a second layer of steel mesh connected to the grouting steel frame; the primary spraying ruler comprises a plurality of anchors nailed into the rock surface of the tunnel, a connecting groove is provided on each anchor, and a first layer of steel mesh installation position is formed between the plurality of anchors; the grouting steel frame is prefabricated in multiple sections and is fitted to the first layer of steel mesh for installation.
[0008] Furthermore, the grouting steel frame includes a base, a lower template connected to the base, and an upper template connected to the first layer of steel bar hanging net.
[0009] Furthermore, the base is fitted to the corners of the tunnel, and the lower template includes at least two columns and an arc surface connected between the columns.
[0010] Furthermore, a drainage pipe is arranged in the lower template.
[0011] Furthermore, the upper template includes a plurality of arc-shaped sections that are spliced in sequence, and a drainage hole is provided on each arc-shaped section, and a water pipe is built into the drainage hole.
[0012] Furthermore, one end of the water delivery pipe is connected to a drainage pipe.
[0013] Compared with the prior art, the utility model has the following advantages: before the steel mesh is hung, the utility model firstly drills holes on the original tunnel rock surface and installs the initial spraying scale, so that the initial sprayed concrete reaches the preset thickness, while avoiding the situation where the initial sprayed concrete is too thin or too thick. At the same time, after the initial spraying of concrete is completed, the connection groove on the surface of the original scale can be directly used for rapid meshing, and the first steel mesh can be accurately and quickly installed in place with high installation accuracy. In addition, the utility model is also provided with drainage pipelines for broken strata to avoid the problem of irregular groundwater flow in the later support process and reduce the probability of collapse. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] In order to more clearly illustrate the technical solutions of the embodiments of the utility model, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the utility model and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other relevant drawings can be obtained based on these drawings without paying creative work.
[0015] Figure 1 The utility model is a schematic diagram of the structure of a rapid support device for a tunnel in a broken stratum provided by the utility model.
[0016] Figure 2 This is a schematic diagram of the structure of the anchor nail of the broken stratum tunnel rapid support device provided by the utility model Figure 2 .
[0017] Reference numerals:
[0018] 1. Column; 2. Anchor nail; 3. Lower formwork; 4. Upper formwork; 5. Water pipe; 6. Steel bar head; 7. Connection groove; 8. Base. DETAILED DESCRIPTION
[0019] In order to make the purpose, technical solution and advantages of the embodiment of the utility model clearer, the technical solution in the embodiment of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiment of the utility model. Obviously, the described embodiment is a part of the embodiment of the utility model, not all of the embodiments. Based on the embodiment of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0020] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.
[0021] In the description of the present utility model, it should be noted that if the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside", etc. appear, the orientation or position relationship indicated is based on the orientation or position relationship shown in the accompanying drawings, or is the orientation or position relationship in which the utility model product is usually placed when used. It is only for the convenience of describing the utility model and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present utility model.
[0022] In addition, the terms “first”, “second”, “third”, etc., if used, are merely used to distinguish between the descriptions and should not be understood as indicating or implying relative importance.
[0023] In addition, the terms "horizontal", "vertical", "overhanging", etc. do not mean that the components are required to be absolutely horizontal or overhanging, but can be slightly tilted. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but can be slightly tilted.
[0024] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", "connection", etc. should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0025] It should be noted that, in the absence of conflict, the features in the embodiments of the present invention may be combined with each other.
[0026] like Figure 1-Figure 2As shown, a rapid support device for a tunnel in a broken stratum comprises a primary spraying scale nailed into the rock surface of the tunnel, a first layer of steel mesh connected to the primary spraying scale, a grouting steel frame and a second layer of steel mesh connected to the grouting steel frame; the primary spraying scale comprises a plurality of anchors 2, and the anchors 2 are nailed into the rock surface of the tunnel, and a connecting groove 7 is provided on each anchor 2, and a first layer of steel mesh installation position is formed between the plurality of anchors 2; the grouting steel frame is prefabricated in multiple sections and is fitted to the first layer of steel mesh for installation.
[0027] Compared with the prior art, in the prior art, the construction process sequence of the initial support is: after the tunnel excavation is completed, it is necessary to immediately spray concrete for the first time to seal the rock surface, set anchor rods, hang steel mesh, and drive in a small advance pipe, and then spray again to the designed thickness. However, in the broken stratum, due to the unstable quality of the stratum rock surface and the abundance of groundwater in most cases, the sprayed surface is prone to gushing, dripping or concentrated water outlets, and drainage treatment is required for these phenomena before re-spraying the sprayed concrete. Therefore, there are the following problems: on the one hand, in the initial spraying process, there is a lack of markers, which places high demands on the construction level of the workers, and it is necessary to avoid the appropriate thickness of the initial sprayed concrete, and it is necessary to quickly set up the steel mesh. On the other hand, the occurrence of gushing points and the like will greatly delay the construction period. In the utility model, by adopting the anchor 2 with a connecting groove 7 and serving as a ruler to be nailed into the soil layer of the rock surface during the initial support. While it can serve as an indicator of the initial spraying thickness, it also serves the purpose of rapid meshing and can improve the installation accuracy of the first layer of steel mesh near the rock and soil layer. In addition, the utility model also provides a drainage structure for broken strata, which can reduce the period of downtime due to drainage and improve construction efficiency.
[0028] The grouting steel frame includes a base 8, a lower template 3 connected to the base 8, and an upper template 4 connected to the first layer of steel bar hanging net. The base 8 is attached to the corner of the tunnel, and the lower template 3 includes at least two columns 1 and an arc surface connected between the columns 1. The grouting steel frame can be quickly installed in place through the base 8 of the grouting steel frame, and the base 8 plays a stabilizing role.
[0029] A drainage pipe is provided in the lower template 3. The upper template 4 includes a plurality of arc sections spliced in sequence, and a drainage hole is provided on each arc section, and a water pipe 5 is built in the drainage hole. One end of the water pipe 5 is connected to the drainage pipe. The drainage structure on the template can effectively reduce the downtime period of drainage after the occurrence of water gushing and water dripping points.
[0030] During the specific construction, the spraying personnel should follow the operating specifications, evenly add the quick-setting agent before spraying, control the water-cement ratio, and the operators should take protective measures. Then, the anchor 2 used as the initial spraying scale is nailed into the rock and soil layer in sequence through the steel bar head 6. Then, the rock surface is immediately sprayed with shotcrete. During the initial spraying, the nozzle and the spraying surface should be kept vertical, and the nozzle is 1.5-2M away from the spraying surface. It is strictly forbidden to stand in front of the nozzle. The thickness of the initial spraying concrete should be 4-6cm. After the initial spraying is completed, the anchor rods are nailed in sequence along the tunnel to play a fixing role. After the anchor rods are installed, the meshing operation is performed again. The first layer of steel mesh is connected according to the anchor rods of the original initial spraying scale, and the mesh is quickly hung, and the gap between the steel mesh and the initial spraying surface is avoided. Then the first layer of steel mesh is reinforced, and the first layer of steel mesh is locked with the anchor rods or other fixings to avoid the first layer of steel mesh shaking during the re-spraying operation. Then the grouting steel frame is installed. The second layer of steel mesh can be pre-connected to the grouting steel frame, installed in place at one time, and then the re-spraying operation is carried out.
[0031] As described above, the above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application.
Claims
1. A rapid support device for a broken stratum tunnel, characterized in that: The invention comprises a primary spraying scale nailed into the rock surface of a tunnel, a first layer of steel mesh connected to the primary spraying scale, a grouting steel frame and a second layer of steel mesh connected to the grouting steel frame; the primary spraying scale comprises a plurality of anchors (2), and the anchors (2) are nailed into the rock surface of the tunnel, and a connecting groove (7) is provided on each anchor (2), and a first layer of steel mesh installation position is formed between the plurality of anchors (2); the grouting steel frame is a multi-section prefabricated type, and is fitted to the first layer of steel mesh for installation.
2. The rapid support device for a broken stratum tunnel according to claim 1 is characterized in that: The grouting steel frame comprises a base (8), a lower template (3) connected to the base (8), and an upper template (4) connected to the first layer of steel bar hanging net.
3. The rapid support device for a broken stratum tunnel according to claim 2 is characterized in that: The base (8) is fitted to the corners of the tunnel, and the lower template (3) includes at least two columns (1) and an arc-shaped surface connected between the columns (1).
4. The rapid support device for a broken stratum tunnel according to claim 3 is characterized by: A drainage pipe is arranged inside the lower template (3).
5. The rapid support device for a broken stratum tunnel according to claim 2 is characterized in that: The upper template (4) comprises a plurality of arc-shaped sections that are spliced in sequence, and a drainage hole is provided on each arc-shaped section, and a water pipe (5) is built into the drainage hole.
6. The rapid support device for a broken stratum tunnel according to claim 5 is characterized by: One end of the water delivery pipe (5) is connected to a drainage pipe.