Gas supply device of crystal growing furnace
By using automatic lifting and sealing components in the crystal growth furnace gas supply device, the problem of manual intervention during gas tank replacement is solved, and the automatic replacement and sealing performance of gas tanks are improved, ensuring continuous operation of the system and efficient gas supply is achieved. .
Patent Information
- Application Number
- CN202420295351.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-18
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2034-02-18
AI Technical Summary
Existing crystal growth furnace gas supply equipment requires manual intervention when replacing the gas tank, resulting in delayed system response time, increased maintenance costs, and may cause failure.
An air supply device including a lifting assembly and a sealing assembly is designed, and the automatic replacement of the gas tank is achieved by driving a threaded rod by a motor, and the sealing performance between the air pipe and the connecting pipe is improved through the sealing ring and the convex ring structure.
Automatic replacement of gas tanks is realized, manual intervention is reduced, continuous operation of the system and gas supply is ensured, the risk of air leakage is reduced, and the reliability and efficiency of the system are improved.
Smart Images

Figure CN222024553U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of crystal growing furnaces, in particular to a gas supply device of a crystal growing furnace. Background Art
[0002] After searching, a flame melting method crystal growth furnace gas supply equipment with a publication number of CN214193509U includes a bottom plate, a furnace body is fixedly installed on the top of the bottom plate, a fixed box is fixedly installed on the top of the bottom plate and on one side of the furnace body, a partition is fixedly installed in the inner cavity of the fixed box, and hydrogen cylinders are arranged in the inner cavity of the fixed box and on both sides of the front and rear of the partition. The above technical scheme is through the setting of two replaceable hydrogen cylinders. When the user uses this device, the hydrogen cylinder is placed in the inner cavity of the fixed box. At this time, the threaded tube on the top of the hydrogen cylinder is located directly below the tube body, and then the user twists the sleeve to connect the threaded tube with the tube body. When the hydrogen cylinder needs to be replaced, the user seals the tube body corresponding to the hydrogen cylinder to be replaced through the control valve, and then reversely twists the sleeve to take out the hydrogen cylinder. Through the setting of this device, the hydrogen cylinder can be replaced without stopping the machine, so as to achieve the purpose of improving work efficiency and heating stability. However, the above technical scheme still has the following shortcomings when it is actually used:
[0003] When the above technical solution is in use, when the gas in the gas cylinder is used up, the staff needs to manually replace the gas cylinder, which takes a certain amount of time, while the automatic replacement system can replace the gas cylinder more quickly. Therefore, manual replacement may cause delays in system response time, especially when continuous gas supply is required. In addition, manual replacement of gas cylinders may require the employment of specialized manpower, and since manual intervention may cause malfunctions, the cost of maintenance and repair may also increase.
[0004] Therefore, it is necessary to design a gas supply device for a crystal growth furnace to solve the above problems. Utility Model Content
[0005] The utility model aims to solve the shortcomings in the prior art and proposes a gas supply device for a crystal growth furnace.
[0006] In order to achieve the above purpose, the utility model adopts the following technical solutions:
[0007] A gas supply device for a crystal growth furnace comprises a base and a crystal growth furnace mounted on the base, wherein a placement box is fixed on the top surface of the base, a partition is fixed inside the placement box, the partition divides the inside of the placement box into two areas of equal size, liftable gas tanks are arranged on both sides of the partition, two lifting assemblies are arranged inside the placement box, two gas tanks are respectively placed on the two lifting assemblies, an air guide assembly is also arranged inside the placement box, and sealing assemblies are arranged on the two gas tanks.
[0008] As a preferred technical solution of the utility model, the lifting assembly includes a base plate, a positioning ring is fixed on the top surface of the base plate, the gas tank is located in the positioning ring, a movable groove is opened on the inner surface of the placement box, and the movable groove is arranged along the height direction of the placement box, a motor is installed on the top of the placement box, the output shaft of the motor is connected to a threaded rod, and the threaded rod is placed in the movable groove, the bottom end of the threaded rod is rotatably installed at the bottom position of the movable groove, a guide groove is opened on the side of the partition, a guide rod is fixed in the guide groove, one end of the base plate is threadedly sleeved on the threaded rod, and the other end of the base plate is slidably sleeved on the guide rod.
[0009] As a preferred technical solution of the utility model, the air guide assembly includes an air inlet pipe, which is connected to the interior of the crystal growth furnace. Two connecting pipes are fixedly connected to the air inlet pipe. An air outlet pipe is installed on the two gas tanks, and the two air outlet pipes are respectively arranged opposite the two connecting pipes. The sizes of the air outlet pipe and the connecting pipes are matched, and solenoid valves are installed on the two air outlet pipes and the two connecting pipes.
[0010] As a preferred technical solution of the utility model, the sealing assembly includes a first sealing ring, which is fixedly sleeved on the connecting pipe, and a plurality of grooves are provided on the outer peripheral surface of the first sealing ring. A second sealing ring is fixed inside the air outlet pipe, and a plurality of convex rings are fixed on the inner ring of the second sealing ring.
[0011] As a preferred technical solution of the utility model, a limiting ring is fixedly sleeved on the two connecting pipes, and the inner diameter of the limiting ring is larger than the inner diameter of the air outlet pipe.
[0012] As a preferred technical solution of the utility model, the shape of the convex ring is matched with the shape of the groove.
[0013] The utility model has the following beneficial effects:
[0014] 1. Through the cooperation of two lifting components, the automatic replacement of gas cylinders is realized to ensure the continuous operation of the system, reducing the dependence on staff and the need for manual intervention, which reduces the possibility of human error and improves the reliability of the system. In addition, the automatic replacement of gas cylinders ensures that the system always has gas supply and will not stagnate due to exhaustion of gas cylinders. This is particularly critical in some applications that require continuous and stable gas supply, such as industrial production, laboratory operations, etc.
[0015] 2. The design of the sealing component improves the sealing performance between the outlet pipe and the connecting pipe during the replacement of the gas tank, avoiding the increase in costs caused by leakage. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 This is a structural schematic diagram of a gas supply device for a crystal growth furnace proposed by the utility model;
[0017] Figure 2 for Figure 1 A magnified view of the local structure;
[0018] Figure 3 for Figure 2 A magnified view of the structure at A;
[0019] Figure 4 It is a schematic diagram of the structure on one side of the partition in the box;
[0020] Figure 5 for Figure 4 A magnified view of the structure at B;
[0021] Figure 6 It is a schematic diagram of the explosion structure of the connecting pipe, the limiting ring and the first sealing ring.
[0022] In the figure: 1 base, 2 crystal growth furnace, 3 placement box, 4 partition, 5 gas tank, 6 bottom plate, 7 positioning ring, 8 moving groove, 9 threaded rod, 10 guide groove, 11 guide rod, 12 motor, 13 air inlet pipe, 14 air outlet pipe, 15 connecting pipe, 16 limit ring, 17 first sealing ring, 18 groove, 19 second sealing ring, 20 convex ring, 21 solenoid valve. DETAILED DESCRIPTION
[0023] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments.
[0024] Reference Figure 1-6A gas supply device for a crystal growth furnace comprises a base 1 and a crystal growth furnace 2 mounted on the base 1, a placement box 3 is fixed on the top surface of the base 1, a partition 4 is fixed inside the placement box 3, the partition 4 divides the inside of the placement box 3 into two areas of equal size, liftable gas tanks 5 are arranged on both sides of the partition 4, two lifting assemblies are arranged inside the placement box 3, the two gas tanks 5 are respectively placed on the two lifting assemblies, a gas guide assembly is also arranged inside the placement box 3, and sealing assemblies are arranged on the two gas tanks 5.
[0025] Reference Figure 2 and Figure 3 The lifting assembly includes a bottom plate 6, a positioning ring 7 is fixed on the top surface of the bottom plate 6, and the gas tank 5 is located in the positioning ring 7. The positioning ring 7 can ensure that the gas outlet pipe 14 on the gas tank 5 is aligned with the connecting pipe 15, and the staff does not need to adjust the position of the gas tank 5. A moving groove 8 is opened on the inner surface of the placement box 3, and the moving groove 8 is arranged along the height direction of the placement box 3. A motor 12 is installed on the top of the placement box 3. The output shaft of the motor 12 is connected to a threaded rod 9, and the threaded rod 9 is placed in the moving groove 8. The bottom end of the threaded rod 9 is rotatably installed on the At the bottom of the movable groove 8, a guide groove 10 is opened on the side of the partition 4, and a guide rod 11 is fixed in the guide groove 10. One end of the bottom plate 6 is threadedly sleeved on the threaded rod 9, and the other end of the bottom plate 6 is slidably sleeved on the guide rod 11. When the motor 12 is running, it can drive the corresponding threaded rod 9 to rotate. Under the limiting action of the guide rod 11, the threaded rod 9 can drive the corresponding bottom plate 6 to move upward when it rotates, and the gas tank 5 will also move upward. In this process, the guide rod 11 plays a limiting role in the movement of the bottom plate 6.
[0026] Reference Figure 4 and Figure 5 The air guide component includes an air inlet pipe 13, which is connected to the interior of the crystal growing furnace 2. Two connecting pipes 15 are fixedly connected to the air inlet pipe 13. An air outlet pipe 14 is installed on each gas tank 5, and the two air outlet pipes 14 are respectively arranged opposite to the two connecting pipes 15. The sizes of the air outlet pipes 14 and the connecting pipes 15 are adapted, and the air outlet pipes 14 can be inserted into the interior of the connecting pipes 15. Solenoid valves 21 are installed on the two air outlet pipes 14 and the two connecting pipes 15. The specific start and stop time, operation time and control method of the solenoid valve 21 are all existing technologies, which are not used as the innovative part of the present technical solution, are not shown in the figure, and will not be described in detail here. The setting of the air guide component is used for the two gas tanks 5 to continuously supply gas to the crystal growing furnace 2 to ensure the continuous operation of the device.
[0027] Reference Figure 5 and Figure 6The sealing assembly includes a first sealing ring 17, which is fixedly sleeved on the connecting pipe 15. A plurality of grooves 18 are formed on the outer peripheral surface of the first sealing ring 17. A second sealing ring 19 is fixed inside the air outlet pipe 14. A plurality of convex rings 20 are fixed on the inner ring of the second sealing ring 19. When the air outlet pipe 14 is inserted into the connecting pipe 15, the second sealing ring 19 will be inserted into the first sealing ring 17, and the plurality of convex rings 20 on the second sealing ring 19 will also be respectively inserted into the plurality of grooves 18 on the first sealing ring 17. The plurality of convex rings 20 and the plurality of grooves 18 can increase the contact area between the first sealing ring 17 and the second sealing ring 19, thereby improving the sealing performance between the air outlet pipe 14 and the connecting pipe 15 and avoiding air leakage between the air outlet pipe 14 and the connecting pipe 15.
[0028] Reference Figure 6 A limiting ring 16 is fixedly sleeved on each of the two connecting pipes 15 . The inner diameter of the limiting ring 16 is larger than the inner diameter of the outlet pipe 14 . The limiting ring 16 limits the movement of the outlet pipe 14 .
[0029] Reference Figure 6 The shape of the convex ring 20 is adapted to the shape of the groove 18 . When the convex ring 20 is inserted into the groove 18 , the outer surface of the convex ring 20 fits with the groove wall of the groove 18 .
[0030] The specific working principle of the utility model is as follows:
[0031] When the gas tank 5 needs to be replaced, the solenoid valve 21 of the air outlet pipe 14 on the working gas tank 5 (hereinafter referred to as gas tank 5A for ease of understanding and expression) and the solenoid valve 21 on the connecting pipe 15 connected to the air outlet pipe 14 are both in a conducting state, and then the motor 12 corresponding to the other gas tank 5 (hereinafter referred to as gas tank 5B for ease of understanding and expression) is energized. When the motor 12 is running, it can drive the corresponding threaded rod 9 to rotate. Under the limiting action of the guide rod 11, the threaded rod 9 can drive the corresponding base plate 6 to move upward when it rotates, and the gas tank 5B will also move upward. In this process, the air outlet pipe 14 on the gas tank 5B will be inserted into the connecting pipe 15 just above it, so that the air outlet pipe 14 is connected to the connecting pipe 15. At this time, the gas tank 5B can supply gas to the crystal growth furnace 2 through the air inlet pipe 13, that is, the two The gas tank 5 supplies gas to the crystal growth furnace 2 at the same time. Further, the solenoid valve 21 of the gas outlet pipe 14 on the gas tank 5A and the solenoid valve 21 on the connecting pipe 15 connected to the gas outlet pipe 14 are both powered off and closed, so that the gas outlet pipe 14 on the gas tank 5A is no longer connected to the connecting pipe 15. Then, the motor 12 corresponding to the gas tank 5A operates and drives the corresponding threaded rod 9 to rotate until the gas tank 5A moves downward. This step can refer to the specific principle of the above-mentioned lifting component and will not be described in detail here. When the gas tank 5A moves downward, the gas outlet pipe 14 on the gas tank 5A will also be detached from the corresponding connecting pipe 15. Based on the above process, the device can use two lifting components to realize automatic replacement of the gas tank 5, and there is no window period in the replacement process. This design is conducive to the continuous operation of the crystal growth furnace 2 and ensures the operating efficiency of the crystal growth furnace 2.
[0032] A sealing assembly is also provided between the air outlet pipe 14 and the connecting pipe 15. Specifically, when the air outlet pipe 14 is inserted into the connecting pipe 15, the second sealing ring 19 is inserted into the first sealing ring 17, and the plurality of convex rings 20 on the second sealing ring 19 are also respectively inserted into the plurality of grooves 18 on the first sealing ring 17. The plurality of convex rings 20 and the plurality of grooves 18 can increase the contact area between the first sealing ring 17 and the second sealing ring 19, thereby improving the sealing performance between the air outlet pipe 14 and the connecting pipe 15, and avoiding air leakage between the air outlet pipe 14 and the connecting pipe 15.
[0033] It is worth mentioning that the specific start and stop time, operation time and control method of the motor 12 are all existing technologies and are not an innovative part of the present technical solution. They are not shown in the figure and will not be elaborated on here.
[0034] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes within the technical scope disclosed by the present invention according to the technical scheme and the utility model concept of the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A gas supply device for a crystal growth furnace, comprising a base (1) and a crystal growth furnace (2) mounted on the base (1), characterized in that: A placement box (3) is fixed on the top surface of the base (1), a partition (4) is fixed inside the placement box (3), the partition (4) divides the inside of the placement box (3) into two areas of equal size, liftable gas tanks (5) are arranged on both sides of the partition (4), two lifting assemblies are arranged inside the placement box (3), the two gas tanks (5) are respectively placed on the two lifting assemblies, an air guide assembly is also arranged inside the placement box (3), and sealing assemblies are arranged on the two gas tanks (5).
2. The gas supply device for a crystal growth furnace according to claim 1, characterized in that: The lifting assembly comprises a base plate (6), a positioning ring (7) is fixed on the top surface of the base plate (6), the gas tank (5) is located in the positioning ring (7), a movable groove (8) is provided on the inner surface of the placement box (3), and the movable groove (8) is arranged along the height direction of the placement box (3), a motor (12) is installed on the top of the placement box (3), the output shaft of the motor (12) is connected to a threaded rod (9), and the threaded rod (9) is placed in the movable groove (8), the bottom end of the threaded rod (9) is rotatably installed at the bottom position of the movable groove (8), a guide groove (10) is provided on the side surface of the partition (4), a guide rod (11) is fixed in the guide groove (10), one end of the base plate (6) is threadedly sleeved on the threaded rod (9), and the other end of the base plate (6) is slidably sleeved on the guide rod (11).
3. The gas supply device for a crystal growth furnace according to claim 1, characterized in that: The air guide assembly comprises an air inlet pipe (13), the air inlet pipe (13) is connected to the interior of the crystal growth furnace (2), two connecting pipes (15) are fixedly connected to the air inlet pipe (13), the two gas tanks (5) are each equipped with an air outlet pipe (14), and the two air outlet pipes (14) are respectively arranged opposite to the two connecting pipes (15), the sizes of the air outlet pipe (14) and the connecting pipes (15) are matched, and solenoid valves (21) are each equipped on the two air outlet pipes (14) and the two connecting pipes (15).
4. The gas supply device for a crystal growth furnace according to claim 3, characterized in that: The sealing assembly comprises a first sealing ring (17), the first sealing ring (17) being fixedly sleeved on the connecting pipe (15), a plurality of grooves (18) being provided on the outer peripheral surface of the first sealing ring (17), a second sealing ring (19) being fixed inside the air outlet pipe (14), a plurality of convex rings (20) being fixed on the inner ring of the second sealing ring (19).
5. The gas supply device for a crystal growth furnace according to claim 3, characterized in that: A limiting ring (16) is fixedly sleeved on each of the two connecting pipes (15), and the inner diameter of the limiting ring (16) is larger than the inner diameter of the air outlet pipe (14).
6. The gas supply device for a crystal growth furnace according to claim 4, characterized in that: The shape of the convex ring (20) is matched with the shape of the groove (18).