Novel ship lock cutoff wall structure suitable for pebble foundation
By adopting a new type of lock water-blocking wall structure on a pebble foundation, using continuous piles as support and water stop, and avoiding the use of a foundation structure, efficient and low-cost construction and seepage prevention effects were achieved in the renovation and expansion of the lock project.
Patent Information
- Application Number
- CN202323451821.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-18
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2033-12-18
AI Technical Summary
In the renovation and expansion of the ship lock project, the existing technology requires the construction of a pier structure and seepage prevention work at the bottom of the approach channel when constructing on the pebble foundation, which makes the construction time-consuming, labor-intensive and increases the additional construction costs.
A new type of lock water-blocking wall structure suitable for pebble foundations is adopted, including a pile foundation structure and a water-blocking wall structure. The water-blocking wall is set on top of the pile foundation structure, using continuous piles as support and water-stopping structure, avoiding the need to set up a foundation at the bottom of the approach channel, and directly casting the breast wall and water-blocking wall on the underwater construction platform.
This method enables efficient construction on pebble foundations, reduces cofferdam construction costs and temporary measures fees, saves construction costs, and ensures underwater water-stopping and seepage prevention effects.
Smart Images

Figure CN222065519U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of ship lock water-blocking walls, in particular to a novel ship lock water-blocking wall structure suitable for a pebble foundation. Background Art
[0002] In ship lock projects, in order to ensure the calm water navigation conditions of the navigation channel, a watertight wall is often arranged on the outside of the navigation channel. Conventional newly built hub ship locks usually choose to arrange relevant navigation buildings on the rock foundation.
[0003] However, for the reconstruction and expansion of ship locks, due to the limitations of external space layout conditions, some pilot channel buildings can only be arranged on non-rock foundations, and dry land construction conditions cannot be guaranteed in this scenario. In the existing technology, it is usually necessary to set up a pedestal structure at the bottom of the pilot channel during water construction, and it is also necessary to solve the problem of anti-seepage during the construction period. This makes the construction process time-consuming and labor-intensive, and generates additional construction costs such as cofferdam anti-seepage.
[0004] In view of this, it is necessary to propose a new type of ship lock watertight wall structure suitable for pebble foundation to solve or at least alleviate the above defects. Utility Model Content
[0005] The main purpose of the utility model is to provide a new type of ship lock watertight wall structure suitable for pebble foundations, so as to solve the problem in the prior art that during water construction, a pedestal structure is usually required to be set at the bottom of the pilot channel and anti-seepage work is performed, so that the construction process is time-consuming and labor-intensive and generates additional construction costs.
[0006] To achieve the above object, the utility model provides a new type of ship lock watertight wall structure suitable for pebble foundation, comprising a pile foundation structure and a watertight wall structure arranged outside the pilot channel, wherein the watertight wall structure is arranged on the top of the pile foundation structure;
[0007] The pile foundation structure includes a plurality of piles arranged side by side along the extension direction of the ship lock, and the watertight wall structure includes a breast wall and a watertight wall extending along the extension direction of the ship lock, wherein the breast wall is connected to the top of the piles, and the watertight wall is connected to the breast wall.
[0008] Preferably, the breast wall comprises a connecting section and a supporting section, the connecting section is connected to the top of the row of piles, the retaining wall is connected to the top of the supporting section, and the cross-sectional size of the supporting section gradually decreases from bottom to top.
[0009] Preferably, the water-blocking wall is provided with a plurality of drainage holes penetrating along the thickness direction thereof, and the plurality of drainage holes are arranged at intervals on the water-blocking wall.
[0010] Preferably, it also includes a plurality of flexible anti-collision units, which are arranged at intervals along the vertical direction, wherein each of the flexible anti-collision units includes a plurality of flexible anti-collision structures arranged at intervals along the horizontal direction, and the flexible anti-collision structure is connected to one end of the side wall of the retaining wall away from the pier.
[0011] Preferably, a plurality of PVC water-permeable holes are pre-buried in the breast wall.
[0012] Preferably, the length of the breast wall is set corresponding to the length of the pile row foundation structure.
[0013] Preferably, the diameter of the drainage hole is 10 mm to 12 mm.
[0014] Preferably, the flexible anti-collision structure adopts one of a rubber pad and a steel-coated composite material fender.
[0015] Preferably, the number of the row of piles in the row of piles foundation structure is eleven, and the eleven row of piles are arranged side by side in sequence along the extension direction of the ship lock.
[0016] Preferably, the diameter of each of the row of piles is 1200 mm to 1500 mm, and the distance between two adjacent row of piles is 100 mm.
[0017] Compared with the prior art, the utility model provides the following beneficial effects:
[0018] The utility model provides a new type of ship lock watertight wall structure suitable for pebble foundation, including a pile foundation structure and a watertight wall structure arranged outside the navigation channel, the watertight wall structure is arranged on the top of the pile foundation structure, the pile foundation structure includes a plurality of continuous piles arranged side by side along the extension direction of the ship lock, the watertight wall structure includes a breast wall extending along the extension direction of the ship lock and a watertight wall, the breast wall is connected to the top of the continuous piles, and the watertight wall is connected to the breast wall. In this way, it is convenient to arrange navigation channel buildings on non-rock foundations, the construction is convenient and efficient, and there is no need to set a cap structure at the bottom of the navigation channel, so there is no need to consider the additional anti-seepage problem during the construction period of the cap. The continuous piles can be used as a supporting structure while ensuring the underwater water-stopping and anti-seepage effect, which can greatly reduce the construction cost of the cofferdam, and at the same time reduce part of the temporary construction measures, saving construction costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on the structures shown in these drawings without paying creative work.
[0020] Figure 1 It is a schematic elevation diagram of the overall structure in one embodiment of the utility model;
[0021] Figure 2 It is a side schematic diagram of an application scenario of the overall structure in one embodiment of the utility model.
[0022] The purpose, features and advantages of the present invention will be further described in conjunction with the embodiments and with reference to the accompanying drawings.
[0023] Description of Figure Numbers:
[0024] 10. Pile foundation structure; 110. Continuous piles; 20. Waterproof wall structure; 210. Breast wall; 211. Connecting section; 212. Support section; 220. Waterproof wall; 221. Drainage hole; 230. Flexible anti-collision structure. DETAILED DESCRIPTION
[0025] It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.
[0026] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0027] It should be noted that all directional indications in the embodiments of the present invention (such as up, down, left, right, front, back...) are only used to explain the relative position relationship, movement status, etc. between the components under a certain specific posture (as shown in the accompanying drawings). If the specific posture changes, the directional indication will also change accordingly.
[0028] In addition, the descriptions of "first", "second", etc. in the present utility model are only used for descriptive purposes and cannot be understood as indicating or implying their relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In addition, the technical solutions between the various embodiments can be combined with each other, but they must be based on the ability of ordinary technicians in this field to implement them. When the combination of technical solutions is contradictory or cannot be implemented, it should be deemed that such a combination of technical solutions does not exist and is not within the scope of protection required by the present utility model.
[0029] Please refer to the attached Figure 1-2In one embodiment, the utility model provides a new type of ship lock watertight wall structure suitable for pebble foundation, including a pile foundation structure 10 and a watertight wall structure 20 arranged on the outside of the pilot channel, and the watertight wall structure 20 is arranged on the top of the pile foundation structure 10. First of all, it should be noted that, unlike the prior art, it is usually necessary to set a pedestal structure at the bottom of the pilot channel during water construction, and it is also necessary to solve the anti-seepage problem during the construction period, which makes the construction process time-consuming and labor-intensive, and generates additional construction costs such as cofferdam anti-seepage. The present application solves the above-mentioned defects in the prior art by setting up a new type of ship lock watertight wall structure suitable for pebble foundation. The details are as follows:
[0030] The pile foundation structure 10 includes a plurality of piles in a row 110 arranged side by side along the extension direction of the ship lock, and the watertight wall structure 20 includes a breast wall 210 and a watertight wall 220 extending along the extension direction of the ship lock, wherein the breast wall 210 is connected to the top of the piles in a row 110 , and the watertight wall 220 is connected to the breast wall 210 .
[0031] Specifically, the new type of ship lock watertight wall structure suitable for pebble foundation in the present application includes a pile foundation structure 10 and a watertight wall structure 20. The pile foundation structure 10 is used to solve the bottom anti-seepage problem and can also serve as a supporting structure. The watertight wall structure 20 is used as a watertight wall 220 arranged in the ship lock project to ensure the still water navigation conditions of the waterway. At this time, the watertight wall structure 20 can be directly set on the top of the pile foundation structure 10, so there is no need to arrange a base structure.
[0032] The pile foundation structure 10 includes a plurality of row piles 110 arranged side by side along the extension direction of the ship lock. The row piles 110 are arranged to avoid the need to set up a construction cofferdam, thereby solving the anti-seepage problem during the construction period. In the early stage of construction, pebbles or mixed soil materials can be used to occupy the island at the target arrangement position of the water-blocking wall 220 to achieve the construction platform and temporary traffic conditions of the pile foundation of the row piles 110. Then, the row piles 110 can be constructed on the island. When pouring the pile foundation, a steel cage can be welded to the outer permanent steel casing and then hoisted into the pile hole to pour concrete. In this way, the cofferdam construction cost can be greatly reduced under underwater construction conditions. Preferably, an additional steel casing (not shown) can be arranged on the periphery of the row piles 110 to prevent the occurrence of water leakage. Strengthening the soil makes the structure more stable and safe. It is worth mentioning that the top of the piles 110 needs to be set higher than the ground line to facilitate the construction of the upper watertight wall structure 20; further, the watertight wall structure 20 includes a breast wall 210 and a watertight wall 220 extending along the extension direction of the ship lock. The breast wall 210 is used to connect the piles 110 and the watertight wall 220. After the piles 110 are cast, the breast wall 210 and the watertight wall 220 can be directly cast on water through the reserved steel bars. This is different from the conventional water construction that requires a pedestal structure to be set at the bottom of the pilot channel. In this way, there is no need to arrange a pedestal structure, which can greatly reduce the temporary measures cost of construction and save construction costs.
[0033] As a preferred embodiment of the present utility model, the breast wall 210 includes a connecting section 211 and a supporting section 212, the connecting section 211 is connected to the top of the row of piles 110, the retaining wall 220 is connected to the top of the supporting section 212, and the cross-sectional size of the supporting section 212 gradually decreases from bottom to top.
[0034] It should be noted that the breast wall 210 includes a connecting section 211 and a supporting section 212. The connecting section 211 is used to connect with the row of piles 110. Therefore, the cross-sectional size (i.e., thickness) of the connecting section 211 needs to be set corresponding to the pile diameter of the row of piles 110 so that the connecting section 211 can cover the row of piles 110. The supporting section 212 is used to support the watertight wall 220 above it so that the watertight wall 220 is connected to the top of the supporting section 212. Since the connecting section 211 is the bottom section of the breast wall 210 and needs to be a partial load-bearing structure, the thickness of the structure is relatively large. The upper part of the supporting section 212 does not need to have the same thickness and can be appropriately reduced. This can reduce the dead weight and save costs. Therefore, the cross-sectional size of the supporting section 212 gradually decreases from bottom to top.
[0035] As a preferred embodiment of the present utility model, the water-blocking wall 220 is provided with a plurality of drainage holes 221 penetrating along the thickness direction thereof, and the plurality of drainage holes 221 are arranged at intervals on the water-blocking wall 220 .
[0036] It should be noted that the drainage hole 221 is used to eliminate the water level difference on both sides of the pilot channel. If the water level difference is too large, it is easy to increase the pressure on the water-blocking wall 220, which is not good for the water-blocking wall 220. Therefore, when the water level difference is too large, it is necessary to drain the water through the drainage hole 221 in time. Therefore, the drainage hole 221 penetrates along the thickness direction of the water-blocking wall 220.
[0037] As a preferred embodiment of the utility model, it also includes a plurality of flexible anti-collision units, which are arranged at intervals along the vertical direction, wherein each of the flexible anti-collision units includes a plurality of flexible anti-collision structures 230 arranged at intervals along the horizontal direction, and the flexible anti-collision structure 230 is connected to the end of the side wall of the water retaining wall 220 away from the bridge pier.
[0038] It is worth mentioning that in some special scenarios, such as when there is an existing bridge outside the pilot channel, a plurality of flexible anti-collision units may be added to the water-blocking wall structure 20 of the present application near the bridge area, so that the structure can also serve as a bridge anti-collision structure to achieve the diversity of one wall with multiple uses, and further save the construction cost of building another anti-collision facility; wherein each of the flexible anti-collision units includes a plurality of flexible anti-collision structures 230 arranged at intervals in the horizontal direction, so that the flexible anti-collision structure 230 can be evenly distributed on the water-blocking wall 220 to ensure the anti-collision effect of various parts of the structure and avoid damage to the structure in the event of a collision.
[0039] As a preferred embodiment of the present invention, a plurality of PVC water-permeable holes are pre-buried in the breast wall 210 .
[0040] It is worth noting that when pouring concrete on the breast wall 210, multiple PVC water-permeable holes (not shown) can be embedded in advance, which can greatly reduce the water level difference inside and outside the pilot channel and avoid different water pressures on both sides, which may pose a threat to the wall structure.
[0041] Furthermore, the length of the breast wall 210 is set to correspond to the length of the pile row foundation structure 10 .
[0042] It should be noted that the corresponding arrangement here means that the length of the breast wall 210 is consistent with the length of the pile row foundation structure 10, so that the bottom of the breast wall 210 is supported by the corresponding row of piles 110 to ensure the stability of the support.
[0043] Furthermore, the diameter of the drainage hole 221 is 10 mm to 12 mm.
[0044] It can be understood that the aperture size of the drainage hole 221 determines the drainage effect. A too small aperture will affect the drainage efficiency, while a too large aperture will lead to a decrease in structural strength. Therefore, in a preferred embodiment, the aperture of the drainage hole 221 can be set to 10mm~12mm. Preferably, a drainage hole 221 with a diameter of 10mm can be used. Technical personnel in this field can set it according to actual conditions.
[0045] Furthermore, the flexible anti-collision structure 230 is a rubber pad or a steel-coated composite material fender.
[0046] It should be noted that the rubber pads and steel-coated composite material fenders are both flexible anti-collision structures 230 with good buffering and energy dissipation effects, which can largely absorb the energy generated by the impact to prevent structural damage and protect the ship at the same time. Technical personnel in this field can make a choice according to specific needs.
[0047] Furthermore, the number of the row of piles 110 in the row of piles foundation structure 10 is eleven, and the eleven row of piles 110 are arranged side by side in sequence along the extension direction of the ship lock.
[0048] It should be noted that the number of the row of piles 110 can be set according to the range that needs to be protected by a new type of lock watertight wall structure in an actual environment, and can also be selected in combination with the pile diameter of each of the row of piles 110. In the present application as a preferred embodiment, the number of the row of piles 110 in the pile foundation structure 10 can be set to eleven, and the eleven row of piles 110 are arranged side by side in sequence along the extension direction of the lock.
[0049] Furthermore, the diameter of each of the row of piles 110 is 1200 mm to 1500 mm, and the distance between two adjacent row of piles 110 is 100 mm.
[0050] It is worth mentioning that when constructing the row of piles 110, taking into account the unbalanced water head inside and outside the pilot channel, the diameter of the row of piles 110 can be set to 1200mm~1500mm, and the specific specification can be 1200mm or 1500mm. At the same time, a gap can be reserved between two adjacent row of piles 110 to facilitate construction.
[0051] The above are only preferred embodiments of the present invention, and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the specification and drawings of the present invention, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. A new type of ship lock watertight wall structure suitable for pebble foundation, characterized in that: It includes a pile foundation structure and a watertight wall structure arranged outside the pilot channel, wherein the watertight wall structure is arranged on the top of the pile foundation structure; The pile foundation structure includes a plurality of piles arranged side by side along the extension direction of the ship lock, and the watertight wall structure includes a breast wall and a watertight wall extending along the extension direction of the ship lock, wherein the breast wall is connected to the top of the piles, and the watertight wall is connected to the breast wall.
2. The novel ship lock watertight wall structure suitable for pebble foundation according to claim 1 is characterized in that: The breast wall includes a connecting section and a supporting section, the connecting section is connected to the top of the row of piles, the retaining wall is connected to the top of the supporting section, and the cross-sectional size of the supporting section gradually decreases from bottom to top.
3. The novel ship lock watertight wall structure suitable for pebble foundation according to claim 1 is characterized in that: The water-blocking wall is provided with a plurality of drainage holes penetrating along the thickness direction thereof, and the plurality of drainage holes are arranged on the water-blocking wall at intervals.
4. The novel ship lock watertight wall structure suitable for pebble foundation according to claim 1 is characterized in that: It also includes a plurality of flexible anti-collision units, which are arranged at intervals along the vertical direction, wherein each of the flexible anti-collision units includes a plurality of flexible anti-collision structures arranged at intervals along the horizontal direction, and the flexible anti-collision structure is connected to one end of the side wall of the retaining wall away from the pier.
5. The novel ship lock watertight wall structure suitable for pebble foundation according to claim 1 is characterized in that: A plurality of PVC water-permeable holes are pre-buried in the breast wall.
6. The novel ship lock watertight wall structure suitable for pebble foundation according to claim 1 is characterized in that: The length of the breast wall is set corresponding to the length of the pile row foundation structure.
7. The novel ship lock watertight wall structure suitable for pebble foundation according to claim 3 is characterized in that: The diameter of the drainage hole is 10 mm to 12 mm.
8. The novel ship lock watertight wall structure suitable for pebble foundation according to claim 4 is characterized in that: The flexible anti-collision structure adopts one of a rubber pad and a steel-covered composite material fender.
9. The novel ship lock watertight wall structure suitable for pebble foundation according to claim 1 is characterized in that: The number of the row of piles in the row of piles foundation structure is eleven, and the eleven row of piles are arranged side by side in sequence along the extension direction of the ship lock.
10. The novel ship lock watertight wall structure suitable for pebble foundation according to claim 9, characterized in that: The diameter of each row of piles is 1200 mm to 1500 mm, and the distance between two adjacent row of piles is 100 mm.