Double-T plate with frame beam formwork
By setting up multiple sets of symmetrically installed L-shaped templates and steel cages at the bottom of the double T-board body to form frame beam templates, the problems of large arch value and poor connection stability of the double T-board during construction are solved, and higher earthquake resistance is achieved Strength and construction efficiency.
Patent Information
- Application Number
- CN202420718869.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-09
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2034-04-09
AI Technical Summary
The existing double T-panel lacks frame beam formwork when building, resulting in large arch value, poor connection stability and insufficient overall strength. After building, additional formwork needs to be installed to build frame beams, which is prone to the problem of steel bar fights.
Design a double T-plate with frame beam formwork. By setting up multiple sets of symmetrically installed L-plate templates at the bottom of the double T-plate body, a frame beam formwork is formed, and a steel cage and steel mesh are installed in the formwork, and tied through longitudinal bars and stirrups. Composition, combined with integrated casting molding, improve overall strength and connection stability.
Effectively reduce the arch value of the double T-plate, improve the connection stability and overall seismic strength between the double T-plate and the main beam, reduce gaps, avoid the phenomenon of steel bars between the secondary beam and the main beam, and improve the The integrity and construction efficiency of the building.
Smart Images

Figure CN222065945U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of environmental protection devices, in particular to a double T-plate with a frame beam template. Background Art
[0002] The prefabricated reinforced concrete load-bearing member combined with the plate and beam is composed of a wide panel and two narrow and high ribs. The panel is both a transverse load-bearing structure and a compression zone for the longitudinal load-bearing ribs. At present, due to land restrictions in my country, many large cities in China have proposed to move industries upstairs and ask for space from the sky. The factory is more suitable for assembly. The traditional construction speed is slow and the cost is high. Therefore, the double T plate is widely used in the construction of single-story or multi-story industrial plants, logistics warehousing, offices and large-span and large-load buildings;
[0003] However, the current double T-plates often do not have frame beam templates, and the number of bottom ribs is limited, resulting in a large arch value. After construction, additional templates need to be installed to build frame beams or secondary beams. In this way, there is a problem of steel bars fighting between the secondary beams and the main beams, and the integrity is poor, affecting the strength.
[0004] Therefore, how to provide a double T-plate with a frame beam formwork is a problem that those skilled in the art need to solve urgently. Utility Model Content
[0005] One purpose of the utility model is to propose a double T-plate with a frame beam formwork. The utility model has its own frame beam formwork, which forms multiple groups of ribs by itself, thereby reducing the arch value, and can be directly located in the adjacent double T-plates to cast a secondary beam that cooperates with the main beam, thereby greatly improving the connection stability between the double T-plate and the main beam, improving the overall seismic strength, and can greatly reduce the gap between the double T-plates.
[0006] The double T-plate with frame beam formwork according to the embodiment of the utility model comprises a double T-plate body, a steel cage and a steel mesh;
[0007] The double T-plate body includes a panel and a rib plate, an L-shaped template is arranged on one side of the bottom of the panel, the number of the double T-plate bodies is multiple groups, and each group of double T-plate bodies is symmetrically installed, and two groups of adjacent L-shaped templates of the double T-plate bodies constitute the frame beam template as a whole, and a steel cage is arranged in the L-shaped template, and the steel cage is composed of longitudinal bars and stirrups.
[0008] Furthermore, the ribs are arranged on both sides of the bottom of the panel.
[0009] In this technical solution, the overall strength of the panel can be improved by setting ribs, so that it can be used for floors with large spans and large coverage areas.
[0010] Furthermore, the ribs, L-shaped formwork and panels are formed by integrated casting.
[0011] In this technical solution, ribs, L-shaped formwork and panels are cast through molds, so that they can be manufactured in the factory and then hoisted to the site for installation. The prefabricated building structure can effectively improve construction efficiency.
[0012] Furthermore, the number of the longitudinal reinforcements is four groups, and the four groups of longitudinal reinforcements are respectively arranged at the four inner corners of the stirrups.
[0013] In this technical solution, a steel cage can be formed by cooperating with longitudinal reinforcement and stirrups, and the binding of the steel cage can effectively improve the overall strength of the beam during casting.
[0014] Furthermore, a steel mesh is laid on the top of the panel, and the steel mesh is formed by bundling steel bars that are staggered horizontally and vertically.
[0015] In this technical solution, the steel mesh can improve the integrity of the panel and the secondary beam, and can effectively prevent the separation between each group of double T-plates and the secondary beam.
[0016] Furthermore, a concrete layer is poured on the inner side of the L-shaped formwork and the top of the panel, and the steel cage and the steel mesh are poured in the concrete layer.
[0017] In this technical solution, the double T-plate, steel cage and steel mesh can be cast in situ as a whole by pouring a concrete layer, thereby improving the overall stability and reducing the gap between adjacent double T-plates.
[0018] The beneficial effects of the utility model are:
[0019] The utility model arranges an L-shaped template on one side of the double T-plate so that the double T-plate has multiple ribs, which can effectively reduce the arching value of the panel. During assembly, adjacent L-shaped templates can form a frame beam template. A steel cage can be hoisted in the frame beam template and can be inserted into the main beam steel bars for binding, thereby reducing or eliminating the situation where the secondary beam steel bars and the main beam steel bars fight each other. Finally, cast-in-place can be performed to form a secondary beam. After casting, the gap between each group of double T-plates is reduced, and the overall strength is higher, thereby enhancing the earthquake resistance effect. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0021] Figure 1 This is a schematic diagram of the cross-sectional structure of the double T-plate with frame beam formwork proposed in the utility model.
[0022] In the figure: 1. Double T-plate body; 2. Panel; 3. Rib plate; 4. L-shaped formwork; 5. Steel cage; 6. Steel mesh; 7. Steel bars; 8. Concrete layer; 9. Longitudinal bars; 10. Stirrups. DETAILED DESCRIPTION
[0023] Now the utility model is further described in detail with reference to the accompanying drawings. These drawings are simplified schematic diagrams, which only illustrate the basic structure of the utility model in a schematic manner, and therefore only show the components related to the utility model.
[0024] refer to Figure 1 , a double T-plate with a frame beam formwork, comprising a double T-plate body 1, a steel cage 5 and a steel mesh 6;
[0025] The double T-plate body 1 includes a panel 2 and ribs 3, wherein the ribs 3 are arranged on both sides of the bottom of the panel 2, and an L-shaped template 4 is arranged on one side of the bottom of the panel 2;
[0026] The rib plate 3, L-shaped formwork 4 and panel 2 are integrally cast;
[0027] In this embodiment, a corresponding production template is first manufactured according to the specific shape and structure of the double T-board, and then the double T-board body 1 is cast in the template, thereby realizing the prefabrication of the double T-board body.
[0028] refer to Figure 1 The number of the double T-plate bodies 1 is multiple, and each group of double T-plate bodies 1 is symmetrically installed, and two groups of adjacent L-shaped templates 4 of the double T-plate bodies 1 form a frame beam template as a whole, and a steel cage 5 is arranged in the L-shaped template 4, and the steel cage 5 is formed by bundling longitudinal bars 9 and stirrups 10;
[0029] There are four groups of longitudinal bars 9, which are respectively arranged at the four inner corners of the stirrups 10. There are multiple groups of stirrups 10, which are evenly distributed on the outer sides of each group of longitudinal bars 9.
[0030] In this embodiment, two groups of double T-plate bodies 1 can be symmetrically installed by hoisting. At this time, the L-shaped templates 4 on adjacent double T-plate bodies 1 are aligned to form a complete frame beam template. Subsequently, the corresponding steel cages 5 can be bundled according to the size of the frame beam template, and then the steel cages 5 can be placed in adjacent L-shaped templates 4.
[0031] refer to Figure 1 A steel mesh 6 is laid on the top of the panel 2, and the steel mesh 6 is formed by bundling steel bars 7 staggered horizontally and vertically, and each group of steel bars 7 is evenly and equidistantly distributed on the surface of the panel 2;
[0032] A concrete layer 8 is poured inside the L-shaped formwork 4 and on the top of the panel 2, and the steel cage 5 and the steel mesh 6 are poured in the concrete layer 8;
[0033] In this embodiment, a whole steel mesh 6 can be laid above the panel 2 and the steel cage 5, and then the double T-plate body 1, the steel cage 5 and the steel mesh 6 are integrated by pouring concrete to form a complete double T-plate with a frame beam formwork.
[0034] Working principle: First, symmetrically assemble and install two groups of double T-plate bodies 1, and at this time, the L-shaped templates 4 under the adjacent double T-plate bodies 1 can be aligned to form a frame beam template, and then the bundled steel cage can be placed in the L-shaped template 4, and then the steel mesh is laid on the panel 2, and finally the overall casting is performed to form it. When in use, due to the L-shaped template on one side of the frame double T-plate body 1, a structure with multiple ribs is formed at its bottom, which can effectively reduce the arch value, and the hoisted steel cage can be placed at the intersection of the L-shaped template and the column, and connected to the main beam by interlaced steel bar binding, and then cast to form a secondary beam. The steel cage and the main beam steel bars are not prone to fighting, and the secondary beam formed is cast in situ, thereby reducing the gap of the double T plate.
[0035] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes within the technical scope disclosed by the present invention according to the technical scheme and the utility model concept of the present invention, which should be covered by the protection scope of the present invention.
Claims
1. Double T-plate with frame beam formwork, It is characterized in that It comprises a double T-plate body (1), a steel cage (5) and a steel mesh (6); The double T-plate body (1) comprises a panel (2) and a rib plate (3); an L-shaped template (4) is arranged on one side of the bottom of the panel (2); the double T-plate body (1) is provided in a plurality of groups, and each group of the double T-plate body (1) is symmetrically installed; two groups of adjacent L-shaped templates (4) of the double T-plate body (1) form a frame beam template as a whole; a steel cage (5) is arranged in the L-shaped template (4); and the steel cage (5) is formed by bundling longitudinal bars (9) and stirrups (10).
2. The double T-plate with frame beam formwork according to claim 1, It is characterized in that The ribs (3) are arranged on both sides of the bottom of the panel (2).
3. The double T-plate with frame beam formwork according to claim 2, It is characterized in that The rib plate (3), L-shaped template (4) and panel (2) are integrally cast and formed.
4. The double T-plate with frame beam formwork according to claim 1, It is characterized in that The number of the longitudinal reinforcements (9) is four groups, and the four groups of longitudinal reinforcements (9) are respectively arranged at the four inner corners of the stirrups (10).
5. The double T-plate with frame beam formwork according to claim 1, It is characterized in that A steel mesh (6) is laid on the top of the panel (2), and the steel mesh (6) is formed by bundling steel bars (7) that are staggered horizontally and vertically.
6. The double T-plate with frame beam formwork according to claim 5, It is characterized in that A concrete layer (8) is poured on the inner side of the L-shaped formwork (4) and the top of the panel (2), and the steel cage (5) and the steel mesh (6) are poured in the concrete layer (8).