Ventilation and dehumidification air conditioning system for mine

The described system simplifies the replacement and maintenance of dehumidification bags and filters in mine ventilation systems by using a sliding mechanism, addressing the challenge of narrow spaces and hidden installations.

CN222121575UActive Publication Date: 2024-12-06HUNAN LIANSHAO CONSTR ENG GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323543652.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-25
Publication Date
2024-12-06
Estimated Expiration
2033-12-25

AI Technical Summary

Technical Problem

Traditional mine ventilation and dehumidification systems face difficulties in replacing dehumidification bags due to their installation in narrow, hidden spaces, making the process cumbersome and time-consuming.

Method used

A mine ventilation and dehumidification system with a mounting frame, limit strips, stop strips, positioning frame, ventilation frame, connecting plate, pull block, and sealing gasket, allowing for easy removal and replacement of dehumidification bags and filters through a sliding mechanism.

Benefits of technology

Facilitates simple and convenient replacement of dehumidification bags and filter maintenance, overcoming space limitations and reducing operational complexity.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222121575U_ABST
    Figure CN222121575U_ABST
Patent Text Reader

Abstract

The utility model discloses a mine ventilation and dehumidification air conditioning system which comprises a ventilation pipeline, an installation frame is installed on one side of the ventilation pipeline, a filter screen is installed in the installation frame, eight limiting strips are installed on one side of the installation frame, two blocking strips are vertically connected to the top of one side of the ventilation pipeline in a sliding mode, and a positioning frame is installed in the ventilation pipeline. A ventilation frame is installed in the positioning frame, and the top of the ventilation frame is horizontally and slidably connected with a connecting plate. When the dehumidification bag is replaced, a pull block is pulled towards the top to drive a connecting plate to move towards the top, so that a ventilation frame is moved out of a sealing groove along with the connecting plate, at the moment, a sealing gasket is moved away, the connecting plate slides towards one side to enable the connecting plate to be moved away from the ventilation frame, two pull strips are pulled towards the top, and then the dehumidification bag can be taken out and replaced, operation is easy, use is convenient and fast, and practicability is high. And the dehumidification bag is convenient to replace, and the replacement difficulty caused by a narrow space is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of ventilation and dehumidification air-conditioning devices, in particular to a ventilation and dehumidification air-conditioning system for mines. Background Art

[0002] Mine ventilation and dehumidification air conditioning devices are important equipment used in coal mines, metal mines and other mining environments to maintain dry and fresh air in mines. These environments usually contain humidity, high temperature and harmful gases, so ventilation and dehumidification air conditioning devices play a vital role in ensuring the health and safety of miners. Traditional ventilation and dehumidification air conditioning devices mainly use ventilation ducts and dehumidification equipment to achieve dehumidification and circulation of air in mines. However, the ventilation and dehumidification air conditioning systems in the prior art still have certain defects when used and need to be improved;

[0003] When the ventilation, dehumidification and air-conditioning system in the prior art is in use, the humidity in the mine is usually high, so the dehumidification bag inside the dehumidification equipment needs to be replaced frequently. The dehumidification bag is installed inside the ventilation duct, and the ventilation duct is usually arranged deep in the mine or in a relatively narrow space, so that the installation position of the dehumidification bag is relatively hidden, which makes it difficult to remove the dehumidification bag for replacement, and requires a series of cumbersome operations to achieve it. Moreover, since the space of the ventilation duct is usually relatively small, removing the dehumidification bag requires overcoming space limitations and operational difficulties, making the replacement work complicated and time-consuming, resulting in the dehumidification bag. Replacement is more difficult, therefore, a mine ventilation, dehumidification and air-conditioning system is proposed to overcome the above-mentioned defects. Utility Model Content

[0004] The utility model aims to solve the disadvantage of the prior art that it is inconvenient to replace the dehumidification bag, and proposes a mine ventilation and dehumidification air conditioning system.

[0005] In order to achieve the above purpose, the utility model adopts the following technical solutions:

[0006] A mine ventilation, dehumidification and air-conditioning system comprises a ventilation duct, a mounting frame is installed on one side of the ventilation duct, a filter is installed inside the mounting frame, eight limit strips are installed on one side of the mounting frame, two stop strips are vertically slidably connected to the top of one side of the ventilation duct, a positioning frame is installed inside the ventilation duct, a ventilation frame is installed inside the positioning frame, a connecting plate is horizontally slidably connected to the top of the connecting plate, a pull block is vertically connected to the top of the connecting plate, and a sealing gasket is installed on the top surface of the connecting plate.

[0007] Preferably, a fan is installed in one side of the ventilation duct, and two stop bars are respectively located between the eight limit bars.

[0008] Preferably, a dehumidification bag is vertically connected to the interior of the ventilation frame, two pull rods are installed on the top of the dehumidification bag, and the two pull rods are horizontally slidably connected to the bottom of the connecting plate.

[0009] Preferably, a limiting groove is provided on one side of the top of the ventilation frame, and limiting plates are installed on both sides of the connecting plate, and the two limiting plates are horizontally slidably connected in the limiting groove.

[0010] Preferably, a clearance groove is provided on the top of the ventilation frame, and the pull block is slidably connected to the clearance groove.

[0011] Preferably, a plurality of ventilation holes are provided on both sides of the ventilation frame, a sealing groove is provided on the top of the ventilation duct, and a sealing gasket is connected in the sealing groove.

[0012] The utility model has the following beneficial effects:

[0013] 1. Under the cooperation of the connecting plate and the ventilation frame, when replacing the dehumidification bag, pull the pull block to the top to drive the connecting plate to move to the top, so that the ventilation frame is moved out of the sealing groove with the connecting plate. At this time, remove the sealing pad, slide the connecting plate to one side to remove the connecting plate from the ventilation frame, and then pull the two pull bars to the top to take out and replace the dehumidification bag. The operation is simple and convenient, which is convenient for replacing the dehumidification bag and avoids the difficulty of replacement due to the problem of narrow space;

[0014] 2. With the cooperation of the limit bars and the stop bars, if the filter is blocked or damaged, pull the two stop bars to the top to release the limit on the installation frame, then pull the installation frame outward to clean or replace the filter. During installation, the two stop bars slide down from between the eight limit bars to ensure the position of the installation frame while fixing the installation frame, thereby facilitating the cleaning of the filter and increasing the practicality of the device. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 This is a schematic diagram of the explosion structure of a mine ventilation, dehumidification and air conditioning system proposed by the utility model;

[0016] Figure 2 This is a three-dimensional structural diagram of a mine ventilation, dehumidification and air conditioning system proposed by the utility model;

[0017] Figure 3 This is a schematic cross-sectional view of the ventilation duct of a mine ventilation, dehumidification and air conditioning system proposed by the utility model;

[0018] Figure 4 The utility model is a schematic diagram of the explosion structure of the connection between the ventilation frame and the connection plate of the mine ventilation, dehumidification and air conditioning system.

[0019] In the figure: 1. ventilation duct; 2. fan; 3. installation frame; 4. filter; 5. limit strip; 6. stop strip; 7. positioning frame; 8. ventilation frame; 801. limit slot; 802. give way slot; 9. dehumidification bag; 10. pull strip; 11. connecting plate; 1101. limit plate; 12. pull block; 13. sealing gasket. Implementation

[0020] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments.

[0021] Reference Figure 1-4 A mine ventilation and dehumidification air conditioning system comprises a ventilation duct 1, a fan 2 is installed in one side of the ventilation duct 1, two stop bars 6 are respectively located between eight limit bars 5, a mounting frame 3 is installed on one side of the ventilation duct 1, a filter screen 4 is installed inside the mounting frame 3, eight limit bars 5 are installed on one side of the mounting frame 3, two stop bars 6 are vertically slidably connected to the top of one side of the ventilation duct 1, a positioning frame 7 is installed inside the ventilation duct 1, a ventilation frame 8 is installed inside the positioning frame 7, a dehumidification bag 9 is vertically connected to the inside of the ventilation frame 8, two pull bars 10 are installed on the top of the dehumidification bag 9, and dehumidification carbon is installed in the dehumidification bag 9, and the dehumidification bag 9 can be easily taken out by pulling the two pull bars 10, the two pull bars 10 are horizontally slidably connected to the bottom of the connecting plate 11, and a limit groove 801 is provided on one side of the top of the ventilation frame 8, and the connecting plate 1 1 are provided with limit plates 1101 on both sides, and the two limit plates 1101 are horizontally slidably connected in the limit grooves 801. Through the set limit plates 1101, when the pull block 12 is pulled toward the top to drive the connecting plate 11 to move, the limit plates 1101 can resist the top two sides of the ventilation frame 8, so that the ventilation frame 8 can also move toward the top. The top of the ventilation frame 8 is provided with a clearance groove 802, and the pull block 12 is slidably connected to the clearance groove 802. When the connecting plate 11 is moved out, the pull block 12 is moved out of the clearance groove 802. A number of ventilation holes are provided on both sides of the ventilation frame 8, and a sealing groove is provided on the top of the ventilation duct 1, and the sealing gasket 13 is connected in the sealing groove. The top of the ventilation frame 8 is horizontally slidably connected with the connecting plate 11, and the top of the connecting plate 11 is vertically connected with the pull block 12, and the top surface of the connecting plate 11 is installed with the sealing gasket 13.

[0022] In this embodiment, the interior of the mine can be ventilated by the fan 2, and the dehumidification bag 9 can absorb moisture in the air and dehumidify the air to ensure dehumidification and circulation of the air in the mine.

[0023] The use method and advantages of the utility model: When the mine ventilation and dehumidification air conditioning system is in use, the working process is as follows:

[0024] like Figure 1 , Figure 2 , Figure 3 and Figure 4 As shown, when using this type of mine ventilation and dehumidification air-conditioning system, first connect the electrical equipment in this type of mine ventilation and dehumidification air-conditioning system to an external power supply. When in use, the air in the ventilation duct 1 is circulated through the fan 2, and dehumidified through the dehumidification bag 9. When the dehumidification bag 9 is replaced, the pull block 12 is pulled toward the top to drive the connecting plate 11 to move toward the top, thereby disengaging the sealing gasket 13 from the sealing groove, and the two limiting plates 1101 limit the ventilation frame 8 so that the ventilation frame 8 is moved out of the sealing groove with the connecting plate 11. At this time, remove the sealing gasket 13, and slide the connecting plate 11 to the side close to the limiting groove 801 to remove the connecting plate 11 from the ventilation frame 8. Then, pull the two pull strips 10 toward the top to remove the dehumidification bag. The wet bag 9 is taken out and replaced, which is simple to operate and easy to use, and avoids the difficulty of replacement due to the small space. During installation, the dehumidification bag 9 is placed in the ventilation frame 8, and the ventilation frame 8 is sent into the ventilation duct 1. The bottom of the ventilation frame 8 can be positioned by the positioning frame 7, which is convenient for installation, and the connection can be sealed by the sealing gasket 13 to avoid air leakage. After long-term use, the filter 4 is blocked or damaged. After pulling the two stop bars 6 toward the top to release the limit on the installation frame 3, the installation frame 3 can be pulled outward to clean or replace the filter 4. During installation, the two stop bars 6 slide down from between the eight limit bars 5 to ensure the position of the installation frame 3 while fixing the installation frame 3, which is convenient for cleaning the filter 4.

[0025] In the present utility model, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.

[0026] In all the schemes mentioned above, the connection between the two parts can be selected according to the actual situation by welding, matching connection of bolts and nuts, bolt or screw connection or other well-known connection methods, which will not be described here one by one. The above is only a preferred specific implementation method of the utility model, but the protection scope of the utility model is not limited to this. Any technician familiar with the technical field within the technical scope disclosed by the utility model, according to the technical scheme of the utility model and its utility model concept, shall be covered by the protection scope of the utility model.

[0027] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A mine ventilation and dehumidification air conditioning system, comprising a ventilation duct (1), Features: A mounting frame (3) is installed on one side of the ventilation duct (1), a filter screen (4) is installed inside the mounting frame (3), eight limit bars (5) are installed on one side of the mounting frame (3), two stop bars (6) are vertically slidably connected to the top of one side of the ventilation duct (1), a positioning frame (7) is installed inside the ventilation duct (1), a ventilation frame (8) is installed inside the positioning frame (7), a connecting plate (11) is horizontally slidably connected to the top of the ventilation frame (8), a pull block (12) is vertically connected to the top of the connecting plate (11), and a sealing gasket (13) is installed on the top surface of the connecting plate (11).

2. A mine ventilation, dehumidification and air conditioning system according to claim 1, Features: A fan (2) is installed in one side of the ventilation duct (1), and the two stop bars (6) are respectively located between the eight limit bars (5).

3. A mine ventilation, dehumidification and air conditioning system according to claim 1, Features: A dehumidification bag (9) is vertically connected to the interior of the ventilation frame (8), two pull bars (10) are installed at the top of the dehumidification bag (9), and the two pull bars (10) are horizontally slidably connected to the bottom of the connection plate (11).

4. A mine ventilation, dehumidification and air conditioning system according to claim 1, Features: A limiting groove (801) is provided on one side of the top of the ventilation frame (8), and limiting plates (1101) are installed on both sides of the connecting plate (11), and the two limiting plates (1101) are horizontally slidably connected in the limiting groove (801).

5. A mine ventilation, dehumidification and air conditioning system according to claim 1, Features: The top of the ventilation frame (8) is provided with a clearance groove (802), and the pull block (12) is slidably connected to the clearance groove (802).

6. A mine ventilation, dehumidification and air conditioning system according to claim 1, Features: A plurality of ventilation holes are provided on both sides of the ventilation frame (8), a sealing groove is provided on the top of the ventilation duct (1), and the sealing gasket (13) is connected in the sealing groove.