Novel hanging beam hook device of bridge crane
The bull horn-shaped hook device for bridge cranes evenly distributes weight across the suspension beam, addressing fatigue tearing and safety issues by integrating horizontal and vertical beams with a receiving groove and limiting structure.
Patent Information
- Application Number
- CN202421025319.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-11
- Publication Date
- 2024-12-13
- Estimated Expiration
- 2034-05-11
AI Technical Summary
Existing bridge crane suspension beam hooks suffer from fatigue tearing due to concentrated weight distribution, leading to reduced service life and safety hazards.
A bull horn-shaped hook device with integrated horizontal and vertical beams, a receiving groove, and a limiting structure to distribute weight evenly across the suspension beam, preventing lateral movement and electromagnet loosening.
Extends the service life of the hook device and enhances safety by evenly distributing weight, improving lifting stability and preventing safety hazards.
Smart Images

Figure CN222159580U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of bridge cranes, and more specifically, to a novel bridge crane suspension beam hook device. Background Art
[0002] The existing bridge type disk crane electromagnet is hung on the suspension beam hook through a chain, such as Figure 1 As shown, in the existing bridge crane suspension beam hook device, the hook 1 of the electromagnet chain is usually welded to the two sides of the crane suspension beam 2. When in use, this hook installation method concentrates the weight of the hanging object and the electromagnet on the hook welding part of the web of the suspension beam. Frequent lifting processes can easily cause fatigue tearing of the web of the suspension beam hook welding part, resulting in a low service life, which can cause the hanging object to fall from a high altitude, posing a major safety hazard.
[0003] Therefore, it is urgent to design a novel bridge crane suspension beam hook device to solve the above-mentioned technical problems. Utility Model Content
[0004] The technical problem to be solved by the utility model is to provide a novel bridge crane suspension beam hook device in view of the above-mentioned deficiencies in the prior art, which can effectively prolong the service life of the hook device and reduce safety hazards.
[0005] The technical solution of the utility model is as follows: a new type of bridge crane suspension beam hook device, including a hook body, the hook body is fixed on the crane suspension beam, the hook body includes a horizontal beam, a vertical beam and a hook, there are two hooks and two vertical beams, and the two hooks are respectively fixed at the bottom ends of the two vertical beams, the horizontal beam is erected between the two vertical beams, and the bottom of the horizontal beam is attached to the top of the crane suspension beam, the inner sides of the two vertical beams are attached to the two side surfaces of the crane suspension beam, the bottom of the hook is attached to the top of the lower cover plate of the crane suspension beam, the horizontal beam, the vertical beam and the hook are an integrally formed structure; a limiting structure is provided on the vertical beam above the hook.
[0006] As a further improvement, the hook body is a steel plate with a thickness of 40 mm and a material of Q355B.
[0007] Furthermore, a receiving groove for receiving the electromagnet chain is provided at the top of the hook on the outer side of the vertical beam, and the bottom surface of the receiving groove is an arc-shaped surface.
[0008] Furthermore, a side of the accommodating groove close to the outside is an inclined surface, and a junction between the inclined surface and the arc surface is located above the center of a circle corresponding to the arc surface.
[0009] Furthermore, the hook body is plugged into the crane suspension beam, and two sides of the hook body are fixedly connected to the crane suspension beam via triangular plates.
[0010] Furthermore, the limiting structure includes a nut, a screw and a limiting plate, the nut is welded and fixed to the outer side of the vertical beam above the hook, one end of the screw is threadedly connected to the nut, the limiting plate is movably sleeved on the other end of the screw, and a baffle is fixed on the screw on the outer side of the limiting plate, the limiting plate is located on the outer side of the hook, and the bottom end of the limiting plate extends to the lower part of the hook.
[0011] Furthermore, a through hole is formed at the upper end of the limiting plate, a magnet is embedded in the inner wall of the through hole, and the screw is inserted into the through hole.
[0012] Beneficial Effects
[0013] Compared with the prior art, the utility model has the following advantages:
[0014] 1. The crane suspension beam hook device of the utility model adopts a bull horn-shaped hook, and by limiting its size, when it is installed on the crane electromagnet suspension beam, the bottom of the hook is just located at the lower cover plate of the electromagnet suspension beam. The lower cover plate supports the bull horn-shaped hook, and the top and bottom of the electromagnet suspension beam are used to bear the weight at the same time, so as to avoid the weight of the hanging object and the electromagnet being concentrated on the web of the suspension beam during operation, which can effectively extend the service life of the hook device and reduce safety hazards.
[0015] 2. The crane suspension beam hook device of the utility model can effectively prevent the electromagnet chain from moving laterally and improve the lifting stability by optimizing the inner wall surface of the accommodating groove; at the same time, the setting of the limiting structure can effectively prevent the problem of the electromagnet loosening and further improve the operation safety. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a schematic diagram of the main structure of the prior art;
[0017] Figure 2 This is a schematic diagram of the main structure of the utility model;
[0018] Figure 3 for Figure 2 A schematic diagram of the structure enlargement at the center A;
[0019] Figure 4 It is a schematic diagram of the top structure of the utility model.
[0020] Among them: 1-hook, 2-crane suspension beam, 3-cross beam, 4-vertical beam, 5-lower cover plate, 6-accommodating groove, 7-arc surface, 8-inclined surface, 9-triangular plate, 10-nut, 11-screw, 12-limiting plate, 13-baffle. DETAILED DESCRIPTION
[0021] The present invention will be further described below with reference to the specific embodiments in the accompanying drawings.
[0022] See also Figure 2-4 The utility model discloses a new type of bridge crane suspension beam hook device, including a hook body, which is fixed on the crane suspension beam 2. The hook body includes a horizontal beam 3, a vertical beam 4 and a hook 1. There are two hooks 1 and two vertical beams 4, and the two hooks 1 are respectively fixed at the bottom ends of the two vertical beams 4. The horizontal beam 3 is erected between the two vertical beams 4 to form a bull horn-shaped hook, and the bottom of the horizontal beam 3 is attached to the top of the crane suspension beam 2, and the inner sides of the two vertical beams 4 are attached to the two side surfaces of the crane suspension beam 2, that is, the distance between the two vertical beams 4 is adapted to the width of the crane suspension beam 2, and the bottom of the hook 1 is attached to the top of the lower cover plate 5 of the crane suspension beam 2, that is, the height of the two vertical beams 4 is adapted to the height of the crane suspension beam 2. The horizontal beam 3, the vertical beam 4 and the hook 1 are an integrated structure, and a piece of 40mm thick Q355B steel plate is cut to form the hook body, and the structural strength is better.
[0023] The crane suspension beam hook device of the utility model adopts an ox-horn-shaped hook, and by limiting its size, when it is installed on the crane electromagnet suspension beam 2, the bottom of the hook 1 is just located at the position of the lower cover plate 5 of the electromagnet suspension beam. The lower cover plate 5 supports the ox-horn-shaped hook, and the top and bottom of the electromagnet suspension beam 2 are used to bear the weight at the same time, so as to avoid the weight of the hanging object and the electromagnet being concentrated on the web of the suspension beam during operation, which can effectively extend the service life of the hook device and reduce safety hazards.
[0024] Preferably, a receiving groove 6 for receiving the electromagnet chain is provided at the top of the hook 1 outside the vertical beam 4. When in use, the electromagnet chain is suspended in the receiving groove 6. The bottom surface of the receiving groove 6 is an arc surface 7, which can effectively prevent the electromagnet chain from moving laterally and improve the lifting stability. Furthermore, an inclined surface 8 is provided on the side of the receiving groove 6 close to the outside, and the junction of the inclined surface 8 and the arc surface 7 is located above the center of the circle corresponding to the arc surface 7, so that a step is formed at the junction of the inclined surface 8 and the arc surface 7 to prevent the electromagnet chain from sliding out of the arc surface 7 when in use.
[0025] Preferably, the hook body is inserted into the crane suspension beam 2, and the two sides of the hook body are fixedly connected to the crane suspension beam 2 through the triangular plate 9. Specifically, when installing the hook device, the hook body is inserted into the crane suspension beam 2, and then the two right-angled sides of the triangular plate 9 are used to respectively support the vertical beam of the hook body and the web of the crane suspension beam 2, and finally the triangular plate 9 is fixed by welding, so that the hook body is fixed to the crane suspension beam 2.
[0026] Preferably, a limiting structure is provided on the vertical beam 4 above the hook 1. The limiting structure includes a nut 10, a screw 11 and a limiting plate 12, wherein the nut 10 is welded and fixed to the outside of the vertical beam 4 above the hook 1, and can be directly made on the existing hook, one end of the screw 11 is threadedly connected to the nut 10, the limiting plate 12 is movably sleeved on the other end of the screw 11, and a baffle 13 is fixed on the screw 11 outside the limiting plate 12, the limiting plate 12 is located outside the hook 1, and the bottom end of the limiting plate 12 extends to the lower part of the hook 1. The screw 11 and the limiting plate 12 cover the receiving groove 6, so that the electromagnet chain will not easily escape from the receiving groove, which plays a role in blocking the electromagnet chain. When the electromagnet chain needs to be removed, the limiting plate 12 is rotated to remove the electromagnet chain from the gap between the screw 11 and the top of the hook 1. When in use, the limiting plate 12 covers the receiving groove 6 under the action of its own gravity, which is very convenient to use.
[0027] Preferably, a through hole is opened at the upper end of the limit plate 12, and a magnet is embedded in the inner wall of the through hole. The screw rod 11 is inserted into the through hole, and the limit plate 12 is connected to the screw rod 11 by a magnet. When the limit plate 12 rotates upward, it plays a positioning role to prevent the limit plate 12 from falling off, making it convenient to remove the electromagnet chain; when the limit plate 12 is reset, it can also play a role in positioning it to prevent the limit plate 12 from rotating automatically as the crane suspension beam 2 moves.
[0028] The above is only a preferred embodiment of the utility model. It should be pointed out that for those skilled in the art, several modifications and improvements can be made without departing from the structure of the utility model, which will not affect the effect of the implementation of the utility model and the practicality of the patent.
Claims
1. A new type of bridge crane suspension beam hook device, characterized in that: The invention comprises a hook body, wherein the hook body is fixed on a crane suspension beam (2), the hook body comprises a horizontal beam (3), a vertical beam (4) and a hook (1), the hook (1) and the vertical beam (4) are both provided with two, and the two hooks (1) are respectively fixed on the bottom ends of the two vertical beams (4), the horizontal beam (3) is erected between the two vertical beams (4), and the bottom of the horizontal beam (3) is fitted on the top of the crane suspension beam (2), the inner side surfaces of the two vertical beams (4) are fitted on the two side surfaces of the crane suspension beam (2), the bottom of the hook (1) is fitted on the top of the lower cover plate (5) of the crane suspension beam (2), the horizontal beam (3), the vertical beam (4) and the hook (1) are an integrally formed structure; a limiting structure is provided on the vertical beam (4) above the hook (1).
2. A novel bridge crane suspension beam hook device according to claim 1, characterized in that: The hook body is a steel plate with a thickness of 40 mm and a material of Q355B.
3. The novel bridge crane suspension beam hook device according to claim 1 is characterized in that: A receiving groove (6) for receiving the electromagnet chain is provided on the top of the hook (1) outside the vertical beam (4), and the bottom surface of the receiving groove (6) is an arc-shaped surface (7).
4. A novel bridge crane suspension beam hook device according to claim 3, characterized in that: The side of the accommodating groove (6) close to the outside is an inclined surface (8), and the connection point between the inclined surface (8) and the arc surface (7) is located above the center of the circle corresponding to the arc surface (7).
5. The novel bridge crane suspension beam hook device according to claim 1 is characterized in that: The hook body is plugged into the crane suspension beam (2), and both sides of the hook body are fixedly connected to the crane suspension beam (2) via triangular plates (9).
6. A novel bridge crane suspension beam hook device according to any one of claims 1 to 5, characterized in that: The limiting structure comprises a nut (10), a screw (11) and a limiting plate (12); the nut (10) is welded and fixed to the outside of the vertical beam (4) above the hook (1); one end of the screw (11) is threadedly connected to the nut (10); the limiting plate (12) is movably sleeved on the other end of the screw (11); and a baffle (13) is fixed on the screw (11) outside the limiting plate (12); the limiting plate (12) is located outside the hook (1), and the bottom end of the limiting plate (12) extends to the lower part of the hook (1).