Wall-mounted gas stove with heat exchange flue structure
By designing a heat exchange flue structure in a gas wall-mounted furnace, and using the combination of connecting pipes, filter bags and liquid storage tanks, the problem of waste of smoke gas is solved, and the heat recovery and long-term and stable operation of the equipment is achieved.
Patent Information
- Application Number
- CN202420474558.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-12
- Publication Date
- 2025-02-18
- Estimated Expiration
- 2034-03-12
AI Technical Summary
The flue gas heat from existing gas wall-mounted furnaces is directly discharged during smoke exhaust, resulting in the failure to effectively utilize heat waste.
A gas wall-mounted furnace with a heat exchange flue structure is designed. By setting up a connecting pipe, filter bag and liquid storage tank in the shell, the flue gas is introduced into the shell through the connecting pipe and filtered through the filter bag. The filtered flue gas is The water body in the liquid storage tank is heat exchanged in the coil to recover heat.
The heat in the flue gas is recovered, the waste of heat is avoided, and the coil is kept clean through the injection and extraction of cleaning agents and the service life of the equipment is extended.
Smart Images

Figure CN222504349U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of gas wall-mounted boilers, in particular to a gas wall-mounted boiler with a heat exchange flue structure. Background Art
[0002] The gas wall-mounted boiler has a powerful home central heating function and can meet the heating needs of multiple rooms. Each room can set a comfortable temperature as needed, and the heating of a certain room can be turned off as needed. It can also provide a large flow of constant temperature sanitary hot water for use in home bathing, kitchen and other places.
[0003] After searching, the patent announcement number CN214680718U discloses a filtering mechanism of a gas wall-mounted boiler flue filter, and its structure includes a box body, a display screen, a power switch, a temperature adjustment switch, a cold water inlet, a hot water outlet, a gas inlet, a smoke outlet, a smoke pipe and a filtering device. The filtering mechanism of the gas wall-mounted boiler flue filter described in the utility model is achieved by installing a semicircular clamp ring on the filtering mechanism of the gas wall-mounted boiler flue filter, so that the smoke pipe and the filtering device can be fixedly connected, and by arranging a spring, a sliding rod and a pull button on the upper end of the semicircular clamp ring, the semicircular clamp ring can provide an inward force through the spring when not in use, so that the two semicircular clamp rings are tightly closed and the fixed ring is clamped. When the filtering device is to be disassembled, the user pulls up the pull button to displace the sliding rod and the semicircular clamp ring, and the smoke pipe can be taken out to complete the disassembly, thereby achieving quick disassembly.
[0004] The CN214680718U in the prior art can take out the smoke pipe and complete the disassembly when in use, so as to achieve quick disassembly. However, in actual use, it only filters the gas in the flue. However, the heat contained in the smoke during exhaust is directly discharged, which is easy to cause waste, so it needs to be improved. Utility Model Content
[0005] The utility model aims to provide a gas wall-mounted boiler with a heat exchange flue structure to solve the problems raised in the above-mentioned background technology.
[0006] To achieve the above purpose, the utility model provides the following technical solutions: a gas wall-mounted boiler with a heat exchange flue structure, comprising a gas wall-mounted boiler body, a shell and a mounting part,
[0007] The top surface of the gas wall-mounted boiler body is provided with a smoke exhaust pipe;
[0008] The bottom end surface of the inner wall of the shell is equipped with a liquid storage tank 1 and a liquid storage tank 2;
[0009] A connecting pipe is embedded and fixed on the top end surface of the shell;
[0010] An inner filter bag covered at the outlet end of the connecting pipe is installed on the mounting piece;
[0011] A pump body 1 is installed on the inner wall of the liquid storage tank 1, and a coil is arranged on the pump body 1;
[0012] One end of the coil facing away from the pump body is embedded and fixed in the liquid storage tank;
[0013] The bottom end surface of the inner wall of the second liquid storage tank is provided with a second pump body, and the second pump body is in liquid communication with the first liquid storage tank through a discharge pipe;
[0014] A cover plate is installed on the front end surface of the shell through bolt 2.
[0015] Preferably, the end of the connecting pipe facing away from the shell is embedded and fixed in the exhaust pipe, and the exhaust pipe is in gas communication with the shell through the connecting pipe. By embedding and fixing the end of the connecting pipe facing away from the shell in the exhaust pipe, the smoke discharged from the exhaust pipe can be discharged into the shell through the connection of the connecting pipe.
[0016] Preferably, the mounting piece is annular, fixed to the housing by means of a bolt, and the opening of the filter bag is pressed between the mounting piece and the housing.
[0017] Preferably, a water injection pipe is embedded and fixed on the top surface of the liquid storage tank 1, and the water injection pipe is in liquid communication with the liquid storage tank 1. Through the water injection pipe and the liquid storage tank 1, personnel can inject water required for heat exchange into the liquid storage tank 1 through the water injection pipe for storage.
[0018] Preferably, a drain pipe is embedded and fixed on the bottom end surface of the liquid storage tank 1, the drain pipe is in liquid communication with the liquid storage tank 1, and a valve is installed on the drain pipe through a flange. Through the drain pipe being in liquid communication with the liquid storage tank 1, a person can open the valve on the drain pipe to discharge the water stored in the liquid storage tank 1.
[0019] Preferably, a medicine injection tube is embedded and fixed on the top surface of the second liquid storage tank, and the medicine injection tube is in liquid communication with the second liquid storage tank. Through the medicine injection tube and the second liquid storage tank, personnel can inject the scale cleaning agent into the second liquid storage tank through the medicine injection tube.
[0020] Preferably, a smoke outlet pipe is embedded and fixed on the bottom end surface of the shell, and the smoke outlet pipe is in gas communication with the shell. The smoke outlet pipe is in gas communication with the shell, so that the smoke entering the shell can be discharged through the smoke outlet pipe.
[0021] Compared with the prior art, the beneficial effects of the utility model are as follows:
[0022] 1. The utility model sets a shell, when personnel use the gas wall-mounted boiler body, the smoke generated by the gas wall-mounted boiler body can be discharged through the smoke exhaust pipe, and the smoke is introduced into the shell through the connecting pipe during discharge, and the smoke is filtered through the filter bag when it is introduced, and the filter bag after filtration can be disassembled by reversing a pair of mounting parts with a bolt, so that the filter bag can be removed to meet the needs of later maintenance, and after the smoke is filtered, the personnel can open the pump body to extract the heat exchange water in the liquid storage tank, so that the heat exchange water is supplied to the coil through extraction, so that the gas containing heat after the filtration treatment contacts the coil, and the circulating water circulates in the coil for heat exchange, so that the heat can be recovered.
[0023] 2. The utility model sets a second liquid storage tank. After processing and recovering the flue gas of the gas wall-mounted boiler body, in order to avoid scale clogging the coil after heat exchange of the water body, the personnel can open the valve on the drain pipe to discharge the water body generated by heat exchange in the liquid storage tank one. After that, the personnel can open the second pump body to extract the scale cleaning agent in the liquid storage tank two, and inject the scale cleaning liquid into the liquid storage tank one, so that the cleaning agent is again supplied into the coil through the opening and extraction of the pump body one, so that the inside of the coil is cleaned by the agent, and the cleaned water body flows back to the liquid storage tank one again and can be discharged through the drain pipe, thereby avoiding the scale generated by the water body to clog the pipe, thereby meeting the heat exchange and maintenance of the flue in the later stage. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 This is a schematic diagram of the main internal structure of the utility model;
[0025] Figure 2 It is a schematic diagram of the top view structure of the utility model;
[0026] Figure 3 It is a schematic diagram of the main appearance structure of the utility model.
[0027] In the figure: 1. Gas wall-mounted boiler body; 2. Medicine injection pipe; 3. Smoke exhaust pipe; 4. Connecting pipe; 5. Coil; 6. Shell; 7. Filter bag; 8. Water injection pipe; 9. Liquid storage tank 1; 10. Pump body 1; 11. Drain pipe; 12. Drain pipe; 13. Smoke exhaust pipe; 14. Pump body 2; 15. Liquid storage tank 2; 16. Mounting parts; 17. Bolt 1; 18. Bolt 2; 19. Cover plate. DETAILED DESCRIPTION
[0028] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0029] Embodiment 1
[0030] like Figure 1-Figure 3 As shown, the utility model provides a gas wall-mounted boiler with a heat exchange flue structure, including a gas wall-mounted boiler body 1, a shell 6 and a mounting member 16.
[0031] The top surface of the gas wall-mounted boiler body 1 is provided with a smoke exhaust pipe 3;
[0032] The bottom end surface of the inner wall of the housing 6 is provided with a liquid storage tank 1 9 and a liquid storage tank 2 15;
[0033] The top surface of the shell 6 is embedded with a connecting pipe 4;
[0034] The filter bag 7 which is covered at the outlet end of the connecting pipe 4 is installed on the mounting member 16;
[0035] A pump body 10 is installed on the inner wall of the liquid storage tank 9, and a coil 5 is arranged on the pump body 10;
[0036] One end of the coil 5 away from the pump body 10 is embedded and fixed in the liquid storage tank 9;
[0037] A pump body 14 is installed on the bottom end surface of the inner wall of the second liquid storage tank 15, and the pump body 14 is in liquid communication with the first liquid storage tank 9 through the discharge pipe 12;
[0038] A cover plate 19 is mounted on the front end surface of the housing 6 via bolts 18 .
[0039] The end of the connecting pipe 4 facing away from the shell 6 is embedded and fixed in the smoke exhaust pipe 3, and the smoke exhaust pipe 3 is gas-connected with the shell 6 through the connecting pipe 4. The end of the connecting pipe 4 facing away from the shell 6 is embedded and fixed in the smoke exhaust pipe 3, so that the smoke discharged in the smoke exhaust pipe 3 can be discharged into the shell 6 through the connection of the connecting pipe 4.
[0040] The mounting member 16 is annular and is fixed to the inner wall of the housing 6 by means of a bolt 17. When the mounting member 16 is installed, the opening of the filter bag 7 is pressed and fixed between the mounting member 16 and the inner wall of the housing 6 to fix the filter bag 7. In order to ensure a better pressing effect on the opening of the filter bag 7, there can be a plurality of bolts 17, and the plurality of bolts 17 are evenly spaced and arranged along the circumferential direction of the mounting member 16.
[0041] A water injection pipe 8 is embedded and fixed on the top surface of the liquid storage tank 9, and the water injection pipe 8 is in liquid communication with the liquid storage tank 9. Through the water injection pipe 8 and the liquid storage tank 9, personnel can inject water required for heat exchange into the liquid storage tank 9 through the water injection pipe 8 for storage.
[0042] Based on Example 1: When personnel use the gas wall-mounted boiler body 1, the smoke generated by the gas wall-mounted boiler body 1 can be discharged through the smoke exhaust pipe 3. During the discharge, the smoke is introduced into the shell 6 through the connecting pipe 4, and the smoke is filtered through the filter bag 7 when it is introduced. The filter bag 7 after filtration can be disassembled by reversing the bolt 17 to the mounting part 16, so that the filter bag 7 can be removed to meet the needs of later maintenance, and after the smoke is filtered, the personnel can open the pump body 10 to extract the hot water in the liquid storage tank 9, so that the hot water is supplied into the coil 5 through extraction, so that the filtered gas containing heat contacts the coil 5, and the circulating water circulates in the coil 5 for heat exchange, so that the heat can be recovered.
[0043] Embodiment 2
[0044] like Figure 1-Figure 3 As shown, the utility model proposes a gas wall-mounted boiler with a heat exchange flue structure. Compared with the first embodiment, this embodiment further includes: a gas wall-mounted boiler body 1, a shell 6 and a mounting member 16.
[0045] The top surface of the gas wall-mounted boiler body 1 is provided with a smoke exhaust pipe 3;
[0046] The bottom end surface of the inner wall of the housing 6 is provided with a liquid storage tank 1 9 and a liquid storage tank 2 15;
[0047] The top surface of the shell 6 is embedded with a connecting pipe 4;
[0048] The filter bag 7 is fitted on the inner wall of the mounting member 16;
[0049] A pump body 10 is installed on the inner wall of the liquid storage tank 9, and a coil 5 is arranged on the pump body 10;
[0050] One end of the coil 5 away from the pump body 10 is embedded and fixed in the liquid storage tank 9;
[0051] A pump body 14 is installed on the bottom end surface of the inner wall of the second liquid storage tank 15, and the pump body 14 is in liquid communication with the first liquid storage tank 9 through the discharge pipe 12;
[0052] A cover plate 19 is mounted on the front end surface of the housing 6 via bolts 18 .
[0053] A drain pipe 11 is embedded and fixed on the bottom end surface of the liquid storage tank 9. The drain pipe 11 is in liquid communication with the liquid storage tank 9, and a valve is installed on the drain pipe 11 through a flange. The drain pipe 11 is in liquid communication with the liquid storage tank 9, so that personnel can open the valve on the drain pipe 11 to discharge the water stored in the liquid storage tank 9, and personnel can use the water contained during the discharge.
[0054] An injection tube 2 is embedded and fixed on the top surface of the liquid storage tank 15, and the injection tube 2 is in liquid communication with the liquid storage tank 15. Through the injection tube 2 and the liquid storage tank 15, personnel can inject scale cleaning agent into the liquid storage tank 15 through the injection tube 2. The scale cleaning agent is common knowledge among personnel in this technical field, and personnel can select it according to needs.
[0055] A smoke outlet pipe 13 is embedded and fixed on the bottom end surface of the shell 6 , and the smoke outlet pipe 13 is in gas communication with the shell 6 . The smoke outlet pipe 13 is in gas communication with the shell 6 , so that the smoke entering the shell 6 can be discharged through the smoke outlet pipe 13 .
[0056] Based on Example 2: After processing and recovering the heat of the flue gas of the gas wall-mounted boiler body 1, in order to avoid scale clogging the coil 5 after the water body is heat exchanged, the personnel can open the valve on the drain pipe 11 to discharge the water body generated by the heat exchange in the liquid storage tank 9, and then open the pump body 14 to extract the scale cleaning agent in the liquid storage tank 15, so that the scale cleaning liquid is injected into the liquid storage tank 9, and the cleaning agent is again supplied to the coil 5 through the opening and extraction of the pump body 10, so that the inside of the coil 5 is cleaned by the agent, and the cleaned water body flows back to the liquid storage tank 9 again and can be discharged through the drain pipe 11, thereby avoiding the scale generated by the water body to clog the pipeline.
[0057] It is obvious to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be regarded as exemplary and non-restrictive from any point of view, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present invention. Any reference numeral in a claim should not be regarded as limiting the claim to which it relates.
Claims
1. A gas wall-mounted boiler with a heat exchange flue structure, comprising a gas wall-mounted boiler body (1), a shell (6) and a mounting member (16), characterized in that: The top end surface of the gas wall-mounted boiler body (1) is provided with a smoke exhaust pipe (3); A liquid storage tank 1 (9) and a liquid storage tank 2 (15) are installed on the bottom end surface of the inner wall of the housing (6); A connecting pipe (4) is embedded and fixed on the top end surface of the shell (6); The mounting member (16) is provided with a filter bag (7) which is covered at the outlet end of the connecting pipe (4); A pump body (10) is installed on the inner wall of the liquid storage tank (9), and a coil (5) is arranged on the pump body (10); One end of the coil (5) facing away from the pump body (10) is embedded and fixed in the liquid storage tank (9); A pump body 2 (14) is installed on the bottom end surface of the inner wall of the second liquid storage tank (15), and the pump body 2 (14) is in liquid communication with the first liquid storage tank (9) through a discharge pipe (12); A cover plate (19) is mounted on the front end surface of the housing (6) via bolts (18).
2. The gas wall-mounted boiler with a heat exchange flue structure according to claim 1, characterized in that: One end of the connecting pipe (4) facing away from the shell (6) is embedded and fixed in the smoke exhaust pipe (3), and the smoke exhaust pipe (3) is in gas communication with the shell (6) through the connecting pipe (4).
3. The gas wall-mounted boiler with a heat exchange flue structure according to claim 1, characterized in that: The mounting member (16) is annular and is fixed to the housing (6) by means of a bolt (17), and the opening of the filter bag (7) is pressed between the mounting member (16) and the housing (6).
4. The gas wall-mounted boiler with a heat exchange flue structure according to claim 1, characterized in that: A water injection pipe (8) is embedded and fixed on the top surface of the liquid storage tank (9), and the water injection pipe (8) is in liquid communication with the liquid storage tank (9).
5. The gas wall-mounted boiler with a heat exchange flue structure according to claim 1, characterized in that: A drainage pipe (11) is embedded and fixed in the bottom end surface of the liquid storage tank (9), the drainage pipe (11) is in liquid communication with the liquid storage tank (9), and a valve is installed on the drainage pipe (11) via a flange.
6. The gas wall-mounted boiler with a heat exchange flue structure according to claim 1, characterized in that: A drug injection tube (2) is embedded and fixed on the top surface of the second liquid storage tank (15), and the drug injection tube (2) is in liquid communication with the second liquid storage tank (15).
7. The gas wall-mounted boiler with a heat exchange flue structure according to claim 1, characterized in that: A smoke outlet pipe (13) is embedded and fixed in the bottom end surface of the shell (6), and the smoke outlet pipe (13) is in gas communication with the shell (6).