Device for optimizing working procedure through crane hoisting

By using the equipment for optimizing the driving lifting process in the construction of steel structures, the problem of difficulty in lifting equipment and pipelines in the inner and outer structures is solved, and safe, reliable and convenient construction is achieved, reducing costs and shortening construction periods.

CN222593198UActive Publication Date: 2025-03-11MCC TIANGONG GROUP
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420872211.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-25
Publication Date
2025-03-11
Estimated Expiration
2034-04-25

AI Technical Summary

Technical Problem

During the steel structure construction, it is difficult to lift equipment and pipelines above the inner and outer structures, the ground and other equipment have been completed, and the lifting machinery has no station position and working surface, and the ground quality cannot be guaranteed.

Method used

A device that uses a driving lifting optimization process is adopted, including a driving lifting structure, a standard section integral and a lifting structure. The standard section integral is lifted through the driving lifting structure, and the standard section integral is connected to the lifting structure for transporting goods.

Benefits of technology

It realizes the construction of steel structures safely and reliably without being restricted by ground conditions, reducing costs and shortening construction periods, and is suitable for construction in a variety of industries and professionals.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222593198U_ABST
    Figure CN222593198U_ABST
Patent Text Reader

Abstract

The utility model discloses a device for optimizing working procedures by utilizing crane hoisting, which can be arranged on a crane and comprises a crane hoisting tool structure, a standard knot whole and a hoisting structure, the crane hoisting tool structure can be arranged on the crane and is used for hoisting the standard knot whole, and the standard knot whole is arranged on the crane hoisting tool structure and is used for connecting the hoisting structure. The lifting structure is arranged on the standard knot whole and used for carrying, and the crane lifting tool structure comprises a lifting hook arranged on a crane and a rigging arranged on the lifting hook and used for being connected with the standard knot whole. According to the device for optimizing the working procedure through crane hoisting, construction which cannot be achieved through a conventional construction working procedure is overcome, cost is reduced, a locomotive does not need to be installed, road planes are backfilled and tamped, cost is saved, application is wide, the device is suitable for installation of brickwork, column row brickwork, steel structures, pipelines and equipment in all industries and majors, efficiency is high, speed is high, and safety and reliability are achieved; and the method is not limited by ground conditions.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of construction, in particular to a device for optimizing working procedures by utilizing a crane for hoisting. Background Art

[0002] With the continuous development of the construction industry, steel structure is highly prefabricated, quick to install and can greatly shorten the construction period. Its steel structure frame system has been applied to various types of projects. On this basis, in order to further reasonably shorten the construction period, the steel structure construction, ground and outer protective wall are reasonably flow-operated during the construction process. However, this will make it difficult to hoist the relevant equipment and pipelines above the subsequent structure inside and outside. Because the ground and other equipment have been completed, the hoisting machinery used has no standing position and working surface, and the ground quality cannot be guaranteed. In order to solve this problem and ensure the construction progress, a utility model is required to use a construction method based on steel structure to optimize the process of crane hoisting. At the same time, this method can effectively solve the problem of wall block transportation and ensure that the constructed ground is not overloaded.

[0003] The utility model aims to provide a safe, reliable and convenient construction method in terms of space and time, so as to save labor and effort and reasonably shorten the construction period, while avoiding the long waiting time due to the unusable ground inside and outside the factory building. It is further explained that even if the ground can be used, a large amount of large-scale lifting machinery will be consumed, which increases costs and time. Utility Model Content

[0004] The purpose of the utility model is to provide a device for optimizing the process by using a crane to hoist, so as to solve the problems raised in the above-mentioned background technology.

[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solution: a device for optimizing the process by crane hoisting, which can be arranged on the crane, comprising:

[0006] A crane hoisting device structure, which can be arranged on the crane and used for hoisting the standard section as a whole;

[0007] The standard section as a whole is arranged on the crane hoisting structure and is used to connect the hoisting structure;

[0008] The hoisting structure is arranged on the entire standard section and is used for transportation.

[0009] Preferably, the crane hoist structure includes a hook arranged on the crane, and a rigging arranged on the hook for integrally connecting with the standard section, and the crane hoist structure is used to hoist the entire device.

[0010] Preferably, the number of the crane hoist structure and the crane is not less than two, which are used to stabilize the standard section as a whole, and the two cranes can change the direction of the standard section as a whole when traveling at different times.

[0011] Preferably, the standard section as a whole includes a lifting lug arranged on the rigging, an assembling plate arranged on the lifting lug, a connecting plate arranged on the assembling plate, and a plug rod arranged on the connecting plate for stabilizing the connecting plate. The standard section as a whole is used for lifting the hoisting unit and the load-bearing stabilizer unit.

[0012] Preferably, the hoisting structure comprises a hoisting unit arranged at one end of the standard section as a whole, and a stabilizer unit arranged at the other end of the standard section as a whole, and the hoisting structure is used to transport goods.

[0013] Preferably, the lifting unit includes a lifting sling arranged on the entire section, and a lifting object arranged on the lifting sling, and the lifting unit is used for lifting cargo.

[0014] Preferably, the stabilizer unit comprises a stabilizer rigging arranged on the quasi-section as a whole, and a stabilizer arranged on the stabilizer rigging, and the stabilizer unit is used for stabilizing the hoisted cargo.

[0015] Compared with the prior art, the beneficial effects of the utility model are: the device which utilizes the crane hoisting optimization process overcomes the construction that cannot be achieved in the conventional construction process, reduces the cost, does not need to install the locomotive, backfill and compact the road surface, saves the cost, is widely used, and is applicable to all industries and professions, all masonry, column bricklaying, steel structure, pipeline, equipment installation, with high efficiency, fast speed, safety and reliability, and is not limited by ground conditions. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is an overall schematic diagram of an embodiment of the utility model;

[0017] Figure 2 This is an overall schematic diagram of a standard section of an embodiment of the utility model;

[0018] Figure 3 It is a schematic front view of the whole standard section of one embodiment of the utility model.

[0019] In the figure:

[0020] 1. Hook 2. Rigging 3. Standard section as a whole

[0021] 4. Lifting rigging 5. Lifting objects 6. Stabilizer

[0022] 8. Stabilizer rigging 31, assembly plate 32, lifting lug

[0023] 33. Connecting plate 34. Insertion rod DETAILED DESCRIPTION

[0024] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0025] like Figure 1 As shown, the utility model provides a technical solution: a device for optimizing the process of crane hoisting, which can be arranged on the crane, including: a crane hoisting device structure, a standard section as a whole 3 and a hoisting structure, the crane hoisting device structure can be arranged on the crane, and is used to hoist the standard section as a whole 3, the standard section as a whole 3 is arranged on the crane hoisting device structure, and is used to connect the hoisting structure, and the hoisting structure is arranged on the standard section as a whole 3 for transportation.

[0026] The crane hoist structure includes a hook 1 arranged on the crane, and the number of the hooks 1 and the number of the rigging 2 are two. The two hooks 1 are respectively arranged on the crane, and the two riggings 2 are used for stabilizing the hoisting of the standard section as a whole 3, and the rigging 2 arranged on the hook 1 for connecting with the standard section as a whole 3. The rigging 2 and the hoisting rigging 4 and the stabilizer rigging 8 are made of the same material and are used for hoisting. The crane hoist structure is used for hoisting the entire device. The number of the crane hoist structure and the cranes is not less than two, which are used to stabilize the standard section as a whole 3. The two cranes can change the direction of the standard section as a whole 3 when traveling at different times. A sliding trolley is arranged under the two cranes, and the trolley is used to connect with the hook 1. When the two cranes and the two trolleys slide to opposite positions, the standard section as a whole 3 can be driven to rotate 360°, thereby facilitating the adjustment movement during construction.

[0027] The standard section as a whole 3 is composed of six groups. The standard section as a whole 3 includes a lifting lug 32 arranged on the rigging 2. The material of the lifting lug 32 is 18mm. The lifting lug 32 is a semicircular ring welded on the assembly plate 31. The assembly plate 31 arranged on the lifting lug 32 has a certain number of assembling plates 31 and is made of HW200 I-steel. Two assembling plates 31 and angle steel are welded to form a standard section. The dimensions of the assembling plate 31 are 3500m long, 1000mm wide, and 200mm high. There is a connecting plate 33 arranged on the assembling plate 31. The material of the connecting plate 33 is a steel plate, and there is a plug rod 34 arranged on the connecting plate 33 for stabilizing the connecting plate 33. The plug rod 34 and the connecting plate 33 are used to connect the standard section. The standard section as a whole 3 is used to hoist the hoisting unit and the load-bearing stabilizer unit.

[0028] The lifting structure includes a lifting unit arranged at one end of the standard section as a whole 3, the lifting unit includes a lifting sling 4 arranged on the standard section as a whole 3, the lifting sling 4 is used to connect the lifting object 5, and the lifting object 5 arranged on the lifting sling 4, the lifting unit is used to lift the cargo, and a stabilizer unit arranged at the other end of the standard section as a whole 3, the lifting structure is used to transport the cargo, the stabilizer unit includes a stabilizer sling 8 arranged on the standard section as a whole 3, the stabilizer sling 8 is used to lift the stabilizer 6, and the stabilizer 6 is arranged on the stabilizer sling 8, the stabilizer 6 is used to counterweight the lifting object 5 to ensure that there is no continuous deviation when the lifting object 5 rotates, and is used to ensure the stability of transporting the lifting object 5, and the stabilizer unit is used to stabilize the lifted cargo.

[0029] As shown above, in this embodiment, a number of assembly plates 31 are connected by means of insert rods 34 and connecting plates 33. The standard section as a whole 3 is used to connect the rigging 2, the hoisting rigging 4 and the stabilizer rigging 8 through the lifting lugs 32. According to the situation on site, the hoisting object 5 can be hoisted onto the outer surface of the factory wall by changing the position of the lifting lugs 32 for installation.

[0030] According to the above embodiment, in this embodiment, after the standard section as a whole 3 is assembled, two riggings 2 and a hook 1 are used to connect the trolleys under the two cranes, so that when the two cranes and the two trolleys slide to opposite positions, the standard section as a whole 3 can be driven to rotate 360°, so that the position of the hoisting object 5 can be adjusted when the hoisting object 5 is connected.

[0031] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A device for optimizing a process by crane hoisting, which can be arranged on a crane, characterized in that: include: A crane hoisting device structure, which can be arranged on the crane and used for hoisting the standard section as a whole; The standard section as a whole is arranged on the crane hoisting structure and is used to connect the hoisting structure; The hoisting structure is arranged on the whole of the standard section and is used for transportation; The hoisting structure comprises a hoisting unit arranged at one end of the standard section as a whole, and a stabilizer unit arranged at the other end of the standard section as a whole.

2. The device for optimizing the process by crane hoisting according to claim 1, characterized in that: The crane hoisting device structure comprises a hook arranged on the crane, and a rigging arranged on the hook and used for being integrally connected with the standard section.

3. The device for optimizing the process by crane hoisting according to claim 2, characterized in that: The number of the crane hoist structure and the crane is no less than two, and they are used to stabilize the standard section as a whole.

4. The device for optimizing the process by crane hoisting according to claim 2, characterized in that: The standard section as a whole comprises a lifting eye arranged on the rigging, an assembling plate arranged on the lifting eye, a connecting plate arranged on the assembling plate, and a plug rod arranged on the connecting plate for stabilizing the connecting plate.

5. The device for optimizing a process by crane hoisting according to claim 1, characterized in that: The object-hanging unit comprises an object-hanging sling arranged on the entire section, and an object-hanging part arranged on the object-hanging sling.

6. The device for optimizing the process by crane hoisting according to claim 1, characterized in that: The stabilizer unit includes a stabilizer rigging provided on the entire section, and a stabilizer provided on the stabilizer rigging.

Citation Information

Cited By

  • Device for optimizing working procedure through crane hoisting and construction method

    CN118324000A