Tower crane wall attaching piece mounting structure for steel tower
Through the prefabricated tower crane wall parts installation structure, the tower crane and steel tower are connected by wall tie rods and tie rod adjustment frames, which solves the safety hazards and installation deviations of high-altitude welding operations, and achieves safe and fast installation of tower crane wall parts.
Patent Information
- Application Number
- CN202420596801.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-26
- Publication Date
- 2025-03-14
- Estimated Expiration
- 2034-03-26
AI Technical Summary
In the prior art, the installation of tower crane wall parts requires high-altitude welding operations, which poses safety risks, and there may be a risk of deviation between the steel tower and the tower crane, affecting the installation process.
The prefabricated tower crane wall-attached installation structure is adopted, including a wall-attached pull rod, a first attachment lift frame, a second attachment lift frame, an outer frame of the tower crane and a tie rod adjustment frame. The tower crane and the steel tower are connected through the wall-attached pull rod, and the position adjustment frame is used to adjust the position to avoid high-altitude welding.
The safety and rapid installation of the wall parts attached to the tower crane is achieved, and the dangerous operation of high-altitude welding is avoided. Through the design of the nut adjustment section and the pull rod adjustment frame, the pull rod length and position can be flexibly adjusted to reduce installation errors.
Smart Images

Figure CN222612800U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the field of tower crane wall mounting equipment, and in particular relates to a tower crane wall mounting structure for a steel tower. Background Art
[0002] With the increase in the span of bridges today, more and more bridges are in the form of large-span cable-stayed bridges and suspension bridges. Cable towers are important components of cable-stayed bridges and suspension bridges. They are usually located at both ends of the bridge or in the middle of the bridge span to support and fix cables or cables. Cable towers are generally built with reinforced concrete or steel structures. They have the function of bearing the gravity and cable force of the bridge, and at the same time play the role of supporting and stabilizing the bridge structure. With the widespread use of super-high cable towers, steel structures are increasingly used in bridge towers. Steel towers are generally more than 100 meters high and have various cross-sectional styles. During the construction process, tower cranes are often used for hoisting. Due to the super-high height of the hoisting construction, the tower crane and the steel tower need to be connected to the wall. In the prior art, the wall attachments are generally composed of steel sections, but there is a dangerous operation of high-altitude welding and docking. In addition, after reaching a certain height, there may be a certain risk of deviation between the steel tower and the tower crane, which affects the installation process.
[0003] Therefore, there is an urgent need to provide a tower crane wall attachment device that does not require high-altitude welding and assembly. Utility Model Content
[0004] The utility model aims to solve the deficiencies in the prior art and provide a tower crane wall attachment installation structure for a steel tower.
[0005] The specific technical solutions adopted by this utility model are as follows:
[0006] The utility model provides a tower crane wall attachment installation structure for a steel tower, comprising a wall attachment tie rod, a first attachment cantilever frame, a second attachment cantilever frame, a tower crane outer frame and a tie rod adjustment frame;
[0007] The tower crane outer frame is arranged on the periphery of the tower crane body and is used for wall-attached connection with the special-shaped steel tower; the first attachment bracket and the second attachment bracket are respectively fixed on the outer wall plates on both sides of the special-shaped steel tower; the tower crane outer frame and the first attachment bracket and the second attachment bracket are connected by wall-attached tie rods, and tie rod adjustment frames for adjusting the positions of the wall-attached tie rods are provided at the connection points;
[0008] The wall-attached tie rod includes a first male joint, a main rod, an adjustment section, and a second male joint; the first male joint is fixedly connected to the outer frame of the tower crane, and an adjustment section for adjusting the length of the tie rod is provided between the first male joint and the main rod; the second male joint is fixedly connected to the first attachment cantilever or the second attachment cantilever; the first male joint and the second male joint are both fixed with in-place adjustment ears for connecting to the tie rod adjustment frame.
[0009] Preferably, the pull rod adjustment frame includes a gantry upright, a gantry beam, an ear plate and a lifting device; the gantry upright is vertically fixed on the outer frame of the tower crane, the first attached cantilever or the second attached cantilever, and the gantry beam is horizontally arranged on the top of the gantry upright; an ear plate for setting the lifting device is fixed on the gantry beam; one end of the lifting device is connected to the outer frame of the tower crane, the first attached cantilever or the second attached cantilever, and the other end is connected to the in-situ adjustment ear on the wall-attached pull rod.
[0010] Furthermore, the lifting device is an electric hoist.
[0011] Preferably, three wall-attached tie rods are provided, namely a first tie rod, a second tie rod and a third tie rod.
[0012] Preferably, the wall-attached tie rod is made of a box-shaped steel pipe.
[0013] Preferably, the first male joint is connected to the outer frame of the tower crane by a pin shaft.
[0014] Preferably, the second male connector is connected to the first attachment bracket or the second attachment bracket via a pin.
[0015] Preferably, the adjusting section is adjusted by a nut.
[0016] Preferably, a lifting lug for lifting the pull rod is welded on the main rod.
[0017] Preferably, the tower crane outer frame is a frame assembled from box beams.
[0018] Compared with the prior art, the utility model has the following beneficial effects:
[0019] (1) The tower crane wall attachment installation structure provided by the utility model is suitable for various special-shaped steel tower structures. The structure adopts prefabricated construction, and there is no high-altitude welding operation or fire during installation, ensuring construction safety.
[0020] (2) Each wall-mounted tie rod provided by the utility model has a nut adjustment section, which can adjust the length of the tie rod within a certain range. If the length of the connected tie rod needs to be adjusted due to installation error during construction, there is no need to remove and reinstall it, and it can be adjusted directly through the nut adjustment section.
[0021] (3) In the utility model, a tie rod adjustment frame for adjusting the position of the wall-attaching tie rod is provided on the outer frame of the tower crane and the first attachment bracket and the second attachment bracket, so that the wall-attaching tie rod can be unloaded in advance after it is in place, and the position is adjusted by the tie rod adjustment frames provided on both sides. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1A top view of the tower crane wall attachment installation structure provided in this embodiment;
[0023] Figure 2 A schematic diagram of the installation structure of the tower crane wall attachment provided in this embodiment;
[0024] Figure 3 A bottom view of the wall-attached tie rod provided in this embodiment;
[0025] Figure 4 An overall schematic diagram of the wall-attached tie rod provided in this embodiment;
[0026] Figure 5 This is a schematic diagram of the connection between the first male joint and the outer frame of the tower crane in this embodiment;
[0027] Figure 6 A schematic diagram of a pull rod adjustment frame provided in this embodiment;
[0028] In the figure: the first tie rod 1, the second tie rod 2, the third tie rod 3, the first attachment cantilever 4, the second attachment cantilever 5, the special-shaped steel tower 6, the tower crane body 7, the tower crane outer frame 8, the tie rod adjustment frame 9, the first male joint 101, the second male joint 102, the main rod 12, the adjustment section 13, the pin 14, the lifting lug 15, the in-situ adjustment lug 16, the gantry upright 91, the gantry crossbeam 92, the ear plate 93, and the lifting device 94. DETAILED DESCRIPTION
[0029] In order to make the above-mentioned purposes, features and advantages of the utility model more obvious and easy to understand, the specific implementation methods of the utility model are described in detail below in conjunction with the accompanying drawings. In the following description, many specific details are set forth to facilitate a full understanding of the utility model. However, the utility model can be implemented in many other ways different from those described herein, and those skilled in the art can make similar improvements without violating the connotation of the utility model. Therefore, the utility model is not limited by the specific embodiments disclosed below. The technical features in each embodiment of the utility model can be combined accordingly without conflicting with each other.
[0030] In the description of the present utility model, it should be understood that the terms "first" and "second" are only used for the purpose of distinguishing descriptions, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features.
[0031] As a preferred embodiment of the present utility model, this embodiment provides a tower crane wall attachment installation structure for a steel tower, as a whole. Figure 1 and Figure 2The tower crane wall attachment installation structure includes a wall attachment rod, a first attachment bracket 4, a second attachment bracket 5, a tower crane outer frame 8 and a rod adjustment frame 9. In this embodiment, three wall attachment rods are provided, namely, a first rod 1, a second rod 2 and a third rod 3.
[0032] like Figure 2 As shown, the outer frame 8 of the tower crane is arranged on the periphery of the tower crane body 7, and is used for wall connection with the special-shaped steel tower 6. In this embodiment, the outer frame 8 of the tower crane is a frame assembled by box beams, which is sleeved on the periphery of the tower crane body 7. The first attachment cantilever 4 and the second attachment cantilever 5 are respectively fixed on the outer wall panels on both sides of the special-shaped steel tower 6. It should be noted that the first attachment cantilever 4 and the second attachment cantilever 5 can be erected with various cross-section steels, as long as the calculation is passed. The position of the outer frame 8 of the tower crane corresponds to the position of the first attachment cantilever 4 and the second attachment cantilever 5 outside the special-shaped steel tower 6. The outer frame 8 of the tower crane and the first attachment cantilever 4 and the second attachment cantilever 5 are connected by wall-attached tie rods, and the connection points are provided with tie rod adjustment frames 9 for adjusting the positions of the wall-attached tie rods.
[0033] Figure 3 A bottom view of the wall-attached tie rod provided in this embodiment, Figure 4 1 is an overall schematic diagram of the wall-mounted tie rod. The wall-mounted tie rod is composed of a first male connector 101, a main rod 12, an adjustment section 13, and a second male connector 102 from left to right. In this embodiment, the main rod is a box-shaped steel pipe, but it should be noted that the cross-sectional shape and size of the main rod 12 can be adjusted and can be replaced with other cross-sections that can pass the verification.
[0034] like Figure 5 As shown, the first male joint 101 is provided with a pin hole for fixedly connecting with the tower crane outer frame 8, and the second male joint 102 is provided with a pin hole for fixedly connecting with the first attachment cantilever 4 or the second attachment cantilever 5. The first male joint 101 is connected to the tower crane outer frame 8 by a pin 14, and the second male joint 102 is also connected to the first attachment cantilever 4 or the second attachment cantilever 5 by a pin 14.
[0035] An adjustment section 13 for adjusting the length of the pull rod is provided between the first male connector 101 and the main rod 12. In this embodiment, the adjustment section 13 is adjusted by a nut. The first male connector 101 and the second male connector 102 are both fixed with an in-situ adjustment lug 16 for connecting with the pull rod adjustment frame 9. Figure 4 shown.
[0036] Figure 6A schematic diagram of the rod adjustment frame 9 provided in this embodiment. The rod adjustment frame 9 includes a portal frame upright 91, a portal frame crossbeam 92, an ear plate 93 and a lifting device 94. The portal frame upright 91 is vertically fixed to the outer frame 8 of the tower crane, the first attachment cantilever 4 or the second attachment cantilever 5. A portal frame crossbeam 92 is horizontally arranged on the top of the portal frame upright 91. In this embodiment, the portal frame upright 91 and the portal frame crossbeam 92 are both made of I-beams. It should be noted that in an actual construction site, the portal frame upright 91 and the portal frame crossbeam 92 can also be made of other steel sections such as square steel and round steel.
[0037] A lug plate 93 for setting a lifting device 94 is fixed on the gantry crossbeam 92. In this embodiment, the lifting device 94 is an electric hoist. The hook at one end of the electric hoist is connected to the tower crane outer frame 8, the first attachment bracket 4 or the second attachment bracket 5, and the hook at the other end is connected to the in-position adjustment lug 16 on the wall-attached tie rod, which is used to adjust the posture of the wall-attached tie rod, thereby further completing the work of fixing the through-pin shaft.
[0038] In order to facilitate the hoisting of the wall-mounted tie rod, in this embodiment, a hoisting lug 15 for hoisting the tie rod is welded on the main rod 12 of the wall-mounted tie rod.
[0039] The specific method for construction using the tower crane wall attachment installation structure for a steel tower provided by the utility model is as follows:
[0040] (1) The attachment brackets on the outside of the special-shaped steel tower 6, namely the first attachment bracket 4 and the second attachment bracket 5, are pre-processed in the factory and welded to the outer wall of the special-shaped steel tower 6, and then transported to the construction site as a whole. The special-shaped steel tower 6 is hoisted by a single-sided tower crane. As the installation height of the special-shaped steel tower gradually increases, when it reaches a certain height, it needs to be connected to the wall of the special-shaped steel tower 6 on one side. When the tower crane body 7 is installed, the tower crane outer frame 8 has been installed on the outer periphery of the tower crane body 7 for connecting to the special-shaped steel tower 6 by attaching to the wall.
[0041] (2) Before installing the wall-mounted tie rod, it is necessary to use measuring equipment to verify the elevations of the tower crane outer frame 8, the first attachment bracket 4, and the second attachment bracket 5. After confirmation, use the tower crane to install the first tie rod 1, the second tie rod 2, and the third tie rod 3 in sequence with the help of the lifting ears 15 welded on the wall-mounted tie rod.
[0042] (3) After the wall-mounted tie rod is smoothly positioned at the installation position, the electric hoist and hook device on the temporary adjustment frame 9 of the tie rod can be used to connect the positioning adjustment lugs 16 on the wall-mounted tie rod. When the positioning adjustment lugs 16 on the first male joint 101 and the second male joint 102 of the wall-mounted tie rod are respectively connected to the temporary adjustment frame 9 of the tie rod, the tower crane can be unhooked. Subsequently, the operator uses the electric hoist and fall chain to adjust the positioning form of the wall-mounted tie rod so that the pin holes on both sides of the wall-mounted tie rod are aligned with the attachment brackets (the first attachment bracket 4 and the second attachment bracket 5) on the outside of the special steel tower 6 or the docking second plates on the outer frame 8 of the tower crane, and the pins are inserted to fix them. The three wall-mounted tie rods are installed according to the same steps. When all are completed, the installation of the tower crane wall attachment is completed.
[0043] The above-described embodiment is only a preferred solution of the present invention, but it is not intended to limit the present invention. Ordinary technicians in the relevant technical field can make various changes and modifications without departing from the spirit and scope of the present invention. Therefore, any technical solution obtained by equivalent replacement or equivalent transformation falls within the protection scope of the present invention.
Claims
1. A tower crane wall attachment installation structure for a steel tower, characterized in that: It comprises a wall-attached tie rod, a first attachment cantilever frame (4), a second attachment cantilever frame (5), a tower crane outer frame (8) and a tie rod adjustment frame (9); The tower crane outer frame (8) is arranged on the periphery of the tower crane body (7) and is used for wall-attachment connection with the special-shaped steel tower (6); a first attachment bracket (4) and a second attachment bracket (5) are respectively fixed on the outer wall panels on both sides of the special-shaped steel tower (6); the tower crane outer frame (8) and the first attachment bracket (4) and the second attachment bracket (5) are connected by wall-attachment tie rods, and tie rod adjustment frames (9) for adjusting the positions of the wall-attachment tie rods are provided at the connection points; The wall-mounted tie rod comprises a first male joint (101), a main rod (12), an adjustment section (13), and a second male joint (102); the first male joint (101) is fixedly connected to the outer frame (8) of the tower crane, and an adjustment section (13) for adjusting the length of the tie rod is provided between the first male joint (101) and the main rod (12); the second male joint (102) is fixedly connected to the first attachment bracket (4) or the second attachment bracket (5); the first male joint (101) and the second male joint (102) are both fixedly provided with an in-situ adjustment ear (16) for connecting to the tie rod adjustment frame (9).
2. The tower crane wall attachment installation structure for a steel tower according to claim 1, characterized in that: The pull rod adjustment frame (9) includes a portal upright (91), a portal crossbeam (92), an ear plate (93) and a lifting device (94); the portal upright (91) is vertically fixed on the outer frame (8) of the tower crane, the first attached cantilever (4) or the second attached cantilever (5), and the portal crossbeam (92) is horizontally arranged on the top of the portal upright (91); an ear plate (93) for setting the lifting device (94) is fixed on the portal crossbeam (92); one end of the lifting device (94) is connected to the outer frame (8) of the tower crane, the first attached cantilever (4) or the second attached cantilever (5), and the other end is connected to the in-situ adjustment ear (16) on the wall-attached pull rod.
3. The tower crane wall attachment installation structure for a steel tower according to claim 2, characterized in that: The lifting device (94) is an electric hoist.
4. The tower crane wall attachment installation structure for a steel tower according to claim 1, characterized in that: The wall-attached tie rods are provided with three, namely a first tie rod (1), a second tie rod (2) and a third tie rod (3).
5. The tower crane wall attachment installation structure for a steel tower according to claim 1, characterized in that: The wall-attached pull rod is made of box-shaped steel pipe.
6. The tower crane wall attachment installation structure for a steel tower according to claim 1, characterized in that: The first male joint (101) is connected to the outer frame (8) of the tower crane by means of a pin shaft (14).
7. The tower crane wall attachment installation structure for a steel tower according to claim 1, characterized in that: The second male connector (102) is connected to the first attachment bracket (4) or the second attachment bracket (5) via a pin shaft (14).
8. The tower crane wall attachment installation structure for a steel tower according to claim 1, characterized in that: The adjusting section (13) is adjusted by a nut.
9. The tower crane wall attachment installation structure for a steel tower according to claim 1, characterized in that: A lifting lug (15) for lifting a pull rod is also welded on the main rod (12).
10. The tower crane wall attachment installation structure for a steel tower according to claim 1, characterized in that: The tower crane outer frame (8) is a frame assembled from box beams.