BIM-based municipal engineering construction progress information management method and system

A technology for construction progress and engineering construction, applied in data processing applications, electrical digital data processing, special data processing applications, etc., and can solve problems such as single information display and analysis, inability to combine city coordinates, and lack of applicable municipal engineering disclosure technology, etc. To achieve the effect of improving the management level

Inactive Publication Date: 2017-06-06
SHANGHAI UNDERGROUND ARCHITECTURAL DESIGN & RESEARCH INSTITUTE +2
View PDF5 Cites 47 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] In the existing technology, although there are some construction progress management methods, these methods are all customized solutions for a specific project, and the solutions can only reflect the project itself, and cannot be combined with the actual city coordinates
Since municipal engineering is closely related to people's daily life, the degree of impact on people's daily life should be considered during the construction process. When making a construction plan, a reasonable plan should be formulated according to the daily life of residents and pedestrians around the construction, and Can be displayed intuitively, therefore, there is no relevant public technology applicable to municipal engineering
Moreover, in the BIM-based municipal engineering construction progress information management in the existing technology, the creation of the BIM model, the association between the BIM model and the WBS cannot meet the requirements of the municipal engineering progress management, and the information display and analysis are too single to be able to Meet the staff's requirements for information management of construction projects

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • BIM-based municipal engineering construction progress information management method and system
  • BIM-based municipal engineering construction progress information management method and system
  • BIM-based municipal engineering construction progress information management method and system

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0024] In order to make the technical means, creative features, goals and effects of the present invention easy to understand, the following embodiments will specifically explain the BIM-based municipal engineering construction progress information management method and system of the present invention in conjunction with the accompanying drawings.

[0025] Such as figure 1 As shown, in this embodiment, the BIM-based municipal engineering construction progress information management method includes the following steps:

[0026] Step S1, constructing a BIM model, such as figure 2 shown, including the following steps:

[0027] Step S1-1, the base point of the project is unified. In the BIM modeling software, the coordinates of each model, construction, and position are measured in millimeters, and the geographic location coordinates of the city are measured in kilometers. Therefore, the geographic location coordinates of the city need to be transformed to make it Unified with ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention provides a BIM-based municipal engineering construction progress information management method. During building of a BIM model, first geographical position coordinates of a city is converted into position coordinates identical to a project base point in modeling software, then the BIM model is built under the unified base point, thus, the BIM model is combined with the geographical position of the city, the general situation of a construction project can be reflectively visually, encoding and numbering are performed on the BIM model, a construction schedule is compiled, the construction schedule includes a plurality of processes and the processes are numbered, and are associated with the codes and serial numbers of the BIM model, thereby determining the planned construction time of each member in the BIM model, through entering of the actual construction process, the actual construction process is compared with the planned construction process, various display modes are utilized for display and analysis, and thus process information of the construction project is known visually and comprehensively.

Description

technical field [0001] The invention belongs to the technical field of municipal engineering construction, and in particular relates to a BIM-based management method and system for municipal engineering construction progress information. Background technique [0002] The construction schedule management of engineering projects is an important part of engineering project management. The characteristics of traditional schedule management methods, such as information lag and low degree of informatization, restrict the development of engineering schedule management. Building information model, referred to as BIM (building information modeling), BIM technology has the characteristics of informatization and visualization. The application of BIM-based construction progress information management mode in municipal engineering can improve the management level of this type of project, and then improve the quality of the project. The overall value is significant. [0003] In the prior...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): G06Q10/06G06F17/30
CPCG06F16/904G06Q10/063116
Inventor 巴雅吉呼刘艳滨张湄严佳梁孔祥平段创峰滕丽顾沉颖胡珉喻钢杨子松
Owner SHANGHAI UNDERGROUND ARCHITECTURAL DESIGN & RESEARCH INSTITUTE
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products