Comprehensive optimized dispatching method of electricity generation and use integration

A technology for optimizing scheduling and power consumption, applied in data processing applications, system integration technology, instruments, etc., can solve problems such as network congestion and inability to effectively adjust market supply and demand

Active Publication Date: 2018-04-06
CHINA ELECTRIC POWER RES INST +4
View PDF2 Cites 1 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Some regions in the initial stage of market development lack complete market operation rules and electricity price formation mechanisms. At present, they cannot adjust market supply and demand in a timely and effective manner through economic means, and the existing network congestion problems cannot be perfectly resolved.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Comprehensive optimized dispatching method of electricity generation and use integration
  • Comprehensive optimized dispatching method of electricity generation and use integration
  • Comprehensive optimized dispatching method of electricity generation and use integration

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0072] In order to better understand the present invention, the content of the present invention will be further described below in conjunction with the accompanying drawings and examples.

[0073] The present invention provides a comprehensive optimization scheduling method for the integration of power generation and utilization. The method includes the following steps:

[0074] 1) Obtain the basic information of the installed capacity of the power plant:

[0075] Obtain the installed power generation capacity of each power plant, the unit maintenance plan, the interruptible load capacity reported by the load side, and the compensation price.

[0076] 2) Calculate the comprehensive interaction cost and the comprehensive satisfaction of power consumption on the power consumption side respectively:

[0077] I. Comprehensive interaction cost includes power generation cost, of which power generation cost C g It is the ratio of the total cost of power generation output to the to...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention provides a comprehensive optimized dispatching method of electricity generation and use integration. The method includes: collecting information of an electricity generation side and anelectricity use side; respectively calculating comprehensive interaction costs and a comprehensive electricity use satisfaction degree of the electricity use side; constructing a comprehensive utilitymodel of electricity generation and use integration dispatching; considering network constraints to optimize a dispatching plan of the electricity generation side and the electricity use side; and determining the dispatching plan. According to the technical solution provided by the invention, network congestion can be effectively eliminated, utilization efficiency of a generator set is also improved, a unit electricity generation cost of the electricity generation side is effectively reduced, dispatching potential of flexible loads is fully exploited at the same time, excessive fluctuation ofan electricity price in a dispatching process is restrained, and minimization of a comprehensive dispatching cost is realized.

Description

technical field [0001] The invention relates to a scheduling method, in particular to a comprehensive optimization scheduling method for the integration of power generation and utilization. Background technique [0002] With the establishment of the power market mechanism, market participants are pursuing the maximization of their own interests, which inevitably leads to network congestion in the lines around the lower-priced power plants in the system. In the traditional grid environment, the load is generally reduced according to the sensitivity to eliminate network congestion. In the smart grid environment, with the improvement of the "source-network-load" interaction capability, the participation of flexible loads in grid scheduling is economical and efficient for solving network congestion problems. [0003] As a supplement to power generation dispatching, flexible load dispatching can cut peaks and fill valleys, balance intermittent energy fluctuations, and provide aux...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): G06Q50/06G06Q10/06
CPCG06Q10/06312G06Q50/06Y02E40/70Y04S10/50
Inventor 王刚朱红嵇文路苏大威江叶峰杨胜春赵奇冯树海王珂李亚平郭晓蕊刘建涛曾丹
Owner CHINA ELECTRIC POWER RES INST
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products