Embodiment 1
[0080] like figure 1 Shown is a work flow chart of a car-sharing business work order scheduling method according to an embodiment of the present invention, including:
[0081] Step S101, obtain work orders as work orders to be calculated, there will be work orders to be calculated that need to be completed, and complete according to the supply and demand forecast of the station;
[0082] Step S102, after calculating the work order price and estimated duration for the work order to be calculated, obtain the pricing work order, and send the pricing work order to the shared car business work order management server, and the price calculation work order is provided by the shared car business The work order management server displays to the salesperson's terminal, or directly displays to the salesperson's terminal.
[0083] Specifically, this embodiment is used in the car-sharing business work order scheduling server, wherein step S101 complements the obtained work orders to be ca...
no. 2 example
[0086] like figure 2 Shown is a work flow chart of a car-sharing business work order scheduling method according to the second embodiment of the present invention, including:
[0087] Step S201, obtaining work orders generated based on supply and demand forecasts as work orders to be calculated.
[0088] Step S202, obtaining the work order that needs to be completed as the work order to be calculated from the car-sharing business work order management server.
[0089] In step S203, the work orders to be calculated with fields that need to be completed are completed according to the supply and demand forecast of the station.
[0090] In one embodiment, there will be work orders to be calculated that need to complete the field of the starting station and / or the field of the ending station, and the completion is performed according to the supply and demand forecast of the station.
[0091] Step S204, after calculating the work order price and estimated duration for the work or...
no. 3 example
[0102] like image 3 Shown is a work flow chart of a car-sharing business work order scheduling method according to the third embodiment of the present invention, including:
[0103] Step S301, obtaining work orders generated based on supply and demand forecasts as work orders to be calculated;
[0104] Step S302, in response to the real-time work order calculation request, obtain the real-time work order that needs to be completed as the work order to be calculated from the shared car business work order management server;
[0105]Step S303, acquiring non-real-time work orders that need to be completed as work orders to be calculated from the car-sharing business work order management server at preset intervals;
[0106] Step S304, there are work orders to be calculated that need to be completed, and are completed according to the supply and demand forecast of the station;
[0107] Step S305, after calculating the work order price and estimated duration for the work order t...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com