Installation and construction method for heavy-duty gas turbine

Through systematic construction methods and precise use of tools, the problems of long installation construction period and high consumables and energy consumption of heavy-duty gas turbines are solved, achieving a more efficient installation process and better environmental protection effects.

CN118855593APending Publication Date: 2024-10-29SICHUAN NO 2 ELECTRIC POWER CONSTR CO
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411099392.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-12
Publication Date
2024-10-29

AI Technical Summary

Technical Problem

The installation and construction period of heavy-duty gas turbines is long, slow, and consumes high consumables and energy. The existing traditional pad-iron method is difficult, which affects the quality of equipment installation and environmental protection.

Method used

A systematic construction method is adopted, including the installation of embedded parts, gas turbine positioning, burner inspection and installation, oil system installation, shafting alignment, generator cover and cooler installation, through hydraulic lifting devices and hydraulic jacks , levels, spirit levels and other tools and equipment to ensure accuracy and efficiency in every step.

Benefits of technology

It shortens the construction period, reduces consumables and energy consumption, improves the quality of equipment installation, reduces environmental pollution, and has good social benefits and economic value.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118855593A_ABST
    Figure CN118855593A_ABST
Patent Text Reader

Abstract

The invention discloses a heavy duty gas turbine installation construction method, which relates to the technical field of gas turbines, and comprises the following steps: S1, installing an embedded part; s2, the gas turbine is in place; s3, a gas compressor end supporting base and a gas turbine end supporting base are installed; s4, checking the combustor; s5, mounting a combustor; s6, mounting an intermediate shaft; s7, an oil system is installed; s8, centering the shaft system; s9, secondary grouting is conducted; s10, a generator housing is installed; and S11, the generator cooler is installed. According to the installation construction method, the construction operation difficulty is reduced, the construction period is shortened, the installation quality of equipment is guaranteed, consumables and energy consumption are reduced in the construction process, environmental pollution is reduced, and good social benefits and economic values are achieved for environmental protection, energy conservation and emission reduction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of gas turbines, and in particular to a heavy-duty gas turbine installation and construction method. Background Art

[0002] Gas turbines are internal combustion power equipment that uses continuous flow of gas as a medium to drive the impeller to rotate at high speed, converting the energy of the fuel into useful work. Gas turbines are widely used in energy, national defense, and transportation fields such as power generation, ship and locomotive power, and pipeline supercharging.

[0004] At present, the installation of heavy-duty gas turbines itself is difficult, and the existing methods mostly use traditional pad iron method. This method has a long construction period, slow speed, and high material and energy consumption.

[0005] In view of this, a heavy-duty gas turbine installation construction method is proposed. Summary of the invention

[0006] The main purpose of the present invention is to provide a heavy-duty gas turbine installation construction method, which can effectively solve the problems in the background technology.

[0007] To achieve the above object, the technical solution adopted by the present invention is:

[0008] A heavy-duty gas turbine installation construction method comprises the following steps:

[0009] S1: Embedded parts installation

[0010] 1): Foundation appearance inspection: The surface is flat, without cracks, holes, honeycombs and exposed reinforcement. The seismic isolation gaps between the foundation and the factory building and related operating platforms are clean and free of debris.

[0011] 2): Mark and review the longitudinal and transverse center lines of the embedded parts. The deviation from the center line of the civil foundation is required to be ±5mm; the center deviation between the anchor bolt sleeve and the civil foundation is ±2mm.

[0012] 3): Use a tape measure to check the position and size of all bolt holes until they meet the requirements of the drawing.

[0013] 4): Place the compressor end support seat, gas turbine end support seat and guide support seat on the foundation, and use the adjusting bolts on the bottom plates of the compressor end support seat, gas turbine end support seat and guide support seat to adjust the elevation until the drawing requirements are met.

[0014] 5): Place the leveling plate on the generator foundation according to the drawing requirements.

[0015] 6): Use a level to check the elevation of the top of the embedded part and adjust it until it meets the requirements of the drawing.

[0016] 7): Carry out secondary grouting on the adjustment plate, compressor end support seat and guide support seat. The grouting height shall be in accordance with the requirements of the drawings.

[0017] 8): After the grouting maintenance and hardening meet the standards, clean up the debris in the embedded pit.

[0018] 9): Use a tape measure to check the position and dimensions of all embedded anchor bolt sleeves and embedded steel plates until they meet the requirements of the drawings.

[0019] 10): Use a level to check the elevation of the embedded steel plate and adjust it until it meets the requirements of the drawing.

[0020] 11): Use a spirit level to check the horizontal and vertical levelness of the embedded steel plate until the levelness meets the requirements of the drawing.

[0021] 12): After the foundation acceptance is completed, clean the foundation surface and remove oil and rust on the equipment surface.

[0022] 13): Measure the elevation of the upper surface of each embedded steel plate, re-measure the foundation axis, and adjust the thickness of the gasket based on the elevation configuration of each embedded steel plate.

[0023] S2: Gas turbine in place

[0024] 1): Preparation before lifting:

[0025] The gas turbine and generator body are assembled as a whole at the manufacturing plant and then shipped to the site. After arriving at the site, the main equipment is temporarily stored on the site, steel plates are laid on the transportation channel in front of the gas turbine foundation, crane tracks are laid on both sides of the transportation channel, and a hydraulic lifting device is used to place the main equipment directly on the foundation.

[0026] 2): Equipment hoisting in place:

[0027] The lifting is carried out using a hydraulic lifting device. After the gas turbine and generator enter the construction site, they are transported along the on-site road to the front of the foundation, so that the longitudinal center line of the large equipment is consistent with the center line of the foundation, and the already arranged lifting system is used to unload and lift them into place.

[0028] 3): When the generator and gas turbine are initially placed, the distance between the couplings should be greater than the design value of 300mm.

[0029] S3: Installation of compressor end support and gas turbine end support

[0030] 1): First, place temporary supports at the bottom of both ends of the gas turbine.

[0031] 2): Use lifting equipment to move the gas turbine above the foundation, ensure the left and right directions are correct, and align the longitudinal and transverse axes with the axis marks on the foundation.

[0032] 3): Lower the gas turbine until the center plane of the gas turbine bearing is 2700mm above the surface of the concrete foundation.

[0033] 4): Clean the two gas turbine end support seats and apply lubricant to the threads.

[0034] 5): Install the support nut onto the gas turbine end support.

[0035] 6): Slowly screw the support nut onto the thread.

[0036] 7): Apply lubricant to the fixing bolts of the compressor end support seat, install the spherical gasket and the spherical valve seat, and insert the fixing bolts into the supporting spherical convex surface of the compressor end support seat to a depth of 10mm.

[0037] 8): Screw down the fixing bolts of the two compressor end support brackets and secure them.

[0038] 9): Place a temporary hydraulic device on the temporary support at the bottom.

[0039] 10): Use the hydraulic jack of the temporary hydraulic device to lift the gas turbine by 0.3-0.5mm, so that the compressor end support seat and the gas turbine end support seat are in a non-stress state.

[0040] 11): Turn off the hydraulic jack, close it with the locking nut, and close the hydraulic valve.

[0041] 12): Horizontal displacement with a maximum increment of 2 mm: ①. Install a scale to monitor the displacement;

[0042] ②. Loosen the horizontal adjustment bolt on the compressor end support seat; ③. Adjust the 4 hydraulic jacks to move the gas turbine 2mm in the required direction; ④. Retract the horizontal adjustment bolt on the compressor end support seat by 2mm; ⑤. Continue the displacement operation until the required position is reached; ⑥. After reaching the specified position, tighten all the locking bolts by hand; ⑦. Release the pressure with the hydraulic jack.

[0043] 13): Screw the horizontal adjustment bolt into the thread of the compressor end support.

[0044] 14): Remove the hydraulic jack at the bottom of the gas turbine until the gas turbine end support base contacts the gas turbine.

[0045] 15): Re-tighten the lock nut to ensure there is no movement.

[0046] 16): The support screw at the gas turbine end should be installed offset, 10mm towards the exhaust direction and 4mm to the outside.

[0047] The anchor bolts of the gas turbine end support seat are M64×1015mm T-head bolts, and the anchor bolt sleeves are processed and manufactured on-site. Each set of anchor bolt sleeves are connected into a whole using steel and then installed.

[0048] S4: Burner Inspection

[0049] 1): Preparation work. Before installing the burner, the foundation should be checked according to the drawings, and the following requirements should be met before it is put into place: ①. Remove the outer packaging and transfer the burner horizontally to the engine room; ②. Use a truck crane to lift the burner and place it horizontally on the sleepers; ③. Use lifting tools to lift the burner, remove the sleepers, rotate the burner with auxiliary tools, move the burner to the side of the gas turbine foundation and put it in place.

[0050] 2): Internal inspection of the burner: ①. Determine the position of the inner casing to the center casing flange and check the gap; ②. Determine the position of the mixing chamber casing and the burner flange and check the gap; ③. If it has been determined that the mixing chamber casing is in the correct position and the gap is correct, the burner is directly installed on the gas turbine; if the cooling air ring does not contact the inner casing or does not reach the gap specified in the drawing, adjust the position of the mixing chamber casing.

[0051] 3): Installation of burner assembly platform.

[0052] S5: Burner Installation

[0053] 1): Preparation: ①. Remove the transport protective cover of the burner flange; ②. Clean the burner flange and threaded holes; ③. Install the 4-section sealing ring parts in the groove of the burner housing flange, check the size of the sealing ring, remove the sealing ring and combine it into a circular ring for welding, and then grind the weld to make it smooth.

[0054] 2): Use a crane to hoist the burner. When hoisting, select the hoisting point at the position indicated in the drawing and connect it with a 32# lifting ring. Other connection methods are strictly prohibited.

[0055] 3): Use a crane to move the burner, slowly move its flange to the engine casing flange and align them, keeping a distance of 100mm between the flanges.

[0056] 4): Move the burner close to the gas turbine interface until the guide holes of the burner interface flange touch the guide bolts of the gas turbine interface flange.

[0057] 5): Adjust the lateral and vertical position of the burner so that the guide bolts slide into the guide holes on the burner flange, ensuring that the edge of the burner mixing chamber shell does not contact the gas turbine inner shell.

[0058] 6): Use a straight edge to check the parallelism of the two flanges and adjust them until the flanges are parallel and the parallelism deviation is no more than 2mm.

[0059] 7): Make the burner parallel to the gas turbine interface flange, clean and apply grease to the connecting bolts, and then insert the connecting bolts into the bolt holes.

[0060] 8): Use a wrench to tighten the connecting bolts at the flange, ensure that the burner flange with the sealing ring is in full contact with the entire area of ​​the center housing flange, and tighten the connecting bolts to a torque of 200Nm.

[0061] 9): Tighten the connecting bolts in clockwise direction and record the initial gap between the flanges and the gap after tightening.

[0062] 10): After the burner is installed, open the burner inspection hole, check the gap size of each burner shell according to the drawing size and adjust it.

[0063] 11): After the burner installation work is completed, remove the assembly platform and install the operating platform and associated pipelines.

[0064] S6: Intermediate shaft installation

[0065] 1): Position the intermediate shaft bracket according to the drawing, and install the intermediate shaft bracket on the foundation using expansion bolts.

[0066] 2): Use a crane to lift the intermediate shaft and keep it level, use a frame level to check the level of the intermediate shaft end flange, rotate the support bolts on the intermediate shaft bracket, place the intermediate shaft on the intermediate shaft bracket and the compressor end bearing, rotate the coupling so that the maximum runout position of the intermediate shaft and the gas turbine rotor end face is 180 degrees apart, mark the end face of the coupling, use a crane to move the intermediate shaft to the gas turbine coupling flange, and allow the coupling bolts to penetrate the intermediate shaft flange hole.

[0067] S7: Oil system installation

[0068] 1): Install the top shaft oil pipeline and lubricating oil pipeline according to the drawing, and the interfaces of all pipelines correspond one to one.

[0069] 2): Before installing the pipeline, check the internal cleanliness of the pipeline, clean the flange surface in advance, apply molybdenum disulfide grease on the surface of the connecting bolts, and tighten them according to the torque required by the drawing after connection.

[0070] 3): Temporary flushing bypass of top shaft oil:

[0071] Use a plug to seal the top shaft oil pipeline interface of the gas turbine, connect the oil inlet pipe and the oil return pipe with a high-temperature and high-pressure hose, and flush the top shaft oil pipeline of each bearing separately.

[0072] 4): Temporary lubricating oil flushing bypass: ①. Install cooler flushing bypass: short-circuit the cooler inlet and outlet pipes; ②. Install filter flushing bypass: short-circuit the filter inlet and outlet pipes; ③. Lubricating oil pipeline flushing bypass: use high temperature and high pressure resistant hose to short-circuit the lubricating oil supply pipe and return pipe of the generator and gas turbine, disconnect the compressor bearing oil supply short pipe, and temporarily fasten the bearing cover.

[0073] 5): HCO pipeline flushing bypass:

[0074] According to the requirements of the drawings, use high-temperature and high-pressure hoses to short-circuit the HCO oil supply pipe and return pipe at the compressor end.

[0075] 6): Carry out oil circulation. After the oil circulation reaches a certain time, take oil samples at the oil drain point. After obtaining a qualified oil quality test report issued by a unit with corresponding qualifications, the oil is flushed through. After the oil circulation flushing is completed, remove the temporary bypass and restore the system.

[0076] S8: Axis centering

[0077] 1): The top shaft oil pipeline is installed before the shaft system is centered and the oil circulation is qualified.

[0078] 2): Adjust the position of the generator stator, check and adjust the gap between the two couplings at both ends of the intermediate shaft.

[0079] 3): Start the top shaft oil pump and start turning the rotor.

[0080] 4): After the rotor reaches the measuring position, stop rotating the rotor, turn off the top shaft oil pump, and wait for the rotor to stop.

[0081] 5): Measure the clearance between the generator and the intermediate shaft coupling end face in the left, right, top and bottom directions.

[0082] 6): Measure the clearance between the gas turbine and the intermediate shaft coupling end face in the left, right, top and bottom directions.

[0083] 7): Calculate the average value of the measured values ​​to ensure that the upper and lower openings of the coupling at the gas turbine end are 0.14±0.02mm and the left and right openings are 0.00±0.02mm; the upper and lower openings of the coupling at the generator end are 0.09±0.02mm and the left and right openings are 0.00±0.02mm.

[0084] 8): Install the coupling bolts and tighten them according to the torque value required by the drawing.

[0085] S9: Secondary grouting

[0086] After the axis system is centered, the foundation is grouted for the second time.

[0087] S10: Generator cover installation

[0088] 1): Remove the transport cover of the generator, install auxiliary supports on both sides of the generator in advance, clean all foreign objects, and ensure the cleanliness of the generator and the generator cover.

[0089] 2): Use a truck crane to lift the generator cover to the open space next to the generator, and then use the truck crane to lift the components of the generator cover to the generator area one by one, and use a hand winch to adjust through the lifting points on the generator cover.

[0090] 3): Install the lifting device.

[0091] 4): Slowly place the generator cover onto the auxiliary support, connect the top connecting bolts, and tighten them.

[0092] 5): After tightening the bolts, make sure all contact points are in contact and remove the lifting tools.

[0093] S11: Generator Cooler Installation

[0094] 1): Remove the outer packaging of the cooler, use a car crane to flip the cooler so that the cooler is in a vertical direction. During the flipping process, the cooler should be protected to prevent the hanger or wire rope from causing damage to the cooler.

[0095] 2): Use a truck crane to lift the cooler and slowly move it to the installation position from the east side of the generator. Hang a hand winch on the steel structure above the east side of the generator, use the hand winch to pull the cooler, level it, and center it. Finally, connect the cooler to the generator and tighten all connecting bolts.

[0096] 3): Install the heat exchanger and cooler end cover to the cooler in the same way.

[0097] The present invention has the following beneficial effects:

[0098] The heavy-duty gas turbine installation construction method of the present invention reduces the difficulty of construction work, shortens the construction period, ensures the installation quality of equipment, reduces consumables and energy consumption during construction, reduces environmental pollution, and has good social benefits and economic value for environmental protection and energy conservation and emission reduction. BRIEF DESCRIPTION OF THE DRAWINGS

[0099] Figure 1 It is a schematic diagram of the process of the present invention. DETAILED DESCRIPTION

[0100] The present invention is further described below in conjunction with the accompanying drawings and embodiments, but is not intended to limit the present invention. Any technical solution based on the transformation or inference of the present invention belongs to the protection scope of the present invention.

[0101] Combined with Figure 1 The present invention is further described by taking a 150MW gas turbine installation construction method, which comprises the following steps:

[0102] S1: Embedded parts installation

[0103] 1): Foundation appearance inspection: The surface is flat, without cracks, holes, honeycombs and exposed reinforcement. The seismic isolation gaps between the foundation and the factory building and related operating platforms are clean and free of debris.

[0104] 2): Mark and review the longitudinal and transverse center lines of the embedded parts. The deviation from the center line of the civil foundation is required to be ±5mm; the center deviation between the anchor bolt sleeve and the civil foundation is ±2mm.

[0105] 3): Use a tape measure to check the position and size of all bolt holes until they meet the requirements of the drawing.

[0106] 4): Place the compressor end support seat, gas turbine end support seat and guide support seat on the foundation, and use the adjusting bolts on the bottom plates of the compressor end support seat, gas turbine end support seat and guide support seat to adjust the elevation until the drawing requirements are met.

[0107] 5): Place the leveling plate on the generator foundation according to the drawing requirements.

[0108] 6): Use a level to check the elevation of the top of the embedded part and adjust it until it meets the requirements of the drawing.

[0109] 7): Carry out secondary grouting on the adjustment plate, compressor end support seat and guide support seat. The grouting height shall be in accordance with the requirements of the drawings.

[0110] 8): After the grouting maintenance and hardening meet the standards, clean up the debris in the embedded pit.

[0111] 9): Use a tape measure to check the position and dimensions of all embedded anchor bolt sleeves and embedded steel plates until they meet the requirements of the drawings.

[0112] 10): Use a level to check the elevation of the embedded steel plate and adjust it until it meets the requirements of the drawing.

[0113] 11): Use a spirit level to check the horizontal and vertical levelness of the embedded steel plate until the levelness meets the requirements of the drawing.

[0114] 12): After the foundation acceptance is completed, clean the foundation surface and remove oil and rust on the equipment surface.

[0115] 13): Measure the elevation of the upper surface of each embedded steel plate, re-measure the foundation axis, and adjust the thickness of the gasket based on the elevation configuration of each embedded steel plate.

[0116] S2: Gas turbine in place

[0117] 1): Preparation before lifting:

[0118] The gas turbine is 1046cm×412cm×405cm in size and weighs 198t; the generator is 1020cm×390cm×407cm in size and weighs 219t. The gas turbine and generator bodies are assembled in the factory and shipped to the site. After arriving at the site, the main equipment is temporarily stored on the site, steel plates are laid on the transport channel in front of the gas turbine foundation, crane tracks are laid on both sides of the transport channel, and the main equipment is placed directly on the foundation using a hydraulic lifting device.

[0119] 2): Equipment hoisting in place:

[0120] Four SBL1100 hydraulic jacks are used for lifting. The rated load of a single SBL1100t hydraulic jack is about 172t at the maximum height of 9668mm in the working state. The height of the hydraulic jack itself in the non-working state is 4370mm. After the gas turbine and generator enter the construction site, they are transported to the front of the foundation along the on-site road, so that the longitudinal center line of the large equipment is consistent with the center line of the foundation, and the already arranged lifting system is used to unload and lift them into place.

[0121] 3): When the generator and gas turbine are initially in place, the distance between the couplings should be greater than the design value of 300mm to facilitate the installation of the intermediate shaft.

[0122] S3: Installation of compressor end support and gas turbine end support

[0123] 1): First, place temporary supports at the bottom of both ends of the gas turbine.

[0124] 2): Use lifting equipment to move the gas turbine above the foundation, ensure the left and right directions are correct, and align the longitudinal and transverse axes with the axis marks on the foundation.

[0125] 3): Lower the gas turbine until the center plane of the gas turbine bearing is 2700mm above the surface of the concrete foundation.

[0126] 4): Clean the two gas turbine end support seats and apply lubricant to the threads.

[0127] 5): Install the support nut onto the gas turbine end support.

[0128] 6): Slowly screw the support nut onto the thread.

[0129] 7): Apply lubricant to the fixing bolts of the compressor end support seat, install the spherical gasket and the spherical valve seat, and insert the fixing bolts into the supporting spherical convex surface of the compressor end support seat to a depth of 10mm.

[0130] 8): Screw down the fixing bolts of the two compressor end support brackets and secure them.

[0131] 9): Place a temporary hydraulic device on the temporary support at the bottom.

[0132] 10): Use the hydraulic jack of the temporary hydraulic device to lift the gas turbine by 0.3-0.5mm, so that the compressor end support seat and the gas turbine end support seat are in a non-stress state.

[0133] 11): Close the hydraulic jack (close it with the lock nut and close the hydraulic valve).

[0134] 12): Perform horizontal displacement in increments of up to 2 mm: ①. Install a scale to monitor the displacement; ②. Loosen the horizontal adjustment bolts on the compressor end support seat; ③. Adjust the 4 hydraulic jacks to move the gas turbine 2 mm in the desired direction; ④. Retract the horizontal adjustment bolts on the compressor end support seat by 2 mm; ⑤. Continue the displacement operation until the desired position is reached; ⑥. After reaching the specified position, tighten all the locking bolts by hand; ⑦. Depressurize the hydraulic jack.

[0135] 13): Screw the horizontal adjustment bolt into the thread of the compressor end support.

[0136] 14): Remove the hydraulic jack at the bottom of the gas turbine until the gas turbine end support base contacts the gas turbine.

[0137] 15): Re-tighten the lock nut to ensure there is no movement.

[0138] 16): The support screw at the gas turbine end should be installed offset, 10mm towards the exhaust direction and 4mm to the outside.

[0139] The anchor bolts of the gas turbine end support seat are M64×1015mm T-head bolts, and the anchor bolt sleeves are processed and manufactured on-site. Each set of anchor bolt sleeves are connected into a whole using steel and then installed.

[0140] The connection part of the gas turbine end support seat adopts a double spherical adjustable support, which can be adjusted and fixed in four directions; after the gas turbine is positioned, the adjustable support is welded to the gas turbine end support seat to reduce the equipment positioning adjustment work caused by installation errors, and the adjustment work can be completed directly when the gas turbine is initially in place, reducing the use of large lifting machinery and improving construction efficiency.

[0141] S4: Burner Inspection

[0142] 1): Preparation work. Before installing the burner, the foundation should be checked according to the drawings, and the following requirements should be met before it is put into place: ①. Remove the outer packaging and transfer the burner horizontally to the engine room; ②. Use a truck crane to lift the burner and place it horizontally on the sleepers; ③. Use lifting tools to lift the burner, remove the sleepers, rotate the burner with auxiliary tools, move the burner to the side of the gas turbine foundation and put it in place.

[0143] 2): Internal inspection of the burner: ①. Determine the position of the inner casing to the center casing flange and check the gap; ②. Determine the position of the mixing chamber casing and the burner flange and check the gap; ③. If it has been determined that the mixing chamber casing is in the correct position and the gap is correct, the burner is directly installed on the gas turbine; if the cooling air ring does not contact the inner casing or does not reach the gap specified in the drawing, adjust the position of the mixing chamber casing.

[0144] 3): Installation of burner assembly platform.

[0145] S5: Burner Installation

[0146] 1): Preparation: ①. Remove the transport protective cover of the burner flange; ②. Clean the burner flange and threaded holes; ③. Install the 4-section sealing ring parts in the groove of the burner housing flange, check the size of the sealing ring, remove the sealing ring and combine it into a circular ring for welding, and then grind the weld to make it smooth.

[0147] 2): Use a crane to hoist the burner. When hoisting, select the hoisting point at the position indicated in the drawing and connect it with a 32# lifting ring. Other connection methods are strictly prohibited.

[0148] 3): Use a crane to move the burner, slowly move its flange to the engine casing flange and align them, keeping a distance of 100mm between the flanges.

[0149] 4): Move the burner close to the gas turbine interface until the guide holes of the burner interface flange touch the guide bolts of the gas turbine interface flange.

[0150] 5): Adjust the lateral and vertical position of the burner so that the guide bolts slide into the guide holes on the burner flange, ensuring that the edge of the burner mixing chamber shell does not contact the gas turbine inner shell.

[0151] 6): Use a straight edge to check the parallelism of the two flanges and adjust them until the flanges are parallel and the parallelism deviation is no more than 2mm.

[0152] 7): Make the burner parallel to the gas turbine interface flange, clean and apply grease to the connecting bolts, and then insert the connecting bolts into the bolt holes.

[0153] 8): Use a wrench to tighten the connecting bolts at the flange, ensure that the burner flange with the sealing ring is in full contact with the entire area of ​​the center housing flange, and tighten the connecting bolts to a torque of 200Nm.

[0154] 9): Tighten the connecting bolts in clockwise direction and record the initial gap between the flanges and the gap after tightening.

[0155] 10): After the burner is installed, open the burner inspection hole, check the gap size of each burner shell according to the drawing size and adjust it.

[0156] 11): After the burner installation work is completed, remove the assembly platform, install the operating platform and auxiliary pipelines, and install the air intake system.

[0157] S6: Intermediate shaft installation

[0158] 1): Position the intermediate shaft bracket according to the drawing, and install the intermediate shaft bracket on the foundation using expansion bolts.

[0159] 2): Use a crane to lift the intermediate shaft and keep it level, use a frame level to check the level of the intermediate shaft end flange, rotate the support bolts on the intermediate shaft bracket, place the intermediate shaft on the intermediate shaft bracket and the compressor end bearing, rotate the coupling so that the maximum runout position of the intermediate shaft and the gas turbine rotor end face is 180 degrees apart, mark the end face of the coupling, use a crane to move the intermediate shaft to the gas turbine coupling flange, and allow the coupling bolts to penetrate the intermediate shaft flange hole.

[0160] S7: Oil system installation

[0161] 1): Install the top shaft oil pipeline and lubricating oil pipeline according to the drawing, and the interfaces of all pipelines correspond one to one.

[0162] 2): Before installing the pipeline, check the internal cleanliness of the pipeline, clean the flange surface in advance, apply molybdenum disulfide grease on the surface of the connecting bolts, and tighten them according to the torque required by the drawing after connection.

[0163] 3): Temporary flushing bypass of top shaft oil:

[0164] Use a plug to seal the top shaft oil pipeline interface of the gas turbine, connect the oil inlet pipe and the oil return pipe with a high-temperature and high-pressure hose, and flush the top shaft oil pipeline of each bearing separately.

[0165] 4): Temporary lubricating oil flushing bypass: ①. Install cooler flushing bypass: short-circuit the cooler inlet and outlet pipes; ②. Install filter flushing bypass: short-circuit the filter inlet and outlet pipes; ③. Lubricating oil pipeline flushing bypass: use high temperature and high pressure resistant hose to short-circuit the lubricating oil supply pipe and return pipe of the generator and gas turbine, disconnect the compressor bearing oil supply short pipe, and temporarily fasten the bearing cover.

[0166] 5): HCO pipeline flushing bypass:

[0167] According to the requirements of the drawings, use high-temperature and high-pressure hoses to short-circuit the HCO oil supply pipe and return pipe at the compressor end.

[0168] 6): Carry out oil circulation. After the oil circulation reaches a certain time, take oil samples at the oil drain point. After obtaining a qualified oil quality test report issued by a unit with corresponding qualifications, the oil is flushed through. After the oil circulation flushing is completed, remove the temporary bypass and restore the system.

[0169] S8: Axis centering

[0170] 1): The top shaft oil pipeline is installed before the shaft system is centered and the oil circulation is qualified.

[0171] 2): Adjust the position of the generator stator, check and adjust the gap between the two couplings at both ends of the intermediate shaft.

[0172] 3): Start the top shaft oil pump and start turning the rotor.

[0173] 4): After the rotor reaches the measuring position, stop rotating the rotor, turn off the top shaft oil pump, and wait for the rotor to stop.

[0174] 5): Measure the clearance between the generator and the intermediate shaft coupling end face in the left, right, top and bottom directions.

[0175] 6): Measure the clearance between the gas turbine and the intermediate shaft coupling end face in the left, right, top and bottom directions.

[0176] 7): Calculate the average value of the measured values ​​to ensure that the upper and lower openings of the coupling at the gas turbine end are 0.14±0.02mm and the left and right openings are 0.00±0.02mm; the upper and lower openings of the coupling at the generator end are 0.09±0.02mm and the left and right openings are 0.00±0.02mm.

[0177] 8): Install the coupling bolts and tighten them according to the torque value required by the drawing.

[0178] S9: Secondary grouting

[0179] After the axis system is centered, the foundation is grouted for the second time.

[0180] S10: Generator cover installation

[0181] 1): Remove the transport cover of the generator, install auxiliary supports on both sides of the generator in advance, clean all foreign objects, and ensure the cleanliness of the generator and the generator cover.

[0182] 2): Use a truck crane to lift the generator cover to the open space next to the generator, and then use the truck crane to lift the components of the generator cover to the generator area one by one, and use a hand winch to adjust through the lifting points on the generator cover.

[0183] 3): Install the lifting device.

[0184] 4): Slowly place the generator cover onto the auxiliary support, connect the top connecting bolts, and tighten them.

[0185] 5): After tightening the bolts, make sure all contact points are in contact and remove the lifting tools.

[0186] S11: Generator Cooler Installation

[0187] 1): Remove the outer packaging of the cooler, use a car crane to flip the cooler so that the cooler is in a vertical direction. During the flipping process, the cooler should be protected to prevent the hanger or wire rope from causing damage to the cooler.

[0188] 2): Use a truck crane to lift the cooler and slowly move it to the installation position from the east side of the generator. Hang a hand winch on the steel structure above the east side of the generator, use the hand winch to pull the cooler, level it, and center it. Finally, connect the cooler to the generator and tighten all connecting bolts.

[0189] 3): Install the heat exchanger and cooler end cover to the cooler in the same way.

[0190] In practical application, the present invention saves one month of construction period compared with the four-month construction period of the same type of traditional pad iron type and on-site assembled gas turbine. The labor cost is calculated based on 8 construction personnel at 500 yuan / man-day, directly saving 30 (days) × 8 (people) × 500 (yuan / man-day) = 120,000 yuan of labor cost, and the construction consumables are saved by about 10,000 yuan compared with the traditional units of equal capacity; the equipment transportation time is saved by 5 days, considering the use of a 65-ton truck crane, 5,000 yuan / shift, saving 5,000 × 5 = 25,000 yuan of machine tool costs. The total cost savings is 120,000 + 10,000 + 25,000 = 155,000 yuan.

[0191] In addition, the installation and construction method of the present invention reduces the difficulty of construction work, speeds up the progress of equipment installation, and various data indicators meet the requirements of the manufacturer's technical standards and regulations. The construction process is smooth and the equipment operates well.

[0192] Compared with the traditional pad type of the same type, the present invention reduces the difficulty of construction work, shortens the construction period, ensures the installation quality of equipment, reduces consumables and energy consumption during construction, reduces environmental pollution, and has good social benefits and economic value for environmental protection and energy conservation and emission reduction.

[0193] The above description shows the basic principle and main features of the present invention and the advantages of the present invention. It should be understood by those skilled in the art that the present invention is not limited to the above embodiments, and the above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, and these changes and improvements fall within the scope of the present invention to be protected. The scope of protection of the present invention is defined by the attached claims and their equivalents.

Claims

1. A heavy-duty gas turbine installation construction method, characterized in that: The following steps are involved: S1: Embedded parts installation 1): Foundation appearance inspection: The surface is flat, without cracks, holes, honeycombs and exposed reinforcement. The seismic isolation gaps between the foundation and the factory building and related operating platforms are clean and free of debris; 2): Mark and review the longitudinal and transverse center lines of the embedded parts. The deviation from the center line of the civil foundation is required to be ±5mm; the center deviation between the anchor bolt sleeve and the civil foundation is ±2mm; 3): Use a tape measure to check the position and size of all bolt holes until they meet the requirements of the drawing; 4): Place the compressor end support seat, gas turbine end support seat and guide support seat on the foundation, and use the adjusting bolts on the bottom plates of the compressor end support seat, gas turbine end support seat and guide support seat to adjust the elevation until the requirements of the drawing are met; 5): Place the leveling plate on the generator foundation according to the drawing requirements; 6): Use a level to check the elevation of the top of the embedded part and adjust it until it meets the requirements of the drawing; 7): Carry out secondary grouting on the adjustment plate, compressor end support seat and guide support seat. The grouting height shall be in accordance with the requirements of the drawings; 8): After the grouting maintenance and hardening meet the standards, clean up the debris in the embedded pit; 9): Use a tape measure to check the position and size of all embedded anchor bolt sleeves and embedded steel plates until they meet the requirements of the drawings; 10): Use a level to check the elevation of the embedded steel plate and adjust it until it meets the requirements of the drawing; 11): Use a level to check the horizontal and vertical levelness of the embedded steel plate until the levelness meets the requirements of the drawing; 12): After the foundation acceptance is completed, clean the foundation surface and remove oil and rust on the equipment surface; 13): Measure the elevation of the upper surface of each embedded steel plate, re-measure the foundation axis, and adjust the thickness of the gasket in combination with the elevation of each embedded steel plate; S2: Gas turbine in place 1): Preparation before lifting: The gas turbine and generator bodies are assembled in the factory and shipped to the site. After arriving at the site, the main equipment is temporarily stored on site. Steel plates are laid on the transport channel in front of the gas turbine foundation, crane tracks are laid on both sides of the transport channel, and the main equipment is placed directly on the foundation using a hydraulic lifting device. 2): Equipment hoisting in place: The gas turbine and generator are hoisted by hydraulic lifting devices. After entering the construction site, they are transported to the front of the foundation along the on-site road, so that the longitudinal center line of the large equipment is consistent with the center line of the foundation, and the hoisting system that has been arranged is used to unload and hoist them into place; 3): When the generator and gas turbine are initially positioned, the distance between the couplings should be greater than the design value of 300mm; S3: Installation of compressor end support and gas turbine end support 1): First, place temporary supports at the bottom of both ends of the gas turbine; 2): Use lifting equipment to move the gas turbine to the top of the foundation, ensure that the left and right directions are correct, and align the longitudinal and transverse axes with the axis marks on the foundation; 3): Lower the gas turbine until the center plane of the gas turbine bearing is 2700mm above the surface of the concrete foundation; 4): Clean the two gas turbine end support seats and apply lubricant to the threads; 5): Install the support nut on the gas turbine end support seat; 6): Slowly screw the support nut onto the thread; 7): Apply lubricant to the fixing bolts of the compressor end support seat, install the spherical gasket and the spherical valve seat, and insert the fixing bolts into the supporting spherical convex surface of the compressor end support seat to a depth of 10mm; 8): Screw down the fixing bolts of the two compressor end support seats and fix them; 9): Place a temporary hydraulic device on the temporary support at the bottom; 10): Use the hydraulic jack of the temporary hydraulic device to lift the gas turbine by 0.3-0.5mm, so that the compressor end support seat and the gas turbine end support seat are in a non-stress state; 11): Turn off the hydraulic jack, close it with the locking nut, and close the hydraulic valve; 12): Horizontal displacement with a maximum increment of 2 mm: ①. Install a scale to monitor displacement; ②. Loosen the horizontal adjustment bolts on the compressor end support seat; ③. Adjust the four hydraulic jacks to move the gas turbine 2mm in the required direction; ④. Retract the horizontal adjustment bolt on the compressor end support by 2mm; ⑤. Continue the displacement operation until the desired position is reached; ⑥. After reaching the designated position, tighten all locking bolts by hand; ⑦. Hydraulic jack pressure relief; 13): Screw the horizontal adjustment bolt into the thread of the compressor end support seat; 14): Remove the hydraulic jack at the bottom of the gas turbine until the gas turbine end support base contacts the gas turbine; 15): Re-tighten the lock nut to ensure there is no movement; 16): The support screw at the gas turbine end should be installed 10mm toward the exhaust direction and 4mm toward the outside; S4: Burner inspection 1): Preparation work: Before installing the burner, the foundation should be checked according to the drawings and the following requirements should be met before installation: ①. Remove the outer packaging and transfer the burner horizontally to the engine room; ②. Use a truck crane to lift the burner and place it horizontally on the sleepers; ③. Use lifting tools to lift the burner, remove the sleepers, use auxiliary tools to rotate the burner, move the burner to the side of the gas turbine foundation and put it in place; 2): Internal inspection of the burner ①. Determine the position of the inner housing to the center housing flange and check the clearance; ②. Determine the position of the mixing chamber shell and the burner flange, and check the gap; ③. If it is determined that the mixing chamber housing is in the correct position and the clearance is correct, the burner is directly installed on the gas turbine; if the cooling air ring does not contact the inner housing or does not reach the clearance specified in the drawing, adjust the position of the mixing chamber housing; 3): Installation of burner assembly platform; S5: Burner Installation 1) Preparation ①. Remove the transport protection cover of the burner flange; ②. Clean the burner flange and threaded holes; ③. Install the four-section sealing ring parts in the groove of the burner housing flange, check the size of the sealing ring, remove the sealing ring and combine them into a ring for welding, and then grind the weld to make it smooth; 2): Use a crane to hoist the burner. When hoisting, the hoisting point should be located at the position indicated in the drawing and connected with a 32# hoisting ring. Other methods of connection are strictly prohibited; 3): Use a crane to move the burner, slowly move its flange to the engine casing flange and align them, keeping a distance of 100mm between the flanges; 4): Move the burner close to the gas turbine interface until the guide hole of the burner interface flange contacts the guide bolt of the gas turbine interface flange; 5): Adjust the horizontal and vertical position of the burner so that the guide bolts slide into the guide holes on the burner flange, ensuring that the edge of the burner mixing chamber shell does not touch the gas turbine inner shell; 6): Use a ruler to check the parallelism of the two flanges and adjust them until the flanges are parallel, and the parallelism deviation is no more than 2mm; 7): Make the burner parallel to the gas turbine interface flange, clean the connecting bolts and apply grease, and then insert the connecting bolts into the bolt holes; 8): Use a wrench to tighten the connecting bolts at the flange, ensure that the burner flange with the sealing ring is in full contact with the entire area of ​​the center housing flange, and tighten the connecting bolts to a torque of 200Nm; 9): Tighten the connecting bolts in clockwise direction and record the initial gap between the flanges and the gap after tightening; 10): After the burner is installed, open the burner inspection hole, check the gap size of each burner shell according to the drawing size and adjust it; 11): After the burner installation is completed, the assembly platform is removed and the operating platform and associated pipelines are installed; S6: Intermediate shaft installation 1): Position the intermediate shaft bracket according to the drawing, and install the intermediate shaft bracket on the foundation through expansion bolts; 2): Use a crane to lift the intermediate shaft and keep it level, use a frame level to check the level of the intermediate shaft end flange, rotate the support bolts on the intermediate shaft bracket, place the intermediate shaft on the intermediate shaft bracket and the compressor end bearing, rotate the coupling so that the maximum runout position of the intermediate shaft and the gas turbine rotor end face is 180 degrees apart, mark the coupling end face, use a crane to move the intermediate shaft to the gas turbine coupling flange, and let the coupling bolts penetrate the intermediate shaft flange hole; S7: Oil system installation 1): Install the top shaft oil pipeline and lubricating oil pipeline according to the drawing, and the interfaces of all pipelines correspond one to one; 2): Before installing the pipeline, check the internal cleanliness of the pipeline, clean the flange surface in advance, apply molybdenum disulfide grease on the surface of the connecting bolts, and tighten them according to the torque required by the drawing after connection; 3): Temporary flushing bypass of top shaft oil: Use a plug to seal the top shaft oil pipeline interface of the gas turbine, connect the oil inlet pipe and the oil return pipe with a high temperature and high pressure hose, and flush the top shaft oil pipeline of each bearing separately; 4): Temporary flushing bypass of lubricating oil: ①. Install cooler flush bypass: Short-circuit the cooler inlet and outlet pipes; ②. Install filter flushing bypass: Short-circuit the filter inlet and outlet pipes; ③. Lubricating oil pipeline flushing bypass: Use high temperature and high pressure hoses to short-circuit the lubricating oil supply pipes and return pipes of the generator and gas turbine, disconnect the compressor bearing oil supply short pipe, and temporarily fasten the bearing cover; 5): HCO pipeline flushing bypass: According to the requirements of the drawings, use high temperature and high pressure hoses to short-circuit the HCO oil supply pipe and oil return pipe at the compressor end; 6): Carry out oil circulation. After the oil circulation reaches a certain time, take oil samples at the oil drain point. After obtaining a qualified oil quality test report issued by a unit with corresponding qualifications, the oil is flushed through. After the oil circulation flushing is completed, the temporary bypass is removed and the system is restored; S8: Axis centering 1): The top shaft oil pipeline is installed before the shaft system is centered and the oil circulation is qualified; 2): Adjust the position of the generator stator, check and adjust the clearance between the two couplings at both ends of the intermediate shaft; 3): Start the top shaft oil pump and start rotating the rotor; 4): After the rotor reaches the measuring position, stop rotating the rotor, turn off the top shaft oil pump, and wait for the rotor to stop; 5): Measure the clearance between the generator and the intermediate shaft coupling end face in the left, right, top and bottom directions; 6): Measure the clearance between the gas turbine and the intermediate shaft coupling end face in the left, right, top and bottom directions; 7): Calculate the average value of the measured values ​​to ensure that the upper and lower openings of the coupling at the gas turbine end are 0.14±0.02mm, and the left and right openings are 0.00±0.02mm; the upper and lower openings of the coupling at the generator end are 0.09±0.02mm, and the left and right openings are 0.00±0.02mm; 8): Install the coupling bolts and tighten them according to the torque value required by the drawing; S9: Secondary grouting After the shafting is centered, the foundation is grouted for the second time; S10: Generator cover installation 1): Remove the transport cover of the generator, install auxiliary supports on both sides of the generator in advance, clean all foreign objects, and ensure the cleanliness of the generator and the generator cover; 2): Use a truck crane to hoist the generator cover to the open space next to the generator, and then use the truck crane to hoist the components of the generator cover to the generator area one by one, and use a hand chain hoist to adjust the lifting points on the generator cover; 3): Install the lifting device; 4): Slowly place the generator cover onto the auxiliary support, connect the connecting bolts on the top, and tighten them; 5): After tightening the bolts, make sure all contact points are in contact and remove the lifting tools; S11: Generator Cooler Installation 1): Remove the outer packaging of the cooler, and use a truck crane to flip the cooler so that the cooler is in a vertical direction. During the flipping process, the cooler should be protected to prevent the hanger or wire rope from causing damage to the cooler; 2): Use a truck crane to lift the cooler and slowly move it to the installation position from the east side of the generator. Hang a hand chain hoist on the steel structure above the east side of the generator, use the hand chain hoist to pull the cooler, and level and center it. Finally, connect the cooler to the generator and tighten all connecting bolts; 3): Install the heat exchanger and cooler end cover to the cooler in the same way.

2. A heavy-duty gas turbine installation construction method according to claim 1, characterized in that: In step S3, the anchor bolts of the gas turbine end support seat are M64×1015mm T-head bolts, and the anchor bolt sleeves are processed and manufactured on site. Each set of anchor bolt sleeves is connected into a whole using steel and then installed.