Arch crown framed bent groove shell construction support

By setting up support components and Bere beams on the arch bridge below the aqueduct, the construction difficulty of the bridge below the aqueduct is solved, and stable support and convenient construction of the aqueduct are achieved.

CN222083342UActive Publication Date: 2024-11-29CHINA RAILWAY 11TH BUREAU GRP CORP LTD +2
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420590103.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-26
Publication Date
2024-11-29
Estimated Expiration
2034-03-26

AI Technical Summary

Technical Problem

When there is an arch bridge below the aqueduct, it is difficult for the prior art to effectively erect the aqueduct support, resulting in construction difficulties.

Method used

A arch top rack groove shell construction bracket is designed. By setting the support components of the first and second aqueduct pier on the arch bridge and setting the Bere beam along the length of the arch bridge, the groove shell formwork is fixed to the Bere beam. , fits the shape of the arch bridge and provides stable support.

Benefits of technology

This device makes the construction of aqueduct more convenient, effectively solves the problem of difficulty in setting up aqueduct brackets under the shape of arch bridges, and ensures stable support and construction efficiency of the groove shell formwork.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222083342U_ABST
    Figure CN222083342U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of aqueduct construction, and particularly relates to a vault bent frame groove shell construction support which comprises an arch bridge body. The first aqueduct pier body and the second aqueduct pier body are constructed on the arch crown of the arch bridge body, a first supporting assembly is arranged on the first aqueduct pier body, and a second supporting assembly is arranged on the second aqueduct pier body; the bailey beam is fixed to the top of the first supporting assembly and the top of the second supporting assembly. The groove shell template is horizontally arranged along the length direction of the bailey beam, and two ends of the groove shell template are fixed on the bailey beam. The aqueduct pier bodies with different heights are constructed on the arch bridge in combination with the shape of the arch bridge, the supporting assemblies are arranged on the aqueduct pier bodies, the bailey beams are arranged through the supporting assemblies, and finally the aqueduct shell formwork is arranged on the bailey beams. The design of the whole device is matched with the actual shape of the arch bridge, stable supporting can be formed on the aqueduct shell formwork, construction is convenient, and aqueduct construction is facilitated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of aqueduct construction, and in particular relates to an arch top frame trough shell construction support. Background Art

[0002] Aqueducts, also known as elevated canals and water transfer bridges, are usually built over valleys, depressions, rivers and roads, and are often used for water, traffic and navigation. Especially in water conservancy projects, aqueducts can transfer water from far away to towns and rural areas with insufficient water for drinking and irrigation. Most aqueducts are located in areas with complex terrain conditions such as canyons or ravines. In some special terrain conditions, it is difficult to directly construct aqueducts. It is often necessary to first construct a bridge under the aqueduct to be constructed, and then construct aqueduct supports on the bridge to facilitate the subsequent construction of the aqueduct. However, when the bridge under the aqueduct is an arch bridge, the top of the arch bridge is an arc section, and it is more difficult to erect the aqueduct support.

[0003] There are also supporting devices for aqueducts disclosed in the prior art. For example, the patent CN202221694613.6 discloses a support system device for the bottom platform of a cast-in-place aqueduct, including a cap, a steel bench, a steel pipe column, a main beam, a truss, a leveling beam, a vertical pole, a top support, a secondary beam and a bottom formwork. The steel bench is cast on the cap, the steel pipe column is installed on the steel bench, the main beam is laid on the upper end of the steel pipe column, the truss is laid on the main beam, the leveling beam is arranged on the upper part of the truss as the base platform of the upper vertical pole, the vertical pole is arranged on the upper part of the leveling beam, the top support is installed on the top of the vertical pole, the secondary beam is laid on the top support, and the bottom formwork is laid on the secondary beam. The support system device for the bottom platform of a cast-in-place aqueduct disclosed in the patent constitutes the main framework of the support system for the bottom platform of a cast-in-place aqueduct through steel pipe columns, trusses, vertical poles and bottom formwork, which effectively improves the efficiency and quality of the construction of the support system for the cast-in-place aqueduct under complex terrain conditions. It is undeniable that the device disclosed in this patent can indeed achieve the above-mentioned effect, but it is not suitable for terrain where the bridge under the aqueduct is an arch bridge.

[0004] The information disclosed in this background technology section is only intended to increase the understanding of the overall background of the present invention, and should not be regarded as acknowledging or suggesting in any form that the information constitutes the prior art already known to a person skilled in the art. Utility Model Content

[0005] The utility model aims to provide a construction support for an arch frame trough shell to solve the problems existing in the prior art in the background technology.

[0006] In order to achieve the above purpose, the utility model provides the following technical solutions:

[0007] A construction support for an arch frame trough shell, comprising:

[0008] Arch bridge body;

[0009] A first aqueduct pier constructed at a position far from the arch top of the arch bridge body, wherein the first aqueduct pier is provided with a first support assembly with a horizontal top;

[0010] A second aqueduct pier constructed near the arch top of the arch bridge body, wherein the second aqueduct pier is provided with a second support assembly with a horizontal top, and the top of the second support assembly is flush with the top of the first support assembly;

[0011] A Bailey beam arranged along the length direction of the arch bridge body, wherein the Bailey beam is fixed to the top of the first support assembly and the second support assembly;

[0012] A trough shell template is horizontally arranged along the length direction of the Bailey beam, and both ends of the trough shell template are fixed on the Bailey beam.

[0013] Preferably, the first supporting assembly includes a concrete pad arranged on the first aqueduct pier, a first longitudinal beam arranged on the top of the concrete pad, a first transverse beam fixed to the top of the first longitudinal beam, a second longitudinal beam fixed to the top of the first transverse beam, and a first distribution beam fixed to the top of the second longitudinal beam; wherein the first distribution beam is arranged horizontally and perpendicular to the second longitudinal beam.

[0014] Preferably, the first supporting assembly further comprises tension threaded rods, which are symmetrically arranged on both sides of the first aqueduct pier, the tops of the tension threaded rods are fixed to the first transverse beams by nuts, and the bottoms of the tension threaded rods are fixed in the first aqueduct pier after passing through the first transverse beams, the first longitudinal beams and the concrete pad.

[0015] Preferably, the second support assembly includes a second transverse beam arranged on the second aqueduct pier, a third longitudinal beam fixed to the top of the second transverse beam, a vertical support frame fixed to the top of the third longitudinal beam, and a second distribution beam fixed to the top of the vertical support frame.

[0016] Preferably, the vertical support frame has diagonal braces fixed inside and stiffening plates fixed outside.

[0017] Preferably, a third distribution beam perpendicular to the length direction of the Bailey beam is fixed on the top of the Bailey beam, and a protective fence is provided at the end of the third distribution beam; a fourth distribution beam perpendicular to the third distribution beam is fixed on the top of the third distribution beam.

[0018] Preferably, the trough shell template consists of an outer template and an inner template, and a gap is left between the outer template and the inner template; a template truss is arranged outside the outer template, and the bottom of the template truss is fixed to the top of the fourth distribution beam.

[0019] Compared with the prior art, the utility model has the following beneficial effects:

[0020] The utility model is based on solving the problem that it is difficult to erect aqueduct supports when the bridge below the aqueduct is an arch bridge. In combination with the shape of the arch bridge, aqueduct piers of different heights are constructed on the arch bridge, and support components are set on the aqueduct piers. Bailey beams are set with the support components, and finally the trough shell template is set on the Bailey beam. The design of the entire device fits the actual shape of the arch bridge, can form a stable support for the trough shell template, and is easy to construct, which is conducive to the construction of the aqueduct, and can effectively solve the problem that it is difficult to erect aqueduct supports when the bridge below the aqueduct is an arch bridge. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0022] Figure 2 It is a structural schematic diagram of the first aqueduct pier of the utility model;

[0023] Figure 3 It is a structural schematic diagram of the second aqueduct pier of the utility model.

[0024] Description of main reference numerals:

[0025] 100. Arch bridge body;

[0026] 200, the first aqueduct pier;

[0027] 300, first support assembly; 301, concrete pad; 302, first longitudinal beam; 303, first transverse beam; 304, second longitudinal beam; 305, first distribution beam; 306, tension threaded rod;

[0028] 400, the second aqueduct pier;

[0029] 500, second support assembly; 501, second transverse beam; 502, third longitudinal beam; 503, vertical support frame; 5031, diagonal brace; 5032, stiffening plate; 504, second distribution beam;

[0030] 600, Bailey beam; 601, third distribution beam; 602, protective fence; 603, fourth distribution beam;

[0031] 700, trough shell formwork; 701, outer formwork; 702, inner formwork; 703, formwork truss; 704, first inner formwork support; 705, second inner formwork support. DETAILED DESCRIPTION

[0032] The following is a clear and complete description of the technical solution of the utility model patent. Obviously, the described embodiments are part of the embodiments of the utility model, not all of them. Based on the embodiments of the utility model, all other embodiments obtained by technicians in this field without creative work are within the scope of protection of the utility model.

[0033] Example

[0034] See attached Figure 1-3 , a construction support for an arch frame trough shell, comprising:

[0035] Arch bridge body 100;

[0036] The first aqueduct pier 200 is constructed at a position far from the arch top of the arch bridge body 100, and a first support assembly 300 with a horizontal top is provided on the first aqueduct pier 200; specifically, the first support assembly 300 includes a concrete cushion 301 provided on the first aqueduct pier 200, a first longitudinal beam 302 provided on the top of the concrete cushion 301, a first transverse beam 303 fixed to the top of the first longitudinal beam 302, a second longitudinal beam 304 fixed to the top of the first transverse beam 303, and a first distribution beam 305 fixed to the top of the second longitudinal beam 304; wherein, the first The distribution beam 305 is arranged horizontally and perpendicular to the second longitudinal beam 304; more specifically, the first support assembly 300 further includes tension threaded rods 306, which are symmetrically arranged on both sides of the first aqueduct pier 200, the top of the tension threaded rods 306 is fixed to the first transverse beam 303 by nuts, and the bottom of the tension threaded rods 306 penetrates the first transverse beam 303, the first longitudinal beam 302 and the concrete pad 301 and is then fixed in the first aqueduct pier 200, and the first transverse beam 303 and the first longitudinal beam 302 can be fixed more firmly by means of the tension threaded rods 306;

[0037] A second aqueduct pier 400 is constructed near the arch top of the arch bridge body 100. A second support assembly 500 with a horizontal top is provided on the second aqueduct pier 400. The top of the second support assembly 500 is flush with the top of the first support assembly 300. Specifically, the second support assembly 500 includes a second transverse beam 501 provided on the second aqueduct pier 400, a third longitudinal beam 502 fixed to the top of the second transverse beam 501, a vertical support frame 503 fixed to the top of the third longitudinal beam 502, and a second distribution beam 504 fixed to the top of the vertical support frame 503. More specifically, a diagonal brace 5031 is fixed inside the vertical support frame 503, and a stiffening plate 5032 is fixed outside the vertical support frame 503. The diagonal brace 5031 and the stiffening plate 5032 can increase the load-bearing capacity of the vertical support frame 503, and improve the stability and reliability of the vertical support frame 503.

[0038] A Bailey beam 600 is arranged along the length direction of the arch bridge body 100, and the Bailey beam 600 is fixed to the top of the first support assembly 300 and the second support assembly 500; a third distribution beam 601 perpendicular to the length direction is fixed to the top of the Bailey beam 600, and a protective fence 602 is arranged at the end of the third distribution beam 601; a fourth distribution beam 603 perpendicular to the third distribution beam 601 is fixed to the top of the third distribution beam 601;

[0039] The trough shell template 700 is horizontally arranged along the length direction of the Bailey beam 600, and both ends of the trough shell template 700 are fixed on the Bailey beam 600; the trough shell template 700 is composed of an outer template 701 and an inner template 702, and a gap is left between the outer template 701 and the inner template 702; a template truss 703 is arranged outside the outer template 701, and the bottom of the template truss 703 is fixed to the top of the fourth distribution beam 603. It should be noted here that a first inner mold support 704 is arranged inside the inner template 702, and a second inner mold support 705 is arranged on the top of the outer template 701.

[0040] During construction, the aqueduct piers corresponding to the aqueduct to be constructed are constructed on the arch bridge body 100, wherein the aqueduct piers 200 are defined as those constructed at a position far from the arch top of the arch bridge body 100, and the aqueduct piers 400 are defined as those constructed at a position close to the arch top of the arch bridge body 100. Then, the first support assembly 300 and the second support assembly 500 are constructed on the first aqueduct pier 200 and the second aqueduct pier 400 respectively, and then the Bailey beam 600 is fixed to the top of the first support assembly 300 and the second support assembly 500, and the third distribution beam 601, the protective fence 602 and the fourth distribution beam 603 are arranged on the Bailey beam 600; then the trough shell formwork 700 is constructed, and finally, concrete is poured into the gap left between the outer formwork 701 and the inner formwork 702, and the aqueduct is formed by demoulding after curing.

[0041] The foregoing description of specific exemplary embodiments of the utility model is for the purpose of illustration and illustration. These descriptions are not intended to limit the utility model to the precise form disclosed, and it is clear that many changes and variations can be made based on the above teachings. The purpose of selecting and describing the exemplary embodiments is to explain the specific principles of the utility model and its practical application, so that those skilled in the art can realize and utilize various different exemplary embodiments of the utility model and various different options and changes. The scope of the utility model is intended to be defined by the claims and their equivalents.

Claims

1. A construction support for an arch frame trough shell, characterized in that: include: Arch bridge body; A first aqueduct pier constructed at a position far from the arch top of the arch bridge body, wherein the first aqueduct pier is provided with a first support assembly with a horizontal top; A second aqueduct pier constructed near the arch top of the arch bridge body, wherein the second aqueduct pier is provided with a second support assembly with a horizontal top, and the top of the second support assembly is flush with the top of the first support assembly; A Bailey beam arranged along the length direction of the arch bridge body, wherein the Bailey beam is fixed to the top of the first support assembly and the second support assembly; A trough shell template is horizontally arranged along the length direction of the Bailey beam, and both ends of the trough shell template are fixed on the Bailey beam.

2. The arch frame trough shell construction support according to claim 1 is characterized in that: The first supporting assembly includes a concrete pad arranged on the first aqueduct pier, a first longitudinal beam arranged on the top of the concrete pad, a first transverse beam fixed to the top of the first longitudinal beam, a second longitudinal beam fixed to the top of the first transverse beam, and a first distribution beam fixed to the top of the second longitudinal beam; wherein the first distribution beam is arranged horizontally and perpendicular to the second longitudinal beam.

3. The arch frame trough shell construction support according to claim 2 is characterized in that: The first supporting assembly also includes tension threaded rods, which are symmetrically arranged on both sides of the first aqueduct pier. The tops of the tension threaded rods are fixed to the first transverse beams by nuts, and the bottoms of the tension threaded rods are fixed in the first aqueduct pier after passing through the first transverse beams, the first longitudinal beams and the concrete pad.

4. The arch frame trough shell construction support according to claim 1, characterized in that: The second support assembly includes a second transverse beam arranged on the second aqueduct pier, a third longitudinal beam fixed to the top of the second transverse beam, a vertical support frame fixed to the top of the third longitudinal beam, and a second distribution beam fixed to the top of the vertical support frame.

5. The arch frame trough shell construction support according to claim 4 is characterized in that: The vertical support frame is internally fixed with an oblique brace and externally fixed with a stiffening plate.

6. The arch frame trough shell construction support according to claim 1, characterized in that: A third distribution beam perpendicular to the length direction of the Bailey beam is fixed on the top of the Bailey beam, and a protective fence is arranged at the end of the third distribution beam; A fourth distribution beam perpendicular to the third distribution beam is fixed on the top of the third distribution beam.

7. The arch frame trough shell construction support according to claim 6, characterized in that: The trough shell template is composed of an outer template and an inner template, and a gap is left between the outer template and the inner template; a template truss is arranged outside the outer template, and the bottom of the template truss is fixed to the top of the fourth distribution beam.