A multi-layer double-beam cantilevered shoulder pole type lifting platform for vertical shaft equipment installation
By designing a multi-layer double-beam cantilevered pole hanging disk, the problems of large size, heavy weight and safety risks in the existing technology are solved, and the lightweight hanging disks, enhanced structural strength and improved construction safety are achieved.
Patent Information
- Application Number
- CN202010558285.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-06-18
- Publication Date
- 2025-02-18
- Estimated Expiration
- 2040-06-18
AI Technical Summary
In the installation and construction of large wellbore equipment, the hanging plate is large in size and heavy in weight. It is difficult to open the large fold during use, and it cannot adapt to complex construction environments, and it poses high safety risks.
Design a multi-layer double-beam cantilevered pole-type hanging disk, including a multi-layer main hanging disk and a secondary hanging disk, connected by cantilevered I-beam and secondary hanging disk columns, and set up the main hanging disk folding and secondary hanging disk folding. Pages form an overall work surface, reduce the maximum folding page volume, and enhance structural strength.
The hanging disk is lightweight and structural strength is enhanced, which reduces the quantity of equipment and materials and energy consumption, reduces construction risks, and improves construction speed and safety.
Smart Images

Figure CN111520143B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of mining hanging platforms, and in particular relates to a multi-layer double-beam cantilevered shoulder pole type hanging platform for installing shaft equipment. Background Art
[0002] In China, large-scale wellbore equipment installation and construction mostly adopts round hoisting plates. This type of hoisting plate has many problems such as large size, heavy weight, and difficulty in opening the large hinges during use. It cannot adapt well to the complex construction environment of symmetrical arrangement of double lifting facilities in large wellbore (diameter above 8m). Due to the large number of components in the wellbore and limited construction space, the construction hoisting plate has to adopt the mode of main plate plus movable hinges to ensure the construction space. At the same time, in order to ensure that the lifting plate is not affected, the main plate is generally small and the movable hinges are large. The large movable hinges also bring higher safety risks. After the installation of the wellbore equipment steel components is completed, the wellbore is divided into multiple areas. If the hoisting plate is used for maintenance or cable laying, the large hinges on both sides of the hoisting plate must be removed. The construction personnel must go up to the steel components to carry out construction, which increases the safety risk. There is also a kind of construction hoisting plate that uses multiple ropes to hang the main hoisting plate and the sub-hoisting plate respectively. It uses more well drilling winches and lifting wire ropes, consumes more electricity, and has poor economic benefits. Summary of the invention
[0003] In order to overcome the shortcomings of the above-mentioned prior art, the present invention provides a multi-layer double-beam cantilevered shoulder-pole type lifting platform for the installation of vertical shaft equipment, so as to realize fast and safe shaft installation operations, achieve lightweight lifting platform, enhance the structural strength of the lifting platform, reduce operation risks, and reduce the number of equipment and materials and energy consumption.
[0004] The present invention is realized through the following technical scheme: a multi-layer double-beam cantilevered shoulder pole type lifting platform for installing shaft equipment, comprising at least a first-layer lifting platform as a protection platform and a second-layer lifting platform, a third-layer lifting platform, a fourth-layer lifting platform and a fifth-layer lifting platform as working platforms; each layer of the lifting platform comprises a main lifting platform and an auxiliary lifting platform, both of which are square structures, and the auxiliary lifting platform comprises an auxiliary lifting platform I and an auxiliary lifting platform II, and the auxiliary lifting platform I and the auxiliary lifting platform II are symmetrically arranged on both sides of the main lifting platform; all of the main lifting platforms are fixedly connected through main lifting platform columns, two cantilevered I-beams are fixed under the main lifting platform of the first-layer lifting platform, and auxiliary lifting platform columns are fixed on both sides of the cantilevered I-beams, and all of the auxiliary lifting platforms I and all of the auxiliary lifting platforms II are It is fixedly connected by corresponding auxiliary hanging plate columns; main hanging plate hinges are provided between the main hanging plate and auxiliary hanging plate I, as well as between the main hanging plate and auxiliary hanging plate II; the hanging plates on adjacent floors are connected by escalators; it also includes an air supply pipeline system and a compressed air pipeline system, the air supply pipeline system includes oxygen cylinders, acetylene cylinders, oxygen pipelines and acetylene pipelines, the oxygen cylinders and acetylene cylinders are arranged on the main hanging plate of the first floor, the oxygen pipelines and acetylene pipelines are laid along the main hanging plate columns, and the oxygen pipelines and acetylene pipelines are provided with multiple sets of quick interfaces on each hanging plate; the compressed air pipeline system includes a compressed air bag and a compressed air pipeline, the compressed air bag is arranged on the main hanging plate of the first floor, the compressed air pipeline is laid along the main hanging plate columns, and multiple sets of compressed air quick connectors are provided on each hanging plate.
[0005] Furthermore, the hinges include a main hanging tray hinge installed on the main hanging tray and a secondary hanging tray hinge installed on the secondary hanging tray.
[0006] Furthermore, the cantilevered I-beam is installed below the main hanging plate of the first-level hanging plate by means of U-bolts.
[0007] Furthermore, the main hanging plate and the auxiliary hanging plate are assembled and welded into a square structure using channel steel and patterned steel plates.
[0008] Furthermore, the main suspension plate columns and the auxiliary suspension plate columns are both formed by welding channel steel or steel pipes and steel plates.
[0009] Furthermore, a sunken tool box is provided on the main hanging tray, and a cover plate of the sunken tool box is flush with the surface of the main hanging tray.
[0010] Furthermore, a plurality of through holes are drilled on the bottom plate of the sunken tool box.
[0011] Furthermore, the cover plate is a double-leaf folding door.
[0012] Furthermore, the auxiliary hanging trays of the first layer hanging tray, the second layer hanging tray and the third layer hanging tray are also provided with auxiliary hanging tray folding pages, and the folding pages of all the auxiliary hanging trays of each layer are opened so that the entire tray surface is combined into a circle.
[0013] The beneficial effects of the present invention are as follows: in the construction of large-diameter, double-lifting equipment and complex vertical shaft equipment, the present application can minimize the area of the maximum folding of the lifting platform, reduce the influence of the steel components in the shaft on the lifting platform's rise and fall; reduce the stress of the lifting platform's folding, and enhance the structural strength of the lifting platform; increase the safety performance of the lifting platform's edge operations, and ensure the safety of edge tank and pipeline installers. The present application solves the problems of the traditional large-scale double-lifting system shaft equipment using a split lifting platform, which requires a large number of well-drilling winch equipment, a large number of hanging wire ropes, and high costs. It has a centralized air supply pipeline system and a compressed air pipeline system to reduce the length of the pipeline used, and the sunken tool box can save the lifting platform space. The use of this construction lifting platform for vertical shaft equipment construction has fast speed, good working conditions, high labor time utilization, and is conducive to safe construction and improving the quality of vertical shaft equipment installation projects. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a structural elevation view of the present invention;
[0015] Figure 2 It is a plan view of the present invention without folding pages;
[0016] Figure 3 It is a three-dimensional diagram of the sinking tool box of the present invention;
[0017] Figure 4 It is a schematic perspective view of the hanging plate of the present invention;
[0018] In the figure, 1. main lifting platform, 2. cantilevered I-beam, 3. auxiliary lifting platform I, 4. auxiliary lifting platform II, 5. main lifting platform column, 6. auxiliary lifting platform column, 7. sunken tool box, 7-1, cover plate, 8. main lifting platform folding, 9. auxiliary lifting platform folding, 10. wire rope. DETAILED DESCRIPTION
[0019] The present invention is further described below with reference to the accompanying drawings and embodiments.
[0020] like Figures 1 to 4As shown, a multi-layer double-beam cantilevered shoulder-pole type lifting platform for installing shaft equipment of a vertical shaft comprises at least a first-layer lifting platform as a protective platform and a second-layer lifting platform, a third-layer lifting platform, a fourth-layer lifting platform and a fifth-layer lifting platform as working platforms. The number of working platforms can be increased or decreased according to actual usage requirements. Each layer of the lifting platform comprises a main lifting platform 1 and an auxiliary lifting platform, and both the main lifting platform 1 and the auxiliary lifting platform are square structures. More specifically, the main lifting platform 1 and the auxiliary lifting platform are assembled and welded into a square structure by using channel steel and patterned steel plates, and channel steels are fixed around the patterned steel plates. Wherein, the auxiliary hanging plate comprises auxiliary hanging plate Ⅰ3 and auxiliary hanging plate Ⅱ4, and auxiliary hanging plate Ⅰ3 and auxiliary hanging plate Ⅱ4 are symmetrically arranged on both sides of the main hanging plate 1; all of the main hanging plates 1 are fixedly connected through the main hanging plate columns 5 (the main hanging plate columns 5 here can be an integral structure or composed of multiple sections, and each section of the main hanging plate columns 5 is used to fix the adjacent main hanging plates 1), and two cantilevered I-beams 2 are fixed below the main hanging plate 1 of the first layer of the hanging plate, and the cantilevered I-beams 2 are installed below the main hanging plate 1 of the first layer of the hanging plate through U-shaped bolts, and auxiliary hanging plate columns 6 are fixed on both sides of the cantilevered I-beams 2, and all of the auxiliary hanging plates Ⅰ3 and all of the auxiliary hanging plates Ⅱ4 are fixedly connected through the corresponding auxiliary hanging plate columns 6 (same as the main hanging plate columns 5, the auxiliary hanging plate columns 6 can be an integral structure or composed of multiple sections); the main hanging plate 1, auxiliary hanging plate Ⅰ3 and auxiliary hanging plate Ⅱ4 of each layer can be used as Independent platform construction, main hoisting tray 1 and auxiliary hoisting tray Ⅰ3 and main hoisting tray 1 and auxiliary hoisting tray Ⅱ4 are all provided with main hoisting tray folding 8, opening the main hoisting tray folding 8 can make the main hoisting tray 1 and auxiliary hoisting tray of the same floor be connected to form an integral work surface; the hoisting trays of adjacent floors are connected by escalators, and the escalators are arranged on the main hoisting tray 1; it also includes an air supply pipeline system and a compressed air pipeline system, the air supply pipeline system includes oxygen cylinders, acetylene cylinders, oxygen pipelines and acetylene pipelines, oxygen cylinders and acetylene cylinders are arranged on the main hoisting tray 1 of the first floor, oxygen pipelines and acetylene pipelines are laid along the main hoisting tray columns 5, and oxygen pipelines and acetylene pipelines are provided with multiple sets of quick interfaces on each floor of the hoisting tray; the compressed air pipeline system includes a compressed air bag and a compressed air pipeline, the compressed air bag is arranged on the main hoisting tray 1 of the first floor of the hoisting tray, the compressed air pipeline is laid along the main hoisting tray columns 5, and multiple sets of compressed air quick connectors are provided on each floor of the hoisting tray.
[0021] As a preferred embodiment of the present invention, the folding leaf comprises a main hanging tray folding leaf 8 installed on the main hanging tray 1 and a secondary hanging tray folding leaf 9 installed on the secondary hanging tray. The main hanging tray folding leaf 8 on the main hanging tray 1 and the secondary hanging tray folding leaf 9 on the secondary hanging tray are unfolded at the same time and spliced into a whole, so that the main hanging tray 1 and the secondary hanging tray on the same layer of the hanging tray form an integral work surface.
[0022] Furthermore, the main suspension plate column 5 and the auxiliary suspension plate column 6 are both formed by welding channel steel or steel pipe and steel plate.
[0023] As a preferred embodiment of this embodiment, a sunken tool box 7 for storing tools is provided on the main hanging tray 1, and the cover plate 7-1 of the sunken tool box 7 is flush with the plate surface of the main hanging tray 1 to avoid affecting the work. Furthermore, a plurality of through holes are drilled in the bottom plate of the sunken tool box 7, and the through holes can prevent water from accumulating in the sunken tool box 7. Furthermore, the cover plate 7-1 is a double-opening hinged door, making it more convenient to open the cover plate 7-1.
[0024] The auxiliary lifting trays of the first-layer lifting tray, the second-layer lifting tray and the third-layer lifting tray are also provided with auxiliary lifting tray folding pages 9. When all the auxiliary lifting tray folding pages 9 of each layer are opened, the entire tray surface is combined into a circle. The lifting tray suspension connection device on the main lifting tray 1 of the first-layer lifting tray is suspended by four steel wire ropes 10. A well-drilling winch is arranged on the ground to wind the steel wire ropes 10. The well-drilling winch is started to make the entire lifting tray rise and fall in the vertical shaft according to the working requirements. The first-layer lifting tray is a protection tray. A signal room and electrical equipment and air supply and wind supply equipment are arranged on the main lifting tray 1 of the first-layer lifting tray, and it serves as a command working tray during unloading and lifting of the lifting tray. The second-layer and third-layer lifting trays are used as working trays for drilling anchor holes, installing anchors, brackets, tankway beams, pipeline beams, tankways, cable brackets, ladder beams and platform plates during the construction of shaft equipment. They can also be used together with the first-layer tray as working trays for cable clamping. The fourth and fifth lifting trays are working trays for installing tanks, pipelines, ladders and fences between ladders, and can also be used as working trays for placing cables during cable laying. The inter-layer spacing of the fifth-layer lifting tray is the same as the inter-layer spacing designed for the standard section of the shaft equipment. The main lifting tray 1 is provided with an escalator hole, and a flip-up movable cover is provided on the escalator hole to prevent people and objects from falling. At the same time, the main lifting tray 1 is reserved with a well equipment construction reference line hole. Escalators are provided between all the main lifting trays 1, and there are anti-fall protection rings on the escalators. Safety protection fences are set around the fourth and fifth-layer lifting trays, and skirting boards are provided under the protection fences to prevent people or small objects from falling.
[0025] After the vertical shaft equipment is constructed using the one-time forming method from bottom to top, the hoisting platform is lifted to the wellhead. At this time, the main hoisting platform can be separated from the auxiliary hoisting platform. The drilling winch used to lift the tankway and pipeline during the installation of the shaft equipment can be used to lift the auxiliary hoisting platform separately through secondary winching. Then, the main hoisting platform and the auxiliary hoisting platform can be independently lifted in the shaft to facilitate tankway maintenance, cable laying and other work.
[0026] This application can minimize the area of the maximum folding of the hoisting platform during the construction of large-diameter, double-lifting equipment and complex vertical shaft equipment, reduce the impact of steel components in the shaft on the rise and fall of the hoisting platform; reduce the stress of the hoisting platform folding, and enhance the structural strength of the hoisting platform; increase the safety performance of the hoisting platform edge operation, and ensure the safety of edge tank and pipeline installers. This application solves the problems of the traditional large-scale double-lifting system shaft equipment using a split hoisting platform, which requires a large number of well-drilling winch equipment, a large number of hanging wire ropes, and high costs. It has a centralized air supply pipeline system and a compressed air pipeline system to reduce the length of the pipeline used, and the sunken tool box can save the hoisting platform space. The use of this construction hoisting platform for vertical shaft equipment construction has fast speed, good working conditions, high labor time utilization, and is conducive to safe construction and improving the quality of vertical shaft equipment installation projects.
Claims
1. A multi-layer double-beam cantilevered shoulder pole type hanging platform for vertical shaft equipment installation, characterized in that: The invention comprises at least a first-layer hanging plate as a protective plate and a second-layer hanging plate, a third-layer hanging plate, a fourth-layer hanging plate and a fifth-layer hanging plate as working plates; each layer of the hanging plate comprises a main hanging plate (1) and an auxiliary hanging plate, the main hanging plate (1) and the auxiliary hanging plate are both of square structure, the auxiliary hanging plate comprises an auxiliary hanging plate I (3) and an auxiliary hanging plate II (4), the auxiliary hanging plate I (3) and the auxiliary hanging plate II (4) are symmetrically arranged on both sides of the main hanging plate (1); all the main hanging plates (1) are fixedly connected by main hanging plate columns (5), two cantilevered I-beams (2) are fixed below the main hanging plate (1) of the first-layer hanging plate, and auxiliary hanging plate columns (6) are fixed on both sides of the cantilevered I-beams (2), and all the auxiliary hanging plates I (3) and all the auxiliary hanging plates II (4) are connected by corresponding auxiliary hanging plate columns (6). ) fixedly connected; main hoisting tray folding pages (8) are provided between the main hoisting tray (1) and auxiliary hoisting tray I (3) and between the main hoisting tray (1) and auxiliary hoisting tray II (4); the hoisting trays on adjacent floors are connected by escalators; it also includes an air supply pipeline system and a compressed air pipeline system, the air supply pipeline system includes oxygen cylinders, acetylene cylinders, oxygen pipelines and acetylene pipelines, the oxygen cylinders and acetylene cylinders are arranged on the main hoisting tray (1) of the first floor, the oxygen pipelines and acetylene pipelines are laid along the main hoisting tray columns (5), and the oxygen pipelines and acetylene pipelines are provided with multiple sets of quick connectors on each floor of the hoisting tray; the compressed air pipeline system includes a compressed air bag and a compressed air pipeline, the compressed air bag is arranged on the main hoisting tray (1) of the first floor of the hoisting tray, the compressed air pipeline is laid along the main hoisting tray columns (5), and multiple sets of compressed air quick connectors are provided on each floor of the hoisting tray; The cantilevered I-beam (2) is installed below the main hanging plate (1) of the first-layer hanging plate by means of U-bolts; Auxiliary hanging tray folding pages (9) are also provided on the auxiliary hanging trays of the first layer hanging tray, the second layer hanging tray and the third layer hanging tray. When all the auxiliary hanging tray folding pages (9) of each layer are opened, the entire tray surface is combined into a circle.
2. The multi-layer double-beam cantilevered shoulder pole type hanging platform for vertical shaft equipment installation according to claim 1 is characterized in that: The main hanging plate (1) and the auxiliary hanging plate are both assembled and welded into a square structure using channel steel and patterned steel plates.
3. The multi-layer double-beam cantilevered shoulder pole type hanging platform for vertical shaft equipment installation according to claim 1 is characterized in that: The main hanging plate column (5) and the auxiliary hanging plate column (6) are both formed by welding channel steel and steel plate.
4. The multi-layer double-beam cantilevered shoulder pole type hanging platform for vertical shaft equipment installation according to claim 1 is characterized in that: A sunken tool box (7) is provided on the main hanging plate (1), and a cover plate (7-1) of the sunken tool box (7) is flush with the plate surface of the main hanging plate (1).
5. The multi-layer double-beam cantilevered shoulder pole type hanging platform for vertical shaft equipment installation according to claim 4 is characterized in that: The bottom plate of the sunken tool box (7) is drilled with a plurality of through holes.
6. The multi-layer double-beam cantilevered shoulder pole type hanging platform for vertical shaft equipment installation according to claim 4, characterized in that: The cover plate (7-1) is a biparting folding door.
Citation Information
Patent Citations
Six-layer construction hoisting platform for shaft equipment installation
CN102287192A
Multilayer double-beam overhanging shoulder pole type hanging scaffold for vertical shaft equipment installation
CN212359759U