A column construction method
By pouring columns in sections, the first section of the column is poured first, and then the second section is poured when it is initially condensed, which solves the problems of low process efficiency and high formwork pressure in the existing technology, and simplifies the construction process and improves The effect of efficiency.
Patent Information
- Application Number
- CN202210316039.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-03-28
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2042-03-28
AI Technical Summary
In the prior art, the process of section casting columns is inefficient and the construction process is cumbersome, while one-time casting can easily lead to the rise of the formwork and cause quality accidents.
Using the segmented pouring method, first pour the first section of the concrete of the column, and then pour the second section when it is initially set. The number of columns to be poured in the same batch is determined based on the concrete pouring time and initial set time, and the second section is reached. Remove the template when preset strength.
The construction process is simplified, construction efficiency is improved, lateral pressure is reduced, and quality accidents caused by the rise of the formwork is avoided.
Smart Images

Figure CN114809632B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a column construction method. Background Art
[0002] In building construction, in order to ensure the quality of the common tall column concrete pouring, two-stage pouring and one-time pouring are usually used for pouring. However, the two-stage pouring construction process is usually accompanied by the disadvantages of long construction period, complicated construction process (need to roughen, inspect in sections), and slightly poor molding quality at the joints. The one-time pouring construction process is simple to construct and has a short construction period, but it is very easy to cause the template to expand due to the lateral pressure caused by the high height of the concrete pouring, resulting in quality accidents.
[0003] Therefore, the prior art still needs to be improved and developed. Summary of the invention
[0004] The technical problem to be solved by the present invention is to provide a column construction method in view of the shortcomings of the prior art, so as to solve the problems in the prior art of low casting efficiency and complicated construction process during segmented casting, and easy generation of large lateral pressure causing the formwork to expand during one-time casting of columns.
[0005] In order to solve the above technical problems, the technical solution adopted by the present invention is as follows:
[0006] A column construction method, comprising:
[0007] Concrete is poured sequentially on the first section of each column to be poured in the same batch of columns to be poured;
[0008] When the concrete of the first section of the column to be cast begins to set, the second section of the column to be cast is cast.
[0009] The column construction method, wherein before sequentially pouring concrete on the first section of each column to be poured in the same batch of columns to be poured, further comprises:
[0010] Determine the number of columns to be poured in the same batch based on the concrete pouring time and initial setting time of the columns.
[0011] The column construction method, wherein before determining the number of columns to be cast in the same batch according to the concrete pouring time and the initial setting time of the concrete, further comprises:
[0012] A trial casting of a column to be cast is performed to obtain the concrete casting time and the concrete initial setting time.
[0013] The column construction method, wherein before determining the number of columns to be cast in the same batch according to the concrete pouring time and the initial setting time of the concrete, further comprises:
[0014] Set up column formwork around the steel bars of the columns to be cast;
[0015] The steel bars and the column formwork are inspected and accepted.
[0016] The column construction method, wherein in the step of determining the number of columns to be cast in the same batch according to the concrete pouring time and the initial setting time of the columns: the number of columns to be cast in the same batch is: N = (T / t) + 1
[0017] Among them, T is the initial setting time of concrete, and t is the concrete pouring time.
[0018] Wherein, when the concrete of the first section of the column to be cast has initially set, in the step of casting the second section of the column to be cast: the first section and the second section are both half of the total height of the column to be cast.
[0019] The column construction method, wherein when the concrete of the first section of the column to be cast begins to set, after casting the second section of the column to be cast, further comprises: when the concrete of the second section reaches a preset strength, disassembling the column formwork.
[0020] Beneficial effects: In the present invention, since the second section is cast when the concrete of the first section of the column to be cast is initially set, the concrete of the second section can be perfectly connected with the concrete of the first section, and there is no need to perform roughening and acceptance after casting the first section, which greatly simplifies the construction process and improves the construction efficiency. In addition, the concrete in the first section of the concrete to be cast transmits mainly vertical pressure after initial setting, and the pressure on the side formwork is relatively small. When the second section is cast, only the second section is liquid concrete, and the side pressure generated is relatively small, which will not cause the formwork to expand and cause quality accidents. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 A flow chart of the column construction method provided by the present invention;
[0022] Figure 2 It is a schematic diagram of the construction sequence of the columns to be cast in the same batch during the construction of the columns provided by the present invention. DETAILED DESCRIPTION
[0023] The present invention provides a column construction method. In order to make the purpose, technical solution and effect of the present invention clearer and more specific, the present invention is further described in detail with reference to the accompanying drawings and examples. It should be understood that the specific embodiments described here are only used to explain the present invention and are not used to limit the present invention.
[0024] It should be noted that when a component is referred to as being "fixed to" or "disposed on" another component, it can be directly on the other component or indirectly on the other component. When a component is referred to as being "connected to" another component, it can be directly connected to the other component or indirectly connected to the other component.
[0025] It should also be noted that the same or similar numbers in the drawings of the embodiments of the present invention correspond to the same or similar parts; in the description of the present invention, it should be understood that if the terms "upper", "lower", "left", "right" and the like indicate directions or positional relationships based on the directions or positional relationships shown in the drawings, it is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction. Therefore, the terms describing the positional relationship in the drawings are only used for illustrative purposes and cannot be understood as limitations on this patent. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.
[0026] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0027] The invention is further described below by describing embodiments in conjunction with the accompanying drawings.
[0028] This embodiment provides a column construction method, such as Figure 1 As shown, the column construction method includes:
[0029] S10, pouring concrete in sequence on the first section of each column to be poured in the same batch of columns to be poured;
[0030] S20. When the concrete of the first section of the column to be cast begins to set, the second section of the column to be cast is cast.
[0031] In this embodiment, the columns to be cast are cast in sections. Specifically, the casting is divided into two sections, namely, the first section located at the lower part of the column to be cast and the second section located at the upper part. At the same time, in building construction, a large number of columns are usually cast. Therefore, in this embodiment, all the columns to be cast are cast in batches, and the same number of columns are cast in each batch to improve the construction efficiency. During the casting, Figure 2 As shown, the first sections of the columns to be cast in the same batch of columns to be cast are first poured with concrete, and when the concrete of the first section of the columns to be cast is initially set, the second section of the columns to be cast is poured. Since the second section is poured when the concrete of the first section of the columns to be cast is initially set, the concrete of the second section can be perfectly connected with the concrete of the first section, and there is no need to perform roughening and acceptance after pouring the first section, which greatly simplifies the construction process and improves the construction efficiency; in addition, since the concrete in the first section of the concrete to be cast is in a semi-solidified state after initial setting, the main pressure transmitted is vertical pressure, which is different from liquid concrete that transmits pressure in all directions. Therefore, the pressure on the side formwork is relatively small. When the second section is poured with concrete, only the second section is liquid concrete, and the lateral pressure generated by the liquid concrete is relatively small, which will not cause the formwork to expand and cause quality accidents.
[0032] When the concrete of the first section of the column to be cast begins to set, in the step of casting the second section of the column to be cast, the first section and the second section are both half of the total height of the column to be cast. In this way, the lateral pressure on the column template during the casting of concrete for the first section and the second section can be equal, and the maximum value of the lateral pressure on the column template during the segmented casting can be reduced as much as possible.
[0033] Before pouring concrete for the columns to be poured in the same batch, it is also necessary to determine the number of columns to be poured in the same batch, so that when the columns to be poured in the same batch are poured in sections, they can be well connected, and the concrete of the first section of the columns of the same batch will not reach the initial setting state before the first section is fully poured due to too many columns to be poured in the same batch, and it will not take a long time for the concrete of the first section to reach the initial setting state after the first section of the columns of the same batch is fully poured due to too few columns to be poured in the same batch, thereby wasting construction time and reducing construction efficiency.
[0034] Therefore, before sequentially pouring concrete on the first section of each column to be poured in the same batch of columns to be poured, the method further includes: determining the number of columns to be poured in the same batch according to the concrete pouring time of the column and the initial setting time of the concrete. Specifically, in the step of determining the number of columns to be poured in the same batch according to the concrete pouring time of the column and the initial setting time of the concrete: the number of columns to be poured in the same batch is:
[0035] N = (T / t) + 1
[0036] Wherein, T is the initial setting time of concrete, and t is the concrete pouring time. Since the initial setting time of concrete is calculated only after the first section of the first column to be poured is completed, the ratio of the initial setting time of concrete to the concrete pouring time in this embodiment substantially refers to the number of columns to be constructed that can be constructed after the first section of the first column to be poured is completed. Of course, N is an integer less than or equal to (T / t)+1.
[0037] Furthermore, before determining the number of columns to be cast in the same batch according to the concrete pouring time and the initial setting time of the columns, the method further includes: trial pouring a column to be cast to obtain the concrete pouring time and the initial setting time of the concrete. That is to say, the concrete pouring time and the initial setting time of the concrete are pre-determined by trial pouring a column to be cast. Of course, concrete with the same proportion needs to be used when pouring other columns later to ensure that the initial setting time of the concrete poured for each column is the same. At the same time, only the first section needs to be poured during the trial pouring, so that the accurate time of pouring the first section can be measured.
[0038] Furthermore, before determining the number of columns to be poured in the same batch according to the concrete pouring time and the initial setting time of the columns, the method further includes:
[0039] Set up column formwork around the steel bars of the columns to be cast;
[0040] The steel bars and the column formwork are inspected and accepted.
[0041] During the civil construction process, the column formwork must first be erected around the steel bars of the column to be cast, and the column formwork must be inspected and accepted to ensure its quality before the subsequent column concrete pouring steps can be carried out to avoid construction quality accidents or even safety accidents in the subsequent pouring construction.
[0042] When the concrete of the first section of the column to be cast begins to set, the second section of the column to be cast is cast, and the column template is removed when the concrete of the second section reaches a preset strength. After the second section is cast and the strength of the column concrete is checked to reach the preset strength at which the template can be removed, the column template can be removed so that the column template can be used for the next column construction.
[0043] In summary, the present invention discloses a column construction method, which includes: pouring concrete in sequence on the first section of each column to be poured in the same batch of columns to be poured; when the concrete of the first section of the column to be poured has initially set, pouring the second section of the column to be poured. In the present invention, since the second section is poured when the concrete of the first section of the column to be poured has initially set, the concrete of the second section can be perfectly connected with the concrete of the first section, and there is no need to perform roughening and acceptance after pouring the first section, which greatly simplifies the construction process and improves the construction efficiency; in addition, the concrete in the first section of the concrete to be poured mainly transmits vertical pressure after initial setting, and the pressure on the side formwork is relatively small. When the second section is poured with concrete, only the second section is liquid concrete, and the side pressure generated is relatively small, which will not cause the formwork to expand and cause quality accidents.
[0044] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A column construction method, It is characterized in that It includes: Concrete is poured sequentially on the first section of each column to be poured in the same batch of columns to be poured; When the concrete of the first section of the column to be cast begins to set, the second section of the column to be cast is cast; Before sequentially pouring concrete on the first section of each column to be poured in the same batch of columns to be poured, the method further includes: Determine the number of columns to be poured in the same batch according to the concrete pouring time of the columns and the initial setting time of the concrete; In the step of determining the number of columns to be poured in the same batch according to the concrete pouring time and the initial setting time of the columns: The number of columns to be cast in the same batch is: N = (T / t) + 1; Where, T is the initial setting time of concrete, and t is the concrete pouring time; The number of columns to be cast in each batch is the same; When the concrete of the first section of the column to be cast has initially set, in the step of casting the second section of the column to be cast: The first section and the second section are both one-half of the total height of the column to be cast; Before determining the number of columns to be poured in the same batch according to the concrete pouring time and the initial setting time of the columns, the method further includes: Set up column formwork around the steel bars of the columns to be cast; The steel bars and the column formwork are inspected and accepted.
2. According to the column construction method of claim 1, It is characterized in that Before determining the number of columns to be poured in the same batch according to the concrete pouring time and the initial setting time of the columns, the method further includes: A trial casting of a column to be cast is performed to obtain the concrete pouring time and the concrete initial setting time.
3. According to the column construction method of claim 1, It is characterized in that When the concrete of the first section of the column to be cast begins to set, after casting the second section of the column to be cast, the method further includes: when the concrete of the second section reaches a preset strength, disassembling the column formwork.