A construction method for a side guide hole buckle arch steel frame and one-time backfilling behind it using a hole pile method
By using the side guide hole arch steel frame and the one-time backfill method in the construction of the hole pile method, and using welded rebar formwork and pre-embedded pump pipes, the problems of slow construction speed of traditional jet concrete and insufficient pump pipe length are solved, and the problems of slow construction speed of traditional jet concrete are improved. The construction quality and efficiency are achieved, and an efficient, fast, economical and environmentally friendly construction method is achieved.
Patent Information
- Application Number
- CN202211070641.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-09-02
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2042-09-02
AI Technical Summary
During the construction of traditional hole pile method and arch cover method, the construction speed of jet concrete is slow, the amount of dust is large, the construction progress is slow, the length of the pump pipe is too short, the concrete flow is reduced, and the arch back space is small, resulting in difficulty in dismantling and recycling, which increases construction. cost.
The hole pile method is used to carry out the construction method of the steel frame on the side guide hole buckle and the one-time backfill behind. By welding the rebar formwork, the embedded long pump pipe and grouting pipe, the internal arc mold installation, the overall concrete pouring and mold removal are realized to ensure the concrete Fluidity and construction quality.
It improves construction speed and quality, reduces construction costs, ensures the integrity and stress capacity of concrete, and achieves an efficient, fast, economical and environmentally friendly construction method.
Smart Images

Figure CN115306449B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a construction method of underground engineering using a hole pile method or an arch cover method, and in particular to a hole pile method side guide hole buckle arch steel frame and a one-time backfilling construction method behind it. Background Art
[0002] In order to avoid affecting ground traffic and reduce the cost of the project, many subway stations adopt the more complicated construction process of the hole pile method and the arch cover method to ensure the construction safety of shallow buried subway stations. Among them, after the construction of the side piles and the crown beam on the top of the pile is completed, the initial support of the arch foot of the crown beam top buckle arch (including the installation of steel frame and initial support shotcrete) and the initial support of the buckle arch main arch are connected according to the traditional method, so as to achieve the initial support of the buckle arch of the main arch after the removal of the initial support of the side guide hole near the buckle arch main arch side, and the initial support of the buckle arch of the side guide hole is formed as a whole to transfer the load to the force conversion of the side pile.
[0003] According to the traditional existing technology or construction method, after the side guide hole buckle arch steel frame is installed, a back mold is set on the back of the arch frame and a closed spraying and mixing operation is completed. After the back mold and foreign objects are removed, the concrete filling construction is carried out in sections behind the side guide hole buckle arch through the pump pipe pre-buried on the top of the side guide hole buckle arch steel frame.
[0004] This method has the following main disadvantages:
[0005] The initial support part inside the arch back formwork needs to be sprayed and mixed. Compared with normal concrete pouring construction, spraying concrete operation is slow and has low efficiency.
[0006] 2) During spray mixing operations, due to the large amount of dust, it is difficult for workers in other processes to continue their respective operations. Therefore, it is difficult to organize continuous flow operations and the construction progress is slow.
[0007] 3) The subsequent concrete filling operation behind the initial support can only be carried out after the spraying and mixing operation is completed, which restricts the subsequent filling construction. The arch backfill cannot be carried out in the sections where the spraying and mixing operation has not been carried out.
[0008] 4) The buried length of the pump pipe is too short and the discharge port is low. When the backfill concrete surface height exceeds a certain height of the pump pipe discharge port, the fluidity of the vault concrete is likely to decrease and block the pump pipe, causing the backfill concrete to be emptied, affecting the quality of the backfill construction.
[0009] 5) The arch back space is small, and it is difficult for workers to organize the demolding and transportation in this space, and it is difficult to recycle. In some constructions, in order to comprehensively consider the construction progress and the demolding and recycling costs, new materials that can be combined with the concrete structure are used. After the spraying and mixing operation is completed, the back form is not removed, and a one-time investment is made, which has a high investment cost. Summary of the invention
[0010] In order to overcome the deficiencies of the above-mentioned prior art, the purpose of the present invention is to provide a construction method for a side guide hole buckle arch steel frame and a one-time backfilling behind it by the hole pile method, so as to realize a more efficient, rapid, economical, environmentally friendly, healthy and civilized construction method.
[0011] In order to achieve the above object, the technical solution adopted by the present invention is:
[0012] A construction method for a side-guide hole buckle arch steel frame and one-time backfilling behind the hole pile method comprises the following steps:
[0013] 1) At every interval between steel frames, a threaded steel bar with a diameter of 14 mm is welded and led out on the same side of each buckle arch steel frame (2) as the template (4) tie bar (3). The tie bar extends out in the direction of the template (4). The length of the tie bar (3) is 10 cm. The circumferential spacing of the tie points is the total width of two templates. The template (4) is made of a wooden board with a length × width × thickness of 4 m * 0.2 m * 0.05 m respectively;
[0014] 2) Between all adjacent rows of tie bars (3) at all levels, a template (4) is laid along the longitudinal direction of the guide hole, and a whole 20 mm diameter threaded steel ring steel bar (5) is used to press against the template and the reserved tie bars (3), and all intersections of the ring steel bar (5) and the tie bars (3) are welded and fixed, and the template (4) is clamped, and the gaps in the template are sealed with foam glue;
[0015] 3) A 125mm diameter pre-buried pump pipe (6) is installed at every 9m interval on the top of the formwork (4) for pouring and observation holes. A 32mm diameter single-end threaded galvanized pre-buried grouting pipe (7) is installed between two adjacent pre-buried pump pipes (6) for backfilling and supplementary grouting. When installing the pre-buried pump pipe (6), it must be ensured that the upper part extends to 20-30cm away from the arch. When installing the pre-buried grouting pipe (7), the upper part should be tightly pressed against the arch of the pilot hole. At the same time, a steel bar support (13) of the cantilevered section of the pre-buried pump pipe (6) is welded on the buckle arch steel frame (2) to prevent loosening and falling off. The steel bar support (13) is made of two 20mm diameter threaded steel bars, one end of each threaded steel bar is welded to the pre-buried pump pipe (6), and the other end is welded to the buckle arch steel frame (2) below to form an eight-shaped arrangement;
[0016] 4) To ensure the stability of the formwork (4), a Φ42 steel pipe (8) back rib is provided in the middle of the annular reinforcement (5) along the longitudinal length of the guide hole. The Φ42 steel pipe (8) is fixed to the annular reinforcement (5) by spot welding at intervals of 1 m. At the same time, a Φ48 steel pipe (9) is provided at intervals of 3 m. The Φ42 steel pipe (8) is pressed against by a top support (10) and the Φ48 steel pipe (9). The Φ48 steel pipe (9) is pressed against a 20 mm diameter threaded steel positioning rib (11) below the side wall along the normal direction of the arc surface.
[0017] 5) Connect the pre-buried pump pipes (6) from one or both ends of the pilot hole simultaneously and sequentially to backfill the concrete (14) behind the formwork (4); during this period, when the pump pressure of the pump truck shows a rapid increase or concrete flows out from another pre-buried pump pipe (6), seal the concrete pumping port being poured and switch to the next pre-buried pump pipe (6) for filling construction; during the pouring process, a dedicated person should be assigned to monitor each concrete pumping construction surface. If there is leakage or loosening of the Φ48 steel pipe (9), stop the concrete pouring construction in time, and continue the construction after the reinforcement is completed;
[0018] 6) Follow step 6) for all remaining pre-buried pump pipes to complete the backfill concrete (14) construction;
[0019] 7) After the concrete reaches the demolding strength, the formwork (4) is removed in a centralized manner and transported out for recovery. The formwork (4) is checked for local voids, and nearby pre-buried grouting pipes (7) are connected or pre-buried grouting pipes (7) are drilled separately to fill the grouting pipes fully to ensure the backfill concrete construction effect.
[0020] The beneficial effects of the present invention are:
[0021] 1) The four processes of outer arc back form installation, initial support spraying, formwork removal, and filling and pouring in the traditional method are innovatively optimized into three processes: inner arc form installation, filling concrete pouring, and formwork removal. Among them, the lengthening of the buried length of the pump pipe can ensure that the concrete construction is not affected by the poor fluidity caused by the back pressure of the filling concrete, which causes pipe blockage. The subsequent anti-emptying supplementary grouting further ensures the fullness and density of the backfill construction and improves the construction quality.
[0022] 2) The traditional design has been optimized. Compared with the original design of first spraying and mixing the side (side) guide hole buckle arch steel frame and then backfilling the concrete behind the sprayed and mixed structure, this method uses the side guide hole buckle arch steel frame and the one-time integral casting and backfilling construction behind it, which is conducive to improving the integrity of the concrete structure and the overall bearing capacity.
[0023] 3) Compared with traditional construction methods, it realizes a more efficient, rapid, economical, environmentally friendly, healthy and civilized construction method. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 It is a front view schematic diagram of a prior art construction method of spraying concrete on the top side of an isolated back formwork and backfilling concrete at the back;
[0025] Figure 2 A schematic side cross-sectional view of a prior art construction method of spraying concrete on the top side of an isolated back formwork and backfilling concrete at the back;
[0026] Figure 3 It is a front view of a construction method of a side guide hole buckle arch steel frame and a one-time integral backfill behind the hole pile method;
[0027] Figure 4 The present invention is a schematic side section diagram of a side guide arch steel frame of a hole pile method and a one-time integral backfill construction method behind it.
[0028] Among them: 1 is the crown beam; 2 is the arch steel frame; 3 is the tie bar; 4 is the formwork; 5 is the circumferential steel bar; 6 is the embedded pump pipe; 7 is the embedded grouting pipe; 8 is the steel pipe; 9 is the Φ48 steel pipe; 10 is the top support; 11 is the positioning bar; 12 is the initial support of the guide tunnel; 13 is the steel support; 14 is the backfill concrete. DETAILED DESCRIPTION
[0029] The present invention is further described below in conjunction with the accompanying drawings
[0030] like Figure 1 , 2 As shown in 3 and 4, a construction method of a side guide hole buckle arch steel frame and a one-time integral backfilling behind the hole pile method comprises the following steps:
[0031] 1) The crown beam (1) of the top of the side (lateral) guide hole pile is pre-buried and installed in the longitudinal whole section. The side guide hole buckle arch steel frame (2) is connected and closed with the buckle arch primary support main arch frame, thereby completing the installation of the buckle arch steel frame (2) of the whole section.
[0032] 2) In the relatively unobstructed construction space below the buckle arch steel frame (2) in the pilot tunnel, the construction personnel utilize the bearing capacity of the buckle arch steel frame (2) to weld and lead out threaded steel with a diameter of 14 mm at the same side of each buckle arch steel frame (2) at a distance of one steel frame as the template (4) tie bar (3). The tie bar extends out in the direction of the template (4). The length of the tie bar (3) is 10 cm. The circumferential spacing of the tie points is the total width of the two templates. The template (4) is made of a wooden board with a length*width*thickness of 4 m*0.2 m*0.05 m respectively;
[0033] 3) Between all adjacent rows of tie bars (3) at all levels, lay the template (4) along the longitudinal direction of the guide hole. In addition, use a whole 20mm diameter threaded steel ring steel bar (5) to press against the template and the reserved tie bars (3), weld all the intersections of the ring steel bar (5) and the tie bars (3), clamp the template (4), and seal the gaps in the template with foam glue.
[0034] 4) Install a 125mm diameter pre-buried pump pipe (6) every 9m on the top of the formwork (4) for pouring and observation holes. Set a 32mm diameter single-end threaded galvanized pre-buried grouting pipe (7) between two adjacent pre-buried pump pipes (6) for backfilling and supplementary grouting. When installing the pre-buried pump pipe (6), ensure that the upper part extends to 20~30cm away from the arch. When installing the pre-buried grouting pipe (7), the upper part should be tightly pressed against the arch of the guide hole. At the same time, weld and reinforce the steel support (13) of the cantilever section of the pre-buried pump pipe (6) on the buckle arch steel frame (2) to prevent loosening and falling off. The steel support (13) uses two 20mm diameter threaded steel bars. One end of each threaded steel bar is welded to the pre-buried pump pipe (6), and the other end is welded to the buckle arch steel frame (2) below to form an eight-shaped arrangement;
[0035] 5) To ensure the stability of the formwork (4), a Φ42 steel pipe (8) back rib is provided in the middle of the annular reinforcement (5) along the longitudinal length of the guide hole. The Φ42 steel pipe (8) is fixed to the annular reinforcement (5) by spot welding at intervals of 1 m. At the same time, a Φ48 steel pipe (9) is provided at intervals of 3 m. The Φ42 steel pipe (8) is pressed against by a top support (10) and the Φ48 steel pipe (9). The Φ48 steel pipe (9) is pressed against a 20 mm diameter threaded steel positioning rib (11) below the side wall along the normal direction of the arc surface.
[0036] 6) Connect the embedded pump pipes (6) from one or both ends of the pilot hole at the same time, and then backfill the concrete (14) behind the template (4). When the pump pressure of the pump truck increases rapidly or concrete flows out of another embedded pump pipe (6), seal the concrete outlet being poured and switch to the next embedded pump pipe (6) for filling. During the construction process, a dedicated person should be assigned to monitor each concrete pumping construction surface. If there is leakage or loosening of the Φ48 steel pipe (9), stop pouring concrete in time and continue construction after reinforcement is completed.
[0037] 7) For all remaining pre-buried pump pipes, complete the backfill concrete (14) construction according to step 6).
[0038] 8) After the concrete reaches the demolding strength, the formwork (4) is removed and transported out for recycling. Check whether there are local voids, connect the nearby pre-buried grouting pipe (7) or drill a separate pre-buried grouting pipe (7), fill the grouting fully, and ensure the backfill construction effect.
[0039] 9) Start the next process.
Claims
1. A construction method for a side-guide arch steel frame and one-time backfilling behind the hole pile method, characterized in that: The following steps are involved: 1) The crown beam (1) of the side guide hole pile top is pre-buried and installed in the longitudinal whole section, and the side guide hole buckle arch steel frame (2) is connected and closed with the buckle arch primary support main arch frame, thereby completing the installation of the buckle arch steel frame (2) of the whole section; 2) At every interval of one steel frame, a threaded steel bar with a diameter of 14 mm is welded and led out on the same side of each buckle arch steel frame (2) as the template (4) tie bar (3). The tie bar extends out in the direction of the template (4), and the circumferential spacing of the tie points is the total width of the two templates; 3) Between all adjacent rows of tie bars (3) at all levels, a template (4) is laid along the longitudinal direction of the guide hole, and a ring steel bar (5) is used to press against the template and the reserved tie bars (3), and all intersections of the ring steel bar (5) and the tie bars (3) are welded and fixed, and the template (4) is clamped, and the gaps in the template are sealed with foam glue; 4) Pre-buried pump pipes (6) are installed at intervals of 9m on the top of the formwork (4) for pouring and observation holes. Single-end threaded galvanized pre-buried grouting pipes (7) are installed between two adjacent pre-buried pump pipes (6). When the pre-buried pump pipes (6) are installed, the upper part extends to a distance of 20 to 30cm from the arch top. When the pre-buried grouting pipes (7) are installed, the upper part should be tightly pressed against the arch top of the guide hole. At the same time, steel bars (13) are welded on the buckle arch steel frame (2) to reinforce the cantilevered section of the pre-buried pump pipe (6). One end of each threaded steel bar is welded to the pre-buried pump pipe (6), and the other end is welded to the buckle arch steel frame (2) below to form an eight-shaped arrangement; 5) To ensure the stability of the formwork (4), a Φ42 steel pipe (8) back rib is provided in the middle of the annular reinforcement (5) along the longitudinal length of the guide hole. The Φ42 steel pipe (8) is fixed to the annular reinforcement (5) by spot welding at intervals of 1 m. At the same time, a Φ48 steel pipe (9) is provided at intervals of 3 m. The Φ42 steel pipe (8) is pressed against by a top support (10) and the Φ48 steel pipe (9). The Φ48 steel pipe (9) is pressed against the threaded steel positioning rib (11) below the side wall along the normal direction of the arc surface. 6) Connect the embedded pump pipes (6) from one or both ends of the pilot hole simultaneously and sequentially to backfill the concrete (14) behind the formwork (4); during this period, when the pump pressure of the pump truck shows a rapid increase or concrete flows out from another embedded pump pipe (6), seal the concrete pumping port being poured and switch to the next embedded pump pipe (6) for filling construction; during the pouring process, a dedicated person should be assigned to monitor each concrete pumping construction surface. If there is leakage or loosening of the Φ48 steel pipe (9), stop the concrete pouring construction in time, and continue the construction after the reinforcement is completed; 7) Follow step 6) for all remaining pre-buried pump pipes to complete the backfill concrete (14) construction; 8) After the concrete reaches the demolding strength, the formwork (4) is removed in a centralized manner and transported out for recovery. The formwork (4) is checked for local voids, and nearby pre-buried grouting pipes (7) are connected or pre-buried grouting pipes (7) are drilled separately to fill the grouting pipes fully, thereby ensuring the backfill concrete construction effect.
2. A construction method for a side guide arch steel frame and one-time backfilling behind the hole pile method according to claim 1, characterized in that: The template (4) is made of a wooden board with a length × width × thickness of 4m*0.2m*0.05m respectively; the tie bar (3) is 10cm long, the annular steel bar (5) is 20mm in diameter, the embedded pump pipe (6) is 125mm in diameter, and the single-end threaded galvanized embedded grouting pipe (7) is 32mm in diameter; the steel bar support (13) is made of two threaded steel bars with a diameter of 20mm, and the threaded steel positioning bar (11) has a diameter of 20mm.
Citation Information
Patent Citations
Method of simply backfilling concrete to inner buckle arch of pilot tunnel of cavern-pile method station
CN111042833A
Construction method of side hole primary supporting buckle arch in underground excavation station construction through hole pile method
CN114060062A
Side pilot tunnel backfill construction method
CN114294020A
Steel frame connecting device for multi-pilot-tunnel combined excavation
CN216894442U