A shallow buried pipe drilling construction transfer device and construction method
By designing a drilling construction transfer device including a base, a first siding plate, a feed cylinder and a second siding plate, the problem of low drilling casing management and transfer efficiency in the prior art is solved, and convenient management of pipes is realized and Improve construction efficiency.
Patent Information
- Application Number
- CN202211044356.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-08-29
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2042-08-29
AI Technical Summary
In shallow buried pipe drilling construction, it is difficult for the existing technology to effectively manage and transfer drilling casings, which increases the labor intensity of staff and poses safety hazards.
A drilling construction transfer device including a base, a first siding plate, a feed cylinder and a second siding plate is designed to facilitate the transfer and fixation of pipes through a roller and a plug-in structure, and combined with specific construction steps to improve construction efficiency.
It realizes unified management and convenient access to pipes, reduces the labor intensity of staff, improves construction efficiency, and reduces safety hazards.
Smart Images

Figure CN115370305B_ABST
Abstract
Description
Technical field:
[0002] The invention relates to a drilling casing transfer device, in particular to a shallow underground pipe drilling construction transfer device and a construction method. Background technology:
[0004] Shallow geothermal energy is thermal energy with development value hidden in shallow rock and soil, groundwater and surface water within 200m below the surface. It can provide hot water for building functions and refrigeration. Its working principle is: the heat transfer medium circulates in sealed vertical and horizontal PE buried pipes, and uses the temperature difference between the heat transfer medium and the underground rock and soil layer and groundwater to exchange heat, thereby achieving the purpose of utilizing shallow geothermal energy, and then realizing energy supply to buildings through ground source heat pump technology.
[0005] In actual drilling construction, workers generally pile the casing for drilling on the ground on one side of the drilling rig. When drilling, they use manual delivery to deliver the drill pipes one by one to the workers at the drilling site and perform drilling operations. This method is time-consuming and labor-intensive, and increases the labor intensity of the workers. The pipes piled on the ground are difficult to manage and bring certain safety hazards to the construction workers on site. Summary of the invention:
[0007] The technical problem to be solved by the present invention is to overcome the shortcomings of the prior art and provide a shallow buried pipe drilling construction transfer device and a construction method, which is convenient for unified management of pipes at the construction site, and at the same time, it is convenient for workers to directly take and remove pipes and carry out drilling construction, thereby improving work efficiency.
[0008] The technical solution adopted by the present invention to solve the technical problem is:
[0009] A shallow underground pipe drilling construction and transfer device comprises a base, a first enclosure, a material receiving tube and a second enclosure, wherein the first enclosure is arranged on the left side of the top of the base, the material receiving tube is arranged above the base, and the material receiving tube is located inside the first enclosure, the second enclosure is arranged on the right side of the top of the material receiving tube, and the first enclosure and the second enclosure are fixedly connected together by an insertion plate, a roller is arranged on the right end of the bottom of the material receiving tube, and an insertion rod is arranged on the outside of the material receiving tube and the second enclosure, a bracket is sleeved on the insertion rod, and a handle is connected to the top of the insertion rod by a thread.
[0010] A rectangular groove is dug on the right side of the base at a position corresponding to the roller.
[0011] A first limiting column and a second limiting column are respectively provided at the edges of both sides of the first enclosure plate and the second enclosure plate, and an inserting plate is provided between the first limiting column and the adjacent second limiting column.
[0012] A bracket is provided on the right side of the bottom of the material receiving tube, and a roller is provided in the bracket, the right end of the bracket extends out of the material receiving tube, and a positioning tube is provided at the top of the right end of the bracket, an insertion rod is inserted in the positioning tube and fixed by bolts; a first sleeve is sleeved above the insertion rod, and a bracket is provided on the outer wall on the right side of the first sleeve, and the first sleeve is fixedly connected to the insertion rod by bolts.
[0013] The two ends of the top of the second enclosure are respectively connected to pillars through threads, and a third enclosure is sleeved on the two pillars, and the third enclosure is fixedly connected to the pillars through bolts.
[0014] The outer end of the first limiting column and the outer end of the second limiting column are located on the same horizontal arc line, and a groove is dug at the lower end of the plug plate corresponding to the position of the first limiting column and the second limiting column.
[0015] The outer wall of the first enclosure is provided with a support block, and a positioning drill is inserted into the support block.
[0016] The construction method of the shallow buried pipe drilling construction transfer device comprises the following steps:
[0017] S1: placing the first enclosure on the ground at one side of the drilling rig, so that the first enclosure and the support at one side of the drilling rig are close together, and the base is fixedly connected to the ground by penetrating the support block with a positioning drill;
[0018] S2: The worker holds the handle and places the material receiving barrel on the ground and supports it with a bracket, and then places the casing required for drilling into the material receiving barrel and the second enclosure;
[0019] S3: After the sleeves in the material receiving barrel are full, the staff holds the handle and lifts the material receiving barrel to a height of 30°-60° from the ground, and uses rollers to move the device to the base on one side of the first displacement plate;
[0020] S4: When the roller is located in the rectangular groove, the first enclosure and the second enclosure are fixed together by inserting the insert plate on the first limit column and the second support column, and the drilling construction is ready. The steps are as follows:
[0021] , measure and lay out, and mark the location of the holes at the construction site, using bamboo and wooden stakes as markers at the center of each hole;
[0022] ②. Position the pipe according to the depth of the shallow PE buried pipe heat exchanger and the reserved length. Reserve 1m of length at the top of the borehole. Before inserting the vertical buried pipe heat exchanger into the borehole, a water pressure test should be performed. Under the test pressure, the pressure should be stabilized for at least 15 minutes. After the pressure is stabilized, the pressure drop should not exceed 3%, and there should be no leakage site. After sealing, insert it into the borehole under pressure;
[0023] ③. When the construction of the previous buried pipe hole is completed and the next buried pipe hole is moved to, the buried pipe hole is positioned. At the same time, the height of the four hydraulic column feet is adjusted to make the drilling rig in a horizontal state to ensure the verticality of the drilling rig drill rod;
[0024] ④ After drilling each well, use an inclinometer to measure the well inclination to ensure that the well inclination meets the requirements before lowering the pipe;
[0025] ⑤. After the drilling is completed and the hole wall is solidified, use a pressure test pump to pressurize the PE pipe immediately, use a special pipe lowering device and lower the pipe steadily under pressure, and install pipe clamps at intervals of 4-5m during the pipe lowering process to ensure that the PE supply and return pipes are separated by a certain distance and do not affect heat exchange;
[0026] ⑥. Protective measures should be taken during the pipe lowering process to avoid damage to the PE pipe. A second pressure test should be carried out from the pipe lowering to the backfill at the bottom of the hole to ensure that the pressure is consistent with the first one;
[0027] ⑦. After drilling is completed, backfill construction should be carried out in time.
[0028] The positive beneficial effects of the present invention are:
[0029] 1. The present invention arranges a material receiving cylinder above the base and rollers at the bottom of the material receiving cylinder, which not only facilitates the transportation of pipes, but also forms a pipe receiving cavity through the first enclosure and the second enclosure, which facilitates the management of pipes.
[0030] 2. The present invention arranges a bracket on the insertion rod to facilitate the material receiving tube to remain in an inclined state when the pipe is loaded into the material receiving tube. By arranging an insertion plate outside the first enclosure and the second enclosure, the two enclosures can be fixed together, thereby increasing the stability of the pipe bearing space.
[0031] 3. The present invention arranges a support block outside the first enclosure and inserts a positioning bar into the support block, so as to facilitate fixing the device to the ground and ensure the overall stability of the device when it is used. The structure is simple and easy to use. Description of the drawings:
[0033] Figure 1 It is a structural schematic diagram of the present invention;
[0034] Figure 2 It is a schematic diagram of the partial structure of the first enclosure of the present invention;
[0035] Among them: 1-base, 10A-rectangular groove, 2-first enclosure, 3-support tube, 4-second enclosure, 5-roller, 6-positioning tube, 7-insertion rod, 8-first sleeve, 9-bracket, 10-handle, 11-pillar, 12-third enclosure, 131-first limiting column, 132-second limiting column, 14-insertion plate, 15-support block, 16-positioning drill. Specific implementation method:
[0037] The present invention will be further explained and illustrated below in conjunction with the accompanying drawings:
[0038] Example 1, see Figure 1-Figure 2 A shallow underground pipe drilling construction and transfer device comprises a base 1, a first enclosure 2, a material receiving tube 3 and a second enclosure 4. The first enclosure 2 is arranged on the left side of the top of the base 1, and the material receiving tube 3 is arranged above the base 1, and the material receiving tube 3 is located in the first enclosure 2, and the second enclosure 4 is arranged on the right side of the top of the material receiving tube 3, and the first enclosure 2 and the second enclosure 4 are fixedly connected together by an insertion plate 14, a roller 5 is arranged on the right end of the bottom of the material receiving tube 3, and an insertion rod 7 is arranged outside the material receiving tube 3 and the second enclosure 4, a bracket 9 is sleeved on the insertion rod 7, and a handle 10 is connected to the top of the insertion rod 7 by threading.
[0039] A rectangular groove 10A is formed on the right side of the base 1 at a position corresponding to the roller 5 .
[0040] A first limiting column 131 and a second limiting column 132 are respectively disposed at the edges of both sides of the first enclosure 2 and the second enclosure 4 , and an inserting plate 14 is disposed between the first limiting column 131 and the adjacent second limiting column 132 .
[0041] A bracket is provided on the right side of the bottom of the material receiving tube 3, and a roller 5 is provided in the bracket. The right end of the bracket extends out of the material receiving tube 3, and a positioning tube 6 is provided at the top of the right end of the bracket. An insertion rod 7 is inserted in the positioning tube 6 and fixed by bolts; a first sleeve 8 is sleeved above the insertion rod 7, and a bracket 9 is provided on the outer wall on the right side of the first sleeve 8, and the first sleeve 8 is fixedly connected to the insertion rod 7 by bolts.
[0042] The two ends of the top of the second enclosure 4 are respectively connected to the pillars 11 through threads, and the third enclosure 12 is sleeved on the two pillars 11, and the third enclosure 12 is fixedly connected to the pillars 11 through bolts.
[0043] The outer end of the first limiting column 131 and the outer end of the second limiting column 132 are located on the same horizontal arc line, and a groove is dug at the lower end of the inserting plate 14 at the position corresponding to the first limiting column 131 and the second limiting column 132 .
[0044] A support block 15 is provided on the outer wall of the first enclosure plate 2 , and a positioning drill 16 is inserted into the support block 15 .
[0045] In the above description, the top of the first enclosure plate and the top of the second enclosure plate are located on the same horizontal line, and the height of the bottom of the material receiving tube from the bottom of the roller matches the height of the base.
[0046] In the above description, when the material receiving cylinder is located on the base, the roller is located in the rectangular groove.
[0047] In the above description, the curvature of the third displacement plate matches the curvature of the second enclosure plate.
[0048] In the above description, the lower end of the support column is connected to the threaded holes at both ends of the top of the second enclosure plate by threads.
[0049] In the above description, the outer wall of the top of the insertion rod is provided with an external thread, and is connected with the thread of the inner wall of the handle through the thread.
[0050] In the above description, the inner wall of the insert plate is tightly attached to the outer wall of the first enclosure plate, the second limiting column is longer than the first limiting column, but the outer ends of the two limiting columns are located on the same arc line.
[0051] In the above description, the outer diameter of the material receiving tube matches the inner diameter of the first enclosure, the cross-section of the first enclosure is half of the base, and the cross-section of the second enclosure is half of the material receiving tube.
[0052] Embodiment 2:
[0053] The above-mentioned construction method of a shallow buried pipe drilling construction transfer device comprises the following steps:
[0054] S1: Place the first enclosure 2 on the ground at one side of the drilling rig, so that the first enclosure 2 and the bracket at one side of the drilling rig are close together, and penetrate the support block 15 through the positioning drill 16 to fix the base 1 to the ground;
[0055] S2: The worker holds the handle 10 and places the material receiving tube 3 on the ground and supports it with the bracket 9, and then places the casing required for drilling into the material receiving tube 3 and the second enclosure 4;
[0056] S3: After the sleeves in the material receiving cylinder 3 are filled, the staff holds the handle and lifts the material receiving cylinder 3 to a height of 30°-60° from the ground, and uses the roller 5 to move the device to the base 1 on one side of the first displacement plate 2;
[0057] S4: When the roller 5 is located in the rectangular groove 10A, the first enclosure 2 and the second enclosure 4 are fixed together by inserting the insert plate 14 on the first limit column 131 and the second support column 132, and the drilling construction is ready. The steps are as follows:
[0058] , measure and lay out, and mark the location of the holes at the construction site, using bamboo and wooden stakes as markers at the center of each hole;
[0059] ②. Position the pipe according to the depth of the shallow PE buried pipe heat exchanger and the reserved length. Reserve 1m of length at the top of the borehole. Before inserting the vertical buried pipe heat exchanger into the borehole, a water pressure test should be performed. Under the test pressure, the pressure should be stabilized for at least 15 minutes. After the pressure is stabilized, the pressure drop should not exceed 3%, and there should be no leakage site. After sealing, insert it into the borehole under pressure;
[0060] ③. When the construction of the previous buried pipe hole is completed and the next buried pipe hole is moved to, the buried pipe hole is positioned. At the same time, the height of the four hydraulic column feet is adjusted to make the drilling rig in a horizontal state to ensure the verticality of the drilling rig drill rod;
[0061] ④ After drilling each well, use an inclinometer to measure the well inclination to ensure that the well inclination meets the requirements before lowering the pipe;
[0062] ⑤. After the drilling is completed and the hole wall is solidified, use a pressure test pump to pressurize the PE pipe immediately, use a special pipe lowering device and lower the pipe steadily under pressure, and install pipe clamps at intervals of 4-5m during the pipe lowering process to ensure that the PE supply and return pipes are separated by a certain distance and do not affect heat exchange;
[0063] ⑥. Protective measures should be taken during the pipe lowering process to avoid damage to the PE pipe. A second pressure test should be carried out from the pipe lowering to the backfill at the bottom of the hole to ensure that the pressure is consistent with the first one;
[0064] ⑦. After drilling is completed, backfill construction should be carried out in time.
[0065] In actual operation, since the drilling rig is surrounded by land, we use positioning drills to fix the base to the ground.
[0066] In actual operation, placing the pipes used for drilling in the cavity formed by the first enclosure and the second enclosure is easier to manage than placing the pipes directly on the ground. At the same time, by arranging rollers at the bottom of the material receiving barrel, the transportation of the pipes is facilitated, and the staff does not need to transport the pipes one by one, thereby improving work efficiency.
[0067] The present invention solves the problem that pipes are piled up on the ground at the construction site and are difficult to manage. At the same time, it improves the efficiency of pipe transportation, reduces the burden on workers, and improves the overall construction efficiency. It is easy to use, simple to operate, and easy to promote.
Claims
1. A construction method for a shallow underground pipe drilling construction transfer device, wherein: The invention comprises a shallow underground pipe drilling construction and transfer device, the shallow underground pipe drilling construction and transfer device comprising a base (1), a first enclosure (2), a material receiving tube (3) and a second enclosure (4), characterized in that: the first enclosure (2) is arranged on the left side of the top of the base (1), the material receiving tube (3) is arranged above the base (1), and the material receiving tube (3) is located inside the first enclosure (2), the second enclosure (4) is arranged on the right side of the top of the material receiving tube (3), the first enclosure (2) and the second enclosure (4) are fixedly connected together by a plug plate (14), and the bottom of the material receiving tube (3) is provided with a second enclosure (4). A roller (5) is arranged at the right end, and an insertion rod (7) is arranged outside the material receiving tube (3) and the second enclosure (4), a bracket (9) is sleeved on the insertion rod (7), and a handle (10) is connected to the top of the insertion rod (7) through a thread; a rectangular groove (10A) is dug at the right side of the base (1) at the position corresponding to the roller (5); a first limiting column (131) and a second limiting column (132) are respectively arranged at the edges of both sides of the first enclosure (2) and the second enclosure (4), and a first limiting column (131) and a second limiting column (132) are arranged between the first limiting column (131) and the adjacent second limiting column (132). The insert plate (14) is provided with a bracket on the right side of the bottom of the material receiving tube (3), and a roller (5) is provided in the bracket, the right end of the bracket extends out of the material receiving tube (3), and a positioning tube (6) is provided on the top of the right end of the bracket, and an insert rod (7) is inserted in the positioning tube (6) and fixed by bolts; a first sleeve (8) is sleeved above the insert rod (7), and a bracket (9) is provided on the outer wall of the right side of the first sleeve (8), and the first sleeve (8) is fixedly connected to the insert rod (7) by bolts; the two ends of the top of the second enclosure plate (4) are respectively connected by threads. There are pillars (11), and a third enclosure (12) is sleeved on two pillars (11), and the third enclosure (12) is fixedly connected to the pillars (11) by bolts; the outer end of the first limiting column (131) and the outer end of the second limiting column (132) are located on the same horizontal arc line, and a groove is dug at the lower end of the plug plate (14) at the position corresponding to the first limiting column (131) and the second limiting column (132); the outer wall of the first enclosure (2) is provided with a support block (15), and a positioning drill (16) is inserted into the support block (15), and it is characterized by comprising the following steps: S1: placing the first enclosure (2) on the ground at one side of the drilling rig, so that the first enclosure (2) and the support at one side of the drilling rig are close together, and the base (1) is fixedly connected to the ground by penetrating the support block (15) with a positioning drill (16); S2: The staff holds the handle (10) and places the material receiving tube (3) on the ground and supports it with the bracket (9), and then places the casing required for drilling into the material receiving tube (3) and the second enclosure (4); S3: After the sleeves in the material receiving barrel (3) are filled, the staff member holds the handle and lifts the material receiving barrel (3) to a height of 30°-60° from the ground, and moves it to the base (1) on one side of the first enclosure (2) using the roller (5); S4: When the roller (5) is located in the rectangular groove (10A), the first enclosure plate (2) and the second enclosure plate (4) are fixed together by inserting the inserting plate (14) on the first limiting column (131) and the second limiting column (132), and the drilling construction is prepared, and the steps are as follows: ①. Measure and lay out the lines, and mark the location of the holes at the construction site, using bamboo and wooden stakes as marks at the center of each hole; ②. Position the pipe according to the depth of the shallow PE buried pipe heat exchanger and the reserved length. Reserve 1m of length at the top of the borehole. Before inserting the vertical buried pipe heat exchanger into the borehole, a water pressure test should be performed. Under the test pressure, the pressure should be stabilized for at least 15 minutes. After the pressure is stabilized, the pressure drop should not exceed 3%, and there should be no leakage site. After sealing, insert it into the borehole under pressure; ③. When the construction of the previous buried pipe hole is completed and the next buried pipe hole is moved to, the buried pipe hole is positioned. At the same time, the height of the four hydraulic column feet is adjusted to make the drilling rig in a horizontal state to ensure the verticality of the drilling rig drill rod; ④ After drilling each well, use an inclinometer to measure the well inclination to ensure that the well inclination meets the requirements before lowering the pipe; ⑤. After the drilling is completed and the hole wall is solidified, use the pressure test pump to pressurize the PE pipe immediately, use the pipe lowering device and lower the pipe steadily, and install pipe clamps at intervals of 4-5m during the pipe lowering process to ensure that the PE supply and return pipes are separated by a certain distance and do not affect the heat exchange; ⑥. Protective measures should be taken during the pipe lowering process to avoid damage to the PE pipe. A second pressure test should be carried out from the pipe lowering to the backfill at the bottom of the hole to ensure that the pressure is consistent with the first one; ⑦. After drilling is completed, backfill construction should be carried out in time.