A formwork-free frame beam, slope protection structure and construction method thereof

By using a formwork-free frame beam structure, concrete can be poured directly after grooves are cut into the slope using steel reinforcement components and wire mesh. This solves the problems of complex formwork and uneven side formwork, achieving efficient construction and improved safety.

CN116290035BActive Publication Date: 2024-11-19CHINA HYDROELECTRIC ENGINEERING CONSULTING GROUP CHENGDU RESEARCH HYDROELECTRIC INVESTIGATION DESIGN AND INSTITUTE
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202310515468.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-05-08
Publication Date
2024-11-19
Estimated Expiration
2043-05-08

AI Technical Summary

Technical Problem

The existing frame beam construction process involves complex and inefficient formwork erection and dismantling procedures, uneven local slopes, and difficulty in tightly bonding the bottom surface of the side formwork with the slope surface, leading to increased construction costs and safety risks.

Method used

The structure adopts a formwork-free frame beam structure with internal steel reinforcement components and wire mesh. Concrete is poured directly after grooves are cut on the slope to form a tightly fitting side formwork, reducing the need for formwork erection and pouring.

Benefits of technology

It improved construction efficiency, reduced construction costs and safety risks, and prevented the fine particles in the lower slope of the frame beam from being washed away by water.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116290035B_ABST
    Figure CN116290035B_ABST
Patent Text Reader

Abstract

The present invention discloses a formwork-free frame beam, a slope protection structure and a construction method thereof, and relates to the technical field of slope reinforcement of hydropower engineering. The frame beam is provided with a steel bar assembly inside; the cross section of the steel bar assembly is square; the steel bar assembly includes a plurality of longitudinal steel bars and transverse steel bars, the plurality of longitudinal steel bars are parallel to each other, and are sequentially arranged at intervals on the circumferential side of the frame beam, and the transverse steel bars are arranged between adjacent longitudinal steel bars; except for the bottom side of the steel bar assembly, the installation area surrounded by the plurality of longitudinal steel bars and transverse steel bars on the remaining sides of the steel bar assembly is provided with a steel wire mesh formed by binding. By adopting this scheme, it can fit closely with the slope surface, and can reduce the processes of formwork, mixing, transportation, conveying, pouring, vibrating, etc. during on-site pouring, thereby improving work efficiency and saving construction costs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of hydropower engineering slope reinforcement, and in particular to a formwork-free frame lattice beam, a slope protection structure and a construction method thereof. Background Art

[0002] The frame beam applies prestress through anchoring measures at the nodes, so that the sliding rock mass on the slope is tightly integrated with the stable rock mass, increasing the stability of each layer. By evenly transferring the anchor cables and anchor rods at the nodes to the slope, the force distribution of the slope can be greatly improved, which not only enhances the stability but also beautifies the environment.

[0003] The frame beam is used to reinforce the broken rock slope or soil slope. It can separate the broken rock mass on the slope, separate the downward force, and separate the management. Greening measures such as planting grass can also be carried out in the frame to form a unified and regular slope. At the node of the frame beam, anchor cables, anchor piles, anchor rods and other measures are used to reinforce the soil, so that the slope surface and the inside of the slope form a whole, increasing the stability of the slope.

[0004] At present, during the construction of lattice beams, after the slope cleaning process is completed, it is necessary to mark the smooth slope trend of the lattice beam location according to the construction blueprint. If the slope is an earth slope or a fully weathered gravel soil, it is also necessary to cut grooves on the slope. After the grooves are cut, steel bars are tied in the grooves. After the steel bars are tied, the formwork is installed. Each formwork is transported and installed, and then dismantled and transported after use. The formwork erection and demoulding processes are relatively complicated and have low work efficiency. There are uneven areas on the local slope, and it is difficult for the bottom surface of the side formwork to be tightly combined with the slope. It is time-consuming and labor-intensive to handle the uneven sections (sometimes crushing equipment is required), resulting in low efficiency, increased costs, and increased safety risks. Summary of the invention

[0005] The present invention aims to solve the deficiencies of the prior art and to provide a formwork-free frame lattice beam, a slope protection structure and a construction method thereof. By adopting the scheme, the structure can fit closely with the slope surface and can reduce the steps of formwork, mixing, transportation, conveying, pouring, vibrating and the like during on-site pouring, thereby improving work efficiency and saving construction costs.

[0006] The present invention is achieved through the following technical solutions:

[0007] A frame beam without formwork, wherein the frame beam has a steel bar assembly inside;

[0008] The cross section of the steel bar assembly is square; the steel bar assembly includes a plurality of longitudinal steel bars and transverse steel bars, the plurality of longitudinal steel bars are parallel to each other and are sequentially arranged at intervals on the circumferential side of the lattice beam, and the transverse steel bars are arranged between adjacent longitudinal steel bars;

[0009] Except for the bottom side of the steel bar assembly, a steel wire mesh formed by binding is provided in the installation area surrounded by a plurality of longitudinal steel bars and transverse steel bars on the remaining side of the steel bar assembly.

[0010] Compared with the prior art, if the slope is an earth slope or a fully weathered gravel soil, it is necessary to cut grooves on the slope. After the cutting is completed, steel bars are tied in the grooves. After the steel bars are tied, the formwork is installed. Each formwork is transported and installed, and then dismantled and transported after use. The formwork and demoulding processes are relatively complicated and have low work efficiency. There are uneven areas on the local slope, and it is difficult for the bottom surface of the side formwork to be tightly combined with the slope. It is time-consuming and labor-intensive to handle the uneven sections (sometimes crushing equipment is required), resulting in low efficiency, increased costs, and increased safety risks. The present invention provides a frame beam without formwork. By adopting this solution, casting can be carried out directly inside the frame beam, so there is no need to handle the uneven sections, and a close fit with the slope is achieved. Concrete can be sprayed at the wire mesh to form a side formwork, thereby greatly reducing the processes such as formwork and casting, thereby improving the implementation efficiency, reducing the construction cost, and also reducing the safety risks during the construction period.

[0011] In the specific scheme, the skeleton structure inside the frame beam is a steel bar assembly, and the steel bar assembly is formed by splicing and tying a plurality of transverse steel bars, a plurality of longitudinal steel bars and a steel wire mesh, wherein a plurality of longitudinal steel bars are parallel to each other and are arranged in sequence along the circumferential side of the frame beam, thereby forming a contour structure with a square cross section, and a plurality of transverse steel bars are connected between two adjacent longitudinal steel bars, so that the entire steel bar assembly is connected to each other to form a whole, and then the steel wire is quickly tied on the basis of the formation, and the tying position is the remaining gap position where the plurality of longitudinal steel bars and the transverse steel bars are connected to each other, and the steel wire mesh is formed by tying with steel wire, and the steel bar assembly There is no wire mesh at the bottom. At this time, steel fiber concrete can be sprayed on the remaining wire mesh except the bottom to form a side wall with a thickness of about 1 cm, which replaces the formwork, thereby reducing the formwork process; then, only concrete that meets the design strength needs to be sprayed inside the steel bar assembly to form a lattice beam. At this time, since there is no side formwork at the bottom of the lattice beam, the concrete sprayed inside can directly form a whole with the slope surface and achieve a close fit with the slope surface, thereby reducing the risk of fine particles in the lower part of the lattice beam being washed away by water on the fully weathered slope surface. There is no need to deal with uneven sections, and the pouring process can be reduced, greatly improving construction efficiency.

[0012] Further optimization is performed by providing longitudinal reinforcements at the end points of the cross section of the reinforcement assembly; by providing longitudinal reinforcements at the square ends, the structural stability of the frame beam can be improved.

[0013] Further optimization, the diameter of the steel wire used to bind the wire mesh is 0.5mm~1.5mm; this solution quickly and easily binds the steel wire on the side wall, so that the spacing between the steel wire, steel wire, and steel bar is about 1.5cm. The steel wire is soft, light, and easy to carry, and the steel wire can be quickly laid and connected on the slope.

[0014] A slope protection structure without formwork frame beams comprises a plurality of frame beams connected vertically and horizontally; the lower side of the slope protection structure is partially embedded in the groove of the slope; the lower side of the slope protection structure is partially embedded in the groove of the slope by 10cm to 20cm.

[0015] This scheme clears the soil or the fully weathered slope surface, marks the position of the frame beam on the slope surface according to the design requirements, and then cuts a groove within the marked range, that is, clears the fully weathered zone on the soil or slope surface, so that the frame beam is embedded in the slope surface to a certain depth, generally 10cm to 20cm. Since the concrete poured on the bottom side fits tightly with the slope surface and is embedded in the groove, it can reduce the erosion of the slope surface by rainwater and reduce the loss of fine particles in the slope body below the frame beam by water.

[0016] The construction method of the slope protection structure comprises the following steps:

[0017] Step 1: Clean the slope surface and carve grooves on it;

[0018] Step 2: arranging a plurality of longitudinal steel bars and transverse steel bars in the groove, and tying a steel mesh in the installation area surrounded by the plurality of longitudinal steel bars and transverse steel bars to form a plurality of longitudinally and transversely connected steel bar assemblies;

[0019] Step 3: Then, concrete is sprayed on the steel wire mesh of the side walls of the plurality of steel bar assemblies, so that side forms are formed on the remaining circumferential sides of the steel bar assemblies except the bottom sides of the steel bar assemblies, and at this time, a lattice beam casting foundation is formed as a whole;

[0020] Step 4: Finally, concrete is sprayed inside the frame beam casting foundation to form a slope protection structure without formwork frame beams.

[0021] In the prior art, during the implementation of the frame beam, the slope surface is molded along the slope, and the steel bars are tied after the mold is erected. After the tying is completed, the pouring is carried out, and reinforcement holes (anchor cables, anchor piles, anchor rods, etc.) are reserved at the nodes of the frame beam. The slope anchor cables and anchor rods are constructed after the strength is equal. The on-site pouring process also includes the steps of mold erection, mixing, transportation, conveying, pouring, and vibration, which leads to complicated procedures, slow construction efficiency, and high construction cost. In particular, when applied to the overburden slope or the slope with a fully weathered bedrock surface, the soil under the frame beam is easily lost under the erosion of rainwater, resulting in the problem of the lower part of the frame beam being emptied. This scheme provides a construction method for a slope protection structure, in which a groove is cut on the soil slope or the fully weathered bedrock slope surface, so that the frame beam is embedded in the slope by about 10cm to 20cm, so as to reduce the loss of fine particles in the slope under the frame beam by water erosion. When tying the steel bars of the frame beam structure, the steel wires are quickly and simply tied on the side walls so that the spacing between the steel wires and between the steel wires and the steel bars is about 1.5 cm. The steel fiber concrete is sprayed on the side walls to quickly gain strength and form a thin wall, which replaces the vertical formwork to form a side formwork. Then, concrete that meets the strength requirements is sprayed layer by layer from the bottom inside the frame beam until the design requirements of the frame beam are met. At this time, since no side formwork is formed at the bottom of the frame beam, the concrete sprayed inside can directly form a whole with the slope surface and achieve a close fit with the slope surface. Therefore, on the fully weathered slope surface, the structure and method can reduce the loss of fine soil particles due to water erosion, and can reduce the processes of vertical formwork, mixing, transportation, conveying, pouring, vibrating, etc. during the on-site pouring process, thereby improving work efficiency and saving construction costs.

[0022] Further optimization, in step 2, the diameter of the steel wire used to bind the steel mesh is 0.5mm to 1.5mm.

[0023] Further optimization, in step three, the concrete sprayed on the steel wire mesh on the side walls of the several steel bar assemblies is steel fiber concrete; in this scheme, steel fiber concrete is a new type of multi-phase composite material formed by adding randomly distributed short steel fibers into ordinary concrete; steel fibers can effectively hinder the expansion of micro cracks inside the concrete and have a certain connection gap function.

[0024] Further optimization, in the step 4, spraying concrete inside the lattice beam casting foundation also includes the following specific steps:

[0025] Concrete with sufficient strength is sprayed layer by layer from the bottom inside the lattice beam casting foundation. The thickness of the sprayed layer is the designed height of the lattice beam, and the concrete strength is the designed strength of the lattice beam concrete, which meets the requirements of the lattice beam.

[0026] For further optimization, in the step 4, when spraying concrete inside the lattice beam casting foundation, the spraying thickness needs to exceed the original lattice beam design height, and then it is leveled with a scraper plate, and then the strength is waited after leveling.

[0027] Compared with the prior art, the present invention has the following advantages and beneficial effects:

[0028] 1. The present invention provides a formwork-free frame beam, a slope protection structure and a construction method thereof. The frame beam is embedded in the soil to a certain depth, which can well protect the soil below the frame beam from being washed away by rainwater; the steel mesh is densely packed on the side wall of the frame beam, and steel fiber concrete is sprayed to make it harden quickly, which can replace the formwork process; concrete that meets the design strength and frame beam height requirements is sprayed to replace the processes of pouring concrete and vibrating concrete. By using this structure and casting method, the formwork and casting processes are reduced, so that the implementation efficiency is improved, the construction cost is reduced, and the safety risks during the construction period are also reduced.

[0029] 2. The present invention provides a formwork-free frame beam, a slope protection structure and a construction method thereof. Since there is no wire mesh at the bottom of the frame beam, a side form cannot be formed at the bottom, and the concrete inside can directly form a whole with the slope surface to achieve a close fit with the slope surface, thereby reducing the risk of fine particles in the lower slope of the frame beam being washed away by water on a fully weathered slope. There is no need to deal with uneven sections, and the pouring process can be reduced, thereby greatly improving the construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] In order to more clearly illustrate the technical solutions of the exemplary embodiments of the present invention, the following briefly introduces the drawings required for use in the embodiments. It should be understood that the following drawings only illustrate certain embodiments of the present invention and should not be regarded as limiting the scope. For those of ordinary skill in the art, other relevant drawings can be obtained based on these drawings without creative work. In the drawings:

[0031] Figure 1 A plan view of a local structure of a slope protection structure according to an embodiment of the present invention;

[0032] Figure 2 A schematic cross-sectional view of a lattice beam according to an embodiment of the present invention;

[0033] Figure 3 A top view of a lattice beam according to an embodiment of the present invention;

[0034] Figure 4 A flowchart of the steps of a construction method according to an embodiment of the present invention.

[0035] Marks and corresponding parts names in the attached drawings:

[0036] 1- lattice beam, 2- reinforcement assembly, 3- longitudinal reinforcement, 4- wire mesh, 5- transverse reinforcement. DETAILED DESCRIPTION

[0037] In order to make the objectives, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with embodiments and drawings. The exemplary embodiments of the present invention and their description are only used to explain the present invention and are not intended to limit the present invention.

[0038] Example 1

[0039] This embodiment 1 provides a frame beam without a formwork, such as Figure 1-Figure 3 As shown, the lattice beam 1 has a steel bar assembly 2 inside;

[0040] The cross section of the steel bar assembly 2 is square; the steel bar assembly 2 includes a plurality of longitudinal steel bars 3 and transverse steel bars 5, the plurality of longitudinal steel bars 3 are parallel to each other and are sequentially arranged at intervals on the circumferential side of the lattice beam 1, and the transverse steel bars 5 are arranged between adjacent longitudinal steel bars 3;

[0041] Except for the bottom side of the steel bar assembly 2, the installation area surrounded by the longitudinal steel bars 3 and the transverse steel bars 5 on the other sides of the steel bar assembly 2 is provided with a tied steel wire mesh 4.

[0042] Compared with the prior art, if the slope is an earth slope or a fully weathered gravel soil, it is necessary to cut grooves on the slope. After the cutting is completed, steel bars are tied in the grooves. After the steel bars are tied, the formwork is installed. Each formwork is transported and installed, and then dismantled and transported after use. The formwork and demoulding processes are relatively complicated and have low efficiency. There are uneven areas on the local slope, and it is difficult for the bottom surface of the side formwork to be tightly combined with the slope. It is time-consuming and labor-intensive to handle the uneven sections (sometimes crushing equipment is required), resulting in low efficiency, increased costs, and increased safety risks. The present invention provides a frame beam 1 without formwork. By adopting this solution, casting can be carried out directly inside the frame beam, so there is no need to handle the uneven sections, and a close fit with the slope is achieved. Concrete can be sprayed at the wire mesh 4 to form a side formwork, thereby greatly reducing the processes such as formwork and casting, thereby improving the implementation efficiency, reducing the construction cost, and also reducing the safety risks during the construction period.

[0043] In the specific scheme, the skeleton structure inside the lattice beam 1 is a steel bar assembly 2, and the steel bar assembly 2 is formed by splicing and binding a plurality of transverse steel bars 5, a plurality of longitudinal steel bars 3 and a steel mesh 4, wherein the plurality of longitudinal steel bars 3 are parallel to each other and are sequentially arranged along the circumferential side of the lattice beam 1, thereby forming a profile structure with a square cross section, and a plurality of transverse steel bars 5 are connected between two adjacent longitudinal steel bars 3, so that the entire steel bar assembly 2 is connected to each other to form a whole, such as Figure 2Then, the steel wire is quickly tied on the basis of the formation, and the tying position is the remaining gap position where several longitudinal steel bars 3 and transverse steel bars 5 are connected to each other, and the steel wire is tied to form a wire mesh 4, such as Figure 3 As shown, the bottom of the steel bar assembly 2 is not provided with a steel mesh 4. At this time, steel fiber concrete can be sprayed on the remaining steel meshes 4 except the bottom to form a side wall with a thickness of about 1 cm, so that it can replace the formwork, thereby reducing the formwork process; then, it is only necessary to spray concrete that meets the design strength inside the steel bar assembly 2 to form the lattice beam 1. At this time, since no side form is formed at the bottom of the lattice beam 1, the concrete sprayed inside can directly form a whole with the slope surface to achieve a close fit with the slope surface, thereby reducing the risk of fine particles in the lower slope of the lattice beam 1 being washed away by water on the fully weathered slope surface, and there is no need to deal with uneven sections, and the pouring process can also be reduced, which greatly improves the construction efficiency.

[0044] like Figure 2 As shown, in this embodiment, longitudinal steel bars 3 are provided at the end points of the cross section of the steel bar assembly 2; by providing the longitudinal steel bars 3 at the square ends, the structural stability of the frame beam can be improved.

[0045] In this embodiment, the diameter of the steel wire used to bind the steel mesh 4 is 0.5 mm to 1.5 mm. This solution allows the steel wire to be quickly and easily bound on the side wall, so that the spacing between the steel wire, the steel wire, and the steel bar is about 1.5 cm. The steel wire is soft, light, and easy to carry. The steel wire can be quickly laid and connected on the slope.

[0046] Example 2

[0047] This embodiment 2 is further optimized on the basis of embodiment 1, and provides a slope protection structure without formwork frame beams, including a plurality of frame beams 1 connected vertically and horizontally; the lower side surface of the slope protection structure is partially embedded in the groove of the slope; the lower side surface of the slope protection structure is partially embedded in the groove of the slope by 10cm to 20cm.

[0048] In this embodiment, the soil or the fully weathered slope surface is cleaned, the position of the frame beam 1 is marked on the slope surface according to the design requirements, and then a groove is carved within the marked range, that is, the soil or the fully weathered zone on the surface of the slope surface is removed, so that the frame beam 1 is embedded in the slope surface to a certain depth, generally 10 cm to 20 cm. Since the concrete poured on the bottom side is closely attached to the slope surface and embedded in the groove, the scouring of the slope surface by rainwater can be reduced, and the fine particles of the slope body below the frame beam 1 can be reduced from being washed away by water.

[0049] Example 3

[0050] This embodiment is further optimized on the basis of Embodiments 1 and 2. Figure 4 As shown, a construction method of a slope protection structure is provided, comprising the following specific construction steps:

[0051] Step 1: clean the soil or the fully weathered slope, mark the position of the frame beam 1 on the slope according to the design requirements, and then make grooves within the marked range, that is, remove the fully weathered zone on the soil or slope surface, so that the frame beam 1 can be embedded in the slope to a certain depth, generally 10cm to 20cm, to reduce the loss of fine particles in the slope below the frame beam 1 by water erosion.

[0052] Step 2: Then set a number of longitudinal steel bars 3 and transverse steel bars 5 in the groove, connect the longitudinal steel bars 3 and transverse steel bars 5 to form a skeleton, and quickly and simply tie steel wires on the side walls of the frame beam 1 structure after the steel bars are tied. The diameter of the thin steel wire is 0.5mm to 1.5mm, so that the distance between the steel wires, steel wires, and steel bars is about 1.5cm. Figure 1-Figure 3 shown.

[0053] Step 3: Mix steel fiber concrete. Steel fiber concrete is a new type of multi-phase composite material formed by adding randomly distributed short steel fibers to ordinary concrete. Steel fibers can effectively hinder the expansion of micro cracks inside concrete and have a certain role in connecting gaps.

[0054] Step 4: Use the mixed steel fiber concrete to spray the steel wire mesh 4 steel bar side wall except the bottom of the frame beam 1, so that it can quickly form a side wall with a thickness of about 1 cm, so that it can replace the template (concrete template). After the side template quickly has strength, it forms the template.

[0055] Step 5: Then spray concrete with sufficient strength layer by layer from the bottom inside the frame beam 1. The thickness of the spray layer is the designed height of the frame beam 1, and the concrete strength is the designed strength of the concrete of the frame beam 1, which meets the requirements of the frame beam 1.

[0056] Step 6: On the basis that the thickness of the sprayed layer meets the design height of the lattice beam 1 (about 0.5cm higher than the original design height), use a hanging plate to scrape it flat and wait for the strength after scraping it flat.

[0057] Through the above scheme, grooves are carved on the soil slope or the fully weathered bedrock slope, so that the frame beam 1 is embedded in the slope by about 10cm to 20cm, so as to reduce the loss of fine particles in the lower part of the frame beam 1 by water erosion. When tying the structural steel bars of the frame beam 1, the steel wires are quickly and simply tied on the side wall, so that the spacing between the steel wires and the steel wires and the steel bars is about 1.5cm, and the steel fiber concrete is sprayed on the side wall to quickly have strength and form a thin wall, so that it replaces the vertical formwork to form a side formwork; then concrete that meets the strength is sprayed layer by layer from the bottom inside the frame beam 1 until the design requirements of the frame beam 1 are met. At this time, since there is no side formwork formed at the bottom of the frame beam 1, the concrete sprayed inside can directly form a whole with the slope surface, and achieve close fit with the slope surface, so that on the fully strongly weathered slope surface, the structure and method can reduce the loss of fine particles in the soil by water erosion, and can reduce the processes of vertical formwork, mixing, transportation, conveying, pouring, vibration and tamping during on-site pouring, improve work efficiency and save construction costs.

[0058] The specific implementation methods described above further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above description is only a specific implementation method of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.

Claims

1. A construction method for a slope protection structure, characterized in that: The slope protection structure comprises a plurality of lattice beams (1) connected vertically and horizontally; the lower side surface of the slope protection structure is partially embedded in the groove of the slope; The lattice beam (1) has a steel bar assembly (2) inside; The cross section of the steel bar assembly (2) is square; the steel bar assembly (2) comprises a plurality of longitudinal steel bars (3) and transverse steel bars (5); the plurality of longitudinal steel bars (3) are parallel to each other and are sequentially arranged at intervals on the circumferential side of the lattice beam (1); and the transverse steel bars (5) are arranged between adjacent longitudinal steel bars (3); Except for the bottom side of the steel bar assembly (2), a steel wire mesh (4) formed by binding is provided in the installation area surrounded by the plurality of longitudinal steel bars (3) and transverse steel bars (5) on the remaining side of the steel bar assembly; The construction method comprises the following steps: Step 1: Clean the slope surface and carve grooves on it; Step 2: arranging a plurality of longitudinal steel bars (3) and transverse steel bars (5) in the groove, and tying a steel mesh (4) in the installation area surrounded by the plurality of longitudinal steel bars (3) and transverse steel bars (5) to form a plurality of longitudinally and transversely connected steel bar assemblies (2); Step 3: Then, concrete is sprayed on the steel meshes (4) on the side walls of the plurality of steel bar assemblies (2), so that side forms are formed on the remaining circumferential sides of the steel bar assemblies (2) except for the bottom sides of the steel bar assemblies (2), and at this time, a lattice beam casting foundation is formed as a whole; Step 4: Finally, concrete is sprayed inside the frame beam casting foundation to form a slope protection structure without formwork frame beams.

2. The construction method of a slope protection structure according to claim 1, characterized in that: Longitudinal steel bars (3) are provided at the end points of the cross section of the steel bar assembly (2).

3. The construction method of a slope protection structure according to claim 1, characterized in that: The lower side of the slope protection structure is partially embedded in the groove of the slope by 10 cm to 20 cm.

4. The construction method of a slope protection structure according to claim 1, characterized in that: In the step 2, the diameter of the steel wire used to bind the steel mesh (4) is 0.5 mm to 1.5 mm.

5. The construction method of a slope protection structure according to claim 1, characterized in that: In the step three, the concrete sprayed onto the steel wire meshes (4) on the side walls of the plurality of steel bar assemblies (2) is steel fiber concrete.

6. The construction method of a slope protection structure according to claim 1, characterized in that: In the step 4, spraying concrete inside the lattice beam foundation casting process also includes the following specific steps: Concrete with sufficient strength is sprayed layer by layer from the bottom inside the lattice beam casting foundation, the thickness of the sprayed layer is the designed height of the lattice beam (1), and the concrete strength is the designed concrete strength of the lattice beam (1), meeting the requirements of the lattice beam (1).

7. The construction method of a slope protection structure according to claim 1, characterized in that: In the step 4, when spraying concrete inside the lattice beam casting foundation, the spraying thickness needs to exceed the original lattice beam design height, and then it is leveled with a scraper plate, and then the strength is waited after leveling.