Method for laying ballasted track on small radius curve tram joint line
Through the laying method of small-radius curve seam lines and ballast tracks, using technologies such as encrypted layout of sleepers and concrete piers, the problems of difficult bending of tracks and insufficient line smoothness on small-radius curves are solved, and the smoothness and safety of the tracks are achieved. , reducing the cost of later maintenance.
Patent Information
- Application Number
- CN202410664707.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-27
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2044-05-27
AI Technical Summary
On small radius curves, the prior art is difficult to ensure the fixed value of track bending and line smoothness, and the pre-bending of the rail is difficult to meet the operating smoothness requirements.
The method of laying ball tracks with small radius curves is adopted, including measurement and review, bottom ball laying, sleeper placement, installation of rail and fastener accessories, whole balling, measurement and pier construction, and laying of sleepers through encrypted layout and concrete Piers and elastic fasteners ensure the accuracy of track line shape and elevation.
The smoothness and safety of small-radius curved tracks have been achieved, reducing investment in later operation and maintenance, and improving construction efficiency and economic benefits.
Smart Images

Figure CN118375010B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of tram track laying construction, and in particular to a method for laying ballasted tracks of small-radius curve tram seam lines. Background Art
[0002] When there is a large overlap between the subway station and the existing operating tram, the tram needs to be temporarily rerouted before the subway construction can be carried out in the overlapping part. According to the "Metro Design Specifications", when the curve radius is less than 350m, it is a small radius curve. Due to site restrictions, the curve radius of the tram temporary reroute project is less than 350m. On a small radius curve, it is extremely difficult to use a track bender to pre-bend the track. In addition, the joint position of the small radius curve is not easy to bend because the rail is not easy to bend. The rail is in a V shape without external force, which cannot meet the line smoothness requirements.
[0003] The Chinese patent with announcement number CN106368089B discloses a construction method for laying and linear control of small radius curve tracks for trams, and the construction method includes: construction preparation; measurement and layout; long rail traction; long rail guide bending; long rail temporary fixation; rail row support; fastener assembly; track fine adjustment and other steps. This construction method uses standard steel rails to weld into long rails, and then uses rail clamps with a winch to pull the long rails to the position to be laid, and sets pulleys and guide pulleys at the target position of the rails. While the long rails are being pulled, corresponding temporary fixation is performed, and finally the long rails are finely adjusted to complete the arrangement of the designed position. The main problem solved by this method is how to ensure the roundness of the curve of the curved part of the track, and overcome the shortcomings of the prior art that the rails are pre-bent by a straight rail machine, the fixed value of the track bending cannot be guaranteed, obvious deformation will be left at the track force point and cannot be restored, and the operation process is inefficient.
[0004] However, this method still cannot solve the problem that it is extremely difficult to pre-bend the rails using a track bender on a small radius curve, and the rails are not easy to bend at the joints of the small radius curve, so the rails are in a V-shape without external force, which cannot meet the line smoothness requirements. Summary of the invention
[0005] The problem to be solved by the present invention is: how to realize the laying of ballasted track on a small-radius curve tram joint line to ensure that the linear control of the small-radius curve track meets the requirements of operational smoothness.
[0006] The technical solution adopted by the present invention is a method for laying ballasted track on a small-radius curve tram joint line, comprising the following steps:
[0007] S1. Construction preparation: measure and verify the elevation of the roadbed surface, and stake out the center piles and side piles of the line;
[0008] S2. Ballast laying: measure and mark out the outer edge of the ballast laying, calculate the height of ballast required for each section according to the loose laying coefficient, and then spread and compact the ballast;
[0009] S3. Laying down sleepers: According to the survey and layout, the left side of the line and the outer part of the curve are taken as the basic rails and the basic rail sleepers are squared; the sleepers are spread on the ballast and placed according to the rail section table. Through measurement and positioning, a sleeper is fixed every 3 meters on the small radius curve by driving two ground anchors within the width of the sleeper; and the sleepers are densely arranged at the rail joint position on the small radius curve, and fixed with additional struts;
[0010] S4. Installation of rails and fasteners: When laying the track, after the track gauge at the small radius curve joint is controlled to the design value, the fishtail clamp is connected;
[0011] S5, Ballasting and track leveling: gradually leveling the newly laid track;
[0012] S6. Measurement and verification: Check the plane and elevation of the center line and curve element positions of the track line, whether the track gauge widening and curve superelevation meet the design requirements, ensure the accuracy of the line, and check whether the sleepers are square, whether the rail buckle accessories and joint clamps are installed correctly, and whether the bolts are tightened along the entire length of the line;
[0013] S7. Pier construction: After all inspections and verifications are completed, plan out an area of the size of four sleepers on the outside of the sleepers at the outer joints of the small radius curve, and construct reinforced concrete piers to rest against the ends of the four sleepers.
[0014] Furthermore, in the above step S2, the ballast is controlled to be 3-5 cm lower than the design elevation after compaction.
[0015] Furthermore, in the above step S3, the sleeper spacing at the rail joint position on the small radius curve is 550mm, and for a curve radius of 50≤R<100 meters, three additional struts are installed before and after the joint for each sleeper, and for a curve radius of R≥100 meters, two additional struts are installed before and after the joint for each sleeper. Ground anchors are provided at a distance of 1 meter on both sides of the sleepers, and both ends of the struts are respectively fixedly connected to the sleepers and corresponding ground anchors. The direction of the struts is in a straight line with the sleepers, and the sleepers are aligned.
[0016] Furthermore, the ballast-loading and track leveling operation in step S5 includes squaring the sleepers, supplementing and tightening the accessories and fasteners, adjusting the track direction, stringing the ballast under the sleepers at the rail bearings, and eliminating the reverse superelevation and triangular pits. The specific steps are as follows:
[0017] (1) Track shifting: shift the track to the centerline position, with the track centerline deviation less than 30 mm;
[0018] Square sleepers: After the track is shifted, the bent and slanted sleepers are squared to control the spacing and deflection of the sleepers within 2cm;
[0019] (2) Ballasting: After track laying is completed, ballast is evenly spread on the track by machine or manually;
[0020] (3) Track raising: Use a hydraulic track raising and shaving machine to raise each track section at several points and pad it with ballast. The amount of track raising at one time shall not exceed 15 cm. The track shall be raised to the designed elevation and slightly increased by 10 mm for settlement. The outer rail of the curve shall be raised to the required superelevation. After track raising, the front-to-back height deviation of the track shall be ≤5 mm and the left-right horizontal deviation shall be ≤5 mm. When raising the track, first calibrate the elevation of one track section (the inner track section for the curve), and adjust the elevation of the other track section accordingly. The track elevation deviation shall be -30 to +50 mm.
[0021] (4) Ballasting: After the track is raised, the ballast on the shoulder is filled into the sleeper box;
[0022] (5) Tamping: Tamp the ballast within 45 cm on the outside and inside of the rails. Tamp the ballast within 60 cm in the middle of the sleeper. Strengthen the tamping of the area under the rails, rail joints and outer rails of the curve.
[0023] (6) Track leveling: Correct the plane position of the line and make the track center line consistent with the line center; repair the roadbed, replenish the ballast in the sleeper box, compact the roadbed slope and top surface and keep them stable; straighten the track, correct the hard bends of the rails to achieve a straight and smooth track, level the small depressions at the start of the track, and correct the left and right level and the front and back height of the rails; put the sleepers in place and tighten the fasteners;
[0024] (7) Tightening: Tighten the joint bolts every day to ensure that the torque reaches above 500 N.m. Tighten the rail fasteners regularly and keep the torque between 100 and 140 N.m.
[0025] Furthermore, in the above step S7, the pier is 2.5m long, 1m wide, and more than half the height from the top of the roadbed to the end of the sleeper. A double-layer, bidirectional steel mesh is arranged. The concrete pier wraps the prestressed steel bars of the positioned sleepers and fits tightly to the sleepers. The vertical steel bars are implanted in the roadbed. After the concrete strength reaches 100%, the support rod structure is removed.
[0026] Furthermore, the ballast bed constructed by this method adopts a crushed stone ballast bed, the rail laying adopts a seam line, a 59R2 grooved rail, a rail bottom width of 180mm, and no rail bottom slope, the rail groove width is 355mm, the distance from the center line of the rail groove on both sides to the center line of the sleeper is 734.625mm, anchor holes are respectively arranged on both sides of the rail groove, the rail adopts a 25m standard rail, the fastener accessories adopt spring bar type I fasteners, and the rail slope of the spring bar type I fastener at the gauge baffle buckling position is 1:10.
[0027] Compared with the prior art, the present invention has the following beneficial effects:
[0028] The method for laying ballasted track on a small-radius curve tram seamless line provided by the present invention realizes the laying of ballasted track with a curve radius designed to be 50m, and the ballasting and whole track on the small-radius curve can meet the line operation conditions at one time, ensuring smooth and safe driving, and achieving better technical and economic benefits.
[0029] In addition to the above effects, the present invention also has the following advantages:
[0030] (1) Concrete piers are used at small radius curve joints to effectively fix the track line shape, ensure the stability of the line in later operation, and reduce the investment in later operation maintenance;
[0031] (2) Arrange sleepers more densely at rail joints on small-radius curves to increase the stability of rail joints;
[0032] (3) First adjust the fixed small radius curve track joint position, then raise the line to the design elevation, adjust the track geometry to the specified range, and finally perform ballasting and tamping to avoid secondary adjustment of the track linearity after the line is raised;
[0033] (4) For small radius curves, track start and line shape adjustment are completed first, which makes it easier to interchange the positions of spring clip type I fasteners for track gauge adjustment, reducing the labor and mechanical input for secondary track gauge adjustment and improving work efficiency.
[0034] (5) It requires fewer mechanical equipment, reduces labor input, is easy to operate, and can effectively improve work efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] Figure 1 Flow chart of the method for laying ballasted track for a tram jointed line with a small radius curve;
[0036] Figure 2 This is a schematic diagram of the support pole installation;
[0037] Figure 3 Schematic diagram of the fixed rails supported by the braces and piers;
[0038] Figure 4 This is a top view of the buttress;
[0039] Figure 5 This is a schematic diagram of the sleeper structure;
[0040] Figure 6 This is a schematic diagram of the installation of spring clip accessories;
[0041] Figure 7 Schematic diagram of the gauge baffle structure;
[0042] Figure 8 This is a schematic diagram of the structure of the working side splint of the fishtail splint;
[0043] Fig. 9 This is a schematic diagram of the structure of the non-working side plywood of the fishtail plywood;
[0044] Markings in the figure: 1. Pier, 2. Sleeper, 201, Rail groove, 3. Strut, 4. Ground anchor, 5. Roadbed, 6. Vertical reinforcement, 7. Circumferential reinforcement, 8. Diagonal reinforcement, 9. Spring bar, 10. Gauge baffle, 11. Baffle seat, 12. Spiral spike, 13. Nut. DETAILED DESCRIPTION
[0045] The present invention will be further explained below in conjunction with the accompanying drawings to facilitate better understanding by those skilled in the art.
[0046] Example 1
[0047] See also Figure 1-9 The method for laying ballasted track on a small radius curve tram joint line comprises the following steps:
[0048] S1. Construction preparation: measure and verify the elevation of the roadbed surface, and stake out the center piles and side piles of the line;
[0049] S2. Ballast laying: measure and mark out the outer edge of the ballast laying, calculate the height of the ballast to be laid in each section according to the loose laying coefficient, and then spread and compact the ballast. Control the ballast to be 3 to 5 centimeters lower than the design elevation after compaction, which can reduce the adjustment of the track line shape during the later stage of the small radius curve.
[0050] S3. Placement of sleepers: Lay out the lines according to the measurements, with the left side of the line and the outer part of the curve as the basic track. After the basic track is determined, use a square caliper to square the sleepers.
[0051] After the basic track is determined, sleepers 2 are first spread on the ballast. The sleepers are placed according to the rail table. Through measurement and positioning, two ground anchors are used to fix a sleeper every 3 meters on the small radius curve within the width of the sleeper 2. The anchor material is 32 round steel, and the bottom is deep below the base. Sleepers 2 are densely arranged at the rail joint position on the small radius curve. The spacing between sleepers 2 is 550mm, and a support rod 3 is attached to one side of the sleeper 2 for fixing. For a curve radius of 50≤R<100m, three support rods are attached before and after the joint, R For curve radius ≥100 meters, two additional struts 3 are installed before and after the joint for two sleepers. Ground anchors 4 are provided at a distance of 1 meter on both sides of the sleeper 2. Both ends of the struts 3 are fixedly connected to the sleeper 2 and the corresponding ground anchors 4 respectively. The ground anchors 4 are fixedly connected to the roadbed 5. The struts 3 and the sleepers 2 remain in a straight line, and the length of the struts 3 is adjustable for easy installation. The sleepers 2 are aligned to ensure that the sleepers 2 will not move after the rails are installed, and the line curve will not be deformed, thereby reducing the problems of the sleepers 2 failing to be squared according to the curve shape and the large amount of line shape adjustment during subsequent ballasting and track leveling.
[0052] S4. Installation of rails and fasteners: When laying the track, the track gauge at the small radius curve joint must be controlled to the design value before the fishtail clamp is connected to avoid adjusting the track gauge after the joint is connected, which will affect the joint and cause secondary construction.
[0053] S5. Ballasting and track leveling: Manual ballasting and track leveling is the process of gradually leveling the newly laid track with manual labor and small machinery during each ballast replenishment. The key points of the operation are: square the sleepers, replenish and tighten the accessories and fasteners, adjust the track direction, tighten the ballast under the sleepers at the rail support, and eliminate reverse superelevation and triangular pits. The specific steps are as follows:
[0054] (1) Track shifting: shift the track to the centerline position, with the track centerline deviation less than 30 mm;
[0055] (2) Square sleepers: After the track is shifted, the bent and slanted sleepers must be squared so that the spacing and deflection of the sleepers are controlled within 2 cm;
[0056] (3) Ballasting: After track laying is completed, the ballast is evenly spread on the track by machine or manually;
[0057] (4) Track raising: Use a hydraulic track raising and shaving machine to raise each track section at several points and pad it with ballast. The track raising amount at one time shall not exceed 15 cm. The track shall be raised to the designed elevation and slightly increased by 10 mm for the settlement. The outer rail of the curve shall be raised to the required superelevation. After track raising, the front and rear height deviation of the track shall be ≤5 mm and the left and right horizontal deviation shall be ≤5 mm. When raising the track, first calibrate the elevation of one track section. The curve is the inner track section, and adjust the elevation of the other track section accordingly. The track elevation deviation shall be -30 to +50 mm.
[0058] (5) Ballast filling: After the track is raised, the ballast on the shoulder should be filled into the sleeper box for effective tamping;
[0059] (6) Tamping: Tamp the ballast within 45cm outside and inside the rails to ensure that it can withstand the load of the train. It is strictly forbidden to tamp within 60cm of the middle of the sleeper; the tamping below the rails should be strengthened, and the tamping range of the rail joints and the outer strands of the curve should be strengthened; when tamping manually, the "five sufficiencies" should be achieved, namely: sufficient height of the pick, sufficient tamping force, sufficient eight-sided picks, sufficient number of tamping picks and sufficient tamping width to ensure the tamping quality;
[0060] (7) Track leveling: Correct the plane position of the line and make the track center line consistent with the line center; repair the roadbed, replenish the ballast in the sleeper box, compact the roadbed slope and top surface and keep them stable; straighten the track, correct the hard bends of the rails to achieve a straight and smooth track, level the small depressions at the start of the track, and correct the left and right level and the front and back height of the rails; put the sleepers in place and tighten the fasteners;
[0061] (8) Tightening: The joint bolts should be tightened every day to ensure that the torque reaches 500N.m or above. The rail fasteners should be tightened regularly and the torque must always be maintained at 100~140N.m.
[0062] S6. Measurement verification: Conduct plane and elevation measurement verification on the center line of the track and the position of curve elements, and check whether the track gauge widening and curve superelevation meet the design requirements to ensure the accuracy of the line. Check along the entire length of the line to see if the sleepers are square, whether the rail buckle accessories and joint clamps are installed correctly, and whether the bolts are tightened.
[0063] S7, pier construction: after all inspections and verifications are completed, plan out an area of the size of four sleepers on the outside of the sleepers at the outer joint of the small radius curve, and construct reinforced concrete piers against the ends of the four sleepers. The top surface of the pier should be more than half and less than two-thirds of the height of the sleeper end surface; Figure 2 As shown, the pier 1 is 2.5m long, 1m wide, and has a height from the end face of the roadbed 5 to the upper part of the sleeper 2. One side of the pier 1 is against the end faces of the four sleepers 2 before and after the joint, and the bottom is fixed to the roadbed 5. Multiple vertical bars 6 are arranged in the pier 1, and the lower ends of the multiple vertical bars 6 are embedded in the roadbed 5. The multiple vertical bars 6 are arranged at intervals and fixed with the circumferential steel bars 7 arranged at the top and middle. It also includes oblique bars 8, and the two ends of the oblique bars 8 are welded to the top of the left vertical bar 6 and the bottom of the right vertical bar 6. After the concrete strength reaches 100%, the support rod 3 structure is removed. Concrete model ≥ C30, steel bar model ≥ C12.
[0064] The ballast track laying method for the small radius curve tram joint line adopts a crushed stone ballast track, and the rails are laid on the same 59R2 groove rails as the original line. The 59R2 groove rails have a rail bottom width of 180mm and no rail bottom slope. The sleepers 2 adopt improved new II-type sleepers, and the fasteners adopt improved spring bar I-type fasteners. The rails adopt 25m standard rails. The improved sleeper 2 is 2500mm long, the width of the rail groove 201 is 355mm, the distance from the center line of the rail groove 201 on both sides to the center line of the rail is 734.625mm, and anchor holes are set on both sides of the rail groove 201.
[0065] The spring clip fastener includes a spring clip 9 and a gauge baffle 10 arranged above the sleeper 2. The rear end of the gauge baffle 10 abuts against the baffle seat 11, and the front end is kept in close contact with the rail bottom. The baffle seat 11 is close to the sleeper shoulder. The spring clip 9 is installed on the gauge baffle 10 and is connected and fastened with matching spiral spikes 12 and nuts 12. The front end lower chin of the middle part of the spring clip 9 contacts the gauge baffle 10, and the torque of the nut 13 is maintained at 100~140N.m. The rail slope at the gauge baffle buckling position is 1:10.
[0066] Application Examples
[0067] The temporary rerouting project of tram line 1 in a certain city has a total length of 472.289m. The line includes 5 small radius curves with the smallest radius of 50m and a length of 103m. The ballast bed adopts gravel ballast bed, and the rails adopt the same 59R2 grooved rails as the original line. The sleepers adopt the improved new type II sleepers, the fastener accessories adopt the improved spring bar type I fasteners, and the rails adopt the 25m standard rails.
[0068] By adopting this method during the construction process, all processes such as ballast laying, sleeper placement, rail buckle accessory installation, track lifting and track shifting can be completed in one go, which greatly saves construction time. In addition, because concrete reinforcement is adopted at the small radius curve joints, driving safety is ensured after the line is connected, the workload of subsequent track maintenance is reduced, and the difficulty of maintenance construction is reduced. It has a very high value of promotion and application in similar projects in the future.
[0069] Economic Benefits
[0070] Compared with the traditional laying process, this method adopts the process of "first adjusting the fixed line shape, and then ballasting and leveling the track". Although some materials such as top support and pier concrete and corresponding personnel input are increased, the track laying construction progress is fast because the small radius curve line shape problem is handled during the implementation of the method. It also avoids the problems of the quadratic squareness, line shape, and track gauge of the sleepers on the later curves, greatly reducing the construction machinery and personnel input required for the later line shape processing. This method can reduce construction costs while ensuring the construction quality of the track.
[0071] (1) Materials and construction personnel investment for top support and pier concrete: RMB 15,000
[0072] (2) Activity income:
[0073] Savings on machinery costs: 20 days × 1 machine × 1,500 yuan / day = 30,000 yuan
[0074] Savings on labor costs: 20 days × 20 people × 220 yuan / day = 88,000 yuan
[0075] Savings on employee wages: 20 days × 40 people × 280 yuan / day = 224,000 yuan
[0076] Conclusion: The economic benefit just achieved is 22.4+8.8+3-1.5=327,000 yuan
[0077] Social Benefits
[0078] The line shape control problem of small radius curves was implemented in advance before laying, which accelerated the track laying construction progress and avoided the problems of quadratic squareness, line shape, and track gauge of the sleepers on the later curves. It greatly reduced the construction machinery and personnel investment required for the later line shape processing, and the construction period benefit was obvious.
[0079] In summary, the present invention changes the traditional construction sequence of ballast and track leveling by first adjusting the fixed line shape and then ballasting and leveling the track, places the track start and line shape adjustment of the small radius curve line before ballast tamping, and during track laying, densely arranges sleepers at the rail joint position, and adds concrete piers next to the sleepers to fix the sleepers, so as to offset the bending stress of the rails themselves and ensure the control accuracy of the line shape and track elevation of the small radius curve line; after the sleepers are placed, the rails are laid and the buckle accessories are installed, and the sleepers are fixed at the end of the rails with support rods, and then the sleepers are fixed by the support rods. The rails are fixed by sleepers, and the rails are bent by construction machinery to enter the rail bearing groove. Then the buckle accessories are installed to tighten the rails to prevent the rail ends from deformation due to excessive bending stress. After completing the above steps, the line is ballasted to ensure that the line shape and elevation are in place at one time. Finally, concrete piers are constructed at the anchor position outside the curve to ensure that after the track is laid, the track will not be deformed due to external forces during operation. The track line shape can be effectively fixed to ensure the stability of the line in later operation and reduce the investment in later operation maintenance.
[0080] The above-described embodiments are only for describing the preferred implementation of the present invention, and are not intended to limit the scope of the present invention. Without departing from the design spirit and principles of the present invention, various modifications and improvements made by those skilled in the art to the technical solution of the present invention should all fall within the scope of protection determined by the claims of the present invention.
Claims
1. A method for laying ballasted track on a small radius curve tram line with seams, characterized in that: The following steps are involved: S1. Construction preparation: measure and verify the elevation of the roadbed surface, and stake out the center piles and side piles of the line; S2. Ballast laying: measure and mark out the outer edge of the ballast laying, calculate the height of ballast required for each section according to the loose laying coefficient, and then spread and compact the ballast; S3. Laying down sleepers: According to the survey and layout, the left side of the line and the outer part of the curve are taken as the basic rails and the basic rail sleepers are squared; the sleepers are spread on the ballast and placed according to the rail section table. Through measurement and positioning, a sleeper is fixed every 3 meters on the small radius curve by driving two ground anchors within the width of the sleeper; and the sleepers are densely arranged at the rail joint position on the small radius curve, and fixed with additional struts; S4. Installation of rails and fasteners: When laying the track, after the track gauge at the small radius curve joint is controlled to the design value, the fishtail clamp is connected; S5, Ballasting and track leveling: gradually leveling the newly laid track; S6. Measurement and verification: Check the plane and elevation of the center line and curve element positions of the track line, whether the track gauge widening and curve superelevation meet the design requirements, ensure the accuracy of the line, and check whether the sleepers are square, whether the rail buckle accessories and joint clamps are installed correctly, and whether the bolts are tightened along the entire length of the line; S7, Pier construction: After all inspections and verifications are completed, plan out an area of the size of four sleepers on the outside of the sleepers at the outer joint of the small radius curve, and construct reinforced concrete piers against the ends of the four sleepers; Among them, the ballast-loading and track-leveling operation in step S5 includes square rail sleepers, supplementing and tightening accessories and fasteners, adjusting the track direction, stringing the ballast under the sleepers at the rail bearings, and eliminating anti-superelevation and triangular pits. The specific steps are as follows: Track shifting: shift the line to the center line position, and the track center line deviation should be less than 30mm; Square sleepers: After the track is shifted, the bent and slanted sleepers are squared to control the spacing and deflection of the sleepers within 2cm; Ballasting: After track laying is completed, ballast is evenly spread on the track by machine or manually; Track raising: Use a hydraulic track raising and squaring machine to raise each track section at several points and pad it with ballast. The track raising amount at one time cannot exceed 15cm. The track is raised to the designed elevation and the settlement amount is increased by 10mm. The outer rail of the curve is raised as required. The front and rear height deviation of the track after track raising is ≤5mm, and the left and right horizontal deviation is ≤5mm. When raising the track, first calibrate the elevation of one track surface. The curve is the inner track, and adjust the elevation of the other track surface accordingly. The track surface elevation deviation is -30~+50mm. Ballasting: After the track is raised, the ballast on the shoulder is filled into the sleeper box; Tamping: tamp the ballast within 45cm outside and inside the rails. It is strictly forbidden to tamp the ballast within 60cm in the middle of the sleeper. Strengthen the tamping of the area under the rails, rail joints and outer strands of the curve. Track adjustment: Correct the plane position of the line, make the track centerline consistent with the line center; repair the roadbed, supplement the ballast in the sleeper box, compact the roadbed slope and top surface and keep it stable; adjust the track, correct the hard bend of the rail, make the straight line smooth, level the small depressions, correct the left and right level and the front and back height of the rail; put the sleepers in place and tighten the fasteners; Tightening: Tighten the joint bolts every day to ensure that the torque reaches above 500N·m. Tighten the rail fasteners regularly and keep the torque at 100~140N·m.
2. The method for laying ballasted track for a small radius curve tram line according to claim 1 is characterized in that: In step S2, the ballast is controlled to be 3-5 cm lower than the designed elevation after compaction.
3. The method for laying ballasted track for a small radius curve tram line according to claim 1 is characterized in that: In the step S3, the sleeper spacing at the rail joint position on the small radius curve is 550mm, and for the small radius curve of 50≤R<100 meters, three additional struts are provided before and after the joint for each sleeper, and for the small radius curve of R≥100 meters, two additional struts are provided before and after the joint for each sleeper, and ground anchors are provided at a distance of 1 meter on both sides of the sleeper, and the two ends of the struts are respectively fixedly connected to the sleeper and the corresponding ground anchors, and the direction of the struts is in a straight line with the sleeper to align the sleeper.
4. The method for laying ballasted track for a small radius curve tram line according to claim 1, characterized in that: In step S7, the pier is 2.5m long, 1m wide, and more than half the height from the top of the roadbed to the end of the sleeper. A double-layer bidirectional steel mesh is arranged in the roadbed. The concrete pier wraps the prestressed steel bars of the positioned sleepers and fits tightly to the sleepers. The vertical steel bars are implanted in the roadbed. After the concrete strength reaches 100%, the support rods are removed.
5. The method for laying ballasted track for a small radius curve tram line according to claim 1, characterized in that: The ballast bed constructed by this method adopts gravel ballast bed, and the rail laying adopts seam line. The bottom width of 59R2 grooved rail is 180mm, and there is no rail bottom slope. The width of the rail groove is 355mm, and the distance from the center line of the rail groove on both sides to the center line of the sleeper is 734.625mm. Anchor holes are arranged on both sides of the rail groove. The rail adopts 25m standard rail, and the fastener accessories are spring clip type I fasteners. The rail slope of the spring clip type I fastener at the gauge baffle buckling position is 1:10.