A kind of installation and maintenance platform for power equipment in thermal power plant and its maintenance method
By designing a foldable hanging basket structure and flexible installation of fences, the problem of size limitations of the boiler's internal maintenance equipment is solved, flexible maintenance and larger working space are achieved inside the boiler, and the flexibility and safety of the boiler's maintenance platform are improved. .
Patent Information
- Application Number
- CN202411119600.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-15
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2044-08-15
AI Technical Summary
Due to the limitation of manhole size during internal maintenance of the boiler, the existing boiler maintenance platform cannot successfully adapt to larger volume maintenance equipment, and the overall structure cannot meet the insulation requirements when used outside the boiler.
A installation and maintenance platform including a hoist and a hanging basket is designed. The hanging basket consists of a half-folded end frame, a bracket and a fence to achieve rapid assembly and stability of the structure through a relay frame and connecting seat, using steel cables and The reversing wheel improves lifting stability, and the fence can be installed horizontally to expand the working space.
The platform structure input through manholes is more flexible and powerful, can adapt to the internal maintenance needs of the boiler, and improve the operating space and load-bearing capacity through the design of the fence, simplify the installation steps, enhance the stability and flexibility of the structure. sex.
Smart Images

Figure CN118637536B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of lifting devices, and in particular relates to an installation and maintenance platform for power equipment in a thermal power plant and a maintenance method thereof. Background Art
[0002] Coal-fired power station boilers are key equipment in thermal power stations that convert the chemical energy of fuel - usually coal - into thermal energy, thereby generating steam to drive the steam turbine to generate electricity. They need to be inspected regularly during use, and when the boiler is damaged, it is also necessary to shut down and repair it in a timely manner.
[0003] The existing Chinese utility model patent with patent number CN220999144U discloses a normal pressure boiler maintenance and assembly platform. The lifting maintenance platform can drive workers to move up and down to avoid the risk of falling from the ladder during climbing. At the same time, the lifting maintenance platform can be raised and lowered to facilitate the maintenance or assembly of boilers at different heights, and has higher applicability.
[0004] In actual use, in order to ensure the thermal insulation performance of the boiler, the boiler will adopt a sealed hollow structure. The overall lifting and maintenance platform can only be used when the boiler is externally repaired. When the inside of the boiler needs to be repaired, the boiler can only be entered and exited through the manhole. During maintenance, personnel can be lowered into the manhole of the boiler through a rope. When parts need to be replaced and larger maintenance equipment is used, the lifting and maintenance platform also needs to be installed in the boiler manhole. Due to the size limitation of the manhole, the overall maintenance platform cannot smoothly adapt to the needs of this scenario. In view of this, this solution provides an installation and maintenance platform for power equipment in a thermal power plant and a maintenance method thereof. Summary of the invention
[0005] The technical problem to be solved by the present invention is to overcome the disadvantages of the above-mentioned prior art and provide an installation and maintenance platform for power equipment in a thermal power plant and a maintenance method thereof.
[0006] The technical solution adopted to solve the above technical problems is: an installation and maintenance platform for power equipment in a thermal power plant, comprising a hoist and a hanging basket, wherein the hanging basket comprises two end frames, a support frame is installed between the two end frames, a fence is installed at the edge of the support frame, and the end frames and the fence are arranged above the support frame to form a working space;
[0007] The end frame includes a main frame and a sub-frame, a relay frame is rotatably connected between the bottom end of the main frame and the top end of the sub-frame, and the sub-frame can rotate 180 degrees around the end of the main frame;
[0008] The support frame comprises two cross bars, the two cross bars are assembled and connected with the main frame, a bottom frame is installed between the two sub-frames parallel to the cross bars, a longitudinal bar is installed between the bottom frame and the cross bars, and a first gusset plate and a second gusset plate arranged in a stacked manner are installed between the two cross bars;
[0009] The fence comprises a side frame and a gantry frame. The side frame can be vertically installed on the top of the cross bar, and the side frame can be horizontally installed on the vertical side wall of the cross bar. A steel rope is connected through the edge of the gantry frame.
[0010] Furthermore, the main frame and the auxiliary frame both adopt a rectangular structure, the long sides of the main frame and the auxiliary frame are located at the top and bottom ends, and the relay frame is installed parallel to the long side of the main frame.
[0011] Through the above technical solution, after the main frame and the auxiliary frame are folded in half, the width is narrower and can adapt to the width of the manhole, so it is easy to be transported to the power station boiler. The main frame and the auxiliary frame are connected by the relay frame and do not need to be reassembled after input, which ensures the structural strength and simplifies the installation steps.
[0012] Furthermore, a connecting seat is rotatably installed in the middle of the main frame, the connecting seat is connected to the steel cable of the hoist, and a reversing wheel is installed at the short side of the main frame.
[0013] Through the above technical solution, during lifting, the connecting seat is rotated to overlap the steel cable at the position of the reversing wheel, and the long side of the end frame is lowered vertically, which makes the lowering smoother and avoids bumps. During assembly, the steel cable is separated from the reversing wheel, and the connecting seat is rotated ninety degrees to make the long side of the end frame horizontal, so as to facilitate subsequent connection into a support frame.
[0014] Furthermore, a socket is installed on the vertical side wall of the auxiliary frame, a vertically arranged pin rod is installed through the socket, and a pin hole 1 and a pin hole 2 cooperating with the pin rod are opened at the bottom of the main frame.
[0015] Through the above technical solution, during hoisting, the main frame and the auxiliary frame are folded in half, and the pin rod passes through the sleeve and pin hole one to prevent accidental unfolding during hoisting. During assembly, the main frame and the auxiliary frame are parallel, and the pin rod passes through the sleeve and pin hole two to ensure the stability of the end frame structure.
[0016] Furthermore, a vertical plug rod is fixedly installed at the bottom end of the side frame, vertical holes are penetrated on both sides of the top and bottom of the cross bar, horizontal holes are penetrated on the vertical side walls of the cross bar, and avoidance openings cooperating with the plug rod are opened at the ends of the longitudinal rods.
[0017] Through the above technical solution, the rod is inserted into the vertical hole to play a role of enclosure protection, and the rod is inserted into the horizontal hole, the fence and the support frame are level, which does not affect the original working space, and the gantry frame can be pulled out and extended to the required position.
[0018] Furthermore, the vertical side wall of the side frame is provided with two groups of outer holes arranged up and down, the vertical side wall of the gantry frame is provided with inner holes matching with the outer holes, and a limiting frame is inserted and installed between the inner hole and the outer hole.
[0019] Through the above technical solution, the two groups of outer holes correspond to the two position states of the gantry frame respectively, the gantry frame is fully inserted into the side frame, the limit frame is inserted into one group of outer holes and inner holes, and when the gantry frame is pulled out, the limit frame is inserted into the other group of outer holes and inner holes to ensure the stable position of the gantry frame.
[0020] Furthermore, an end block is installed at one end of the steel rope located on the inner side of the side frame, an end sleeve is installed at one end of the steel rope located on the outer side of the side frame, a circular hole for sliding the steel rope is opened at the top of the gantry frame, and the outer diameter of the end block is larger than the inner diameter of the circular hole.
[0021] Through the above technical solution, after the fence is laid flat, the steel rope is pulled out of the gantry frame, the end block is stuck in the round hole to prevent it from falling off, and the steel rope is hung on the top of the vertical fence or on the reversing wheel. The load-bearing capacity of the fence is increased by oblique pulling of the steel rope, and the steel rope can provide an installation position for the safety buckle.
[0022] Furthermore, hooks with openings facing downward are provided at the ends of the first and second gusset plates, and the hooks at the ends of the first and second gusset plates are staggered, and the width of the gantry frame at a horizontal position is smaller than the inner diameter of the opening of the hooks.
[0023] Through the above technical solution, the hooks with downward openings can be used to conveniently disassemble and assemble the gusset plate 1 and the gusset plate 2, and the hooks are staggered with each other, which does not affect the simultaneous laying of the gusset plate 1 and the gusset plate 2 in the same position.
[0024] The method for carrying out maintenance using an installation and maintenance platform for power equipment in a thermal power plant comprises the following steps:
[0025] S1, the hoist is transported from the manhole to the power station boiler and fixed on the top of the inner wall of the power station boiler;
[0026] S2. The connecting seats of the two end frames are connected to the steel cables of the hoist. The main frame and the auxiliary frame are folded in half around the relay frame. The connecting seats are rotated to make the steel cables parallel to the long sides of the end frames, and the end frames are lowered vertically along the manhole.
[0027] S3. During the process of lowering the end frame, the pin rod is inserted into the pin hole 1 to fix the main frame and the auxiliary frame. After reaching the boiler of the power station, the pin rod is separated from the pin hole 1, and the main frame and the auxiliary frame are unfolded and rotated 90 degrees to be arranged horizontally;
[0028] S4, the bottom frame is installed between the two sub-frames by bolts, a plurality of longitudinal bars are overlapped on the top of the bottom frame, a cross bar is overlapped and installed on the top of the longitudinal bars, and the cross bar is fixed and assembled with the two main frames by bolts;
[0029] S5, gusset plate 1 and gusset plate 2 are hoisted into the power station boiler through the manhole, laid above the crossbar, and fences are installed at the vertical holes of the crossbar to form an upward-opening working space;
[0030] S6. When it is necessary to expand the maintenance space, remove the fence at the corresponding position and insert it into the horizontal hole of the cross bar. Pull the steel rope to pull out the gantry frame and fix it diagonally. Lay the gusset plate between the cross bar and the gantry frame.
[0031] The beneficial effects of the present invention are as follows:
[0032] (1) The present invention provides an end frame and a support frame. The end frame adopts a structure that can be folded and unfolded. When folded, the size of one side is narrowed, which is convenient for passing through a manhole. When unfolded, the surface area is large, and more installation positions can be provided to connect the double-layer support frame. The load-bearing capacity is strong. After the end frame transfer position is unfolded, it can be pinned and locked. The relay frame position does not require on-site assembly, and the installation is quick and the connection structure has high strength.
[0033] (2) The present invention adopts the design of fences and supports. The fences are installed vertically at the edges of the supports to form a safe operating space, which can provide stable enclosure protection. When the fences are moved to a position where the inner diameter of the boiler is larger, the vertical fences can be changed to a horizontal position to extend the working coverage. The steel ropes can smoothly pull out the gantry frame and bind with the adjacent fences to fix the horizontal fences diagonally, thereby improving the load-bearing capacity. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] Figure 1 It is a schematic diagram of the overall structure of the present invention;
[0035] Figure 2 is a partial side view of the hoist, the end frame and the support frame of the present invention;
[0036] Figure 3 It is a partial front view between the hoist, the end frame and the support frame of the present invention;
[0037] Figure 4 It is a schematic diagram of the state during the hoisting process between the hoist and the end frame of the present invention;
[0038] Figure 5 It is a schematic diagram of the combination of the hoist, the end frame and the support frame of the present invention;
[0039] Figure 6 is a partial schematic diagram of the present invention in a first use state;
[0040] Figure 7 is a partial schematic diagram of the second use state of the present invention;
[0041] Figure 8 It is a schematic diagram of the separation between the fence and the support frame of the present invention;
[0042] Fig. 9 It is a schematic diagram of the disassembly of the fence of the present invention.
[0043] Figure numerals: 1. Hoist; 2. End frame; 21. Main frame; 22. Auxiliary frame; 23. Connecting seat; 24. Relay frame; 25. Pin rod; 26. Reversing wheel; 27. Pin hole one; 28. Pin hole two; 29. Insert sleeve; 3. Support frame; 31. Base frame; 32. Longitudinal rod; 33. Transverse rod; 34. Buckle plate one; 35. Buckle plate two; 36. Vertical hole; 37. Avoidance; 38. Transverse hole; 4. Fence; 41. Side frame; 42. Gantry frame; 43. Steel rope; 44. End sleeve; 45. End block; 46. Inner hole; 47. Outer hole; 48. Limit frame; 49. Insert rod. DETAILED DESCRIPTION
[0044] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.
[0045] like Figure 1 - Fig. 9 As shown, this embodiment provides an installation and maintenance platform for power equipment in a thermal power plant, including a hoist 1 and a hanging basket. When inspecting the boiler of the power station, the staff needs to enter the boiler through a manhole for inspection. When parts need to be replaced or maintenance equipment needs to be used, the hanging basket needs to be placed into the boiler through the manhole to carry the parts and equipment. The hoist 1 is fixed in the boiler and can directly transmit the lifting force to the hanging basket position through a steel cable to lift and lower personnel and equipment. Due to the size of the manhole, the hanging basket needs to adopt a detachable combined structure, which is first dispersed into parts and transported to the boiler, and then assembled into a whole in the boiler for use. Refer to Figure 1 The hanging basket includes two end frames 2, which provide installation positions. A support frame 3 is installed between the two end frames 2. The support frame 3 and the end frames 2 play a load-bearing role after being combined. A fence 4 is installed at the edge of the support frame 3, and the fence 4 plays a role of safety enclosure. The end frames 2 and the fence 4 are arranged above the support frame 3 to form a working space. However, after the assembled hanging basket is connected to the steel cable, it is necessary to carry out targeted structural reinforcement of the load-bearing structure and improve the flexibility of the device.
[0046] In order to solve the problem of structural strength and flexibility of use, refer to Figure 2 , Regarding the end frame 2, the end frame 2 includes a main frame 21 and a sub-frame 22, and the main frame 21 and the sub-frame 22 are arranged in layers up and down, wherein a relay frame 24 is rotatably connected between the bottom end of the main frame 21 and the top end of the sub-frame 22, and the relay frame 24 rotatably connects the main frame 21 and the sub-frame 22, so that the sub-frame 22 can be rotated 180 degrees around the end of the main frame 21, and the size is small after folding, and it can be smoothly input into the manhole, and the width is large after unfolding, and two upper and lower installation positions can be provided;
[0047] For support 3, refer to Figure 2 and Figure 3 The support frame 3 includes two cross bars 33, and the two cross bars 33 are assembled and connected with the main frame 21 to form a rectangular hollow structure, which can constitute the bearing structure of the first layer. A bottom frame 31 is installed between the two sub-frames 22 in parallel with the cross bars 33. The bottom frame 31 is a triangular prism-shaped cage frame, and the bottom frame 31 constitutes the bearing structure of the second layer. A longitudinal bar 32 is installed between the two layers of bearing structures, that is, between the bottom frame 31 and the cross bars 33. The longitudinal bar 32 can use the bearing structure of the lower layer to improve the bearing capacity of the upper layer bearing structure, and the bearing capacity is strong. A stacked gusset plate 1 34 and a gusset plate 2 35 are installed between the two cross bars 33, which can fill the gap between the cross bars 33 and facilitate the bearing and transportation of personnel and equipment.
[0048] For fence 4, refer to Figure 6 and Figure 7 The fence 4 includes a side frame 41 and a gantry frame 42. There is a mesh plate in the middle of the side frame 41. The side frame 41 can be vertically installed on the top of the cross bar 33 for enclosure protection. When it is lowered to a position with a larger inner diameter of the boiler, the gap between the hanging basket and the boiler is larger, and the vertical fence 4 can be disassembled and horizontally installed at the position of the cross bar 33 to form an extended platform so as to be closer to the inner wall of the boiler. At the same time, a steel rope 43 is connected through the edge of the gantry frame 42. The steel rope 43 is stored in the internal space of the fence 4 when not in use and can be pulled out when in use. The gantry frame 42 can be pulled out, and the buckle plate 34 can be stuck between the gantry frame 42 and the cross bar 33 to increase the load-bearing capacity. The steel rope 43 is obliquely fixed between the top of the adjacent vertical fence 4 and the end of the fence 4 in a horizontal state to improve the load-bearing capacity of the horizontal fence 4.
[0049] In a further embodiment, referring to Figure 4 The main frame 21 and the auxiliary frame 22 both adopt a rectangular structure. After the main frame 21 and the auxiliary frame 22 are folded in half, the width is narrower and can adapt to the width of the manhole, so as to be easily transported to the power station boiler. The long sides of the main frame 21 and the auxiliary frame 22 are at the top and bottom ends. The relay frame 24 is installed parallel to the long side of the main frame 21. The main frame 21 and the auxiliary frame 22 are connected by the relay frame 24. After being input into the boiler, there is no need to recombine the main frame 21 and the auxiliary frame 22, so as to ensure that the structural strength between the main frame 21 and the auxiliary frame 22 is high and the installation steps can be simplified.
[0050] In a further embodiment, referring to Figure 4 The main frame 21 is rotatably mounted with a connecting seat 23 in the middle, and the connecting seat 23 is connected to the steel cable of the hoist 1. The main frame 21 is mounted with a reversing wheel 26 at the short side. When hoisting, the connecting seat 23 is rotated to overlap the steel cable at the position of the reversing wheel 26, and the long side of the end frame 2 is vertically lowered, which is more stable when lowered, and the narrow side is at the bottom to avoid bumping against the inner wall of the boiler. Figure 5During assembly, the steel cable is separated from the reversing wheel 26, and the connecting seat 23 is rotated ninety degrees to make the long side of the end frame 2 horizontal, so as to facilitate the subsequent connection of the support frame 3, and the assembly operation is more convenient.
[0051] In a further embodiment, referring to Figure 3 and Figure 4 A socket 29 is installed on the vertical side wall of the auxiliary frame 22, and a vertically arranged pin rod 25 is installed in the socket 29. A pin hole 27 cooperating with the pin rod 25 is opened at the bottom of the main frame 21. When hoisting, the main frame 21 and the auxiliary frame 22 are folded in half, and the pin rod 25 passes through the socket 29 and the pin hole 27 to prevent accidental unfolding during hoisting. A pin hole 28 is opened at the bottom of the main frame 21 parallel to the pin hole 27. When assembling, the main frame 21 and the auxiliary frame 22 are parallel, and the pin rod 25 passes through the socket 29 and the pin hole 28 to ensure that the end frame 2 is stable and will not swing, which is convenient for installing the base frame 31 and the cross bar 33.
[0052] In a further embodiment, referring to Figure 6 and Figure 7 The bottom end of the side frame 41 is fixedly installed with a vertical plug rod 49, which is a solid rod with high overall structural strength. Vertical holes 36 are opened on both sides of the top and bottom of the cross bar 33, and the plug rod 49 is inserted in the vertical hole 36, which can play a role in enclosure protection. The vertical side wall of the cross bar 33 is opened with a horizontal hole 38, and the plug rod 49 is inserted in the horizontal hole 38. The fence 4 is horizontal with the support frame 3, and the gantry frame 42 can be pulled out and extended to the position required to reach, providing a maintenance coverage range. The end of the longitudinal bar 32 is provided with an avoidance opening 37 that cooperates with the plug rod 49. When changing the position of the fence 4, the plug rod 49 can be smoothly plugged in and out, and the avoidance opening 37 can also allow the plug rod 49 to be inserted into the longitudinal bar 32, thereby improving the firmness of the installation, and transmitting the force of the fence 4 to the position of the longitudinal bar 32 through the plug rod 49, and dispersing it between the base frame 31 and the cross bar 33, thereby improving the structural strength of the fence 4 when it is installed horizontally.
[0053] In a further embodiment, referring to Figure 6 - Fig. 9 The vertical side walls of the side frame 41 are provided with two groups of outer holes 47 arranged up and down, and the vertical side walls of the gantry frame 42 are provided with inner holes 46 matching the outer holes 47. When the gantry frame 42 is fully inserted into the side frame 41, a limit frame 48 is installed between the inner hole 46 and the outer hole 47. The limit frame 48 is inserted into a group of outer holes 47 and inner holes 46 located at the lower part, providing a placement space for the limit frame 48 to prevent loss and facilitate taking and use. When the gantry frame 42 is pulled out, the limit frame 48 is inserted into another group of outer holes 47 and inner holes 46 to ensure the stable position of the gantry frame 42 and prevent the gantry frame 42 from sliding at will.
[0054] In a further embodiment, referring to Fig. 9The steel rope 43 is located at one end of the inner side of the side frame 41 and is equipped with an end block 45. A round hole for the steel rope 43 to slide is opened at the top of the gantry frame 42. The outer diameter of the end block 45 is larger than the inner diameter of the round hole. After the fence 4 is laid flat, the end block 45 is stuck in the round hole to prevent it from falling off. The gantry frame 42 can be smoothly pulled out by pulling the steel rope 43. At the same time, the steel rope 43 is located at one end of the outer side of the side frame 41 and is equipped with an end sleeve 44. The end sleeve 44 is hung on the top of the vertical fence 4 or on the reversing wheel 26 to straighten the pulled out steel rope 43. At this time, the load-bearing capacity of the fence 4 is improved by the oblique pulling of the steel rope 43. In addition, the steel rope 43 can provide an installation position for the safety buckle to ensure that personnel can move safely on the fence 4. At this time, the fence 4 is open all around and there is no obstruction to prevent the inner wall of the boiler from being blocked, thereby ensuring the smooth progress of maintenance.
[0055] In a further embodiment, referring to Figure 8 The ends of the gusset plates 1 34 and 35 are provided with hooks with openings downward, and the hooks with openings downward are directly and movably placed on the cross bar 33. The hooks at the ends of the gusset plates 1 34 and 35 are staggered and stacked on each other, which can improve the load-bearing capacity. During hoisting, the gusset plates 1 34 and 35 can be hoisted into place at one time. When it is necessary to expand the working space, the gusset plate 1 34 can be conveniently removed and overlapped on the flat fence 4, wherein the width of the gantry frame 42 at the horizontal position is smaller than the inner diameter of the opening of the hook. After overlapping, the hook and the gantry frame 42 are stably connected without displacement and have strong safety. Moreover, after the gusset plate 1 34 is moved away, the position of the gusset plate 2 35 remains unchanged, which will not affect the normal use of the support frame 3.
[0056] In a further embodiment, referring to Fig. 9 The limit frame 48 includes a cylindrical rod, and the cylindrical rod is designed to be inclined. A hand buckle plate is fixedly installed on the end of the cylindrical rod. When the fence 4 is installed vertically, the hand buckle plate is fixed to the highest point of the cylindrical rod, and the limit frame 48 will be hung on the vertical side wall of the fence 4. The installation is stable and will not fall off. At the same time, when the fence 4 is arranged horizontally, after the limit frame 48 limits the gantry frame 42, the pulling of the steel rope 43 can stably lock the gantry frame 42 and the side frame 41.
[0057] In a further embodiment, a method for performing maintenance using a thermal power plant power equipment installation and maintenance platform comprises the following steps:
[0058] S1, the hoist 1 is transported from the manhole to the power station boiler and fixed on the top of the inner wall of the power station boiler. The hoist 1 is divided into two parts, the left and right parts, and the distance between them is roughly equal to the width of the support frame 3;
[0059] S2, the connecting seats 23 of the two end frames 2 are connected to the steel cables of the hoist 1, the main frame 21 and the auxiliary frame 22 are folded around the relay frame 24, and the narrowed size can smoothly pass through the manhole, the connecting seat 23 is rotated to make the steel cable parallel to the long side of the end frame 2, and the end frame 2 is vertically lowered into the power station boiler along the manhole;
[0060] S3, during the lowering process, the pin rod 25 is inserted into the pin hole 1 27 to fix the main frame 21 and the auxiliary frame 22. After reaching the boiler of the power station, the pin rod 25 is separated from the pin hole 1 27, the main frame 21 and the auxiliary frame 22 are unfolded, and rotated 90 degrees to be arranged horizontally, and the pin rod 25 is inserted into the pin hole 2 28 to ensure the stability of the main frame 21 and the auxiliary frame 22;
[0061] S4, the bottom frame 31 is installed between the two sub-frames 22 by bolts, a plurality of longitudinal bars 32 are overlapped on the top of the bottom frame 31, and a cross bar 33 is overlapped on the top of the longitudinal bars 32. The cross bar 33 is fixedly assembled with the two main frames 21 by bolts, and the main frame 21 and the sub-frame 22 are stably connected by the relay frame 24, so the structure is firm and the assembly is quick;
[0062] S5, the gusset plate 1 34 and the gusset plate 2 35 are hoisted into the power plant boiler through the manhole and laid above the crossbar 33 to facilitate walking and equipment placement. The fence 4 is plugged and installed at the vertical hole 36 of the crossbar 33. The fence 4 is arranged front and back to form an upward opening working space so that people will not fall accidentally when walking;
[0063] S6. When it is necessary to expand the maintenance space in a certain direction, for example, when the maintenance reaches the part with a larger inner diameter of the boiler, the distance between the entire hanging basket and the inner wall of the boiler increases. In order to get closer to the inner wall of the boiler and avoid risks, the fence 4 at the corresponding position can be disassembled and plugged into the horizontal hole 38 of the cross bar 33. At this time, the fence 4 can be extended horizontally to facilitate personnel to approach the inner wall of the boiler. At the same time, the steel rope 43 is pulled to pull out the gantry frame 42 and fix it obliquely to improve the load-bearing capacity of the flat fence 4. The buckle plate 34 is laid between the cross bar 33 and the gantry frame 42 for load-bearing. In addition, the staff can buckle the hook of the safety rope on the steel rope 43, which does not affect the forward and backward walking, and can ensure safety without setting up a new enclosure structure. There is no obstruction between the personnel and the inner wall of the boiler, and the maintenance and maintenance operations are also more convenient.
[0064] The above are only preferred embodiments of the present invention and are not intended to limit the protection scope of the present invention.
Claims
1. An installation and maintenance platform for power equipment in a thermal power plant, comprising a hoist (1) and a hanging basket, Features: The hanging basket comprises two end frames (2), a support frame (3) is installed between the two end frames (2), a fence (4) is installed at the edge of the support frame (3), and the end frames (2) and the fence (4) are arranged above the support frame (3) to form a working space; The end frame (2) comprises a main frame (21) and a sub-frame (22), a relay frame (24) is rotatably connected between the bottom end of the main frame (21) and the top end of the sub-frame (22), and the sub-frame (22) can rotate 180 degrees around the end of the main frame (21); The support frame (3) comprises two cross bars (33), the two cross bars (33) are assembled and connected to the main frame (21), a bottom frame (31) is installed between the two sub-frames (22) parallel to the cross bars (33), a longitudinal bar (32) is installed between the bottom frame (31) and the cross bars (33), and a first gusset plate (34) and a second gusset plate (35) are installed between the two cross bars (33). The fence (4) comprises a side frame (41) and a gantry frame (42); the side frame (41) can be vertically mounted on the top of the crossbar (33); the side frame (41) can be horizontally mounted on the vertical side wall of the crossbar (33); and a steel rope (43) is connected to and penetrates the edge of the gantry frame (42); The main frame (21) and the auxiliary frame (22) both adopt a rectangular structure, the long sides of the main frame (21) and the auxiliary frame (22) are located at the top and bottom ends, and the relay frame (24) is installed parallel to the long side of the main frame (21); A connecting seat (23) is rotatably mounted in the middle of the main frame (21), the connecting seat (23) is connected to the steel cable of the hoist (1), and a reversing wheel (26) is mounted on the short side of the main frame (21); A socket (29) is installed on the vertical side wall of the auxiliary frame (22), a vertically arranged pin rod (25) is installed through the socket (29), and a first pin hole (27) and a second pin hole (28) cooperating with the pin rod (25) are opened at the bottom of the main frame (21); A vertical insertion rod (49) is fixedly mounted at the bottom end of the side frame (41); vertical holes (36) are formed through the top and bottom sides of the cross bar (33); a horizontal hole (38) is formed through the vertical side wall of the cross bar (33); and an avoidance opening (37) that cooperates with the insertion rod (49) is formed at the end of the longitudinal bar (32); The vertical side wall of the side frame (41) is provided with two groups of outer holes (47) arranged up and down, the vertical side wall of the gantry frame (42) is provided with inner holes (46) matching with the outer holes (47), and a limiting frame (48) is inserted and installed between the inner hole (46) and the outer hole (47).
2. The installation and maintenance platform for power equipment in a thermal power plant according to claim 1, It is characterized in that An end block (45) is installed at one end of the steel rope (43) located inside the side frame (41), and an end sleeve (44) is installed at one end of the steel rope (43) located outside the side frame (41). A circular hole for sliding the steel rope (43) is provided at the top end of the gantry frame (42), and the outer diameter of the end block (45) is greater than the inner diameter of the circular hole.
3. The installation and maintenance platform for thermal power plant power equipment according to claim 1, It is characterized in that The ends of the first gusset plate (34) and the second gusset plate (35) are provided with hooks with openings facing downwards, the hooks at the ends of the first gusset plate (34) and the second gusset plate (35) are arranged in a staggered manner, and the width of the gantry frame (42) at a horizontal position is smaller than the inner diameter of the opening of the hook.
4. The method for repairing power equipment in a thermal power plant using an installation and maintenance platform according to claim 1, It is characterized in that The steps include: S1, hoist (1) is transported from the manhole to the power station boiler and fixed to the top of the inner wall of the power station boiler; S2, the connecting seats (23) of the two end frames (2) are connected to the steel cables of the hoist (1), the main frame (21) and the auxiliary frame (22) are folded in half around the relay frame (24), the connecting seats (23) are rotated so that the steel cables are parallel to the long sides of the end frames (2), and the end frames (2) are lowered vertically along the manhole; S3, during the process of lowering the end frame (2), the pin rod (25) is inserted into the pin hole 1 (27) to fix the main frame (21) and the auxiliary frame (22). After reaching the boiler of the power station, the pin rod (25) is separated from the pin hole 1 (27), and the main frame (21) and the auxiliary frame (22) are unfolded and rotated 90 degrees to be arranged horizontally; S4, the bottom frame (31) is installed between the two sub-frames (22) by means of bolts, a plurality of longitudinal bars (32) are overlapped on the top of the bottom frame (31), a cross bar (33) is overlapped and installed on the top of the longitudinal bars (32), and the cross bar (33) is fixedly assembled with the two main frames (21) by means of bolts; S5, the first gusset plate (34) and the second gusset plate (35) are hoisted into the power station boiler through the manhole, laid above the crossbar (33), and the fence (4) is inserted and installed at the position of the vertical hole (36) of the crossbar (33) to form an upwardly open working space; S6. When it is necessary to expand the maintenance space, the fence (4) at the corresponding position is disassembled and inserted into the horizontal hole (38) of the cross bar (33), the steel rope (43) is pulled to pull the gantry frame (42) out and fix it obliquely, and the gusset plate (34) is laid between the cross bar (33) and the gantry frame (42).