Pipe gallery pipeline construction method
By setting a single lifting point on the pipeline and using a pipe transfer device to optimize the lifting process, combined with the design of a safe working platform, the existing technology problems of multiple crane shifts and large space occupation are solved, and construction efficiency and safety are improved. Efficient and low-cost pipe gallery installation is achieved.
Patent Information
- Application Number
- CN202411028540.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-30
- Publication Date
- 2024-10-01
AI Technical Summary
The existing pipe gallery pipeline construction method has many crane shifts, frequent construction interruptions, high site requirements, high operator ability requirements, and low safety, resulting in low construction efficiency and high costs.
A single lifting point is set up on a long-distance pipeline, a pipe transfer is used to realize orbital movement, and a safe working platform is set up to reduce the number of crane shifts and site occupation, and improve operating efficiency and safety.
It achieves high efficiency and low cost in pipeline construction, shortens the construction period, reduces safety risks, and meets the specification requirements of construction quality.
Smart Images

Figure CN118729052A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of pipeline construction, and in particular to a pipeline corridor pipeline construction method. Background Art
[0002] The pipeline construction method of the pipe gallery is extremely common in chemical engineering, industrial installation and other devices, such as oil refining projects, steelmaking, long-distance ground pipelines, urban pipelines, etc., and the pipe gallery is usually tens of meters or hundreds of meters. Using conventional construction technology, the construction procedure is construction preparation → material acceptance → pipeline transportation → pipeline first axis hoisting → crane cooperates with pipeline laying → pipeline group welding → pipeline second axis hoisting → crane cooperates with pipeline laying → pipeline group welding → pipeline third, fourth,... axis hoisting → crane cooperates with pipeline laying → pipeline group welding → pipeline testing → pipeline anti-corrosion and thermal insulation → pipeline installation acceptance. In the prior art, the main problems existing in the construction of pipe gallery pipelines are: The crane is frequently relocated: generally, one crane station can meet the hoisting needs of 1-2 axes of the corridor. The crane needs to be relocated and repositioned every 2-3 axes (about 8-15m). The crane has to repeat its position many times, which takes a long time.
[0003] Frequent construction interruptions: Because the relocation of the crane requires inspection and confirmation that the foundation conditions meet the requirements of the lifting position, each relocation takes a certain amount of time, resulting in a lack of continuity in the installation process.
[0004] High site requirements: Conventional pipeline corridors have high site requirements and are not suitable for pipeline corridor installation in narrow areas. For pipeline corridor installation in coastal areas, especially for land reclamation, it is necessary to significantly increase the land reclamation area, which is costly. For urban pipeline corridors, conventional installation methods require pipe laying first, and then the top-level construction of the integrated pipeline corridor is carried out.
[0005] High requirements on the ability of operators: When the pipes in the pipe gallery are installed, the pipe gallery structure has been installed, and the pipes are inserted in almost every axis. The crane driver and the lifting and hoisting operators must work closely together to adjust the pipe insertion angle in real time, insert the pipes slowly, and then lay the pipes. In a complex pipe gallery, there are many layers of pipes with small spacing, and the pipe insertion is very difficult, which puts high demands on the professional ability of the operators.
[0006] Low safety: During the pipeline laying process in the pipeline corridor, the crane cannot lay the pipeline in place at one time. During the pipeline laying process, personnel work at high altitude, which greatly limits the labor capacity of people. In addition, there is a lack of corresponding safety platforms, which makes safety accidents very likely to occur.
[0007] High cost: The installation method of conventional cranes combined with pipe threading requires multiple crane shifts, and the foundation of the lifting station generally needs to be leveled or hardened, which is costly. Summary of the invention
[0008] The technical problem to be solved by the present invention is to provide a pipeline construction method for a pipe gallery, so as to achieve the purpose of improving construction efficiency and saving costs.
[0009] In order to solve the above technical problems, the present invention provides a pipeline corridor pipeline construction method, comprising: Step 1: On a long-distance pipeline corridor, set up a hoisting point within 100-200m, and install 200-400m of corridor pipeline at a time at this hoisting point; Step 2: Lift the pipeline from the lifting point to the installation height, place the pipeline on the pipeline mover, and use the pipeline mover to move the pipeline on the track. The pipeline mover includes a horizontal guide tube, a linear track, and an arc track. The horizontal guide tube on the arc track moves in an arc shape to position the pipeline at the axial position of the pipeline installation, and then moves the pipeline along the linear track to the center line position of the pipeline installation. Step 3: According to the different diameters of the pipelines, a set of horizontal guide tubes and deviation guide tubes are set every 6-20m, and a towing point is set at about 50m in the upper layer of the corridor for auxiliary towing of the pipeline; Step 4: Set up a pipeline safety operation platform as an operation platform for pipeline welding and pipe threading; Step 5: Pipeline welding and testing.
[0010] Furthermore, in step 2, a 25-50t crane is selected for pipe lifting.
[0011] Furthermore, in step three, the horizontal guide tube device includes a base, a fixing device, a shaft and rollers; the two fixing devices are respectively vertically arranged at both ends of the base, the shaft is horizontally installed between the two fixing devices, the rollers are installed on the shaft, and the base is fixed on the main beam.
[0012] Furthermore, in step three, the deflection adjusting guide device includes a fixed base plate and an inclined roller assembly, and the two inclined roller assemblies are respectively installed at both ends of the fixed base plate. At least two fixed clips are arranged at the bottom of the fixed base plate, and the fixed clips are connected to the secondary beam.
[0013] Furthermore, in step 4, the first safe working platform is set up from the 1st column to the 6th to 10th columns, and then a safe working platform is set up at intervals of 12 to 20 axes.
[0014] Furthermore, in step four, the safe working platform includes a suspended scaffolding, the scaffolding pipes of the suspended scaffolding are connected to the flange plates of the supporting beams through suspension beam fasteners to form a portal frame, the cross bars of the suspended scaffolding are connected to the horizontal beams of the corridor structure or the frame structure by cantilever fasteners, scaffolding boards are laid on the suspended scaffolding and guardrails are installed, and a straight ladder or an inclined ladder is set up to connect to the suspended scaffolding.
[0015] The present invention optimizes the arrangement of pipeline hoisting points, optimizes the selection of hoisting points and basically fixes them during the installation process, and can install multiple pipelines over longer distances at one time; a pipeline plane pipe mover, a horizontal conduit device, and an adjustable deflection conduit device are used for long-distance pipe threading, so that the pipeline can be smoothly moved from the hoisting point to the location to be installed. The working platform adopts an independent safety platform, which only needs to be centrally set at the group welding location of the pipeline installation in the pipe gallery. The working platform is standardized and the number is small.
[0016] The present invention is not limited by the height and length of the pipeline corridor, does not need to occupy too much construction site, does not need to use a large number of cranes, can achieve smooth pipe threading, and realize continuous flow operation of one lifting, two threading, three welding and four conveying, thereby improving installation efficiency. The present invention is used for the installation of pipelines in pipeline corridors with more than 2 floors. For more complex integrated pipeline corridors, the construction period is shortened by at least 40% compared with the method of installing pipelines by conventional cranes, the investment in safety measures is reduced by 40%, the construction quality fully meets the specifications and design requirements, and has been unanimously recognized by multiple project construction units, achieving good social and economic benefits.
[0017] The present invention is suitable for above-ground pipeline corridor projects, especially multi-span pipeline corridors, pipeline corridors with narrow operating ranges and dense pipelines, such as comprehensive pipeline corridors of oil refining projects, above-ground pipeline corridors of large and medium-sized chemical plants, urban comprehensive pipeline corridors, etc. The above-ground pipeline corridors are mainly used for the centralized laying of various medium pipelines and water supply, drainage, gas, heat, pipelines, communications, and electricity. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The drawings herein are used to provide further explanation of the present invention and constitute a part of this application. The illustrative embodiments of the present invention and their description are used to explain the present invention and do not constitute improper limitations on the present invention.
[0019] Figure 1 It is a schematic diagram of the structure of the horizontal catheter device; Figure 2 It is a structural schematic diagram of the deflection guide device; Figure 3 This is a schematic diagram of horizontal and oblique pipe penetration of pipelines; Figure 4 This is a schematic diagram of setting up a safe working platform.
[0020] In the figure, 1-base, 2-fixing device, 3-axis, 4-roller, 5-fixed bottom plate, 6-inclined roller assembly, 7-fixing clip, 8-scaffolding pipe, 9-suspended beam fastener, 10-supporting beam, 11-scaffolding board, 12-guardrail. DETAILED DESCRIPTION
[0021] In order to make those skilled in the art better understand the present invention, the present invention is further clearly and completely described below in conjunction with the accompanying drawings and embodiments. It should be noted that, in the absence of conflict, the features in the embodiments and examples of this application can be combined with each other.
[0022] The typical implementation method of the present invention provides a pipeline corridor pipeline construction method, including construction preparation, pipeline acceptance, pipeline hoisting, pipeline threading, pipeline welding, pipeline testing, pipeline anti-corrosion patching and thermal insulation, which is characterized in that during construction preparation, a pipeline construction plan is planned, and a construction method of customizing a conduit device and setting up a special safety work platform is used to perform pipe threading and installation operations. Pipeline acceptance is to inspect and accept the pipeline material, standard, specification, quantity, etc. from the time the pipeline is purchased and brought into the site, and to perform acceptance procedures; pipeline hoisting is to stack and hoist the pipeline from the warehouse to the installation site of the corridor and to the pipe threading operation site; pipeline threading is to accurately determine the threading position, reasonably set up a custom conduit device, protect the pipeline anti-corrosion layer, and ensure that the pipeline is installed in place; pipeline welding is to perform safe welding operations on a special safety work platform; pipeline testing is to inspect the pipeline after installation by using air pressure, water pressure, etc. according to design requirements; pipeline anti-corrosion patching and thermal insulation are to carry out subsequent construction processes after the above processes are completed.
[0023] 1. Pipeline construction preparation 1) According to the drawings, the construction plan of the pipe penetration mode shall be clearly defined, and the number and arrangement of pipeline hoisting points, conduit arrangement, and safe working platforms shall be determined. The hoisting site shall meet the hoisting requirements.
[0024] 2) The construction site has three connections and one leveling, the intermediate handover of the pipe gallery structure has been completed, the tools and pipe installation materials have passed the acceptance inspection, the operating personnel are in place and certified, etc., and all installation conditions are met.
[0025] 2. Acceptance of pipeline materials 1) The pipeline conduit device is manufactured and assembled according to a special plan, and the rollers, telescopic plates, etc. are flexible in operation and meet the requirements of use.
[0026] 2) Pipes and fittings must have a factory certificate or quality inspection certificate, and their inspection items and technical indicators must comply with national standards or industry standards and relevant technical documents. Products without quality certificates shall not be used.
[0027] 3) The material certificate should include: steel grade, furnace batch number, specification, chemical composition, mechanical properties, supply status and material standard number.
[0028] 4) For pipeline components and pipeline supports, in addition to the specifications, materials, models, and quality that must comply with the requirements of the design documents, they must also be visually inspected in accordance with current national standards, and those that do not meet the standards shall not be used.
[0029] 5) If the indicators provided are incomplete or there are doubts about the material, re-inspection should be carried out.
[0030] 6) The appearance inspection of pipes and fittings shall comply with the following provisions: (1) There are no defects such as cracks, shrinkage holes, folds, and heavy skin on the surface.
[0031] (2) If there are local rust depressions on the surface, the minimum wall thickness must be guaranteed and not less than the negative deviation.
[0032] (3) If there are unacceptable defects on the surface, they should be eliminated. After the defects are eliminated, the tube wall thickness should not be less than the minimum wall thickness.
[0033] 7) Pipeline components related to pipeline installation should be inspected and accepted according to procedures and signed.
[0034] 8) If the pipeline has anti-corrosion requirements, the anti-corrosion construction of the pipeline except for the last coat of paint should be completed before the pipeline is hoisted.
[0035] 3. Pipeline fixed-point lifting 1) Optimization of pipeline lifting point settings The optimization of the pipe lifting point setting directly affects the efficiency of the pipe gallery installation. The pipe lifting point setting must meet the following requirements: the ground is flat, meets the crane bearing capacity requirements, is close to the pipe gallery, and has crane rotation space. In order to optimize the setting of the lifting point, in the installation of a pipe gallery several kilometers long, one lifting point is selected for about 100-200m, the span should be greater than 8m, and the ground conditions meet the lifting requirements. Lifting points should be set at the corners of the pipe gallery to facilitate the initial lifting and threading of the pipe.
[0036] 2) Pipeline hoisting Select the crane with the heaviest lifting weight, largest size and highest lifting height for crane selection calculation. Consider the specifications, length, weight, installation height and other parameters of the pipeline, and select a 25-50t crane for pipeline lifting.
[0037] Before hoisting, arrange and fix the pipe conduit in advance, slowly put the hoisted pipe into place on the pipe conduit, and then carry out the pipe threading operation.
[0038] 3) Pipeline relocation Arrange the pipe mover in advance, which consists of 2 horizontal guides, 1 linear track and 1 curved track. When the pipe is lifted to the installation location, place the pipe on the pre-arranged pipe mover, and then move the horizontal guide on the curved track in an arc shape to position the pipe in the axis of the pipe installation, and then move it along the linear track to the centerline of the pipe installation.
[0039] 4. Pipeline threading 1) Catheter, tube puller and settings Horizontal conduit devices include horizontal axial conduit devices, horizontal transverse conduit devices and deviation adjustment conduit devices. Horizontal conduit devices are installed on the main beam, and deviation adjustment conduit devices are installed on the secondary beam. Horizontal axial conduit devices are used to adjust the axial penetration of pipelines, and horizontal transverse conduit devices are used to adjust the transverse position of pipelines with a diameter of DN200 or above. Horizontal conduit devices are suitable for pipelines of various specifications and diameters. When the penetration length exceeds 100m, a pipe puller is used to assist the axial penetration of the pipeline.
[0040] Horizontal conduit devices are mainly used for horizontal axial transportation and oblique transportation of pipelines. Oblique transportation is set at the lifting point, turning point or lateral movement of the pipeline, which is to adjust the pipe gallery to a position parallel to the pipeline installation axis.
[0041] like Figure 1 As shown, the horizontal conduit device includes a base 1, a fixing device 2, a shaft 3 and rollers 4; the two fixing devices 2 are vertically arranged at both ends of the base 1, the shaft 3 is horizontally installed between the two fixing devices 2, the rollers 4 are installed on the shaft 3, and the base 1 is fixed on the main beam.
[0042] like Figure 2 As shown, the deflection-adjusting conduit device comprises a fixed base plate 5 and an inclined roller assembly 6. Two inclined roller assemblies 6 are respectively installed at both ends of the fixed base plate 5. At least two fixing clips 7 are arranged at the bottom of the fixed base plate 5. The fixing clips 7 are connected to the secondary beam. The deflection-adjusting conduit device is mainly used to adjust the deflection when the pipe is axially inserted to ensure that the pipe is installed in a straight line.
[0043] The above-mentioned horizontal guide tube and deflection guide tube are equipped with anti-scratch rubber protective pads to ensure that the anti-corrosion layer of the pipeline is not damaged during the pipe threading process, and can effectively prevent the contact between stainless steel and other non-ferrous metal pipelines and carbon steel rollers to cause carburization. It is suitable for pipelines of various specifications and materials. The guide tube adopts a telescopic bottom plate, which can be directly and firmly fixed on the structural beam of the pipe gallery after placement, and can pass through multiple pipe gallery pipelines of 200-400m at a time.
[0044] 2) Pipe threading Pipe threading operations are divided into horizontal lateral transportation and horizontal oblique transportation. Horizontal axial transportation along the pipeline installation axis is used in straight sections, and horizontal oblique transportation is used at pipeline lifting points, pipeline turning sections, and lateral movement locations.
[0045] The conduit device, in cooperation with hand chain hoists, ropes, electric pipe pullers, and plate clamps, lifts, pulls, and transports the process pipelines to be installed. The deflection-adjusting conduit device ensures that the pipeline does not deviate during the pulling process. The horizontal conduit device is mainly used for load bearing and axial pipe threading. It has low friction. A group of people can easily move 20 meters (about 3 pipes connected) of DN700 axially. If it exceeds 20m, it can be easily operated with the electric pipe puller. The crane does not need to be shifted, and the efficiency of pipe threading and installation is significantly improved. Many welds can also be welded on the ground or on the platform, which improves the welding efficiency.
[0046] According to the construction schedule, pipeline conduits can be added to achieve simultaneous installation of multiple pipelines and improve pipeline installation efficiency.
[0047] 5. Pipeline safety operation platform setting 1) Location of safe working platform Determine the location and number of platforms according to the corridor structure, length, effective length of the pipeline in the conduit, and the location of the square compensator. Select the first pipe hanging and pipe threading platform from the 1st column to the 6th-10th column, and then select a pipe hanging and pipe threading platform at intervals of about 100-200m from 12-20 axes. The platform should not conflict with the vertical support of the beam. If there is a collision, extend one column backward as the selected location for the platform. The square compensators of large-scale integrated corridors are relatively concentrated, and a working platform is set up below the square compensators. When the distance to the square compensators is close according to the above calculation, the platform should be adjusted to the square compensator. In addition to setting up platforms at the above positions, working platforms are set up at the welding sites after the pipelines are threaded.
[0048] 2) Installation of suspended platform and vertical ladder After selecting the platform location, the suspended platform is set up. The suspended scaffolding is set up on the main beam and secondary beam of the steel structure of the pipe gallery. The scaffolding pipe 8 is connected to the flange plate of the support beam 10 through the suspension beam fastener 9. The scaffolding pipe 8 is fixed to the support beam by the suspension beam fastener 9 to form a portal frame, and the scaffolding board 11 is laid on the crossbar of the suspended scaffolding. A guardrail 12 is installed 1.5m above the horizontal plane of the beam as a safety enclosure. In order to facilitate the workers to go up and down, a straight ladder or an inclined ladder should be set up to connect with the working platform. The working platform should be inspected and accepted after installation.
[0049] The specific steps are as follows: (1) The suspension rod of the suspended scaffold is an independent rod and shall not be extended for use. When the gap between the edge of the working layer and the building is greater than 150mm, protective measures shall be taken. Railings and footboards shall be installed on the outside of the working layer.
[0050] (2) Suspended scaffolding should be erected against the horizontal beams of structures such as pipe gallery structures and frame structures, connected to the flange plates of support beams 10 using suspension beam fasteners 9, and the scaffolding pipes 8 are fixed to the support beams using suspension beam fasteners 9 to form a portal frame, and scaffolding boards 11 are laid on the crossbars.
[0051] (3) The distance between the horizontal bars of the suspended scaffolding is less than 2m; when the span of the horizontal bar suspension point is large, an eight-shaped diagonal brace is set under the scaffolding for reinforcement support.
[0052] (4) Cantilever fasteners 13 are used between the crossbars of the suspended scaffolding and the horizontal beams of the pipe gallery structure, frame structure and other structures. The fastener connection must be tightened and the tightening torque must comply with the regulations.
[0053] (5) The scaffolding board 11, guardrail 12 and upper and lower passages of the suspended scaffold are arranged in the same manner as those of the ground scaffold.
[0054] (6) The height of the scaffolding board of the suspended scaffolding is 400mm from the upper plane of the beam.
[0055] The platform that has passed the acceptance inspection is used as an operating platform for pipeline welding and pipe threading, and the pipeline is threaded section by section to the pipeline installation location using a conduit device.
[0056] 6. Pipeline welding and testing According to the pipeline material, welding position, pipeline interface form, and national standards and the company's mature welding process assessment, a wind and rain shelter is set up, and the welders with corresponding certificates perform welding according to regulations. After welding, non-destructive testing, water pressure testing and other procedures are carried out according to the design and specification requirements to determine the quality of pipeline installation.
[0057] 7. Pipeline anti-corrosion and insulation The construction is carried out in accordance with national standards and specifications and conventional pipeline anti-corrosion and insulation construction techniques.
[0058] The scope of protection claimed by the present invention is not limited to the above specific embodiments. For those skilled in the art, the present invention may have various deformations and changes. Any modifications, improvements and equivalent substitutions made within the concept and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A pipeline corridor pipeline construction method, characterized in that: include: Step 1: On a long-distance pipeline corridor, set up a hoisting point within 100-200m, and install 200-400m of corridor pipeline at a time at this hoisting point; Step 2: Lift the pipeline from the lifting point to the installation height, place the pipeline on the pipeline mover, and use the pipeline mover to move the pipeline on the track. The pipeline mover includes a horizontal guide tube, a linear track, and an arc track. The horizontal guide tube on the arc track moves in an arc shape to position the pipeline at the axial position of the pipeline installation, and then moves the pipeline along the linear track to the center line position of the pipeline installation. Step 3: According to the different diameters of the pipelines, a set of horizontal guide tubes and deviation guide tubes are set every 6-20m, and a towing point is set at about 50m in the upper layer of the corridor for auxiliary towing of the pipeline; Step 4: Set up a pipeline safety operation platform as an operation platform for pipeline welding and pipe threading; Step 5: Pipeline welding and testing.
2. The pipeline corridor pipeline construction method according to claim 1 is characterized in that: In step 2, select a 25-50t crane for pipe lifting.
3. The pipeline corridor pipeline construction method according to claim 1 or 2, characterized in that: In step three, the horizontal conduit device includes a base, a fixing device, a shaft and rollers; two fixing devices are vertically arranged at both ends of the base, the shaft is horizontally installed between the two fixing devices, the rollers are installed on the shaft, and the base is fixed on the main beam.
4. The pipeline corridor pipeline construction method according to claim 3 is characterized in that: In step three, the deflection guide device includes a fixed base plate and an inclined roller assembly, and the two inclined roller assemblies are respectively installed at both ends of the fixed base plate. At least two fixed clips are arranged at the bottom of the fixed base plate, and the fixed clips are connected to the secondary beam.
5. The pipeline corridor pipeline construction method according to claim 1 or 4, characterized in that: In step 4, the first safe working platform is set up from the 1st column to the 6th-10th column, and then a safe working platform is set up every 12-20 axes.
6. The pipeline corridor pipeline construction method according to claim 5 is characterized in that: In step 4, the safe working platform includes a suspended scaffolding, the scaffolding pipes of the suspended scaffolding are connected to the supporting beam flange plates through suspension beam fasteners to form a portal frame, the cross bars of the suspended scaffolding are connected to the horizontal beams of the corridor structure or the frame structure by cantilever fasteners, scaffolding boards are laid on the suspended scaffolding and guardrails are installed, and a straight ladder or an inclined ladder is set up to connect to the suspended scaffolding.