Production scheduling method, controller and computer readable storage medium
In the production of new energy vehicles, through the optimization of production schedules and carbon emission benefits based on mold production parameters and duration parameters, the problem of multi-factory coordination and carbon emission reduction is solved, and an efficient and low-carbon production process is achieved.
Patent Information
- Application Number
- CN202410791578.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-18
- Publication Date
- 2024-10-01
AI Technical Summary
In the production process of new energy vehicles, existing technology cannot effectively solve the production scheduling difficulties and carbon emission problems caused by multi-factory coordination and carbon emission reduction requirements.
Optimize the production schedule based on the mold production parameters and production time parameters of the production line, optimize carbon emission benefits based on raw material materials, adjust the production sequence to minimize carbon emissions, and provide technical solutions to ensure production efficiency and resource utilization.
It achieves improved production efficiency and waste classification and recycling revenue during the production process, reduces raw material and parts inventory, meets the needs of green and low-carbon production, and ensures less resource input and greater output.
Smart Images

Figure CN118735047A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of production scheduling, and in particular to a production scheduling method, a controller and a computer-readable storage medium. Background Art
[0002] With the rapid rise of new energy vehicles, the speed of product iteration has accelerated, and production coordination between multiple factories has become particularly important. At the same time, new changes have taken place in the business scenarios of production. In the production process, the more business scenarios are involved, the more difficult it is to schedule production. At the same time, the vehicle scheduling process may also involve multiple different factories, and the production methods and information feedback channels between different factories will be different.
[0003] As a new energy vehicle company that develops all-aluminum bodies, under the current national strategy of developing new energy, waste aluminum recycling has become the most effective measure to reduce carbon emissions, which can effectively reduce the demand for electrolytic aluminum liquid.
[0004] Therefore, during the stamping production process, it is necessary to comprehensively consider the actual operating conditions of the vehicle factory to achieve lean production and carbon emission reduction needs.
[0005] Accordingly, the art needs a new production scheduling solution to solve the above problems. Summary of the invention
[0006] In order to overcome the above-mentioned defects, the present application is proposed to solve or at least partially solve the technical problem of how to achieve lean production and carbon emission reduction in the production process.
[0007] In a first aspect, a production scheduling method is provided, the method comprising:
[0008] Based on the mold production parameters of the production line and the production time parameters of the production line, the production schedule is optimized to obtain a first target solution of the production schedule of the production line;
[0009] According to the first target solution and the raw material material corresponding to the first target solution, the carbon emission benefit is optimized to obtain the second target solution of the production line scheduling plan
[0010] In a technical solution of the above production scheduling method, the production scheduling optimization includes a first optimization and a second optimization;
[0011] The obtaining of a first target solution of the production schedule of the production line includes:
[0012] Based on the mold production parameters and the production time parameters, the first optimization is performed to obtain a preliminary production scheduling target solution for the production line;
[0013] A second optimization is performed based on the preliminary production scheduling target solution of the production line for multiple days to obtain the first target solution.
[0014] In a technical solution of the above production scheduling method, obtaining a preliminary production scheduling target solution for the production line includes:
[0015] Setting an optimization goal for the first optimization; the optimization goal includes maximizing the production time of the production line and minimizing the mold replacement time of the production line;
[0016] Setting the first optimization constraint conditions; the constraint conditions include the maximum production time constraint of the production line and the upper and lower limits of the production volume of the molds of the production line;
[0017] The first optimization is performed according to the optimization objective and the constraint conditions to obtain the preliminary production scheduling target solution.
[0018] In a technical solution of the above production scheduling method, the production duration is determined according to the following formula:
[0019]
[0020] The mold replacement time is determined according to the following formula:
[0021]
[0022] Where n is the total number of molds, is the mold replacement time of the mold produced after the Pi mold, For mold P i production volume.
[0023] In a technical solution of the above production scheduling method, the maximum production time constraint is determined according to the following formula:
[0024]
[0025] The upper and lower limits of the mold production volume are determined according to the following formula:
[0026]
[0027]
[0028]
[0029]
[0030] Where n is the total number of molds, For the P i The mold replacement time of the mold produced after the first mold, For mold P i of production, For the i-th mold P i The demand on day j+1 is is the i-th mold P i The inventory on day j, For P i The production limit of each mold is For P i The production limit of each mold.
[0031] In a technical solution of the above production scheduling method, obtaining the first target solution includes:
[0032] Based on the preliminary production scheduling target solution of the production line for multiple days and the inventory days of the mold, the production duration of the multiple days is balanced to achieve the second optimization and obtain the first target solution.
[0033] In a technical solution of the above production scheduling method, the method further includes obtaining the inventory days of the mold according to the following formula:
[0034]
[0035] Among them, DOH i is the inventory days of the i-th mold, For the i-th mold P i The demand on day j is is the i-th mold P i The inventory on day j.
[0036] In a technical solution of the above production scheduling method, the obtaining of the second target solution of the production scheduling plan of the production line includes:
[0037] According to the first target solution and the raw material material corresponding to the first target solution, the production sequence of the production line is adjusted to optimize the carbon emission benefits and obtain the second target solution.
[0038] In a technical solution of the above production scheduling method, the adjusting the production sequence of the production line includes:
[0039] When the production line is a single-line production line, adjusting the production sequence of the production line so that molds made of the same raw material in the production line are produced simultaneously to obtain the second target solution;
[0040] When multiple production lines are producing simultaneously, a baseline production line for adjusting the production sequence is determined based on the carbon emission benefits of the waste corresponding to the raw material material of each production line; and based on the baseline production line, the production sequence of multiple production lines is adjusted to maximize the degree of overlap of the same raw material material of multiple production lines to obtain the second target solution.
[0041] In a technical solution of the above production scheduling method, before adjusting the production sequence of the plurality of production lines according to the reference production line, the method further includes:
[0042] According to the inventory days of the mold, determine whether there are molds for emergency production;
[0043] If so, first sort the molds for emergency production;
[0044] If it does not exist, the step of "adjusting the production sequence of the plurality of production lines according to the reference production line" is executed.
[0045] In a second aspect, a controller is provided, comprising at least one processor; and a memory communicatively connected to the at least one processor; wherein a computer program is stored in the memory, and when the computer program is executed by the at least one processor, the method described in any one of the technical solutions of the above-mentioned production scheduling method is implemented.
[0046] In a third aspect, a computer-readable storage medium is provided, wherein a plurality of program codes are stored therein, wherein the program codes are suitable for being loaded and run by a processor to execute the method described in any one of the technical solutions of the above-mentioned production scheduling method.
[0047] Solution 1. A production scheduling method, characterized in that the method comprises:
[0048] Based on the mold production parameters of the production line and the production time parameters of the production line, the production schedule is optimized to obtain a first target solution of the production schedule of the production line;
[0049] According to the first target solution and the raw material material corresponding to the first target solution, carbon emission benefit optimization is performed to obtain a second target solution for the production scheduling plan of the production line.
[0050] Solution 2. The production scheduling method according to Solution 1 is characterized in that the production scheduling optimization includes a first optimization and a second optimization;
[0051] The obtaining of a first target solution of the production schedule of the production line includes:
[0052] Based on the mold production parameters and the production time parameters, the first optimization is performed to obtain a preliminary production scheduling target solution for the production line;
[0053] A second optimization is performed based on the preliminary production scheduling target solution of the production line for multiple days to obtain the first target solution.
[0054] Solution 3. The production scheduling method according to Solution 2 is characterized in that:
[0055] The obtaining of a preliminary production scheduling target solution for the production line includes:
[0056] Setting an optimization goal for the first optimization; the optimization goal includes maximizing the production time of the production line and minimizing the mold replacement time of the production line;
[0057] Setting the first optimization constraint conditions; the constraint conditions include the maximum production time constraint of the production line and the upper and lower limits of the production volume of the molds of the production line;
[0058] The first optimization is performed according to the optimization objective and the constraint conditions to obtain the preliminary production scheduling target solution.
[0059] Solution 4. The production scheduling method according to Solution 3 is characterized in that:
[0060] The production time is determined according to the following formula:
[0061]
[0062] The mold replacement time is determined according to the following formula:
[0063]
[0064] Where n is the total number of molds, For the P i The mold replacement time of the mold produced after the first mold, For mold P i production volume.
[0065] Solution 5. The production scheduling method according to Solution 3 is characterized in that:
[0066] The maximum production time constraint is determined according to the following formula:
[0067]
[0068] The upper and lower limits of the mold production volume are determined according to the following formula:
[0069]
[0070]
[0071]
[0072]
[0073] Where n is the total number of molds, For the P i The mold replacement time of the mold produced after the first mold, For mold P i of production, For the i-th mold P i The demand on day j+1 is is the i-th mold P i The inventory on day j, For P i The production limit of each mold is For P i The production limit of each mold.
[0074] Solution 6. The production scheduling method according to Solution 2 is characterized in that:
[0075] The obtaining of the first target solution comprises:
[0076] Based on the preliminary production scheduling target solution of the production line for multiple days and the inventory days of the mold, the production duration of the multiple days is balanced to achieve the second optimization and obtain the first target solution.
[0077] Solution 7. The production scheduling method according to Solution 6 is characterized in that the method further comprises obtaining the inventory days of the mold according to the following formula:
[0078]
[0079] Among them, DOH i is the inventory days of the i-th mold, For the i-th mold P i The demand on day j is is the i-th mold P i The inventory on day j.
[0080] Solution 8. The production scheduling method according to Solution 1 is characterized in that:
[0081] The obtaining of a second target solution of the production schedule of the production line includes:
[0082] According to the first target solution and the raw material material corresponding to the first target solution, the production sequence of the production line is adjusted to optimize the carbon emission benefits and obtain the second target solution.
[0083] Solution 9. The production scheduling method according to Solution 8 is characterized in that:
[0084] The adjusting the production sequence of the production line includes:
[0085] When the production line is a single-line production line, adjusting the production sequence of the production line so that molds made of the same raw material in the production line are produced simultaneously to obtain the second target solution;
[0086] When multiple production lines are producing simultaneously, a baseline production line for adjusting the production sequence is determined based on the carbon emission benefits of the waste corresponding to the raw material material of each production line; and based on the baseline production line, the production sequence of multiple production lines is adjusted to maximize the degree of overlap of the same raw material material of multiple production lines to obtain the second target solution.
[0087] Solution 10. The production scheduling method according to Solution 9 is characterized in that:
[0088] Before adjusting the production sequence of the plurality of production lines according to the reference production line, the method further includes:
[0089] According to the inventory days of the mold, determine whether there are molds for emergency production;
[0090] If so, first sort the molds for emergency production;
[0091] If it does not exist, the step of "adjusting the production sequence of the plurality of production lines according to the reference production line" is executed.
[0092] Solution 11. A controller, characterized by comprising:
[0093] at least one processor;
[0094] and, a memory communicatively coupled to the at least one processor;
[0095] Wherein, a computer program is stored in the memory, and when the computer program is executed by the at least one processor, the production scheduling method described in any one of Schemes 1 to 10 is implemented.
[0096] Scheme 12. A computer-readable storage medium storing a plurality of program codes, characterized in that the program codes are suitable for being loaded and run by a processor to execute the production scheduling method described in any one of Schemes 1 to 10.
[0097] The above one or more technical solutions of the present application have at least one or more of the following beneficial effects:
[0098] In implementing the technical solution of the production scheduling method provided by this application, this application optimizes the production scheduling plan based on the mold production parameters and production time parameters of the production line, obtains the first target solution of the production scheduling technology of the production line, optimizes the carbon emission benefits according to the first target solution and the raw material material corresponding to the first target solution, and obtains the second target solution of the production scheduling plan. Through the above configuration method, this application can achieve carbon emission benefit optimization under the premise of ensuring the optimization of the production scheduling plan, and can simultaneously improve the production efficiency of the production line and the waste sorting, recycling and packaging benefits, reduce the raw materials and parts in-process inventory of the production line, achieve less resource input and greater output of economic benefits, and meet the normal production needs of subsequent workshops, and realize green and low-carbon production of production lines. BRIEF DESCRIPTION OF THE DRAWINGS
[0099] The disclosure of the present application will become easier to understand with reference to the accompanying drawings. It is easy for those skilled in the art to understand that these drawings are only for illustrative purposes and are not intended to limit the scope of protection of the present application. Among them:
[0100] Figure 1 It is a flowchart of the main steps of the production scheduling method according to an embodiment of the present application;
[0101] Figure 2 is a flowchart of the main steps of obtaining a first target solution according to an implementation method of an embodiment of the present application;
[0102] Figure 3 It is a schematic flow chart of the main steps of a single production line production scheduling method according to an implementation of an embodiment of the present application;
[0103] Figure 4 It is a schematic flow chart of the main steps of a dual production line production scheduling method according to an implementation method of an embodiment of the present application;
[0104] Figure 5 This is a schematic diagram of the packaging process of two production lines according to an example of an embodiment of the present application:
[0105] Figure 6 It is a flowchart of the main steps of the production scheduling process according to an implementation example of the present application. DETAILED DESCRIPTION
[0106] Some embodiments of the present application are described below with reference to the accompanying drawings. Those skilled in the art should understand that these embodiments are only used to explain the technical principles of the present application and are not intended to limit the protection scope of the present application.
[0107] In the description of the present application, "module" and "processor" may include hardware, software or a combination of the two. A module may include hardware circuits, various suitable sensors, communication ports, memory, and may also include software parts, such as program code, or a combination of software and hardware. The processor may be a central processing unit, a microprocessor, an image processor, a digital signal processor or any other suitable processor. The processor has data and / or signal processing functions. The processor may be implemented in software, hardware or a combination of the two. Computer-readable storage media include any suitable medium that can store program code, such as a disk, a hard disk, an optical disk, a flash memory, a read-only memory, a random access memory, etc. The term "A and / or B" means all possible combinations of A and B, such as only A, only B or A and B. The term "at least one A or B" or "at least one of A and B" has a similar meaning to "A and / or B" and may include only A, only B or A and B. The singular terms "one" and "the" may also include plural forms.
[0108] Here we first explain some terms involved in this application.
[0109] Carbon emissions refer to the greenhouse gas emissions generated during the production, transportation, use and recycling of a product. Dynamic carbon emissions refer to the cumulative greenhouse gas emissions per unit of goods. Different batches of the same product will have different dynamic carbon emissions. For stamping production lines, waste will be generated during the production process, thus generating carbon emissions.
[0110] Carbon emission benefit optimization refers to minimizing carbon emissions through optimization methods.
[0111] See attached Figure 1 , Figure 1 FIG. 1 is a flow chart of the main steps of the production scheduling method according to an embodiment of the present application. Figure 1 As shown, the production scheduling method in the embodiment of the present application mainly includes the following steps S101 to S102.
[0112] Step S101: Optimize the production schedule based on the mold production parameters and production duration parameters of the production line to obtain a first target solution for the production schedule of the production line.
[0113] In this embodiment, the production schedule can be optimized based on the mold production parameters and production time parameters of the production line to obtain the first target solution of the production schedule of the production line.
[0114] In one embodiment, the mold production parameters may include the raw material material corresponding to the mold, the production efficiency of the mold, the upper and lower limits of the mold production batch, the mold change time, etc. The production time parameter may include the single-day production time, etc. For the convenience of description, the involved mold production parameters and production time parameters may be defined in mathematical symbols as follows:
[0115] Mold: There is a one-mold-multiple-piece relationship between the mold and the parts. Here, the mold can be used as a parameter: P1, ..., P n ;
[0116] Production scheduling cycle: the number of days required to schedule production: D;
[0117] Demand: Daily demand for each mold:
[0118] Rack: used to store production parts. The sum of inventory and production quantity cannot exceed the rack's capacity:
[0119] Inventory: Record the current inventory capacity:
[0120] Mold change time: Switching between different molds requires changing different molds. The time for this switch is called mold change time:
[0121] Single-day production time: Day-level production time: t1,…,t D ;
[0122] The upper and lower limits of mold production batch: Upper limit: Lower limit:
[0123] ASPM, that is, the production efficiency of the mold: AP1, AP2, ..., AP n .
[0124] Step S102: According to the first target solution and the raw material material corresponding to the first target solution, the carbon emission benefit is optimized to obtain the second target solution of the production line's production schedule.
[0125] In this embodiment, on the basis of the first target solution, the carbon emission benefit can be optimized according to the raw material material of the production line corresponding to the first target solution, so as to obtain the second target solution of the production scheduling plan.
[0126] Based on the method described in steps S101 to S102 above, the embodiment of the present application optimizes the production schedule based on the mold production parameters and production time parameters of the production line, obtains the first target solution of the production scheduling technology of the production line, optimizes the carbon emission benefits according to the first target solution and the raw material material corresponding to the first target solution, and obtains the second target solution of the production schedule. Through the above configuration method, the embodiment of the present application can achieve carbon emission benefit optimization under the premise of ensuring the optimization of the production schedule, and can simultaneously improve the production efficiency of the production line and the waste classification, recycling and packaging benefits, reduce the raw materials and parts in-process inventory of the production line, achieve less resource input and greater output economic benefits, and meet the normal production needs of subsequent workshops, and achieve green and low-carbon production of production line production.
[0127] Step S101 and step S102 are further described below.
[0128] In one implementation of the embodiment of the present application, the production scheduling optimization may include a first optimization and a second optimization, and step S101 may further include the following steps S1011 and S1012:
[0129] Step S1011: Based on the mold production parameters and the production time parameters, a first optimization is performed to obtain a preliminary production scheduling target solution for the production line.
[0130] In this embodiment, step S1011 may further include the following steps S10111 to S10113:
[0131] Step S10111: setting the optimization target of the first optimization; the optimization targets include maximizing the production time of the production line and minimizing the mold replacement time of the production line.
[0132] Specifically, the production time can be determined using the following formula (1):
[0133]
[0134] The time required to change the mold can be determined according to the following formula (2):
[0135]
[0136] Where n is the total number of molds, For the P i The mold replacement time of the mold produced after the first mold, For mold P i production volume.
[0137] That is, the optimization goal of the first optimization is to maximize formula (1) and minimize formula (2).
[0138] Step S10112: setting the constraints of the first optimization; the constraints include the maximum production time constraint of the production line and the upper and lower limits of the production volume of the molds of the production line.
[0139] In this embodiment, the maximum production time constraint can be determined according to the following formula (3):
[0140]
[0141] The upper and lower limits of mold production can be determined according to the following formulas (4) to (7):
[0142]
[0143]
[0144]
[0145]
[0146] Where n is the total number of molds, For the P i The mold replacement time of the mold produced after the first mold, For mold P i of production, For the i-th mold P i The demand on day j+l is is the i-th mold P i The inventory on day j, For P i The production limit of each mold is For P i The production limit of each mold.
[0147] Step S10113: Perform the first optimization according to the optimization objectives and constraints to obtain a preliminary production scheduling target solution.
[0148] In this embodiment, a first optimization may be performed according to the optimization objective and the constraints to obtain a preliminary production scheduling target solution.
[0149] In one implementation, the inventory and racks will change dynamically with the daily consumption and production. In addition to the above constraints, some rule-like conditions can also be set, such as certain molds cannot be produced on the same day.
[0150] In one implementation, during the first optimization process, some constraints can be broken. For example, if there is a risk of production suspension, overtime production may be required, and at this time, the constraint of the maximum production time can be broken. In addition, there are other conditions that can be used as breakable constraints, with the goal of finding a feasible preliminary production scheduling target solution as much as possible.
[0151] Step S1012: Perform a second optimization based on the preliminary production scheduling target solution of the production line for multiple days to obtain the first target solution.
[0152] In this embodiment, step S1012 can be further configured as: balancing the production duration for multiple days based on the preliminary production scheduling target solution of the production line for multiple days and the inventory days of the mold to achieve the second optimization and obtain the first target solution.
[0153] In this implementation, the inventory days can be obtained according to the following formula (8):
[0154]
[0155] Among them, DOH i is the inventory days of the i-th mold, For the i-th mold P i The demand on day j is is the i-th mold P i The inventory on day j.
[0156] Calculating the inventory days of each mold can help you find the most urgent molds. Then, based on the inventory days, you can optimize the initial production schedule and balance the production time over multiple days to meet the following requirements:
[0157] 1. The same mold will not be produced on the same day, unless in extreme cases all racks cannot meet the demand of the two days on the previous day;
[0158] 2. By balancing the production time, the production time of each day can be as balanced as possible.
[0159] After the second optimization, a more balanced, stable and efficient solution to the first objective can be obtained.
[0160] Here are two examples of why the second optimization is necessary:
[0161] 1. Assume that there is insufficient production time on the i-th day (perhaps because there are no necessary molds to produce), and overtime production is required on the i+1th day. At this time, it is necessary to find a more efficient solution on a global scale, such as bringing forward some molds from the i+1th day to the i-th day.
[0162] 2. The production is extremely unbalanced over many days, with some days having longer production time and some days having shorter production time.
[0163] In one embodiment, please refer to the attached Figure 2 , Figure 2 FIG. 1 is a flow chart of the main steps of obtaining the first target solution according to an implementation of an embodiment of the present application. Figure 2 As shown, the process of obtaining the first target solution can be through the coarse-grained optimization solution recall in stage 1 (i.e., the first optimization) and the fine-grained optimization solution adjustment in stage 2 (i.e., the second optimization). In stage 1, multiple optimization targets (optimization target 1, optimization target 2, ..., optimization target m) and multiple constraints (constraint 1, constraint 2, ..., constraint n) can be set to obtain target solution 1 (i.e., the preliminary scheduling target solution). In stage 2, based on the optimization target x, target solution 2 (i.e., the first target solution) is obtained.
[0164] In one implementation of the embodiment of the present application, step S102 may be further configured as follows:
[0165] According to the first target solution and the raw material material corresponding to the first target solution, the production sequence of the production line is adjusted to optimize the carbon emission benefits and obtain the second target solution.
[0166] In this embodiment, the production order of the production line can be adjusted based on the first target solution to achieve the highest overlap of the same raw materials packaged together, so as to optimize the carbon emission benefits and obtain the second target solution.
[0167] Specifically, step S102 may further include the following steps S1021 and S1022:
[0168] Step S1021: When the production line is a single-line production, the production sequence of the production line is adjusted so that molds made of the same raw material in the production line are produced simultaneously to obtain a second target solution.
[0169] In this embodiment, if single-line production is optimized, the production sequence of the production line can be adjusted so that molds made of the same raw material are produced at the same time, thereby obtaining the second target solution.
[0170] For details, please refer to the attached Figure 3 , Figure 3 1 is a flow chart of the main steps of a single production line production scheduling method according to an implementation of an embodiment of the present application. Figure 3 As shown, when optimizing a single production line, after the coarse-grained optimization in stage 1 and the fine-grained optimization in stage 2, the maximum optimization of carbon emission benefits in stage 3 can be performed, that is, the same material sorting of the production line can be performed.
[0171] Step S1022: When multiple production lines are producing simultaneously, determine the baseline production line for adjusting the production sequence according to the carbon emission benefits of the waste corresponding to the raw material materials of each production line; and adjust the production sequence of multiple production lines according to the baseline production line to maximize the overlap of the same raw material materials of multiple production lines to obtain the second target solution.
[0172] In this embodiment, if multiple production lines are optimized, the benchmark production line can be determined based on the output of the multiple production lines. For example, the production line with a greater carbon emission benefit of the waste corresponding to the raw material material can be used as the benchmark production line, and the production order of the multiple production lines can be adjusted according to the benchmark production line to maximize the overlap of the same raw material material of the multiple production lines, and obtain the second target solution.
[0173] For details, please refer to the attached Figure 4 , Figure 4 FIG. 1 is a flow chart of the main steps of a dual production line production scheduling method according to an implementation of an embodiment of the present application. Figure 4 As shown in the figure, when optimizing multiple production lines (production line A and production line B), the results of the two production lines need to be coordinated. That is, after the coarse-grained optimization in stage 1 and the fine-grained optimization in stage 2, when the carbon emission benefit is maximized in stage 3, the overlap rate of the two production lines is maximized, thereby obtaining the target solution 3 of line A and the target solution 3 of line B (i.e., the second target solution).
[0174] For an example, see the attached Figure 5 , Figure 5 FIG. 1 is a schematic diagram of the packaging process of two production lines according to an example of an embodiment of the present application. Figure 5 As shown, the output value of production line A and production line B can be calculated separately. Assuming that the output value of production line A is larger, production line A is used as the benchmark, and the production sequence of production line A and production line B is adjusted at the same time to maximize the overlapping part of the same raw material materials of the two production lines.
[0175] against Figure 5 , the optimization goal of obtaining the second objective solution is:
[0176]
[0177] Among them, m is the raw material material.
[0178] In one implementation, the molds for emergency production can be determined based on the inventory days of the molds. If there are molds for emergency production, the molds for emergency production can be sorted first, and then the production order of multiple production lines can be adjusted according to the reference production line.
[0179] In one implementation, product distribution of different factories, BOM (Bill of Materials) information of materials, mold master data, product packaging master data, etc. can be obtained through upstream and downstream systems of the production line.
[0180] Data information can be obtained, including but not limited to the distribution of products in various production lines, product material grades, waste weight, production rhythm, carbon emission data, etc.
[0181] Based on the mold management system, different forms of mold parameters such as one mold for multiple pieces, single mold production and spare parts production can be managed.
[0182] Based on finished product demand management, customer demand of the stamping workshop can be obtained by disassembling the vehicle production plan orders of different factories to ensure that the demand summary of all customers is completed.
[0183] Based on the parts inventory and rack management, the stamping parts delivery action can be completed through the visual scanning system, and the parts inventory can be created in the logistics management system. Through the online production consumption of the welding workshop, the closed-loop management of the parts inventory can be completed to achieve real-time and accurate parts inventory; at the same time, packaging container management is established in the logistics management system, and refined management is carried out from packaging procurement to packaging occupancy and packaging maintenance to ensure real-time monitoring of the packaging container quantity flow data;
[0184] Based on the production line capacity management, the monthly capacity of each production line can be calculated according to the monthly and annual production plans of the automobile OEMs. The mold distribution of each production line can be optimized and adjusted according to the monthly calculation results, and the monthly attendance working days and overtime hours can be used as the input conditions for production scheduling.
[0185] In one embodiment, please refer to the attached Figure 6 , Figure 6 FIG. 1 is a flow chart of the main steps of the production scheduling process according to an implementation method of the present application. Figure 6 As shown, the production scheduling process can include job planning, master data management, demand management, inventory management, capacity management, planning management, algorithm management, and order management.
[0186] Static data management can include setting factory data, obtaining materials, Bom information, maintaining product information, obtaining mold master data, obtaining rack master data, setting vehicle models, and mold data.
[0187] Obtaining gross demand may include collecting the welding workshop online operation plan, collecting project demand, collecting after-sales demand, and summarizing the gross demand of stamping parts. Obtaining the latest inventory of stamping parts may include collecting the number of existing inventory of stamping parts. Calculating net demand may include calculating the net demand of stamping parts = gross demand - inventory.
[0188] Setting basic capacity may include setting factory calendar, setting shift mode, and setting production line calendar. Setting actual capacity may include setting other capacity losses and calculating the actual production time period of the production line.
[0189] Creating a plan can include creating a plan, selecting a model, and obtaining the latest information and constraints required by the algorithm model. Obtaining inventory information can include collecting the current inventory quantity of stamping parts, collecting the available sheet material inventory of stamping parts, collecting the available rack inventory of stamping parts, calculating inventory DOH, and recording all inventory information. Short-term model calculations can include setting constraints and scheduling strategies, and recording planning results. Master plan creation can include user checks based on planning results and merging master plans.
[0190] Order issuance can include selecting a master plan, manual import, creating an order, issuing an order, modifying an order, deleting an order, and issuing changes. Order closing can include automatic closing across days, manual closing, and order closing.
[0191] It can synchronize stamping plant information with XBOM (x-Bill of Materials). It can synchronize mold-related information with MOP (Manufacturing Operation Platform), and MOP (Manufacturing Operation Platform) can receive order information. LES (Logistics Execution System) can synchronize rack-related information, the latest product inventory, inventory information, and order submission.
[0192] It should be pointed out that although the various steps in the above embodiments are described in a specific order, those skilled in the art can understand that in order to achieve the effect of the present application, different steps do not have to be executed in such an order. They can be executed simultaneously (in parallel) or in other orders. These adjusted schemes are equivalent to the technical schemes described in this application, and therefore will also fall within the scope of protection of this application.
[0193] It is understood by those skilled in the art that all or part of the processes in the method for implementing the above-mentioned embodiment of the present application can also be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a computer-readable storage medium, and the computer program can implement the steps of the above-mentioned various method embodiments when executed by the processor. Among them, the computer program includes computer program code, and the computer program code can be in source code form, object code form, executable file or some intermediate form. The computer-readable storage medium may include: any entity or device, medium, U disk, mobile hard disk, disk, optical disk, computer memory, read-only memory, random access memory, electrical carrier signal, telecommunication signal and software distribution medium, etc. that can carry the computer program code.
[0194] Another aspect of the present application also provides a computer-readable storage medium.
[0195] In an embodiment of a computer-readable storage medium according to the present application, the computer-readable storage medium may be configured to store a program for executing the production scheduling method of the above method embodiment, and the program may be loaded and run by a processor to implement the above production scheduling method. For ease of explanation, only the parts related to the embodiment of the present application are shown. For specific technical details not disclosed, please refer to the method part of the embodiment of the present application. The computer-readable storage medium may be a storage device formed by various electronic devices. Optionally, the computer-readable storage medium in the embodiment of the present application is a non-temporary computer-readable storage medium.
[0196] Another aspect of the present application also provides a controller.
[0197] In an embodiment of a controller according to the present application, the controller may include at least one processor; and a memory communicatively connected to the at least one processor; wherein a computer program is stored in the memory, and when the computer program is executed by the at least one processor, the method described in any of the above embodiments is implemented.
[0198] So far, the technical solution of the present application has been described in conjunction with an embodiment shown in the accompanying drawings, but it is easy for those skilled in the art to understand that the protection scope of the present application is obviously not limited to these specific embodiments. Without departing from the principles of the present application, those skilled in the art can make equivalent changes or substitutions to the relevant technical features, and the technical solutions after these changes or substitutions will fall within the protection scope of the present application.
Claims
1. A production scheduling method, characterized in that: The method comprises: Based on the mold production parameters of the production line and the production time parameters of the production line, the production schedule is optimized to obtain a first target solution of the production schedule of the production line; According to the first target solution and the raw material material corresponding to the first target solution, carbon emission benefit optimization is performed to obtain a second target solution for the production scheduling plan of the production line.
2. The production scheduling method according to claim 1, characterized in that: The production scheduling optimization includes a first optimization and a second optimization; The obtaining of a first target solution of the production schedule of the production line includes: Based on the mold production parameters and the production time parameters, the first optimization is performed to obtain a preliminary production scheduling target solution for the production line; A second optimization is performed based on the preliminary production scheduling target solution of the production line for multiple days to obtain the first target solution.
3. The production scheduling method according to claim 2, characterized in that: The obtaining of a preliminary production scheduling target solution for the production line includes: Setting an optimization goal for the first optimization; the optimization goal includes maximizing the production time of the production line and minimizing the mold replacement time of the production line; Setting the first optimization constraint conditions; the constraint conditions include the maximum production time constraint of the production line and the upper and lower limits of the production volume of the molds of the production line; The first optimization is performed according to the optimization objective and the constraint conditions to obtain the preliminary production scheduling target solution.
4. The production scheduling method according to claim 3, characterized in that: The production time is determined according to the following formula: The mold replacement time is determined according to the following formula: Where n is the total number of molds, For the P % The mold replacement time of the mold produced after the first mold, For mold P % production volume.
5. The production scheduling method according to claim 3, characterized in that: The maximum production time constraint is determined according to the following formula: The upper and lower limits of the mold production volume are determined according to the following formula: Where n is the total number of molds, For the P % The mold replacement time of the mold produced after the first mold, For mold P % of production, For the i-th mold P % The demand on day j+1 is is the i-th mold P % The inventory on day j, For P % The production limit of each mold is For P % The production limit of each mold.
6. The production scheduling method according to claim 2, characterized in that: The obtaining of the first target solution comprises: Based on the preliminary production scheduling target solution of the production line for multiple days and the inventory days of the mold, the production duration of the multiple days is balanced to achieve the second optimization and obtain the first target solution.
7. The production scheduling method according to claim 6, characterized in that: The method further includes obtaining the inventory days of the mold according to the following formula: Among them, DOH i is the inventory days of the i-th mold, For the i-th mold P i The demand on day j is is the i-th mold P % The inventory on day j.
8. The production scheduling method according to claim 1, characterized in that: The obtaining of a second target solution of the production schedule of the production line includes: According to the first target solution and the raw material material corresponding to the first target solution, the production sequence of the production line is adjusted to optimize the carbon emission benefits and obtain the second target solution.
9. The production scheduling method according to claim 8, characterized in that: The adjusting the production sequence of the production line includes: When the production line is a single-line production line, adjusting the production sequence of the production line so that molds made of the same raw material in the production line are produced simultaneously to obtain the second target solution; When multiple production lines are producing simultaneously, a baseline production line for adjusting the production sequence is determined based on the carbon emission benefits of the waste corresponding to the raw material material of each production line; and based on the baseline production line, the production sequence of multiple production lines is adjusted to maximize the degree of overlap of the same raw material material of multiple production lines to obtain the second target solution.
10. The production scheduling method according to claim 9, characterized in that: Before adjusting the production sequence of the plurality of production lines according to the reference production line, the method further includes: According to the inventory days of the mold, determine whether there are molds for emergency production; If so, first sort the molds for emergency production; If it does not exist, execute the step of "adjusting the production sequence of the multiple production lines according to the benchmark production line".
Citation Information
Cited By
Low-carbon resource production plan generation method and related equipment
CN120562932A
Low-carbon resource production plan generation method and related device
CN120562932B